About this file
This file contains Project Design Criteria (PDCs) issued by the U.S. Army Corps of Engineers (USACE) for in-water construction activities in Florida, specifically applicable to the City of New Smyrna Beach's Police Boathouse project located adjacent to the Indian River North. The criteria establish mandatory environmental compliance requirements for the construction of a timber dock system, covered roof structure, integrated boat lift system, and associated utilities including electrical service, lighting, and potable water connections. The project has obtained all required environmental permits from the Florida Department of Environmental Protection (FDEP) and USACE and must comply with all permit conditions throughout execution. Key operational requirements include mandatory personnel education regarding protected species under the Endangered Species Act (ESA) and Marine Mammal Protection Act (MMPA), with specific instruction on civil and criminal penalties for harm to protected species.
The design criteria establish strict protective measures for vessel operations and construction equipment, including mandatory Idle Speed/No Wake operations in shallow water depths with less than 4-foot clearance from bottom, immediate cessation of work within 50 feet of observed protected species, and operation suspension during adverse weather conditions that prevent species detection. All in-water activities require installation and maintenance of floating turbidity barriers with weighted skirts extending to within 1 foot of the bottom, with specifications that barriers not block species entry or exit from critical habitat. Additional requirements mandate minimum approach distances including 150 feet for sea turtles, 1,500 feet for North Atlantic right whales, and 300 feet for other marine mammals, along with secured in-water lines using stiff, taut, non-looping materials to prevent entanglement. Any collisions with or injuries to protected species must be immediately reported to NMFS's Protected Resources Division via specified contact numbers and email addresses. The project is funded by the Florida Inland Navigation District (FIND), and all contractors must comply with permit conditions and submit required documentation through the City's eProcurement Portal.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Design Criteria (PDCs) for In-Water Activities
AP.7. Education and Observation: The permittee must ensure that all personnel associated with the project are instructed about the potential presence of species protected under the ESA and the Marine Mammal Protection Act (MMPA). All on-site project personnel are responsible for observing water-related activities for the presence of protected species. All personnel shall be advised that there are civil and criminal penalties for harming, harassing, or killing ESA-listed species or marine mammals. To determine which species may be found in the project area, please review the relevant Protected Species List at:
http://sero.nmfs.noaa.gov/protected_resources/section_7/threatened_endangered/index.
html
AP.8. Reporting Interactions with Protected Species:
a) Any collision(s) with and/or injury to any sea turtle, sawfish, whale, or sturgeon occurring during the construction of a project, shall be reported immediately to NMFS’s Protected Resources Division (PRD) at (1-727-824-5312) or by email to:
takereport.nmfsser@noaa.gov and SAJ-RD-Enforcement@usace.army.mil. .
b) Smalltooth sawfish: Report sightings to 1-844-SAWFISH or email:
Sawfish@MyFWC.com
c) Sturgeon: Report dead sturgeon to 1-844-STURG 91 (1-844-788-7491) or email:
nmfs.ser.sturgeonnetwork@noaa.gov
d) Sea turtles and marine mammals: Report stranded, injured, or dead animals to 1-
877-WHALE HELP (1-877-942-5343).
e) North Atlantic right whale: Report injured, dead, or entangled right whales to the USCG via VHF Channel 16.
AP.9. Vessel Traffic and Construction Equipment: All vessel operators must watch for and avoid collision with species protected under the ESA and MMPA. Vessel operators must avoid potential interactions with protected species and operate in accordance with the following protective measures:
a) Construction Equipment:
i) All vessels associated with the construction project shall operate at “Idle Speed/No Wake” at all times while operating in water depths where the draft of the vessel provides less than a 4-foot (ft) clearance from the bottom, and in all depths after a protected species has been observed in and has departed the area.
ii) All vessels will follow marked channels and/or routes using the maximum water depth whenever possible.
iii) Operation of any mechanical construction equipment, including vessels, shall cease immediately if a listed species is observed within a 50-ft radius of construction equipment and shall not resume until the species has departed the area of its own volition.
iv) If the detection of species is not possible during certain weather conditions (e.g., fog, rain, wind), then in-water operations will cease until weather conditions improve and detection is again feasible.
