This document contains a consolidated list of questions and answers related to solicitation W15QKN-21-R-5005 for base operations services at Picatinny Arsenal. The solicitation seeks maintenance and operations services across several contract line item numbers, including preventative maintenance, demand maintenance, project work orders, other direct costs and materials. Offerors are to price requirements using the provided pricing matrix template by labor category without breaking out subcontractor pricing. The incumbent contractor may use their own CMMS system to supplement the Army's GFEBS system. Anticipated revisions to technical exhibits will not delay the extended proposal due date of 6 May 2021.

View the file

Other files

File Type Posted
Recommended Sol Closing Instruction_PicaBASOPS_20210507.doc DOC document
W15QKN21R5005_Amendment 0006.docx DOCX document
DD Form 1423-1-A018 (Tree Srvc-Maint PMP)-REVISED.pdf PDF
Consolidated List of Questions (for publication) AMD 0006.xlsx XLSX spreadsheet
DD Form 1423-1-A041 (Scheduled Pest Inspections-Work)-NEW.pdf PDF
DD Form 1423-1-A003 (QCP)-REVISION 01.pdf PDF
DD Form 1423-1-A022 (Real Property Records Updates)-NEW.pdf PDF
012.1-CBA-Picatinny_ 2018_2021.pdf PDF
TE 3.9 Athletic Field Maint Requirements_Rev1.doc DOC document
W15QKN21R5005_Amendment 0005.docx DOCX document
DD Form 1423-1-A013 (Damage Report)-REVISION 01.pdf PDF
TE 3.5 Picatinny Owned Lights on Base as July 22nd_Rev1.xlsx XLSX spreadsheet
DD Form 1423-1-A028 (Key Control-Inventory)-NEW.pdf PDF
DD Form 1423-1-A038 (Daily Log of Chiller Inspection)-NEW.pdf PDF
011-DD Form 254-NEW.pdf PDF
7.7-Preventative Maintenance Checks and Services_AR 58-1-NEW.pdf PDF
7.6-LRC Picatinny Maintenance SOP 2020-NEW.pdf PDF
TE 2.5 IDS Zones by Bldg_Rev1.docx DOCX document
08.1-Davis Bacon Wage Determination-Building-REVISION 01 (NJ20210038-1 Jan 21).pdf PDF
DD Form 1423-1-A017 (Dispute Contingency Plan)-REVISED.pdf PDF
DD Form 1423-1-A037 (Lab Water Analysis Report)-NEW.pdf PDF
DD Form 1423-1-A019 (Records-All Monthly Maint Activity)-NEW.pdf PDF
TE 7.3 LIST OF UPS SYSTEMS FOR PREVENTIVE MAINTENANCE_Rev1.XLS XLS spreadsheet
TE 2.7 Kitchen Equipment 20200610_Rev1.xlsx XLSX spreadsheet
DD Form 1423-1-A014 (Spill Plan)-REVISION 01.pdf PDF
DD Form 1423-1-A018 (Tree Srvc-Maint PMP)-NEW.pdf PDF
09-Service Contract Act (SCA) Wage Determination-REVISION 01_20201221.pdf PDF
DD Form 1423-1-A012 (Affirmative Procurement)-REVISION 01.pdf PDF
7.5-Dispatching Procedures-NEW.pdf PDF
012-CBA Wage Determination-DOL Cover Letter.pdf PDF
0004 Technical Exhibit List of Picatinny Historic Buildings Use and Distribution_Rev1.pdf PDF
DD Form 1423-1-A009 (Safety Plan)-REVISION 01.pdf PDF
9.3-Picatinny Staffing Matrix-REVISION 01.XLSX XLSX spreadsheet
DD Form 1423-1-A006 (Physical Security-GFP)-REVISION 01.pdf PDF
DD Form 1423-1-A005 (Key Personnel)-REVISION 01.pdf PDF
DD Form 1423-1-A027 (Utilization of GFF Plan)-NEW.pdf PDF
07 - Price Matrix (Sanitized)-REVISION 01.xlsx XLSX spreadsheet
DD Form 1423-1-A032 (Storm Water Mgmt System Maint Plan (SWMSMP))-NEW.pdf PDF
DD Form 1423-1-A026 (Quality Control Report)-NEW.pdf PDF
06-PRICING Matrix-REVISION 01_20210310.xlsx XLSX spreadsheet
TE 3.14 Gate Locations_Rev1.docx DOCX document
DD Form 1423-1-A031 (Storm Water Collection System Maint Work Plan)-NEW.pdf PDF
DD Form 1423-1-A007 (Key Control)-REVISION 01.pdf PDF
TE 2.2 Attachment A Equipment List_2020_Rev1.pdf PDF
