This document contains responses to questions regarding a federal solicitation for repair work on an Air National Guard hangar building. The solicitation seeks firm fixed-price proposals to repair hangar building 1201 at the 187th Fighter Wing in Montgomery, Alabama. Work includes removing and replacing mechanical systems, partially removing and replacing plumbing systems, replacing the metal retrofit roof and hangar floor slab, and modifying electrical systems. The estimated value is between $5 million and $10 million. The NAICS code is 236210 for commercial and institutional building construction. The small business set-aside requires the awardee be less than $39.5 million in annual revenue. A pre-bid conference and site visit were held on June 8, 2021 to brief requirements and answer questions. Proposals are due within 365 calendar days of award.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: 14 July 2021

To: CMSgt. William Hall

Subject: RESPONSES TO RFI #002

Project: F-35 – REPAIR HANGAR BUILDING 1201

Job #: ANG# FAKZ182352 / SSL# 18072

From: David Donovan

1) Question: P0.3. Can a deadman anchor system be used for the buried storgage tank as opposed to the ballast pad?

Response: No. Provide as indicated.

2) Question: Can all excavated dirt and concrete demo be removed from the base or is it required to remain on base?

Response: All excavated earth shall be removed from the base and disposed of in accordance with all applicable codes, regulations, etc…

3) Question: Please provide location of vent pipe required for Fuel Spill Containment Tank.

Response: Refer to Addendum No. 3.

4) Question: AM 01. Please issue the drawings provided with Am 01 as a full size separate file.

Response: Sheet M0.1 is attached to these RFI Reponses as requested. No changes have been made to the contents of sheet M0.1.

5) Question: Due to current building material market volatility, can this project be a firm fixed price with economic adjustments under the FAR clause 16.203-1?

Response: No. Bid in accordance with the current solicitation requirements.

6) Question: Spec 22 0000, 2.2, A.1 calls for underground sanitary & drain piping to be service weight cast iron. Is it acceptable to use Sch 40 PVC instead?

Response: No. Provide as specified.

7) Question: Spec 22 0000, 2.2, A.2 calls for above ground sanitary & drain piping to be no hub cast iron. Is it acceptable to use Sch 40 PVC instead?

Response: No. Provide as specified.

F-35 – REPAIR HANGAR, BUILDING 1201 FAKZ182352

RESPONSES TO RFI NO. 002 Page 2 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

8) Question: What type of piping material is required for the 4” underground fuel drain piping to the storage tank, shown on sheet P2.1? Is Sch 40 PVC acceptable?

Response: Refer to revised specification section 22 0000 issued as part of Addendum No. 3.

9) Question: Sheet P0.2 shows a “End of Main Drain Detail”. Is the 3” Sch 40 steel pipe intended to be a sleeve or is this installed in-line with pipe reducers?

Response: Design intent is for in-line piping with bushings as required.

10) Question: Sheet P2.2, note 7, calls for SS tubing with valve for NG-1 Nitrogen Generator. Please provide a spec on the tube and fittings required for this system.

Response: Refer to revised specification section 22 0000 issued as part of

11) Question: Sheet P2.2 shows the NG-1 Nitrogen Generator overlapping the tire cage.

The footprint of the Nitrogen Generator on the plans matches the size of the specified unit. However, in addition to nitrogen storage bottles that are part of the system, the manufacturer advises that several feet of clearance is needed for the generator. Please advise if any of these components can be or should be relocated, as this appears to require more than just field coordination and will impact that amount of SS tubing required for connection.

Response: Designed acknowledges potential conflict. Refer to revised drawing sheet P2.2 for revised notional configuration. Contractor will be required to field verify all dimension and coordinate equipment sizes and clearances for all equipment intended for installation with the manufacturer selected by the bidder to furnish the equipment required to meet the design intent and requirements.

12) Question: Sheet P2.1 shows a direct buried fuel spill storage tank. Is there a Civil or outside drawing showing where this is to be located in reference to the site? Is this a clear area or is there a concern that there may be existing utilities in the installation area? Is GPR required prior to excavation outside the building?

Response: Drawing sheet P2.1 is accurate regarding the location of the tank relative to required piping lengths etc… See screenshot below for overlay of the plumbing drawing with the existing base utility map. As indicated in the screenshot, the new plumbing and vent piping will cross one known existing water utility. The Government will locate utilities and provide a dig permit prior to excavation. Contractor will be required to pothole and verify depth of existing water utility in order to field verify and coordinate exact tank placement and depth to coordinate with existing water utility.

