UCB001321-13.00-Liquidated Damages.docx
DOCX document 15 KB Posted
- Attached to
- CU Boulder-UCB001321-SITE-Lot 548 Reconstruction
- Solicitation number
- Notice No. 25-47
- Issued by
- Boulder County, Colorado
About this file
This document is a Liquidated Damages notification for the University of Colorado Boulder's SITE-Lot 548 Reconstruction Project (UCB001321), detailing specific contractual terms for parking lot reconstruction. The project involves complete removal and replacement of approximately 70,000 square feet of parking lot 548, with a strict timeline mandating demolition start on June 1, 2025, and substantial completion by August 15, 2025. The contractor must repave the lot, stripe parking stalls, and complete lighting modifications within this timeframe, with a separate stormwater quality interceptor scope to be completed after initial substantial completion.
The document establishes clear financial penalties for project delays, with liquidated damages assessed at $2,702 per day beyond the August 15, 2025 completion deadline. The calculation is based on the lot's 193 parking stalls, with the university seeking 50% compensation for lost parking revenue at a rate of $28.00 per stall per day. This approach demonstrates the university's commitment to minimizing disruption to campus parking services and ensuring timely project completion, with significant financial consequences for contractual non-compliance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| UCB001321-14.00-Attestation.docx | DOCX document | |
| UCB001321-12.00-Drawings.pdf | ||
| UCB001321-02.00-Advertisement for Bids.docx | DOCX document | |
| UCB001321-11.00-Prevailing Wage and Apprenticeship Rates.pdf | ||
| UCB001321-08.00-Sales and Use Tax.pdf | ||
| UCB001321-05.00-Alternates.docx | DOCX document | |
| UCB001321-07.00-Supplemental Terms and Conditions.pdf | ||
| UCB001321-12.00-Specs.pdf | ||
| UCB001321-04.00-Bid Form.docx | DOCX document | |
| UCB001321-03.00-Info to Bidders.docx | DOCX document | |
| UCB001321-06.00-Bid Bond.docx | DOCX document | |
| UCB001321-01.00-Table of Contents.docx | DOCX document | |
| UCB001321-09.00-Labor Burden Example.PDF | ||
| UCB001321-10.00-Apprenticeship Cert Example.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: SITE-Lot 548 Reconstruction Project Number: UCB001321 Notification of Liquidated Damages
Due to the extent of the project scope impacting revenue generating parking services for the University of Colorado, the University reserves the right to assess liquidated damages from the contractor according to the stipulations below:
The contractor may begin demolition of parking lot 548 on June 1, 2025 (after spring commencement) and must be complete by August 15th, 2025.
Completion of parking lot 548 means it is repaved, stalls striped, and lighting modifications are complete per contract documents. It is understood that the stormwater quality interceptor scope will take place at a later date after substantial completion of the parking lot surface when the material arrives.
Parking stall cost = $28.00/day/stall # of parking stalls in lots 548 = 193 stalls Parking is requesting 50% compensation.
Liquidated damages will be assessed at $2,702 for each day that Lot 548 is left incomplete after August 15th, 2025 per the definition above.
File details come from the government source that posted it. Updated .