Technical Report - AC-922579_HWY-21.pdf

PDF 20 MB Posted

Attached to
Landslide Repairs in The West Region C1
Solicitation number
693C73-25-B-000009
Issued by

About this file

This technical report details a landslide repair project for Route PR-108 in Las Marias, Puerto Rico, damaged by Hurricane Maria in September 2017. The site-specific report (ER-HWY-21) analyzes a landslide at kilometer 16.90 that caused a partial road closure, with an average daily traffic of 2,900 vehicles. Three primary retaining wall alternatives were evaluated: gabion wall, gravity concrete wall, and secant pile wall, with the secant pile wall ultimately recommended due to its ability to maintain single-lane traffic during construction.

The recommended hybrid secant pile wall solution involves installing secant piles into competent soil and a cast-in-place concrete wall with soil anchors for areas requiring fill. The project's total estimated cost ranges from approximately $1.3 million (gravity wall) to $2.2 million (gabion wall), with a 15% contingency included. Key technical considerations include drainage improvements, erosion control, utility protection, and maintaining the existing roadway's geometric characteristics. The project's cross-sections and detailed engineering drawings are included in the report's appendices, demonstrating a comprehensive approach to addressing the landslide and road infrastructure damage.

View the file

Other files

File Type Posted
Results of Bid Opening - PR ER DOT PRMNT RPR(25).pdf PDF
Amendment 0004 - PR ER DOT PRMNT RPR(25).pdf PDF
Amendment 0003 - PR ER DOT PRMNT RPR(25).pdf PDF
Amendment 0002 - PR ER DOT PRMNE RPR(25).pdf PDF
Amendment 0001 - PR ER DOT PRMNT RPR(25).pdf PDF
State Historic Preservation Office Report - Cult_Assess_Report_HWY-347.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-922579_HWY-80.pdf PDF
PRHTAs Project Special Provisions with Index.pdf PDF
VETS-4212 Form.pdf PDF
Geotechnical Report - AC-922579_HWY-80.pdf PDF
Geotechnical Report Addendum - 3 AC-922579_HWY-21.pdf PDF
Asbestos Report - AC-922579_HWY-21.pdf PDF
IFB Solicitation - PR ER DOT PRMNT RPR(25).pdf PDF
PRHTAs Standard Drawings_Revised GABI Drawings_GABI 9-10.pdf PDF
Plans - PR ER DOT PRMNT RPR(25) - AC-924579_Hwy-105.pdf PDF
Categorical Exclusion Form (NEPA) - AC-883579_HWY-369.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-845579_HWY-362.pdf PDF
Categorical Exclusion Form (NEPA) - AC-924579_HWY-105.pdf PDF
Utility Status Report - AC-922579_HWY-80.pdf PDF
Geotechnical Report - AC-814579_HWY-73_03.pdf PDF
Plans - PR ER DOT PRMNT RPR(25) - AC-922579_Hwy-21_80.pdf PDF
Asbestos and Lead Report - AC-924579_HWY-105.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-814579_HWY-73.pdf PDF
Geotechnical Report - AC-814579_HWY-73_02.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-883579_HWY-369.pdf PDF
Technical Report - AC-883579_HWY-347.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-883579_HWY-347.pdf PDF
Technical Report Addendum -AC-883579_HWY-347.pdf PDF
Asbestos Report - AC-883579_HWY-369.pdf PDF
Asbestos and Lead Certification - AC-922579_HWY-80.pdf PDF
Lead Report - AC-922579_HWY-21.pdf PDF
Geotechnical Report - AC-883579_HWY-347.pdf PDF
Hydrologic and Hydraulic Analysis Report - AC-922579_HWY-21.pdf PDF
Technical Report - AC-814579_HWY-73.pdf PDF
Geotechnical Report - AC-814579_HWY-73_01.pdf PDF
Plans - PR ER DOT PRMNT RPR(25) - AC-883579_HWY-369.pdf PDF
Utility Status Report - AC-883579_HWY-347.pdf PDF
Geotechnical Report - AC-830579_HWY-105.pdf PDF
Geotechnical Report Addendum - 3 AC-922579_HWY-80.pdf PDF
Lead Report - AC-883579_HWY-369.pdf PDF
Geotechnical Report - AC-883579_HWY-369.pdf PDF
Asbestos Report - AC-883579_HWY-347.pdf PDF
Technical Report - AC-922579_HWY-105.pdf PDF
Asbestos and Lead Certification - AC-883579_HWY-369.pdf PDF
Plans - PR ER DOT PRMNT RPR(25) - AC-814579_Hwy-73.pdf PDF
Technical Report - AC-922579_HWY-80.pdf PDF
Categorical Exclusion Form (NEPA) - AC-922579_HWY-80.pdf PDF
State Historic Preservation Office Report - Concurrence_Sites_347_361.pdf PDF
PRHTAs Material Testing Schedule.pdf PDF
Geotechnical Report Addendum - AC-922579_HWY-21.pdf PDF
Show 40 more

