2023.06.29 - 1819 - MANG Building 25 - revised A2.00.pdf

PDF 520 KB Posted

Attached to
REPAIR MAINTENANCE HANGAR, BLDG 25
Solicitation number
W50S7L23B0002
Issued by

About this file

This document outlines an Invitation for Bids for repair and maintenance services at Building 25 of the Montana Air National Guard facility. Key details include:

  • The solicitation number is W50S7L23B0002 and seeks a firm fixed-price contract for roof replacement, asphalt and drainage repair, hangar bay floor modifications including installation of a high performance floor coating system, fire sprinkler system updates, and mechanical and electrical work. The performance period is 120 calendar days.

  • The pre-bid conference is scheduled for June 13, 2023 and the bid opening is July 7, 2023. The project location is the Montana Air National Guard facility in Great Falls, MT and the NAICS code is 236220.

  • The opportunity is set aside 100% for small businesses with a size standard of $45 million. The estimated value is between $1-5 million.

  • Interested contractors should register in SAM and monitor the Contract Opportunities page on SAM.gov for solicitation documents and any amendments. Questions are due by June 23, 2023.

View the file

Other files

File Type Posted
C4 - Abstract of Offers - CS_KO.pdf PDF
B8 - Amendment 6 - Modification Solicitation W50S7L-23-B-0002-P0006 Bld 25.pdf PDF
B8 - Amendment 6 - Conform Solicitation W50S7L-23-B-0002-P0006 Bld 25.pdf PDF
B8 - Amendment 5 - Conform Solicitation W50S7L-23-B-0002-P0005 Bld 25.pdf PDF
B8 - Amendment 5 - Modification Solicitation W50S7L-23-B-0002-P0005 Bld 25.pdf PDF
Questions and Answers 2 W50S7L-23-B-0002 - 7 July 2023.pdf PDF
B8 - Amendment 4 - Modification Solicitation W50S7L-23-B-0002-P0004 Bld 25.pdf PDF
MTANG B25 Environmental remediation dwgs and cut sheets.pdf PDF
B8 - Amendment 4 - Conform Solicitation W50S7L-23-B-0002-P0004 Bld 25.pdf PDF
10 51 13 FL - Metal Lockers.pdf PDF
B8 - Amendment 3 - Conform Solicitation W50S7L-23-B-0002-P0002 Bld 25.pdf PDF
32 13 14.13 Spec update 6_30_23.pdf PDF
Questions and Answers W50S7L-23-B-0002 - 30 June 2023.pdf PDF
B8 - Amendment 3 - Modification Solicitation - W50S7L-23-B-0002-P0002 Bld 25.pdf PDF
B8 - Amendment 2 - Modification Solicitation - W50S7L-23-B-0002-P0002 Bld 25.pdf PDF
B8 - Amendment 2 - Conform Solicitation W50S7L-23-B-0002-P0002 Bld 25.pdf PDF
B7 - Pre-Bid Conference Minutes - W50S7L-23-B-0002.pdf PDF
B8 - Amendment 1 - Modification Solicitation - W50S7L-23-B-0002-P0001 Bld 25.pdf PDF
B8 - Amendment 1 - Conform Solicitation W50S7L-23-B-0002-P0001 Bld 25.pdf PDF
B8 - Amendment 1 - Conform Solicitation W50S7L-23-B-0002-P0001 Bld 25.pdf PDF
B8 - Amendment 1 - Modification Solicitation - W50S7L-23-B-0002-P0001 Bld 25.pdf PDF
A3 - JKSE172220 B25 SPEC VOL 1 Revised 5.30.23.pdf PDF
A3 - JKSE172220 B25 SPEC VOL 1.pdf PDF
A3 - JKSE172220 B25 SPEC VOL 1.pdf PDF
A3 - 1.26.22 - B-3 - JKSE172220 B25 SPEC VOL 2.pdf PDF
B8 - Solicitation - W50S7L-23-B-0002 Bld 25.pdf PDF
A3 - 4.19.23 - JKSE172220 - B25 - B-3 Drawings w_ABI.pdf PDF
B4 - SAM Wage Determination - MT20230062 Dated 4-28-2023.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. DIMENSIONS ARE TYPICALLY TAKEN TO GRID, FACE OF MASONRY, FACE OF CONCRETE, FACE

OF STUD OR DOOR/WINDOW OPENINGS. DIMENSIONS TO OPENINGS ARE NOMINAL, VERIFY

ALL OPENINGS WITH ROUGH OPENING REQUIREMENTS.