DD Form 1423-1-A036 (Quarterly Visual Insp Report)-NEW.pdf PDF
011.1-USAG Picatinny VGSA-DD 254 Continuation Sheet.docx DOCX document
DD Form 1423-1-A042 (Pest Management License and Certifications)-NEW.pdf PDF
DD Form 1423-1-A024 (Disaster Contingency Plan)-NEW.pdf PDF
DD Form 1423-1-A035 (Wastewater and Storm Water Systems Safeguarding Plan)-NEW.pdf PDF
DD Form 1423-1-A004 (Accident Reporting)-REVISION 01.pdf PDF
Show 40 more

Latest 50 of 121 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Post 20210303 thru 20210319

RFP or PWS SectionThe ProblemQUESTIONANSWERS
RFP or PWS SectionThe ProblemQUESTIONANSWERS
Attachment 1-CLS 501 Heating and Cooling Services 9.2.2Regarding the effort to configure the central monitoring station and install Delta controls/routers1) Which assets are considered "non-ESPC" that require relocation by the contractor?

2) The PWS indicates that currently only about 40% of listed assets currently have controls installed. Is the Government requiring the incoming contractor to install controls on the remaining 60%?

3) Will the relocation of existing controls and the installation of new controls be accomplished via project work orders?1) All equipment listed in the TE is considered non-ESPC. 2) Yes 3) Yes, this work will most likely be issued on a PWO.
Attachment 1-CLS 501 Heating and Cooling Services 2.15In the Q&A the Government stated they intend to have all buildings under central control.Are the controls to be furnished and installed by the ESPC contractor or will it be the responsibility of the BOS contractor?Congruent with the above question, yes the scope of the BASOPS solicitation does include the requirement to install controls within the remaining 60% of buildings. However, the intent is to request a proposal from the successful contract awardee, then negotiate and issue this requirement on a stand-alone task order.
Paragraph 1.7 Page 29Utility Locations. The Government has indicated the contractor is responsible for all utility locates and excavation permits.Will the Government provide historical or estimated workload regarding the number of locates and permits that may be required each year?There were approximately 380 location requests submitted in calendar year 2020. However, this information cannot be relied upon to determine future requests.
Q&A published 3 March 2021The answer to the question on row 260 stated that all materials for snow and ice removal is the contractor's responsibility under a reimbursable materials CLIN.What is the delineation of the type and purpose of materials that can be charged under the Cost Reimbursable CLIN? What types of material must be included in the offerors FFP? What type of materials can be included in the Cost Reimbursable CLIN?Any materials consumed for an individual repair/response less than $1000 will be costs included as part of the work order. Material costs above $1000 will have material invoices submitted to the COR, which may be reimbursed on the materials CLIN in Section B.
Price MatrixCBA Rates TabIs it the governments intent to include the health, benefits, & pension funds in the health & welfare cell of the “CBA Rates” tab in the price matrix?Yes please. That is the intent.
Price MatrixCBA Rates TabThe formula to compute health & welfare is referencing cell Lll, should it be referencing cell L9? Should the offeror be inputting the H&W rate into L11 or L9?Please input the data into cell L11.