Latest 50 of 77 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PUERTO RICO HIGHWAY AND

TRANSPORTATION AUTHORITY

TECHNICAL REPORT

SITE - 21

Hurricane Maria Efforts for Landslide and Road Damage Evaluation and Repair Recommendations

Contract Number:2019-000141

AC-810544 / ER-9999(319)

MARCH 7,2019

REVISION 1 – AUGUST 5, 2019

REVISION 2 – DECEMBER 5, 2019

REVISION 3 – DECEMBER 14, 2023

REVISION 4 – MARCH 25, 2024

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 1 kimley-horn.com Millennium Park Plaza, 15 Calle 2, Suite 135, Guaynabo PR 00968 787 782 5050

Table of Contents

1.0 INTRODUCTION

2.0 DAMAGE ASSESSMENT

3.0 WORK EXECUTED

3.1 Site Reconnaissance

3.2 Highway Design Criteria

4.0 TECHNICAL SOLUTION ALTERNATIVES

4.1 Schematic Geometric Alignments

4.2 Plan and Profile of Proposed Structures

4.3 Drainage Considerations

4.4 Principal Structures

4.4.1 Geotechnical

4.5 Description of Impacted Utilities

4.6 Typical Cross-Sections

4.7 Environmental Considerations

4.8 Right of Way

5.0 ALTERNATIVE EVALUATION

5.1 Alternatives

5.2 Alternatives - Recommendation

5.3 Construction Cost Opinion

Appendices Appendix A – Site Specific Topographic Drawing

Appendix B – Geotechnical Evaluation

Appendix C – Plan and Profile Sheets

Appendix D – Subsurface Utility Survey Report

Appendix E – Cross Sections

Appendix F – Opinion of Probable Cost

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 2

1.0 INTRODUCTION

Kimley-Horn Puerto Rico, LLC (KHPR) presents the Technical Report for the site ER-HWY-21 as part of the Hurricane María Efforts for Landslide and Road Damage Evaluation and Repair Recommendations contract requirements.

Route PR -108 suffered damage due to Hurricane Maria in September 2017. At site ER-HWY-21, there is a landslide on the westbound of the road. The roadway structure suffered a collapse causing the responsible authorities to implement a partial closure.

ER-HWY-21 is located at route PR-108, Km 16.90 in a steep mountainous area of the municipality of Las Marias. The site is about 7.51 km to the northwest of the township of Las Marias. The project site is on a rural two-lane route. According to the HPMS 2016, PR-108 (from Km 15.9 intersection with PR-406 to Km 22.00 intersection with PR-109) has a Functional Classification of Minor Arterial with an AADT of 2,900 vehicles.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 3

2.0 DAMAGE ASSESSMENT

KHPR's first visit to the site was on April 16, 2018. Our staff visited the site accompanied by our Geotechnical sub-consultant Geo-Engineering, LLC in a general site recognition. In this visit, KHPR documented among others, the general characteristics of the landslide, length of affected roadway, visible geologic characteristics of the soil, possible cause for the landslide, and apparent possible solutions.

The site was visited again on November 30, 2018, for a kickoff inspection with a multidisciplinary team. In that visit, KHPR established the scope of the geotechnical and surveying assessments and started the execution of them. The team members performed a detailed inspection of the site to confirm some aspects from the previous visit and determine others like probable MOT strategies, drainage issues, mitigation of adjacent hazards not included in the original scope, constructability, possible environmental issues, traffic protection devices, and utilities.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 4

3.0 WORK EXECUTED

Once the site was visited and inspected by the KHPR and sub-consultant, the team proceeded with their assignments. A topographic study was performed to determine the as-built conditions of the roadway, drainage structures, exposed utilities, and the landslide area among others. It was determined the required geotechnical borings and its location and immediately they started the coordination for the geotechnical exploration. Other studies like surveying subsurface utilities, asbestos and lead testing, research of affected properties, cultural resources, habitat categorization, tree inventory, and mitigation plan, and biological assessment followed through the design process accordingly.