http://sero.nmfs.noaa.gov/protected_resources/section_7/threatened_endangered/index.ht http://sero.nmfs.noaa.gov/protected_resources/section_7/threatened_endangered/index.ht http://sero.nmfs.noaa.gov/protected_resources/section_7/threatened_endangered/index.ht mailto:takereport.nmfsser@noaa.gov mailto:takereport.nmfsser@noaa.gov mailto:SAJ-RD-Enforcement@usace.army.mil mailto:Sawfish@MyFWC.com mailto:Sawfish@MyFWC.com mailto:nmfs.ser.sturgeonnetwork@noaa.gov mailto:nmfs.ser.sturgeonnetwork@noaa.gov
b) All Vessels:
i) Sea turtles: Maintain a minimum distance of 150 ft.
ii) North Atlantic right whale: Maintain a minimum 1,500-ft distance (500 yards).
iii) Vessels 65 ft in length or longer must comply with the Right Whale Ship Strike Reduction Rule (50 CFR 224.105) which includes reducing speeds to 10 knots or less in Seasonal Management Areas (http://www.fisheries.noaa.gov/pr/shipstrike/).
iv) Mariners shall check various communication media for general information regarding avoiding ship strikes and specific information regarding right whale sightings in the area. These include NOAA weather radio, USCG NAVTEX broadcasts, and Notices to Mariners.
v) Marine mammals (i.e., dolphins, whales [other than North Atlantic right whales], and porpoises): Maintain a minimum distance of 300 ft.
vi) When these animals are sighted while the vessel is underway (e.g., bow-riding), attempt to remain parallel to the animal’s course. Avoid excessive speed or abrupt changes in direction until they have left the area.
vii) Reduce speed to 10 knots or less when mother/calf pairs or groups of marine mammals are observed, when safety permits.
AP.10. Turbidity Control Measures during Construction: Turbidity must be monitored and controlled. Prior to initiating any of the work covered under this Opinion, the Permittee shall install turbidity curtains as described below. In some instances, the use of turbidity curtains may be waived by the USACE project manager if the project is deemed too minimal to generate turbidity (e.g., certain ATON installation, scientific survey device placement, marine debris removal) or if the current is too strong for the curtains to stay in place. Turbidity curtains specifications:
a) Install floating turbidity barriers with weighted skirts that extend to within 1 ft of the bottom around all work areas that are in, or adjacent to, surface waters.
b) Use these turbidity barriers throughout construction to control erosion and siltation and ensure that turbidity levels within the project area do not exceed background conditions.
c) Position turbidity barriers in a way that does not block species’ entry to or exit from designated critical habitat.
d) Monitor and maintain turbidity barriers in place until the authorized work has been completed and the water quality in the project area has returned to background conditions.
e) In the range of ESA-listed corals (St. Lucie Inlet, Martin County south to the Dry Tortugas and the U.S. Caribbean) and Johnson’s seagrass (Turkey Creek/Palm Bay south to central Biscayne Bay in the lagoon systems on the east coast of Florida):
i. Projects that include upland earth moving (e.g., grading to install a building or parking lot associated with a dock and seawall project), must install sediment control barriers to prevent any upland sediments from reaching estuarine or marine waters.
ii. The turbidity curtain requirement cannot be waived for any project that moves or removes sediment (e.g., dredging, auger to create a pile, trenching to install a cable http://www.fisheries.noaa.gov/pr/shipstrike/ line). If turbidity curtains are not feasible in an area based on site conditions such as water current, high wave action, or stormy conditions, the project must undergo individual Section 7 consultation and is not covered under this
Programmatic Opinion.
AP.11.Entanglement: All turbidity curtains and other in-water equipment must be properly secured with materials that reduce the risk of entanglement of marine species
(described below). Turbidity curtains likewise must be made of materials that reduce the risk of entanglement of marine species.
a) In-water lines (rope, chain, and cable, including the lines to secure turbidity curtains) must be stiff, taut, and non-looping. Examples of such lines are heavy metal chains or heavy cables that do not readily loop and tangle. Flexible in-water lines, such as nylon rope or any lines that could loop or tangle, must be enclosed in a plastic or rubber sleeve/tube to add rigidity and prevent the line from looping and tangling. In all instances, no excess line is allowed in the water.
b) Turbidity curtains and other in-water equipment must be placed in a manner that does not entrap species within the construction area or block access for them to navigate around the construction area.