This document outlines the HQ AMC-Level Protest Program, which is an alternative dispute resolution forum for addressing complaints related to U.S. Army Materiel Command procurements. The program encourages interested parties to resolve concerns internally within AMC rather than escalating protests to the General Accounting Office or other external forums. Protests must be filed within the timeframes specified in FAR 33.103 to be considered timely. Contract award or performance is suspended during the protest period to the same extent and duration as protests filed at the GAO, with AMC aiming to resolve protests within 20 working days from filing.

Protests (other than those directed to the contracting officer) should be submitted to the Headquarters U.S. Army Materiel Command, Office of Command Counsel–Deputy Command Counsel, located at 4400 Martin Road, Room A6SE040.001, Redstone Arsenal, AL 35898-5000. Submissions can be made via fax at (256) 450-8840 or email at usarmy.redstone.usamc.mbx.protests@mail.mil. The complete AMC-level protest procedures are available on the command counsel website at http://www.amc.army.mil/amc/commandcounsel.html, or protesters without internet access may contact the contracting officer or HQ AMC directly to obtain the procedures.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HQ AMC-LEVEL PROTEST PROGRAM

If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible contracting officer. However, you can also protest to Headquarters, AMC. The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the General Accounting Office or other external forum.

Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103.

Send protests (other than protests to the contracting officer) to:

• Address:

Headquarters U.S. Army Materiel Command Office of Command Counsel- Deputy Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898-5000

• Fax: (256) 450-8840

• Email: usarmy.redstone.usamc.mbx.protests@mail.mil

• The AMC-level protest procedures are found at:

Web Address: http://www.amc.army.mil/amc/commandcounsel.html

If Internet access is not available contact the contracting officer or HQ, AMC to obtain the AMC-Level Protest Procedures.