2. MASONRY IS DIMENSIONED NOMINALLY TO THE FACE. ACTUAL DIMENSIONS WILL BE +1/2"

FOR INSIDE DIMENSIONS AND MASONRY OPENINGS, AND -1/2" FOR OUTSIDE DIMENSIONS.

3. EXISTING CONSTRUCTION TO REMAIN SHOWN HALF-TONE, TYP.

4. SEE SHEET A1.00 FOR WALL TYPE DESIGNATIONS.SEE SHEET A1.00 FOR WALL TYPE

DESIGNATIONS.

SHEET NOTES - FLOOR PLAN

1A1A

1.71.7

10.510.5

10.610.6

EE

EE

A

A

C

C

D

D

CC

CC

AA

AA

B

B

E

E

F

F

G

G

H

H

J

J

K

K

L

L

M

M

A3.00 4

A3.00

A3.002

A3.00

MAINTENANCE

HANGAR BAY

B100

MTL SHOP

B107B

MTL. TECH SHOP

B107A

NDI SHOP

B109

PNEUDRALIC

B118

ELECTRO ENVIRO

SHOP

B119

BATTERY SHOP

B117

AVIONICS SHOP

B104

TIRE SHOP

B101

TIRE SHOP

SPRVSR

B101A

STAIRS

S001

S0

-B

B1

-B

B1

A- A

B102-A

B1

B- A

B106-A

B1

-B

B1

A- A

B1

B- A

B1

A- A

B1

C -B

B1

D -B

B107B-AB1

C -A

B1

D -A

B1

-A

S0

-B

B107B-D

B1

-A

B1

D -A

B1

-A

B1

A- A

B1

B- A

B1

-A

B118B-A

B1

A- A

B119B-A

B1

A- A

B121-C

S0

-B

B1

-A

B1

A- A

B122B-A

B123-B

B1

A- A

S0

-A

B1

-A

B1

-A

B127-AB128A-A

B128B-A

B1

-A

B1

A- B

B121A-A

B121-A

B120-A

B116-A

B1

-A

B1

-B

B1

-A

B1

-A

B1

-A

B1

-A

B1

-A

B1

-C

B119-A B119-B

B118-A

B1

C -A

B109-A

B1

-B

B1

-A

B103-A

B113-A

B109-B

B107A-A

B121-D

B1

-B

B120-B

B130-B

B1

-A

TIRE SHOP

OFFICE

B101B

TRAINING

B102

TUG ACCESS

B103

AVIONICS SHOP

TRAINING

B104A

SORVSR ECM

B105A

SPIR

B105B

ECM SHOP

B105

SPRVSR

AVIONICS

B104B

B104B-B

CORR.

A106

STAIRS

S002

MTL TECH

OFFICE

B107C

MTL TECH

SPRVSR

B107D

ELEV. MECH.

B108

B108-A

B107B-C

NDI SPRVSR

B109A

NDI STRG

B109B

JOAP LAB

B110

ACC OFFICE

B118D

FILM DVLPNT

B112

FILM VIEWING

B111

X RAY ROOM

B113

B1

-A

B118-B

TEST STND

B118C PNEUDRALIC

TRAINING

B118B

MECH. ELEC.

B114E

MECH. ELEC.

B114A

PNEUDRALIC

SPRVSR

B118A

ELECTRO

TRAINING

B119B SHOP LOCKERS

B116

B1

B- B

TOOL CRIB

B122B

MAINT. SUPPORT

EQUIP.

B120

ELECTRO/ENVIRO

SPRVSR

B119A

B122B-B

TOOL RM BENCH

STOCK

B122A

CORR.