3.1 SITE RECONNAISSANCE

This site presents steep slopes westbound side of the roadway. The downhill slope landslide provoked damage to the roadway's westbound lane closure. As part of the measures taken by the responsible authorities to keep the road open, the roadway pavement was widened towards the eastbound shoulder to provide a two-lane section. The affected slope has an elevation difference of more than 20.00 M up to the point of the nearest probable support platform for the construction of a retaining system.

The site is adjacent to a private access road. Special considerations shall be taken for the MOT.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 5

Aerial Photo – Location of ER-HWY-21

Aerial Photo – Location of ER-HWY-21

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 6

Photo – Roadway Damage at ER-HWY-21

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 7

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 8

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 9

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 10

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 11

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 12

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 13

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 14

3.2 HIGHWAY DESIGN CRITERIA

Route PR-108, at Km 16.9 is a rural two-lane roadway having a Functional Classification of Minor Arterial with an AADT of 2,900 vehicles. Based on the AADT of 2,900 vehicles the roadway section shall be an R-6 with two 3.65 M lanes. The existing condition at the point of analysis shows a paved roadway that varies slightly from 5.00 to 6.60 meters. According to the PRHTA Highway Design Manual 1979, the paved section provided corresponds to an R-9 section instead of a R-6 section.

The scope of this project is to correct the landslide caused by the Hurricane Maria event and provide a roadway section with similar geometric characteristics to the existing one. Based on the above exposed information, KHPR will base the geometric design on the requirements of an R-9 section.

Table 1-12

Design Class Code Approximate ADT Range Min. Level of Service Terrain (2) L R M L R M L R M L R M Min. Design Speed (mph) 60 60 50 60 50 40 50 40 30 40 40 30 Number of Lanes Lane Width Pavement Min. Median Width Expandable Med. Midth Min. Shoulder Width 3.0 3.0 2.4 3.0 3.0 2.4 2.4 2.4 1.8 1.8 1.8 1.8 Min. Row Width Max. Superelevation Min. Curve Radius 350 350 230 350 230 140 230 140 75 150 150 70 Min. Stop. Sight Desitance 145 145 110 145 110 85 110 85 60 85 85 60 Min. Pass. Sight Distance 640 550 460 550 460 335 460 460 335 Max. Grade (%) 3 4 7 3 5 8 4 6 9 5 6 9 Min. Grade (%) Design Vehicle Bridges See Chapter 6

(1) All dimensions in meters unless otherwise specified.

(2) L=Level, R=Rolling, M=Mountainous.

General Design Standard for Other Rural Arterials and Collectors (1)

(Non-Controlled Access)

0.5 0.5 0.5 0.5

WB-50 WB-50 WB-40 WB-40

50 30 22 20 8% 8% 8% 6%

See Chapter 7

6.0 None None None

13.3 --- --- ---

4 2 2 2

3.65 3.65 3.35 3.05

R-7 R-8 Under 1,000

DD

1,000-2,000

C Over 6,000

R-5 R-6 2,000-6,000

C

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 15

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 16

Table 1-13

Design Class Code Approximate ADT Range Terrain (2) L R M L R M L R M Min. Design Speed (mph) 40 30 25 35 25 20 30 25 20 Pavement Width Pavement Min. Shoulder Width Min. Row Width (3)

Max. Superelevation Min. Curve Radius 150 70 50 100 50 30 70 50 30 Min. Stop. Sight Desitance 85 60 50 75 50 40 60 50 40 Min. Pass. Sight Distance 460 335 --- 400 --- --- 335 --- --- Max. Grade (%) 7 8 10 8 10 12 8 12 15 Min. Grade (%) Design Vehicle Bridges

(3) Absolute minimum. Desirable minimum is 20 meters.

General Design Standard for Local Rural Roads (1)

See Chapter 6

See Chapter 7

1.25 1.25 1.25

(1) All dimensions in meters unless otherwise specified.

(2) L=Level, R=Rolling, M=Mountainous.