RESPONSES TO RFI NO. 002 Page 3 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

13) Question: The Air Compressor Schedule on sheet P0.1 calls for Ingersoll Rand RS22i air compressor, which an oil-flooded model. Spec 221519, 2.3 calls for the air compressors to be oil-free. Which is correct?

Response: Design intent is for an oil-free system in accordance with specification 22 1519. Refer to Addendum No. 3 for corrections to the compressor schedule.

14) Question: The Air Compressor Schedule on sheet P0.1 calls for the system to run at 140 psi. Spec section 221519, 2.3, A.5 calls for the system to run between 50 psi – 100 psi. Spec section 221519, 2.3, B.3. d & e calls for the system to run at 120 psi with the relief valve set at 140 psi. Which is correct?

Response: Refer to revised specification section 22 1519 included in Addendum No. 3.

15) Question: Spec 221519, 1.5, A calls for seismic qualification certificates. Is seismic bracing required on this system?

Response: Refer to revised specification section 22 1519 included in Addendum

16) Question: Spec 221513, 1.4, A. refers to seismic performance. What exactly is required for seismic on this system, as there are no piping details on the drawings.

Response: Refer to revised specification section 22 1513 included in Addendum

RESPONSES TO RFI NO. 002 Page 4 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

17) Question: On page A2.4 there are two diamond 4's going into the corridor at the bottom left side but 4's are left out on A3.5. Please advise.

Response: Refer to Addendum No. 3. Door 247A is intended to be a new door install in an existing opening system. Storefront tag has been removed from A2.4. Storefront type 4 at door 249 has been added to sheet A3.5.

18) Question: Please confirm who is to provide the required services of a Professional Roof Consultant. Specification sections 07 4113, 07 4293, and 07 5400 suggest the Government will provide these services. Section 07 4213 suggests these services shall be provided by the Contractor.

Response: Roofing consultant services shall be provided by the Contractor.

Refer to revised specification section 07 4113, 07 4293, and 07 5400 included in

19) Question: On the addendum plans on A3.1, what is the meaning of the Floor/Material column which all says ETR(should this say Not applicable)? Are we to ignore this column and figure all new floors per the Floor/Finish column?

Response: Floor Material column is intended to indicate substrate conditions.

ETR represents existing substrate intended to remain. Contractor to remove existing coatings (if present) and prep existing substrate as required to receive new specified floor finish material indicated in the finish column of sheet A3.1.

20) Question: On the finish schedule on A3-1, WP1 is indicated on Rms 110, 109D & 109C. but on the RCP A8.1 WP1 is only shown on 2 Rooms. Please Clarify?

Response: Refer to Addendum No. 1. A3.1 sheet was revised and location of WP-1 was corrected.

21) Question: On the finish schedule on A3-1, LVT1 is indicated on Rm 105. but on the Floor Pattern Plan A9-1, SSC1 sealed concrete is shown Room 105. Please Clarify Response: Refer to Addendum No. 1. A3.1 sheet was revised and floor finish for room 105 was corrected.

22) Question: Item 13.1 of the solicitation lists Johnson controls as Sole Source. Is JCI’s scope controls only, or all HVAC work?

Response: Intent of the limited source is for controls only so that new building controls systems can properly communicate with existing base energy management / DDC controls infrastructure.

23) Question: Item 13.2 of the solicitation lists Monaco controls as Sole Source. Is Monaco’s scope Fire Alarm only, or all fire suppression work?

Response: Intent of the limited source is for communication with the existing base fire department only. Fire alarm systems not manufactured by Monaco, provided they meet the requirements of the solicitation, are acceptable if they are compatible with the Monaco transceiver that is required to communicate between building 1201 and the existing base fire department.

RESPONSES TO RFI NO. 002 Page 5 of 11

24) Question: Does detail 15 S4.0 need dowels between the existing SOG and new footing?ign Response: No. Dowels are not required in the locations shown on detail 15/S4.0.

25) Question: On the reflected ceiling plan A8.3 are show 3 Big Ass fans. Are these three fans currently located as shown on this drawing and are these ETR items?

Response: Yes.

26) Question: 01 50 00-3. Spec requires installation of Government provided perimeter security warning signs along temporary fence. Please provide a quantity for the signs to be installed.

Response: Signage locations will be as directed on site by the 187th Security Forces Squadron. Signs will be Government Furnished for installation by the Contractor. A maximum of 15 signs should be anticipated.

27) Question: 32 05 33. Specification 32.05.33 required 365 days for groundcover establishment period. Being that we are installing sod, can this establishment period be reduced since it will be established soon after the sod has been placed and approved. This will help reduce the cost to the overall budget and eliminate unnecessary expenditures.