B123

MSL

B121MSL OFFICE

B121A

WOMENS

LATRINE

B125

MENS LATRINE

B126

STORAGE

B124

STAIRS

S003

B123-A

BREAK ROOM

B127

ISO SPVSR

B128A

ISO OFFICE

B128B

ISO PHASE

B128

TUG ACCESS

B129

FLIGHT LINE

B130

CONF

B135

CLOSET

B134OFFICE

B133

OFFICE

B132

OFFICE

B131

7 7

A3.00

A2.00

B1

-A12

B1

B- A 12

14 14

B128A-B

B1

-C

A2.00

A2.00

FLOOR

FM1 RUBBER SECTIONAL FLOORING MAT

ARS ACID-RESISTANT SHEET FLOORING

AS ANTI STATIC SHEET FLOORING

V1 VINYL 1

HPC HIGH PERFORMANCE COATING

ROOM FINISH KEY

BASE

T1 TILE

WD WOOD

R4 4" RUBBER

WALL

P1 PAINT COLOR #1

P2 PAINT COLOR #2

CEILING

P1 PAINT COLOR #1

G

G

BREAK ROOM

B127

A2.00

RELOCATED REFRIGERATOR

(N) WATER BOTTLE FILL STATION

RELOCATED ICE MACHINE

FIRST FLOOR

100'-0"

B127-A

(N) BOTTLE FILLING STATION - SEE MECH.

RELOCATED ICE MACHINE - SEE MECH/ELECT.

(E) CABINETS TO REMAIN

PATCH, REPAIR, AND REPAINT GWB AS REQ. - MATCH ADJACENT

(E) WALL BASE TO REMAIN

1/

2"

VARIES - VERIFY

MIN.

3 1/2" 3/4"

VARIES - VERIFY

MIN.

3 1/2" (E) CONC. FLOOR SLAB

JOINT NOSING MORTAR

BACKER ROD

JOINT SEALANT

JOINT NOSING MORTAR

REMOVE (E) SPALLED, LOOSE,

DAMAGED CONC. SLAB AS REQ. -

PREP. FOR (N) NOSING MORTAR

PER MORTAR MFR.

CONSTRUCTION NOTES:

1. CUT A MIN. 1 1/2" X 3 1/2" BLOCK OUT IN THE (E) CONCRETE ON BOTH SIDES

OF THE JOINT OPENING.

2. ANY CLEANING AND INSTALLATION PROCEDURES SHALL CONFORM TO THE

MANUFACTURER'S PRODUCT DATA SHEET.

3. ANY SPALLS IN CONCRETE FACES SHALL BE FILLED WITH JOINT NOSING

MORTAR.

4. SEAL NEW JOINT FOLLOWING MANUFACTURER'S RECOMMENDED

PROCEDURES.

JOINT REPAIR NOTES:

MATERIALS SHALL BE PER SPECIFICATION SECTION 07 90 00.

THE FOLLOWING MATERIALS COMPLY WITH SPECIFICATIONS:

JOINT NOSING MORTAR: SIKADUR 72 JNS

CAULK: SIKAFLEX 2C NSTG

SELECT A BACKER ROD THAT IS CHEMICALLY COMPATIBLE WITH MORTAR AND CAULK.

SUBMIT PRODUCT DATA FOR ALL MATERIALS, INCLUDE A STATEMENT OF MATERIAL COMPATABILITY THAT

INDICATES ROD MATERIAL IS CHEMICALLY SUITABLE FOR USE WITH MORTAR AND CAULK.

PER 07 90 00 SECTION 3.01B, PREPARE SURFACE PER MORTAR MANUFACTURER'S GUIDANCE. FOR SIKAFLEX 72JNS, SURFACE SHALL BE CLEAN, OPEN TEXTURED CSP 3-4 TO DVP-4 BY BLAST CLEANING OR

EQUIVALENT MECHANICAL MEANS. REFER TO DATA SHEET FOR MORE DETAIL.

NOTE: THE MECHANICAL PROPERTIES OF SIKADUR 42 AND SIKAFLEX 1C SL VARY FROM SPECIFICATION.

THESE PRODUCTS ARE NOT APPROVED.

CONTRACTOR TO FIELD VERIFY ALL EXISTING CONDITIONS AT DETERIORATED SLAB.

BIM FILE PATH:

SHEET NO.:

TITLE:

copyright 2021 SMA, P.C.