SU SU SU

6% 6% 6%

0.5 0.5 0.5

14.0 13.4 12.5

5.5 4.9 4.0

R-9 R-10 R-11 Over 400 100-400 Under 100

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 17

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 18

Survey and Topography (Horizontal Datum PR NAD 83, Puerto Rico Vertical Datum)

Photo – Location and General Topography at ER-HWY-21 (Source: USGS)

Project Site

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 19

ER-HWY 21 Site Specific Topographic Drawing

Please refer to Appendix A for an 11x17 copy of the site-specific topographic drawing.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 20

4.0 TECHNICAL SOLUTION ALTERNATIVES

Based on the site reconnaissance, survey information, geotechnical data, and constructability evaluation, several retaining options were considered for downslope site repair. The three main alternatives considered were:

1. Gabion Retaining Wall

2. Gravity Concrete Wall

3. Secant Pile Wall (This wall is composed of 2 parts: 1- the secant pile wall portion below the existing ground and 2- a cast-in-place concrete wall portion above the existing ground).

Alternative Description:

1. Gabion Retaining Wall This alternative consists of a stepped-face gabion basket wall placed at the downslope edge of the roadway typical section and using embankment to backfill the void created by the landslide.

Advantages:

· Easy and fast construction

· Wall face allows drainage

· Flexible wall, which tolerates differential ground settlements

Disadvantages:

· Wide base, which may require the full road closure during construction due to the needed excavation

2. Gravity Concrete Wall This alternative consists of a trapezoid shaped concrete wall at the downslope edge of the roadway typical section and uses an embankment to backfill the void created by the landslide.

Advantages:

o Easy construction

Disadvantages:

· Wide base, which may require the full road closure during construction due to the needed excavation

· Requires additional construction time when compared to the gabion wall (for concrete curing period)

· Rigid structure does not tolerate differential settlements without cracking.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 21

3. Secant Pile Wall This alternative consists of a “hybrid wall” with secant CFA piles constructed below the existing ground and a cast-in-place concrete wall attached at the top of the secant piles above the existing ground. This wall is constructed at the downslope edge of the roadway typical section and uses an embankment to backfill the void created by the landslide.

Depending on the wall height and soil conditions additional lateral support (such as tiebacks) be required. The anchor will be designed by the contractor’s specialty engineer.

The information provided in plans is sufficient for construction. This report includes an estimated value based on the site conditions, this estimated value is used to adjust the cost of the retaining wall.

Advantages:

· Less site preparation

· Does not require as much construction area as the gabion or gravity walls

Disadvantages:

· Specific equipment required for drilling operations

· Requires additional construction time when compared to the gabion and gravity wall (for drilling and concrete curing period)

· Rigid structure does not tolerate differential settlements without cracking.

Other retaining options were considered but were dismissed as they were not considered feasible based on several factors:

A. Sheet Pile Wall. This type of wall was dismissed based on concerns associated with the construction procedures (driving process) and the site stability. KHPR considered that the driving process could cause further damage at the site.

· Cantilever Concrete Wall. This type of wall was dismissed based on construction cost, and additional construction space needed (when compared to gravity or gabion).

4.1 SCHEMATIC GEOMETRIC ALIGNMENTS

Roadway alignments are included with the plan sheets, please refer to Appendix C (plan and profile sheets).

4.2 PLAN AND PROFILE OF PROPOSED STRUCTURES

Please refer to Appendix C for copies of the plan and profile sheets.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 22

4.3 DRAINAGE CONSIDERATIONS

Existing Drainage

The project is located within the Rio Grande de Añasco Watershed. The entire portion of the roadway near the landslide location drains from the southern uphill residential area directly to the steep northern downhill slopes of the mountain. The roadway has no paved surface drainage system on either shoulder. No drainage structures or features were observed.

Proposed Drainage

In the proposed condition, a standard shoulder gutter system will be introduced along the northern portion of the roadway to improve roadway conditions and route water away from the landslide location. Shoulder inlets will be placed on the northern portion of the roadway to control spread, which will drain to an 18” pipe and will outfall to the northern downhill slopes. As an alternative, an additional barrier wall inlet will be placed at the low point in the roadway profile along the uphill southern side of the roadway and connect to the system by an 18” pipe. A headwall and rubble riprap, to reduce erosion at the outlet, will also be introduced. Erosion control slope protection matting will be provided along the downhill slopes of the road in areas where a large portion of the road drains directly to these slopes.