Price MatrixMaterial - CLIN X003 TabCan the government please provide an example of what is needed in columns A, B, and C of the “Material – CLIN X003” tab?Material costs are no longer being required with proposals. Instead, the awarded contract will include a cost reimbursable materials CLIN, to be addressed post-award. All material quotes over $1000 must be submitted to the PCO/COR for disbursment of funds.
Price MatrixMaterial - CLIN X003 Tab & Summary TabWhat is the difference between level 1 and level 2 of the Sub-CLIN X003AA and Sub-CLIN X003AB?The price matrix will be revised in order to remove any reference to "Levels".
Price MatrixMaterial - CLIN X003 Tab & Summary TabIs it the intent that the offeror include only the costs to complete the additional duties required for capability 1 & 2 in the SUB-CLINs X003AC and X00AD; or should the costs for Sub-CLIN X003AA also be included in these Sub-CLINs and added to the additional cost?Capability 1 and 2 have been removed from the price matrix. All corresponding SubCLINS have also been removed. Please submit all PMO and DMO work under CLIN X004, as capability level 3.
ASSIST22 Company appointed ASSIST Individuals for ENsCan the Gov't clarify where/location in Volume I does this goIt can be submitted within TAB B. Paragraph L.6.1.1.2 has been amended to reflect this instruction.
C 1.5Grounds Maintenance for TreesCan the Gov't please clarify which CLS this should fall under for pricing and organizational purposes.There is no specific CLS. This requirement falls under the overarching PWS.
Staffing MatrixOverarching PWS 1.8-1.8.6 TabCan the Gov't please clarify if this is the correct PWS reference as we are unable to locate paragraph 1.8.The staffing matrix will be revised to remove this reference.
Price MatrixPrice MatrixWhere does the government intend for the offeror to price subcontractor costs within the price matrix?Include the subcontractor prices within the proposed prices. Offerors are not required to break out the subcontractor prices. See additional pricing related Q&A below for additional details.
Overarching PWS.1.Is it the contractor's responsibility to receive their materials or is that a duty of the logistics contractor?The BASOPS contractor will be responsible for procuring all materials needed to perform under the BASOPS scope.
Amendment 0001Past Performance QuestionnaireIs it required to submit another PPQ using the changed PPQ from Amendment 0001 if we have already sent them in?No. We can work with the original format.
Section C Paragraph 2.3.3GISCan the Government provide the estimated annual workload for GIS?Thre were approximately 35 servicing request for GIS in calendar year 2020. However, this information cannot be relied upon to determine future requests.
Section C Paragraph 2.3.6CAD SupportCan the Government provide the estimated annual workload for CAD?Thre were approximately 315 servicing request for CAD in calendar year 2020. However, this information cannot be relied upon to determine future requests.
CLS 501 Heating and Cooling Services PWS Paragraph 2.2, Section J Attachment 10 (CBA)Heating and Boiler Plant StaffingReferenced paragraph 2.2 indicates that the Contractor shall provide boiler operators. The CBA does not list a boiler operator classification. Is there an addendum to the CBA adding the Boiler Operator classification to the CBA?This labor category would fall under the service contract act (SCA), rather than a CBA.
CLS 501 Heating and Cooling Services PWS Paragraph 6.1Normal Business HoursReferenced paragraph 6.1 lists normal business hours as Mondays through Fridays, 6:30AM - 5:00PM which conflicts with normal business hours listed in Overarching PWS which indicated normal business hours of 7:00AM - 4:00PM. Can the Government please clarify what are the normal business hours?The correct hours are 7:00AM to 4:00 PM.
Section J Attachment 10 (CBA), CLS 411 Facility Maintenance - Vertical Paragraph 2.3 HVACRHVACR StaffingReferenced paragraph 2.3 lists various components for maintenance and repair typically performed by HVAC Mechanics, however the CBA does not list a HVAC Mechanic classification. Is there an addendum to the CBA adding the HVAC Mechanic classification to the CBA?These labor categies would fall under the service contract act (SCA), rather than a CBA.