Response: Reviewer cannot locate specification section 32 0533 or the referenced 365 day establishment period in the solicitation documents.

Contractor shall maintain sod in accordance with section 3.05 of specification section 32 9223. Contractor shall guarantee installation in accordance with part

1.09 of specification section 32 9223.

28) Question: 32 05 33. Specification 32.05.33 requires the contractor to perform lawn maintenance for the duration of the 365-day establishment period. Being that we are installing sod and the facility has a current base wide lawn service, can this maintenance requirement be removed or reduced which will save the Government cost from paying the Contractor for work that is already currently under contract with a lawn care company.

Response: Reviewer cannot locate specification section 32 0533 or the referenced maintenance requirement in the solicitation documents. Contractor shall maintain sod in accordance with section 3.05 of specification section 32 9223. Contractor shall guarantee installation in accordance with part 1.09 of specification section 32 9223.

29) Question: Drawing Sheet A2.1. Please provide specification for the permanent fencing that must be installed.

Response: Refer to Addendum No. 3.

RESPONSES TO RFI NO. 002 Page 6 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

30) Question: Drawing Sheet A0.1. Please provide depth of proposed asphalt or minimum.

Response: Pavement patch to match existing pavement makeup – refer to detail 3/A0.1. Existing pavement makeup is estimated to be a 4” thick asphalt section.

31) Question: Drawing Sheet A0.1. Please clarify if temp. fencing will require a windscreen fabric to be installed.

Response: No.

32) Question: Drawing Sheet A2.2. Please provide inverts, elevation or depths for perforated underdrain pipe and solid pvc pipe.

Response: Exact depths to be field verified and coordinated on site. Curb inlet CI#5 discharges at elevation 200.58. Finished floor of the boiler room is +/- 203.

Contractor shall install new drainage system as required to maintain a maximum elevation of 6” below the boiler room slab for the perforated pipe, maintain required minimum slope on both perforated and solid pipe, and enter existing curb inlet CI#5 at or above an elevation of 201.08.

33) Question: 10 14 00 / A.17 & A1.8. Demo Note #20 says that "existing painted lettering to remain and be repainted. Prepare existing surfaces as required to install new painted lettering." Will the existing lettering remain and be re-painted or will new lettering be required?

Response: Existing painted lettering will remain and be re-painted. Contractor shall prepare existing substrate as required to ensure successful installation of new paint. Substrate preparation may require removal of portions of existing painted lettering where existing paint has failed or existing conditions would adversely affect the installation of new painted lettering.

34) Question: 10 14 00 - Section E. Section E of the Signage specs references "A" - the spec gives a description for the new cast aluminum lettering and says to refer to exterior elevations. When referring to exterior elevations, the note attached to the letter "A" on the drawing indicates to repaint existing letters. Is any exterior signage in this contract?

Response: Paragraph 2.0(E) of section 10 1400 describes the cast aluminum lettering intended to be installed adjacent to the new main entrance (door 159).

Refer to North Exterior Elevation (1/A4.1) for configuration of new cast aluminum lettering.

35) Question: 10 28 00 / A6.1 & A6.2. There is no accessory schedule on the enlarged restroom plans and the letters that are shown to indicate the type of accessory do not match up to the letters provided in the specification section. Please provide an accurate toilet accessory schedule to the plans.

Response: Refer to Addendum No. 1. This addendum revised specification section 10 2800 to properly coordinate with the accessories indicated on the drawings.

RESPONSES TO RFI NO. 002 Page 7 of 11

36) Question: 10 28 00 / A6.1 & A6.2. Accessory Type "P" on the plans indicated a sanitary napkin disposal in the Women's Restroom. This item is not listed in the toilet accessories spec. Please include on requested accessory schedule and add to specs if required for this project.

Response: Refer to Addendum No. 1.

37) Question: T3.0. A Towel Bar is shown in the Height Schedule on T3.0, but there is no specification for towel bars nor are they shown on enlarged plans A6.1 and A6.2.

Please include on requested accessory schedule and add to specs if required for this project.

Response: Towel bars are not required. Refer to Addendum No. 1 for the correct accessory schedule.

38) Question: 10 51 00. Specification Section is for HDPE Lockers, however in 2.05 LOCKER UNITS, note "G" says tops should be sloped plastic, but note "J" say s to fabricate sloped METAL tops, ends and closures. Plastic lockers generally have plastic tops. Please clarify whether sloped plastic or sloped metal tops are desired.

Response: Refer to Addendum No. 1. HDPE lockers were replaced with solid phenolic lockers and conflict in construction of sloped tops was corrected.