4.4 PRINCIPAL STRUCTURES

There are two alternatives for site 21. The first alternative uses retaining walls to replace the roadway without impacting the existing conditions along the right side of the road. For this alternative three walls options are analyzed: gabion, concrete gravity, and secant walls. The second alternative shifts the existing roadway to the right, reducing the overall need of a retaining wall on the left side of the road, but requiring retaining on the right side of the road to minimize impacts to adjacent properties. For this alternative only secant walls are analyzed.

Concrete gravity walls are large concrete structures with mild reinforcement that use their mass to retain soil. Gabion walls are wire baskets filled with stone and their mass is used to retain soil, similar to gravity walls. Secant walls are auger cast concrete piles that are drilled in line. Every other pile is reinforced and provides flexural strength to retain the soil.

For the preliminary design of the gravity walls, a slope of 9:12 (H:V) was used for the backwall.

This slope equates to an approximate ratio of 0.8 wall width to wall height. The gravity wall is embedded a minimum of three feet into the soil. The wall is located such that it does not interfere with any guardrail or traffic railing.

The preliminary design of the Gabion walls is based on the details provided in the Puerto Rico Department of Transportation standard plans for gabion walls that support a surcharge load. The gabion walls are sloped at 1:6 (H:V) and are embedded a minimum of 3 feet into the soil. The wall is located such that it does not interfere with any guardrail or traffic railing.

The secant wall preliminary design assumes cantilever walls for retained heights of 5 meters or less and anchored walls for retained heights greater than 5 meters. Embedment depths for

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 23 cantilever secant walls are based on a ratio of 2:1 (embedment: retained height), and embedment depths for the anchored walls are based on a ratio of 1.5:1. The wall is located such that it does not interfere with any guardrail or traffic railing.

4.4.1 GEOTECHNICAL

Analysis regarding the global stability of the selected alternative will be performed during the final design stage when the final geometry and depth of the alternative are established.

Slopes will be protected from the effects of erosion by placing a suitable fixing grass or open mesh fabric.

4.5 DESCRIPTION OF IMPACTED UTILITIES

A site-specific utility exploration was performed on 3/10/2019. The exploration consisted of designating the existing facilities. A copy of the Subsurface Utility Survey Report is included in Appendix D.

Three facilities were identified: - A water line was found along the upslope side of the road. The depth of cover on this utility is estimated between 3-5 ft. An overhead power line and an overhead communications line were found running along the landslide side of the road.

It is anticipated that the construction operations associated with the landslide repair (retaining wall construction, temporary cuts, and backfill) and drainage improvements may impact these facilities. The contractor shall coordinate with utility providers if impact is anticipated during construction.

4.6 TYPICAL CROSS-SECTIONS

Multiple sets of cross-sections have been included depicting the landslide repair alternatives.

Please refer to Appendix E.

4.7 ENVIRONMENTAL CONSIDERATIONS

The area surrounding the site consists of steep side slopes with vegetation. Based on a review of existing GIS data, the project site is not located within an area designated as critical habitat or with known threatened or endangered species. No known historical or archaeological sites are present based on a review of data from the Puerto Rico State Historic Preservation Office.

There are residences located nearby but they will not be directly impacted by the proposed repairs. Therefore, the project will not involve any relocations or displacements.

The proposed repairs will occur adjacent to the existing roadside and could potentially affect some plants and trees depending on the construction staging and methods used.

No additional environmental reviews or documentation is scoped for this project site.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 24

4.8 RIGHT OF WAY

A review of the information contained in the Junta de Planificacion website indicates that the existing right-of-way is ~15 meters centered on the road. The Right of Way information included in this report is not an actual Right of Way survey.

Based on this information most of the roadway, drainage, and structural improvements appear to be just inside the existing right of way lines. Some drainage features, such as: pipe outfalls, end walls, and rip rap are located outside the Right of Way lines (these items may require permanent easements).

Based on our evaluation of the possible construction procedures, we have determined that temporary construction easements may be needed to accomplish the proposed improvements.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 25

5.0 ALTERNATIVE EVALUATION

5.1 ALTERNATIVES

KHPR staff have evaluated three structural downslope retaining alternatives to address the repair at this site:

1. Gabion Walls

2. Concrete Gravity Walls

3. Secant Pile Walls

These alternatives were evaluated based on:

· Environmental considerations

· Constructability

· Cost

· Construction time

· Complexity

· Right-of-Way Impacts

The table provided below provides a comparison of the retaining wall alternatives evaluated while maintaining the existing road alignment.