REVISIONS:

KEYMAP:

HELENA

920 Front Street | Suite 101 Helena | MT | 59601 P| 406/442.4933 www.architects-sma.com

ARCHITECT SEAL:

PROJECT:

PROJECT LOCATION:

PREPARED FOR:

LOGO:

CONSULTANT:

PROJECT NUMBER:

DRAWN BY:

CHECKED BY:

TEAM:

PHASE:

DATE:

PROJECT NUMBER:

Pl ot

D at e:

BOZEMAN

109 East Oak Street | Suite 2E Bozeman | MT | 59715 P| 406/219.2216 www.architects-sma.com

C:\Users\Peterr\Documents\1819 - MANG Building 25-R23_peterrJNJMV.rvt

6/

/2

:4 4:

A

M

A2.00

JKSE172220

2023.06.29

FIRST FLOOR PLAN

PR/TJ

PR

REPAIR MAINTENANCE

HANGAR BLDG 25

JKSE172220

MONTANA AIR NATIONAL GUARD

GREAT FALLS AIR NATIONAL GUARD BASE

GREAT FALLS, MT

Type B-3 SUBMITTAL

N

KEYNOTES - LEVEL 1 FLOOR PLAN

1 REMOVE (E) DOOR RAILS & CONC. STRIP APPROX 6'-0" WIDE - FULL WIDTH OF BAY -

REPLACE W/ (N) CONC. SLAB TO MATCH (E) PER STRUCT.

2 SHADED AREA - INSTALL (N) HIGH-PERFORMANCE FLOOR COATING SYSTEM - APPLY (N)

FLOOR STRIPING TO MATCH (E) REMOVED STRIPING - COORD W/ FM AND GOVERNMENT

3 INSTALL (N) FLOOR COATING SYSTEM TO MATCH (N) FLOORING IN HANGAR BAY B100

4 INSTALL (N) ACID-RESISTANT SHEET FLOORING - REVERSE SWING OF DOOR B117-A

5 INSTALL (N) ANTI-STATIC SHEET FLOORING

6 INSTALL (N) RUBBER FLOORING TO MATCH (E) AT REMAINDER OF ROOM

7 (N) DOWNSPOUT

8 (E) CONC. SIDEWALK TO REMAIN

9 (N) ASPHALT PAVING & COMPACTED FILL AS REQ. - SEE CIVIL.

10 (N) CONC. SLAB AS REQ. W/ COMPACTED FILL - INSTALL (N) FLOORING TO MATCH (E)

ADJACENT - VERIFY

11 PATCH & REPAIR (E) GWB TO MATCH (E) & REPAINT - VERIFY

12 REINSTALL (E) DOOR W/ (N) HARDWARE PER DOOR SCHEDULE

13 (N) WALL MOUNTED CONTROLS FOR (N) ELECTRIC OPERATOR AT (E) OVERHEAD DOOR - SEE

ELECT.

14 (N) WASH SINK - SEE MECH - LOCATE ON WALL CENTERED IN LOCATION OF PREVIOUS

COUNTER AND SINKS. PATCH, REPAIR, AND PAINT EXISTING ADJACENT SURFACES AS

REQUIRED TO MATCH EXISTING CONDITIONS. FIELD VERIFY ALL ADJACENT TOILET

ACCESSORIES ON WALL (MIRRORS, SOAP DISPENSERS, ETC.) AND REMOVE/REINSTALL IN

EXISTING LOCATIONS AS REQ.

15 (N) SOLID YELLOW STRIPE - CENTER IN DOOR OPENING - COORD. W/ FM, GOVERNMENT

16 (N) EXTERIOR SOLID YELLOW STRIPE - CENTER IN DOOR OPENING - EXTEND OUT ON (N)

APRONG TO EDGE OF (E) CONC. APRON - VERIFY - SEE CIVIL - COORD. W/ FM, GOVERNMENT

17 (N) SOLID RED STRIPE - MATCH ORIGINAL LOCATION, VERIFY PRIOR TO REMOVAL OF (E)

FLOOR COATING SYSTEM - COORD. W/ FM, GOVERNMENT

18 FLOOR PATCH & JOINT REPAIR WORK AT THIS AREA PRIOR TO INSTALLATION OF (N) FLOOR

COATING

19 PATCH REPAIR (E) CONC. AS REQ. TYP. AT ALL DAMAGED FLOOR AREAS - FIELD VERIFY

20 (N) EXP. JOINT - W/ SEALANT & BACKER ROD PER SEALANT MFR. - SEE DETAIL THIS SHEET

1/16" = 1'-0"A2.00

1 BLDG 25 FIRST FLOOR PLAN

FIRST FLOOR DOOR SCHEDULE

DOOR #

WIDTH X

HEIGHT DOOR TYPE FRAME TYPE FIRE RATING HARDWARE HEAD DETAIL JAMB DETAIL

THRESHOLD

DETAIL COMMENTS

B101-A 8'-0"X10'-0" O.H. MFR - 3 INSTALL (N) SWEEPS, SEALS & BAFFLES AS REQ. - COORD W/ DOOR MFR.