39) Question: 10 51 00. Section 2.02 LOCKER APPLICATIONS calls for lockers to be "recessed mounted. Section 2.05 LOCKER UNITS calls for them to be surface mounted. Please clarify whether lockers are to be recessed or surface mounted.

Response: Refer to revised specification section 10 5100 issued as part of Addendum No. 1.

40) Question: 05 16 50. A cut section of the building is required to better understand the design narrative. Can the engineer provide a cut section showing bearing conditions and top & bottom chords of the retro system?

Response: Refer to drawing sheet A2.7A (issued as part of Addendum No. 1) and drawing sheet A2.6. Sheet A2.6 indicates demolition details and new construction details for both roof eave condition and roof to wall transition condition (high side of roof) for both the base bid (TPO) and bid option (retrofit metal) roofing options.

41) Question: Please clarify if temp. fencing will be required along the North and East side of Building 1201 during the installation of the exterior improvements or will orange safety fence be sufficient.

Response: Temporary fencing will be required when existing permanent flight line security fencing is compromised and construction crews would have unimpeded access to areas on the secure side of the permanent flight line security fencing. Duration of required temporary fencing will be a result of Contractor’s means, methods, and scheduling. Orange safety netting would be acceptable for work on the non-secure side of the flight line security fence once

RESPONSES TO RFI NO. 002 Page 8 of 11 permanent fencing is in place provided the fencing is properly installed and deemed appropriate to adequately mitigate risk to Contractor and Government personnel.

42) Question: Will termite control be required for this project. If so, please include specification section.

Response: Termite control is not required.

43) Question: 02 83 13. Paragraph 1.06 D and E call out the testing company to be "independent". Is the intent here for the testing company providing air monitoring and clearance testing to be independent of the abatement contractor, ie a first tier sub to the GC?

Response: Yes.

44) Question: 07 00 00. Will Air Barrier testing and Thermography be required for this contract? If so, please issue spec section 07 05 23 pressure testing an air barrier system for air tightness Response: No. Air barrier testing and thermography will not be required.

45) Question: Sheet A7.1 detail 4. Detail 4 shows us that there are (2) Vending Machines to be CF/CI. These vending machines are not included as part of the Spec Section 11 Residential Equipment. Please provide a type and size for these vending machines.

We have no basis to provide pricing.

Response: All vending machines are intended to be Government Furnished/Government installed (GFCI)

46) Question: Sheet A7.1 detail 4. Is the bidding contractor required to stock the vending machines as part of the base bid? Does the base have a vendor to stock the vending machines?

Response: All vending machines are intended to be Government Furnished/Government installed (GFCI)

47) Question: Sheet M0.1 and Sheet M0.2 Mechanical Schedules. On the mechanical schedules, pages M0.1 and M0.2, some of the equipment has a specific basis of design or a specific Manufacturer listed. Some Mechanical equipment does not have a basis of design or a manufacturer listed, just performance information. If a piece of mechanical equipment has a Basis of Design or a specific manufacturer listed, is the bidding contractor required to use that Basis of Design or Manufacturer for this project?

Response: No. Any equipment meeting listed performance criteria will be considered.

48) Question: DDC Controls General Question. Please provide the specific contract for Johnson Controls to help us secure DDC controls pricing for this project.

Response: Dan Taylor, Account Executive. 205-682-3972.

RESPONSES TO RFI NO. 002 Page 9 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

49) Question: Sheet M1.3 & M1.4, Sheet Note 2. This note tells us to provide a pre work

"TAB" to record diffuser airflow at VAV box Maximum cooling. Will this report need to be submitted to the government prior to installing the new equipment or at the end of our project with the test reports and O and M Manuals?

Response: Submit the report to the Contracting Officer upon completion of the testing.

50) Question: Overall timeframe. The contract gives us 365 calendar days to construct this project. Would the government consider additional time as lead time for materials such as roofing materials and steel are running longer than usual?

Response: No. It is the Government’s expectation that 365 calendar days is sufficient to complete the work.

51) Question: Spec Section 01 3000 Administrative Requirements. Please confirm that a separate Superintendent and a separate Quality Control Manager are required for this project and that the Superintendent cannot act as a dual hat?

Response: Confirmed. The intent is to have a separate and dedicated quality control manager. The superintendent may not act in this capacity.

52) Question: Spec Section 01 3000 Administrative Requirements. Is a separate Site Safety and Health Manager Required for this project or can the QC manager act as the SSHO?

Response: No as separate SSHO is not required. The Quality Control Manager may also act as the SSHO.

