This is a Planning, Design and Construction Guidelines specification document issued by the University of New Hampshire (UNH) for the Kingsbury Hall Fire Alarm Replacement project, detailing alternates and unit prices applicable to Division 28 - Electronic Safety and Security work and Section 28 3110 - Fire Alarm Systems. The document establishes two Add Alternates and four Unit Prices that bidders must price and submit with their bids. Add Alternate No. 1 requires replacement of all existing addressable smoke and heat detectors with new equivalent devices compatible with the fire alarm system, including removal, installation, addressing, programming, labeling, testing per NFPA 72, and record documentation updates. Add Alternate No. 2 involves replacing the existing fire alarm dialer with a Keltron LS NET9000 network transceiver for alarm transmission over the campus network, including serial connection to the control panel, network integration, dedicated UPS support, Keltron technician coordination, and full end-to-end testing in accordance with NFPA 72.
The four Unit Prices establish pre-established costs for potential field contingencies: Unit Price No. 2A covers removal and replacement of initiating devices failing during testing; Unit Price No. 2B addresses removal and replacement of notification appliances failing during testing; Unit Price No. 2C covers furnishing and installing additional NAC booster power supplies if required; and Unit Price No. 2D addresses NAC booster battery replacement. All unit price work requires written authorization from the Owner, with prices remaining valid for the project duration and quantities verified by the Owner or Engineer. All work must comply with UNH Construction Guidelines, including Division 1 - General Requirements and Division 26 - Electrical, with contract drawings and general Contract provisions applying to the specifications.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PLANNING, DESIGN AND CONSTRUCTION GUIDELINES March 04, 2026
ALTERNATES AND UNIT PRICES 01 2300 - 1
SECTION 01 2300 – ALTERNATES AND UNIT PRICES
PART 1 - GENERAL
1.1 GENERAL REQUIREMENTS
A. This Section defines Add Alternates and Unit Prices applicable to Work associated with Division 28 – Electronic Safety and Security and Section 28 3110 – Fire Alarm Systems.
B. Alternates and Unit Prices described in this Section apply to Work associated with Division 28 – Electronic Safety and Security and Section 28 3110 – Fire Alarm Systems.
C. Refer to individual technical Sections for materials, equipment, and installation requirements associated with each Alternate and Unit Price item.
1.2 RELATED DOCUMENTS
A. Contract Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. Section 28 3110 – Fire Alarm Systems.
1.3 DEFINITIONS
A. Add Alternate: Work that may be added to the Base Bid at the Owner’s discretion
B. Unit Price: Pre-established cost for specific work items that may be required during construction.
1.4 SUBMITTALS
A. Submit pricing for all Add Alternates and Unit Prices with the Bid.
B. Work must comply with the University of New Hampshire Construction Guidelines;
including but not limited to Division 1 - General Requirements and Division 26 - Electrical.
ALTERNATES AND UNIT PRICES 01 2300 - 2
1.5 ADD ALTERNATES
A. ADD ALTERNATE NO. 1 – REPLACEMENT OF EXISTING INITIATING DEVICES
1. Provide all labor, materials, equipment, and services required to replace all existing addressable smoke detectors and addressable heat detectors with new equivalent addressable smoke and heat detection devices.
(1) Scope shall include:
a) Removal and disposal of existing devices.
b) Furnishing and installation of new devices of the same type and function.
c) Compatibility with the fire alarm system provided under the Base
Bid.
d) Addressing, programming, and labeling.
e) Testing in accordance with NFPA 72.
f) Updating record documentation.
2. Utilize the existing points list included in the attached Annex for device counts.
3. The existing fire alarm system protocol is Velociti
B. ADD ALTERNATE NO. 2 – REPLACE EXISTING DIALER WITH NEW KELTRON LS
NET9000 TRANSCEIVER
1. Provide all labor, materials, equipment, and services required to replace the existing fire alarm dialer with a Keltron LS NET9000 network transceiver for transmission of alarm, supervisory, and trouble signals over the campus network.
2. Scope shall include:
a. Removal and disposal of the existing dialer and associated equipment.
b. Furnishing and installation of a Keltron LS NET9000 transceiver at the fire alarm control panel.
c. Connection of the LS NET9000 to the fire alarm control panel as follows:
(1) Connect to the serial output of the addressable fire alarm control panel for transmission of system status and point-level information.
(2) Where required, provide connections to dry contacts for monitoring of alarm, supervisory, and trouble signals from auxiliary systems (e.g.
generator status).
d. Provide one (1) dedicated data drop at the FACP location for connection of the Keltron transceiver. Coordinate with the Owner for activation of the data connection.
e. Coordinate with the Owner’s IT/network provider to obtain required network configuration, including IP addressing, for integration with the campus fire alarm monitoring system.
f. The installing contractor will be responsible for conduit infrastructure between FACP and designated telecom closet, as identified by UNH. To
ALTERNATES AND UNIT PRICES 01 2300 - 3
ensure transceiver’s proper installation, the system installer and UNH must coordinate with one another.
g. Provide a dedicated UPS to support the network switch and any required communication equipment associated with the Keltron connection.
h. Coordinate with a Keltron technician for programming, configuration, and commissioning of the transceiver and integration with the monitoring head-end.
i. Coordinate signal descriptors, point mapping, and naming conventions between the FACP and the monitoring system.
j. Perform full end-to-end testing from the FACP to the central monitoring station in accordance with NFPA 72.
k. The Keltron IP transceiver will use a serial RS232 input to interface with the FACU’s serial outputs.
1.6 UNIT PRICES
A. UNIT PRICE NO. 2A – INITIATING DEVICES FAILING DURING TESTING
1. Provide unit price per each for removal and replacement of initiating devices that fail testing.
(1) Unit price shall include:
a) Device.
b) Labor for removal and installation.
c) Programming and addressing.
d) Testing and documentation.
e) Disposal of failed device.
B. UNIT PRICE NO. 2B – NOTIFICATION APPLIANCES FAILING DURING TESTING.
1. Provide unit price per each for removal and replacement of initiating devices that fail testing.
(1) Unit price shall include:
a) Device.
b) Labor for removal and installation.
c) Circuit testing
d) Programming if required.
e) Testing and documentation.
f) Disposal of failed device.
ALTERNATES AND UNIT PRICES 01 2300 - 4
C. UNIT PRICE NO. 2C – ADDITIONAL NAC BOOSTERS
1. Provide unit price per each for furnishing and installing additional NAC booster power supplies, if required due to final load calculations or field conditions.
(1) Unit price shall include:
a) NAC booster panel
b) Batteries.
c) Conduit, wiring, and terminations
d) Programming and integration into the fire alarm system.
e) Testing and commissioning
D. UNIT PRICE NO. 2D – NAC BOOSTER BATTERY REPLACEMENT
1. Provide unit price per each battery set for NAC booster battery replacement.
(1) Unit price shall include:
a) Batteries.
b) Removal and disposal of existing batteries
c) Installation and testing.
d) Testing and commissioning
E. GENERAL REQUIREMENTS FOR UNIT PRICE WORK
1. Perform unit price work only when authorized in writing by the Owner
2. Unit prices shall remain valid for the duration of the project.
3. Quantity adjustments shall be based on actual installed quantities verified by the
Owner or Engineer.
END OF SECTION 01 2300
File details come from the government source that posted it. Updated .