B101-C 8'-0"X10'-0" O.H. MFR - 3 INSTALL (N) SWEEPS, SEALS & BAFFLES AS REQ. - COORD W/ DOOR MFR.

B103-A 14'-0"X10'-0" O.H. MFR - 1 INSTALL (N) SWEEPS, SEALS & BAFFLES AS REQ. - COORD W/ DOOR MFR. -

INSTALL (N) SAFETY EDGE AND EYE SENSORS AND (N) POWERED OPERATOR

AND CONTROLS EA. SIDE OF DOOR - SEE ELECT.

B105B-A 4'-0"X7'-0" H.M. H.M. - 2 REINSTALL (E) DOOR W/ (N) HARDWARE

B107B-B 12'-0"X10'-0" O.H. MFR - 3 INSTALL (N) SWEEPS, SEALS & BAFFLES AS REQ. - COORD W/ DOOR MFR.

B109-A 8'-0"X7'-0" H.M. H.M. - 4 INSTALL (N) SWEEPS, SEALS @ EXISTING DOOR

B117-A 3'-0"X7'-0" H.M. H.M. - 2 REINSTALL (E) DOOR W/ (N) HARDWARE

B121-B 8'-0"X8'-0" O.H. MFR - 3 INSTALL (N) SWEEPS, SEALS & BAFFLES AS REQ. - COORD W/ DOOR MFR.

B128A-B 3'-0"X7'-0" H.M. H.M. - 2 INSTALL (N) HM DOOR & FRAME IN (E) WALL

FIRST FLOOR ROOM FINISH SCHEDULE - EXISTING UNLESS NOTED BELOW

ROOM

NUMBER ROOM NAME

FLOOR BASE NORTH WALL EAST WALL SOUTH WALL WEST WALL

CODED NOTESMAT FIN CLR FIN CLR MAT FIN CLR MAT FIN CLR MAT FIN CLR MAT FIN CLR

B100 MAINTENANCE HANGAR BAY HPC Install (N) high performance coating system over (E) conc. flooring

B101 TIRE SHOP FM1 Install additional (N) rubber mat flooring to match (E)

B103 TUG ACCESS HPC Install (N) high performance coating system over (E) conc. flooring

B104 AVIONICS SHOP AS Install (N) anti-static flooring

B107A MTL. TECH SHOP HPC Install (N) high performance coating system over (E) conc. flooring

B107B MTL SHOP HPC Install (N) high performance coating system over (E) conc. flooring

B109 NDI SHOP HPC Install (N) high performance coating system over (E) conc. flooring

B117 BATTERY SHOP ARS Install addtional acid-resistant flooring

B118 PNEUDRALIC HPC Install (N) high performance coating system over (E) conc. flooring

B118B PNEUDRALIC TRAINING

B119 ELECTRO ENVIRO SHOP HPC Install (N) high performance coating system over (E) conc. flooring

B122A TOOL RM BENCH STOCK

B122B TOOL CRIB HPC Install (N) high performance coating system over (E) conc. flooring

B125 WOMENS LATRINE

B126 MENS LATRINE

B127 BREAK ROOM GWB P1 Patch & repair (E) GWB walls as req. for (N) work

B129 TUG ACCESS HPC Install (N) high performance coating system over (E) conc. flooring

1/8" = 1'-0"A2.00

2 B127-BREAK ROOM REMODEL PLAN

1/4" = 1'-0"A2.00

3 B127 BREAK ROOM REMODEL ELEVATION

3" = 1'-0"A2.00

4 TYPICAL FLOOR JOINT REPAIR DETAIL

NO. DATE REVISION DESCRIPTION

Sheets
A2.00 - FIRST FLOOR PLAN