53) Question: General. Should the Contractor consider the Install of the FFE package by the government as part of the 365 calendar days of construction or will the installation of FFE take place after the 365 calendar days Response: No. The 365 day duration will be from notice to proceed until beneficial occupancy. The FFE installation will occur following beneficial occupancy.

54) Question: Spec Section 01 5000 paragraph 1.06 fencing. We are to provide two types of temp fencing for this project, 6' high fencing around the construction site with vehicular and pedestrian gates and Flight line security fencing. Can the 6' high fencing around the construction site be installed in phases as we work around the building to help overall costs or does the contractor need to plan for the entire building to be surrounded by temp fencing for the duration of the project?

Response: Temporary fencing can be installed in phases. It shall be the Contractor’s responsibility to ensure site safety/protection and erect temporary fencing/barricades as required to protect the site, the contractor’s materials/equipment, and prevent access to potentially hazardous areas of the construction site by the base population. In addition, the Contractor shall also erect and maintain flight line security access fencing to prevent unimpeded access to the flight line by Contractor personnel for the duration of the project.

RESPONSES TO RFI NO. 002 Page 10 of 11

The location and duration of each required fence will be considered Contractor’s means and methods and phasing/relocation of the fencing will be acceptable. However, the Contractor shall comply with base security forces and safety officers at all times and erect fences and barriers to mitigate safety and security risks if identified by the Government. The Contracting Officer will provide direction to the Contractor if safety or security risks are identified by Security Forces or the Base Safety Office.

55) Question: Spec Section 01 5719 Paragraph 3.02 Building Flush Out. Paragraph 3.02 letter A. States "Testing Option": Engage testing agency to perform satisfactory air contaminant testing. Is this an option the contractor can elect to perform or is this required 3rd party testing for air contaminants that the contractor must carry costs for?

Response: Air testing is an acceptable alternative to building flush out. The Contractor may elect to hire a testing agency to conduct air contamination testing prior to conducting a building flush out. If air contamination testing documents acceptable contamination levels, the building flush described in section 3.02 will not be required. If higher than allowable air contamination is detected during testing, a building flush out and re-testing will be required. The Contractor shall bear the cost of all air contamination testing.

56) Question: Spec Section 01 5719 Paragraph 3.01 Construction Procedures. Paragraph

3.01 Letter D. States that the use of HVAC equipment and ductwork for ventilation during construction is not permitted. Is this statement for the new HVAC equipment that is to be installed or the existing HVAC equipment? If this statement pertains to the equipment that is to remain in place for this contract, bring in temp heat and air for a facility this size will add significant costs to the overall budget over the course of a year.

Response: The intent of this is to prevent existing and new systems from being used for construction ventilation. Existing and new systems may be operated to regulate temperature and humidity provided adequate filtration of each system is provided. Contractor shall provide dedicate point of use ventilation systems to adequately ventilate construction activities (i.e. welding, sanding, etc…).

57) Question: Utilities General Question. Is the contractor required to pay for any privatized utility work to be done on this contract? Example, install of water line 5' outside the building, installation of gas line and gas meter to 5' outside the building.

Response: All utilities are owned and operated by the 187th Fighter Wing. Any exterior utility infrastructure modification indicated on the drawings shall be the Contractor’s responsibility and should be included within the Contractor’s cost proposal.

RESPONSES TO RFI NO. 002 Page 11 of 11 Seay Seay & Litchfield, P.C. 14 July 2021

58) Question: What will the new (alternate) metal roof slope be at drawing details 3/A2.6, 4/A2.6 & 7/A2.6? This information is required to determine the volume of spray foam to be installed.

Response: The design intent is to match the slope of the existing standing seam metal roof assembly. However, the Contractor shall coordinate the existing conditions with the metal roofing system manufacturer to ensure the manufacturer’s minimum slopes required to furnish all specified warranties are maintained.

59) Question: M1.1: Note #5 & 12: the demo plans & new work plans do not seem to be the same. We can not determine the intent. The plan notes do not correspond to plans Note # 8 : provide louver sizes & schedule #10 : provide existing louver sizes #11 : provide opening sizes required

Response: Refer to Addendum No. 3. Notes 5 & 12 have been clarified in the revised plan. Contractor to field verify existing louver sizes.

60) Question: M1.2: Provide new louvers sizes in 3 locations Response: Contractor to field verify existing louver sizes.

61) Question: M3.2: Provide info for CV-5 Room 118. Verify louver size LV-5 louver is 60 x 48 ductwork to louver is 4” Room 117.

Response: Refer to Addendum No. 3, louver size has been clarified.

End of Response to RFI #002

Attachments:

- M01.1 – Mechanical Schedules, Legend, Abbreviations, and Notes