Questions and Answers 7 RFP W15QKN-21-R-0034.pdf

PDF 133 KB Posted

Attached to
M121 120mm Carrier Mounted and M120A1 120mm Ground Mounted Mortar Systems
Solicitation number
W15QKN21R0034
Issued by

About this file

This document contains questions and answers regarding solicitation number W15QKN21R0034 for the manufacture and production of M121 120mm Carrier Mounted Mortar Systems and M120A1 120mm Ground Mounted Mortar Systems. The U.S. Army Contracting Command - New Jersey is seeking to award a single firm-fixed price, indefinite delivery indefinite quantity contract with a total estimated ceiling of $49.2 million over five one-year ordering periods. The scope of work involves the production of 120mm M298 Mortar Cannons, 120mm Mortar Stowage Kits, and kitting of government furnished property items into complete assemblies and kits. Technical data is marked as Distribution Statement D and interested contractors must complete non-disclosure and technical data agreements to receive technical data packages from the Project Manager for Combat Ammunition Systems.

View the file

Other files

File Type Posted
W15QKN21R0034-0003.pdf PDF
Questions and Answers 11 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 10 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 10 MWS RFP W15QKN-21-R-0034.docx DOCX document
Questions and Answers 9 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 8 RFP W15QKN-21-R-0034.pdf PDF
Attachment 0001 Price Matrix - 23SEP2021.xlsx XLSX spreadsheet
W15QKN21R0034-0002.pdf PDF
Question and Answers 6 RFP W15QKN-21-R-0034.pdf PDF
W15QKN21R0034-0001.pdf PDF
Questions and Answers 5 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 4 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 3 RFP W15QKN-21-R-0034.pdf PDF
Attachment 0008 - Past Performance Questionnaire_Rev 1.docx DOCX document
Questions and Answers 2 RFP W15QKN-21-R-0034.pdf PDF
Questions and Answers 1 MWS RFP W15QKN-21-R-0034.docx DOCX document
CDRL A004- Report_Production or Delivery Problem(s) SOW Risk Assessment.pdf PDF
CDRL A018- Accident Incident Report.pdf PDF
CDRL A005-Suppliers Configuration Management Plan.pdf PDF
Attachment 0004 - AMSTA-AR Form 1350 Technical Data Request Questionnaire.pdf PDF
Attachment 0006 - Certificate of Destruction.DOC DOC document
CDRL A006-Engineering Change Proposal (ECP).pdf PDF
CDRL A011- Production Status Report.pdf PDF
CDRL A019- Failure Summary and Analysis Report.pdf PDF
Attachment 0010- Live Fire Testing Government Furnished Property (GFP) List.docx DOCX document
CDRL A010- Integrated Program Mgmt Data and Analysis Report (IPMDAR).pdf PDF
CDRL A002-Status of GFP Report.pdf PDF
CDRL A026- Critical Item Characteristic List (CICL).pdf PDF
CDRL A013- Test Inspection Report (Rework).pdf PDF
CDRL A007-Notice of Revision (NOR).pdf PDF
CDRL A016- Measurement System Evaluation (MSE).pdf PDF
Attachment 0002 - NonDisclosureNonUseAgreement.docx DOCX document
CDRL A020- Safety Assessment Report (SAR).pdf PDF
CDRL A021- Record of Meeting.pdf PDF
CDRL A017- Certification Data Report.pdf PDF
Attachment 0001 120mm MWS Price Matrix.xlsx XLSX spreadsheet
Attachment 0003 - DD2345 Military Critical Technical Data Agreement.pdf PDF
CDRL A012- Test Inspection Report.pdf PDF
Attachment 0011 - Demilitarized Items.docx DOCX document
Attachment 0005 - AMSTA AR Form 3002 Clearance of Technical Information for Public Release.pdf PDF
CDRL A008-Specification Change Notice.pdf PDF
CDRL A001-Quality Deficiency Report (QDR).pdf PDF
CDRL A023- Technical Report - Study-Services.pdf PDF
Attachment 0008 - Past Performance Questionnaire.docx DOCX document
CDRL A025- Critical Plan of Action (CPOA).pdf PDF
CDRL A009-Request for Variance (RFV).pdf PDF
CDRL A015- Quality Program Plan (QPP).pdf PDF
Attachment 0009- Mortar Weapon Systems Parts.docx DOCX document
CDRL A024- Critical Characteristics Control Plan (CCCP).pdf PDF
W15QKN21R0034.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers #7 submitted in response to RFP W15QKN-21-R-0034