Relative ordinal ratings between the alternatives are included for comparison between the 3 alternatives, with 1 meaning the most favorable alternative for the condition evaluated and 3 meaning the least favorable alternative for the condition evaluated.

Gabion Wall Gabion Rating

Concrete Gravity Wall

Gravity Rating

Secant Pile Wall

Secant Rating

Environmental May require a temporary platform and access road, which could have impacts outside of the limits of the roadway and landslide repair area.

3 May require a temporary platform and access road, which could have impacts outside of the limits of the roadway and landslide repair area.

2 Can be constructed without the temporary access road.

Constructability Relatively easy. Does not require special

1 Relatively easy. Does not require special

2 Relatively easy but requires specialized

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 26 equipment.

Due to the size of the gabion wall’s base, a full closure of the road may be needed.

equipment.

Due to the size of the gabion wall’s base, a full closure of the road may be needed.

labor and equipment.

Cost High 3 Medium 2 Low 1 Construction Time

Fast Requires additional time for concrete curing

Slower process due to multiple drillings and concrete curing.

Complexity Simple. 1 Simple. 2 Simple, but requires specialized labor and equipment.

Right-of-Way Impacts

Construction may occur outside of the road Right of Way, but only impacting the damaged downside slope.

3 Construction may occur outside of the road Right of Way, but only impacting the damaged downside slope.

2 Could be constructed within the roadway Right-of-Way.

MOT Requires full road closure.

3 Requires full road closure.

2 Can be constructed while keeping one lane open.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024 | Page 27

5.2 ALTERNATIVES - RECOMMENDATION

The recommended option for this site is a Hybrid Secant Pile Wall.

During the final structural design of the hybrid retaining wall, it was determined that modifications to the wall type was required. To accommodate the proposed roadway typical, the location of the wall had to extend downslope to such a distance that the existing ground profile was 3 to 10 meters below the proposed grade. Secant piles are installed in existing ground and cannot be extended above grade. Due to the location of the wall, a hybrid wall design was required. Secant piles are to be installed into the competent existing soil, and in areas where a wall is needed in a “fill” condition, a cast-in-place concrete wall with soil anchors was designed. The structural analysis of this wall and the required soil anchors is for the internal stability of the wall.

Coordination between the structural engineer and the geotechnical engineer took place during the final design, and it was determined that the anchors were not needed for global stability. Since the anchors were not needed for global stability, a modified geotechnical report was not produced.

Structural calculations designing the anchors were provided with the submitted construction documents.

When all the factors were evaluated, the gabion and gravity walls required full road closure and the secant pile wall allowed the road to remain open (with single-lane operation), this MOT factor weighted heavily on our recommendation to use a secant pile wall to minimize the disruptions to the traveling public.

5.3 CONSTRUCTION COST OPINION

Please refer to Appendix F for the Opinion of Probable Cost of the alternatives evaluated.

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024

APPENDIX A

Site Specific Topographic Drawing

ER-HWY-21 Technical Report | Revision 4 – March 25, 2024

APPENDIX B

Geotechnical Evaluation

REPORT

GEOTECHNICAL EVALUATION

Landslide ID # ER-HWY-21

PRHTA DESIGN AREA

EMERGENCY RELIEF PROGRAM

LAS MARIAS, PUERTO RICO

GEO 925-2018

REPORT

Prepared for

Kimley-Horn Puerto Rico, LLC Guaynabo, PR

PO Box 270328

San Juan

PR, 00927

T. 787.781.6340

F.787.706.0183

Geotechnical engineering

Construction materials testing

GEOTECHNICAL EVALUATION

LANDSLIDE ID# ER-HWY-21

PRHTA DESIGN AREA

EMERGENCY RELIEF PROGRAM

LAS MARÍAS, PUERTO RICO

GEO 925-2018

AASHTO AAP

Accredited

Laboratory

Validated

Laboratory

PR/FL DTOP

Certified

Disadvantaged

Business Enterprise

DBE

SBA Certified

HUBZone

MBE Certified

LETTER | page 1

PO Box 270328

San Juan

PR, 00927

T. 787.781.6340

F.787.706.0183

Geotechnical engineering

Construction materials testing

May 10, 2019

Eileen M. Vélez-Vega, PE

Kimley-Horn Puerto Rico, LLC

Millennium Park Plaza

Suite 435, Metro Office Park

15 Second Street

Guaynabo, Puerto Rico 00968

Tel. 787-244-5758, e-mail: Eileen.Velez@kimley-horn.com

Re: Geotechnical Evaluation of

Landslide ID # ER-HWY-21

PRHTA Design Area

Emergency Relief Program

Las Marías, PR

Dear engineer Vélez-Vega:

We are submitting our report on the geotechnical evaluation for the referenced landslide. If you have any questions with regards to this evaluation or require additional services, please do not hesitate to contact us. We are available to meet with you or your representative for any explanation concerning this evaluation.