L.6.1.2.2 TAB B,SUBFACTOR 2: WORKFLOW EXECUTION"This is such a broad statement, is it the Government intent that we speak to every maintenance services workload or only as it applies to subset a- Preventive Maintenance Plan and subset b- Demand Maintenance Plan? If we must speak to every maintenance service, it appears to be missing from Section M and could the Government provide details on how they will be evaluating our proposal "The parameters of the proposal submission and evaluation are encapsulated within Sections L&M, respectively. All information required to be included in the PMP and DMP can be located within the Overarching PWS, ancillary PWS's, or the Technical Exhibits. Please take care to follow the references called out in paragraph L.6.1.2.2.
Picatinny CBA with Local 68, Engineers UnionThe Department of Labor declared on 27 Aug 2020 that the actuary certified that the Local 68 Pension Plan is in 'endangered status,' reflecting that the funded percentage is less than 80%.Is the Government planning to offset the risk of an endangered pension plan by compensating the contractor for future liabilities?No. The Government is not endorsing or suggesting any CBAs be established with any particular labor union, or any union at all. The decision to use union labor (or not) is left up to the successful BASOPS awardee.
Gov Q&A responses #112 & #289.The Gov responses/answers to these two GFEBS related questions appear to contradict. As a response to question 112, the Gov states that the offeror can choose to dual hat the two embedded "GFEBS Liaisons" directed in PWS para 2.1.12.1 with the "GFEBS Service Order Dispatchers" identified in PWS para 2.2.2.4.2 (DMO Service Call Desk). Conversely, as a response to question #289, the Gov acknowledges that the GFEBS liaisons embedded in Bldg. 3002 are 'in addition to' the Service Order Dispatchers noted in para 2.2.2.4.2. However, para 2.2.2.4.2. states that the "GFEBS Service Order Dispatchers...will be embedded in building 3002." Since these two positions are being directed by the Gov, we do not see that we have a choice to dual hat or reassign them to work beyond the embedded requirement.Can the Gov clarify whether the requirement for (2) embedded "GFEBS Liaisons" (para 2.1.12.1) is the same as the requirement for (2) "GFEBS Service Order Dispatchers" (para 2.2.2.4.2) also directed as embedded positions in bldg. 3002? In other words, the requirement is for a total of (2) embedded positions? If the GFEBS Service Order Dispatchers are intended by the Gov to be aligned with the contractor established "DMO Service Desk," then shouldn't offerors assume those to be distinctly different functions; operating in different locations (Bldg. 3002 & the Contractor Service Order Desk)?Staffing decisions such as these are left up to the individual offeror to determine.
Price Matrix AttachmentClin XX3 has the breakdown for Capability 3 Maintenance into two parts (Level 1) and (Level 2). We do not see in any of the attachments the differences in regulation for Level 1 vs Level 2.Will the government provide clarity between these Two Levels? Or What is the Army Regulation that provides guidance on the Work Capability Levels?The price matrix will be revised in order to remove any reference to "Levels".
CBAHas the existing contractor received or requested an audit from the pension Trust Funds as to the financial status, health and strength of their trust funds (and have they ever received any notices from the Trust Funds in the last 3-5 years related to health and strength of their funds)?No. This appears to be business that is solely within the incumbent contractors purview. The Government would not be involved.
CBAWill the Government be responsible for any withdrawal liability as part of the regular reimbursement for expenses/labor (assuming the Company complies with all fund contribution requirements)?No. Such negotiations are entirely between the labor union and the BASOPS contractor. The Government does not get involved.
Attachment 1-CLS 501 Heating and Cooling Services
Please confirm that only a handful of buildings return steam condensate to their boilers while the remainder go to drain or dump on the ground.Confirmed.
Attachment 1-CLS 501 Heating and Cooling Services
Please confirm that none of the steam systems use corrosion inhibiters.Confirmed.