46. Section A/ #8 : Watervliet Arsenal states “ Watervliet Arsenal (WVA) is the current Mortar Cannon producer and will continue to produce the 120mm M298 Cannon, in accordance with the Arsenal Act (10 U.S.C. Section 4532). The Mortar Cannons may be provided as Government Furnished Property (GFP) or purchased on this contract under CLINs 0040 0046.”

Can USG provide contact information for the POC at Watervliet that potential offerors can contact for M298 Cannon pricing?

Can USG provide historical pricing for the M298 Cannon Assembly?

A:

Watervliet Arsenal POC:

Wayne Baumgartner Industrial Specialist / Program Manager Wayne.M.Baumgartner.civ@mail.mil Office: (518) 266-4326

No historical pricing will be provided. Per question 16, The USG expects the Offeror to have a production source (internal or external) for the 120mm M298 Cannons.

47. In response to Question 28, the USG has answered that yes, that CLINs 1 and 8 is to include the cost for FATs for the major subassemblies. Therefore, in the event the USG executes CLINs 1 and 8, the USG will end up paying twice for baseplate, bipod, barrel assembly FATs. And further, if for example, the USG additionally executes CLIN 21, the USG will end up paying 3x for the baseplate FAT. Is this what is intended?

A: The CLIN pricing is needed since there is an unknown about which FAT CLIN may be exercised first. If a USG approved FAT for an item is still valid (per TDP), no additional FAT will be required and only production CLINs will be exercised.

48. Section L.2.3.1(c) says, As a requirement under the 120mm Mortar Weapon System solicitation, all Offerors must submit Reps/Certs data into the System for Award Management (S.A.M.) https://www.sam.gov and provide one (1) hard copy and one (1) electronic copy (on CD) submitted as an .XPS file. Can we submit this information in PDF instead of an .XPS file?

A: You may submit the information in PDF, in accordance with Section L.2.3.1(b), “Alternatively, files may be provided in Portable Document Format (.pdf).”

49. After reading C.3.6 through C.3.7 I have concluded that we are to work through the LMP system to “pull” inventory as we require to meet schedules. So will it be up to us how much inventory we have to store or does the USG have numbers predetermined?

mailto:Wayne.M.Baumgartner.civ@mail.mil

A: Offeror will store the production inventory and associated GFE necessary to meet the contract requirements.

50. Page 4 No. 8 of the SOW states that the mortar cannon may be provided as GFP; as the offeror how would we make a request for the USG to provide the cannons?

A: The Offeror must present a contract production source for M298 cannons. The USG is maintaining flexibility for completion of 120mm Mortar Systems (either utilizing GFP or contract production). If the cannon is provided as GFP it will be as part of system staging CLINs 0046-0050 or 0058-0062, which will be added as part of Amendment 0002.

51. Will live fire testing be required for the life of the contract or only for first article test?

A: Live fire testing is conducted in accordance with the TDP for both FAT and production lot acceptance.

52. What is the government established rate for testing?

A: The proving grounds (Aberdeen Proving Grounds/Yuma Proving Grounds) can provide Government established cost rates to the Offeror. If the question is about the level of testing required, it is defined in the TDP.

53. Revision to the response for #33 from Questions and Answers #6:

The page count requirements as the wording, Paragraph L.3.3.1, is a bit confusing in the solicitation when it speaks to required attachments. Can you please confirm if an attachment IS a required part of the RFP, that it will NOT count against the page limitations?

Paragraph L.3.3.1 ….. “Annexes, documentation and attachments that are submitted bythe Offeror, which are not required as part of the RFP, will count against the page limitations……The following will not count against page limitations: volume title pages, table of contents pages, cross-referencing pages, indices, acronym lists and page dividers (used to separate proposal sections).”

The revision is captured in Amendment 0002 and the response is as follows:

FROM:

A: Annexes, documentation and attachments that are required by the RFP will not count against the page limitation.

TO:

A: Annexes, documentation and attachments that are submitted by the Offeror will count against the page limitations.