SZCQ192256_ SZCQ152149 B149 and 256_Drawings Sheet AE101 Update.pdf
PDF 563 KB Posted
- Attached to
- Building 149 & 256 Roof Replacement
- Solicitation number
- W50S8A
About this file
This document contains an invitation for bid for roof replacement services at two buildings on Pease Air National Guard Base in New Hampshire. The USPFO for New Hampshire will award a firm fixed-price contract to remove and replace the built-up asphalt roof systems on Building 149 and 256 with new EPDM or PVC roof systems. The scope of work includes installation of the new roof membranes, removal and replacement of exterior insulation and fascia, provision of all flashings and sealing of all penetrations and mechanical systems, replacement of failed wood decking, asbestos abatement, and an option to replace ceiling tiles. A pre-bid conference will be held on January 20th, with questions due by January 18th and bids due on February 10th. Interested contractors must be registered in SAM and follow conference registration and base access requirements in the attached solicitation.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
O'
E"
a. -n�
LO W
""1 I Ol
0 <D
NO
0 Ol N-
N ·/a. OJ OJ -
(/) ti=
Ol/ 0 ..
NOT IN
CONTRACT 3'-8"±
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
N
.I I')
213'-4"±
7 8 7 8
1 1
\ I \ I \ r
I r
�i._c I I I I I I L ____ J
7 8
) )------�01---------,,�----t--->s:------------jQt----------;,�----t--->s:------------jQt---------,'�----t--->s:------------jQI---------{ (
I
7 8 EXTERIOR FACE OF WALL BELOW (TYP)
1 BUILDING 149 ROOF PLAN
AE101 SCALE: 1/8"=1'-0"
3'-9"±
T
C
PLAN
NORTH
\ I
T
7 8 f-----+----+----------------+----=-i----BUILT-UP EPDM ROOF SYSTEM, SEE
ROOF HATCH INFILL DETAIL
SCALE: 1 1/2"=1'-0"
DETAIL 1/AE501
_J_....--- AP A RA TED PLYWOOD ROOF
SHEA THING, MATCH THICKNESS OF
EXISTING WOOD ROOF DECKING
2x WOOD JOISTS AT 1'-4" OC 2x WOOD FRAMING
2x WOOD EXISTING FRAMING
NOJE:
CONNECT 2x6 JOISTS WITH
GALVANIZED JOIST HANGER WITH A
MINIMUM CAPACITY OF 300 POUNDS.
\ I
T
GENERAL SHEET NOTES
1. SEE SHEET G-002 FOR GENERAL CONSTRUCTION
NOTES.
2. ROOF ELEVATION WORK SURFACE IS
APPROXIMATELY 16'-6" ABOVE FINISH GRADE.
3. EXISTING ROOF TOP EQUIPMENT AND
PENETRATIONS INDICATED SHALL REMAIN AND BE
MAINTAINED IN WORKING CONDITION DURING
RE-ROOFING WORK UNLESS NOTED OTHERWISE.
4. DURING ROOF REMOVALS, EXISTING 3/4"± WOOD
DECKING IS TO BE EXAMINED FOR DAMAGE AND
DECAY. IF UNSUITABLE WOOD DECKING IS
ENCOUNTER, REMOVE AND PROVIDE WOOD
DECKING TO MATCH EXISTING ADJACENT
CONSTRUCTION. FOR BIDDING PURPOSES ASSUME
20% F Al LURE OF EXISTING WOOD DECKING.
5. PREPARE ROOF DECK PER THE ROOFING
MATERIAL MANUFACTURES PRINTED INSTRUCTIONS.
BID OPTION /12
OU 2 - REPLACE CEILING TILES:
REPLACE INTERIOR ACOUSTICAL CEILING TILES
TO MATCH EXISTING.
QUANTITIES: (89) 24" X 24" TILES,
(6) 24" X 48" TILES,
7 8
KEYNOTES (THIS SHEET ONLY)
[I] EPDM ROOF SYSTEM ON EXISTING WOOD ROOF DECKING.
SEE DETAIL 1/AE501.
� ROOF DRAIN ASSEMBLY, SEE DETAIL 7 / AE501.
� FLASHING AT EXISTING VENT THROUGH ROOF, SEE
DETAIL 6/AE501.
[±J EQUIPMENT CURB AND FLASHING. REINSTALL SALVAGED
MECHANICAL EQUIPMENT. SEE DETAIL 12/AE501.
@J REINSTALL SALVAGED EVACUATED TUBE SOLAR
COLLECTOR AND FRAME. INSTALL SLEEPERS, FLASHING
AT WOOD SLEEPERS AND FOUR (4) WATER PIPE
PENETRATIONS, SEE DETAILS 4/AE501 AND 8/AE501.
(§] INFILL ROOF OPENING. SEE DETAILS 2/AE101 AND
9/AE501.
[I] METAL FASCIA, SEE DETAIL 10/AE501.
[fil METAL SOFFIT PANELS AT UNDERSIDE OF ROOF
OVERHANG, SEE DETAIL 5/AE501.
[fil TAPERED RIGID INSULATION CRICKET. SLOPE 1/4": 1'-0"
MIN.
[QI PVC VENT THROUGH ROOF, SEE DETAIL 3/AE501.
II] FLASHING AT EXIST EQUIPMENT CURB, SEE DETAIL
2/AE501. REINSTALL SALVAGED MECHANICAL
EQUIPMENT.
GRAPHIC SCALES
1 /8"=1 '-0" 8' 4' 0 8'
1· 8. 4• o
1-1;2·=1'-o·
CHECK GRAPHIC SCALES BEFORE USING
16'
1'
PEASE
AIR NATIONAL
GUARD BASE
NEWINGTON, NH
lll'iili OE ii; 8 0-:..,;
Iii II iii -c
� ·o c,;� o• i1■11 �o
!e:f ..... m z ►
-� ro
0� ro a.=
C E llo: � < ro
DESCRIPTION DATE
t REVISIONS
PROJECT
NO./NAME:
SZCQ152149
REPAIR
ROOF BUILDING 149
SZCQ192256
REPAIR
ROOF BUILDING 256
FACILITY:
149 AND256
DRAWING
TITLE:
BUILDING 149
ROOFPLAN
DATE
9-14-2020
SCALE
AS NOTED
NO.
DR BY:
RMT
CHKD BY:
BML
AE101
SHEET
NO. 7 OF 10
CAD FILE NO.
21906.09-AEI0I
12Jan211 - BID OPTION #2
1012784771N Polygon
1012784771N Callout