Attachment 6 - Price Matrix Attachment.xlsQ&A released on 3/3/2021 (Row 220) stated that "Offerors are not required to breakout the subcontractor prices…" in regards to the details of holidays, vacation, etc. Q&A released on 3/15/20201 (Row 9) contradicts the previous Q&A's and requires the same level of detail for the subcontractor as prime contractors.This type of cost data (direct labor, fringe, etc.) is proprietary to each company. Please confirm if the prime contractor is required to request this type of proprietary cost information from the subcontractor, or if the answer to the 3/3/21 Q&A should be followed where the subcontractor cost break out is NOT required.Offerors are required to propose one fully loaded labor rate per labor category but do not need to identify whether it is the prime or subcontractor by labor category. However, if SCA or CBA labor categories are proposed the same level of detail for the prime is required for the subcontractor. This level of detail is as well required for future SCA or CBA (if CBA is applicable) wage determination adjustments. If the subcontractor will not provide the level of detail required to the prime they may submit it directly to the Government.
Attachment 6 - Price Matrix Attachment.xls'CBA Rates' tab, 'SCA Rates' tab, andThe CBA, SCA and Exempt Rate tabs appear to conform to how the prime contractor should provide calculations of their fully loaded rates. It does not, however, conform to how prime contractors should provide a rate for subcontractors. Is the Prime contractor allowed to modify how the cost information is input into the CBA, SCA, and Exempt Rate tabs for subcontractor costs? This may include NOT filling in Holiday, vacation, and sick hour and cost data as it may be proprietary data to the subcontractor.Include the subcontractor prices within the proposed prices. Offerors are not required to break out the subcontractor prices.
06 - Pricing Matrix AttachmentSubcontract PricingAre subcontractors required to provide the same cost detail as the Prime?Subcontract effort shall be included in the appropriate labor categories for CLINs X002, X003 and X004 and the same level of detail as reflected in the price matrix shall be provided. Any subcontract effort in regard to CLIN X0006 - PWO/OWO will be proposed under future task orders when solicited. No subcontract effort shall be included in CLIN X008 Other Direct Costs (ODCs).
“21R5005 BASOPS Consolidated QAs-20210315 (pricing) published.xls”, row 36Government Answer in cell D36 indicates “Yes, section B will be amended to match the CLIN structure within the price matrix. Language in Section L.6.1.1 will also been revised to match the significant figure (to the hundredths place) in Section M. Aside from this correction, Offerors are to submit all pricing in the Price Matrix and not Section B.”With respect to the last phrase, will the government confirm that offerrors are to submit both the completed Pricing Matrix and Section B?Only the price matrix is to be completed and submitted with the proposal. Section B will only be used at the time of contract award.
TE 2.1 Government Furnished Property (GFP) and Section C – Performance Work Statement – Overarching, Paragraph 7.4 and 7.5.2; W15QKN-21-R-5005 BASOPS Consolidated QAs-20200303 (published)Per the Q&A response in row 239, the government will revise 7.5.2 to: "The Contractor shall provide all facilities, vehicles, equipment, parts, tools, fuel, oil, materials and any other items required to perform all Contract requirements that are not otherwise provided as GFM, GFP, GFE, and GFF as defined in PWS section 7.4."Does the current contractor provide its own vehicles or equipment to supplement the GFP listed in TE 2.1? If so, what does it provide?This is up to the contractor to determine. It should be noted that there will be no Government furnished vehicles or equipment dedicated to the HVAC requirement of the contract.
W15QKN-21-R-5005 BASOPS Consolidated QAs-20200303 (published), rows 104, 116The government responses indicate that a contractor may use their own CMMS system to supplement GFEBS.Is there currently third party connectivity in place to support a contractor using its own CMMS? Is third party internet service currently connected to the applicable facilities?There is no third party connectivity involved. The CMMS (now referred to as AEMS) is connected through Picatinny's organic local area network.
Anticipated Amended Technical ExhibitsThe Government stated in the last consolidated Q&As that Industry would receive revised Technical Exhibits in a future amendment.In order to incorporate additional requirements, work load data, etc. contained within these files, would the government please consider extending the proposal due date until mid-April?Solicitation has been extended through 06 May.