We thank you for providing us with the opportunity to perform this study.

Cordially, GEO-Engineering

Carlos E. Rodríguez Pérez, PhD, PE

Geotechnical Engineer

Enclosures

D:\Proyectos Vigentes\Kimley-Horn-Landslides-ACT-apr2018\21\Report-Landslide ER-HWY-21-KH.docx

Table of Contents

CONTENTS | I

1. GENERAL PROJECT INFORMATION

1.1 Introduction

1.2 Landslide General Information

2. SUBSOIL EXPLORATION

2.1 Site Geology

2.2 Site Aerial Photointerpretation

2.3 Subsoil Conditions

3. GEOTECHNICAL ASSESSMENT

3.1 Alternatives of Corrective Measures

3.1.1 Gabion Retaining Wall

3.1.2 Gravity Concrete Wall

3.1.3 Secant Pile Wall (CFA Pile Wall)

3.1.4 Preferred Alternative – Secant Pile Wall

3.2 New Fill

3.3 Construction Considerations

4. GENERAL COMMENTS

4.1 General Comments

FIGURES

Figure 1 Landslide Schematic Location – Las Marías, PR

Figure 2 Views of Landslide ER-HWY-21

Figure 3 Landslide Location on USGS Geologic Map (I-660)

Figure 4 Schematic Location of Borings

Figure 5 Generalized Soil Profile

Figure 6 Alternatives of Corrective Measures – Gabion Retaining Wall

Figure 7 Alternatives of Corrective Measures – Gravity Concrete Wall

Figure 8 Alternatives of Corrective Measures – Secant Pile Wall

CONTENTS | II

APPENDICES

Appendix 1 Standard Clause for Unanticipated Subsoil Conditions

Appendix 2 Procedures Summary

Appendix 3 General Earthwork Recommendations

Appendix 4 Boring Logs and Laboratory Test Results

General Project Information

Section ONE | page 1

1. GENERAL PROJECT INFORMATION

1.1 Introduction

The Puerto Rico Highway and Transportation Authority (PRHTA) requested Kimley-Horn Puerto Rico, LLC to provide support for their

Emergency Relief Program (ER). The program includes the reconstruction of highway segments damaged by landslides associated with the pass of hurricanes Irma and María throughout Puerto Rico.

This report presents the results of a preliminary geotechnical evaluation performed for Landslide ID# ER-HWY-21, which occurred in Las Marías, PR. Eileen Vélez-Vega, PE, Assistant Vice-President, Kimley-Horn

Puerto Rico, LLC (KHPR), requested this evaluation to GEO-

Engineering, LLC (GEO) on behalf of PRHTA. The purpose of this evaluation is to draw possible corrective measures for the affected road segment. Ramón F. Bretón, PE, from Kimley-Horn’s Orlando, FL office, is the Project Manager.

The evaluation is based upon soil information from borings drilled at the landslide site, a detailed site reconnaissance, a site aerial photointerpretation, topographic and geologic information from the area, and laboratory test results. Information in conjunction with data submitted to this office by Eng. Bretón were also utilized.

General Project Information

Section ONE | page 2

1.2 Landslide General Information

Figures 1 and 2 show the schematic location of the landslide and views of the landslide area. Given below is general information on the landslide and damaged road segment:

Landslide General Information

ID# Highway Latitude Longitude Municipality

ER-HWY-21 PR-108, Km 16.90 18.255227° -67.061779° Las Marías

Landslide Morphology

Approximate Landslide Geometry: Width: ≈98-190 ft Length: ≈325 ft Height: >100 ft

Landslide Location: Downslope of road pavement northern side

Landslide Type:

Earthflow combined with erosion caused by runoff

Failure probably due to erosion and soil softening

V-shaped

Landslide Development Stage: Total collapse

Main Scarp Height:

Type:

≈ 3 ft

Curved

Sliding Surface:

Inclination:

Largely exposed and with deep carved trenches of erosion

Steep inclination (approximately 37 degrees with respect to the horizontal) (60 degrees within the carved trenches)

Affected Ground:

Partial failure of road embankment, affecting one lane

Moving Ground:

Mainly fill from road embankment and eroded saprolitic soils washed down and deposited downslope several hundreds of feet along the descending slope

Associated structures:

Cut located at the other side (south) of the road with significant instability problems in localized sectors

Existing structures along the cut crest

Subsoil Exploration

Section TWO | page 1

2. SUBSOIL EXPLORATION

2.1 Site Geology

The following table summarizes information on the geology of the landslide area, based on published information by the US Geological

Survey (USGS). Figure 3 schematically shows the landslide site within the corresponding USGS geologic map.

USGS Geological Map Information

Quadrangle: Central La Plata Map ID: I-660 Published Date:

Type of Deposits

Landslide area: Yauco Mudstone (Ky) (Upper Cretaceous)

USGS Description:

Chiefly thin-bedded dark gray calcareous mudstone, sandstone and chert. Usually deeply weathered to a brownish-orange or yellowish-brown saprolite.

Site Observed Ground Conditions:

Fill from the road construction and in-situ saprolite along the descending slope

Comments:

Loose soil and saprolitic soil observed along the cut located at the other side (south) of the road

Faults

N/A

Present

Approx.

location:

Prob. Active

Prob. Inactive

Ky Mudstone and sandstone underlie the landslide area

Section TWO | page 2

2.2 Site Aerial Photointerpretation

The evaluation of the landslide site was performed utilizing aerial photographs that covered a period of several years. According to the aerial photographs, the site showed the following physical features:

Summary of Aerial Photointerpretation

Site original topography:

Elongated top of ridge widened by the road construction

Top of a wide V-shaped gully

Road PR-105: Already existed by 1964

Road construction at site:

Minor cuts along the road southern side

Fill along the road northern side

Landslide occurred at:

Road sector where fill was deposited for the road construction

Comments:

Deep trenches of erosion continue developing along the exposed sliding surface

Other smaller slope failures involving existing fill occurred during the hurricane in the descending slope located west of the site

No signs of slope instability were detected in the aerial photographs for the last 25 years

The landslide occurred at a road sector where fill was deposited for the road construction

Section TWO | page 3

2.3 Subsoil Conditions

A soil exploration program consisting of five (5) borings (21-01 to 21-05), accompanied by field and laboratory testing, was performed to obtain information on the subsoil conditions along the project site. The following table summarizes the fieldwork performed at the site for the subsoil exploration:

Summary of Fieldwork

Type of Test Quantity

SPT Borings 5

Figure 4 schematically shows the location of the borings. The borings were distributed along the road pavement adjacent to the landslide. No borings could be performed downslope of the site because the area was not accessible to the drilling equipment (a bulldozer and permit into a private land would have been required to open trails, which would have required more time than available for this investigation). However, the subsoil information obtained with the borings, the laboratory test results, the area’s geology, and the information gathered with the site reconnaissance helped to estimate the subsoil conditions downslope of the site.

The borings were performed with a drill rig. The depth of the borings was defined in the field taking into consideration the soil/rock conditions obtained while drilling, the area’s geology, and the observed ground conditions during the site reconnaissance. The borings were stopped after reaching several feet within the underlying hard ground. The following table shows the depths reached by the borings:

Section TWO | page 4

Summary of Boring Depths

Boring Depth (ft)

21-01 60

21-02 60

21-03 60

21-04 60

21-05 60

Soil samples from the borings were recovered, identified in the field and laboratory, and subjected to laboratory testing. Appendix 2 provides a brief description of the drilling and sampling procedures utilized.

Appendix 4 presents the boring logs as well as field and laboratory test results.

Three types of materials were found with the borings performed at the project site:

Summary of Materials

Type of Material

Existing Fill

Saprolite

Highly weathered volcanic rock

Section TWO | page 5

Figure 5 shows a schematic soil profile obtained with the borings. The soil profile is a simplified representation of the subsoil and the layer boundaries found at the borings during the drilling operations. Detailed soil descriptions and engineering properties can be found in the attached boring logs. The following table summarizes the type and approximate depths of the soil/rock layers found with the borings:

Summary of Soil Information from the Borings

Soil Type Description Approx. Depth Range

Existing fill

Recovered as an upper layer of gray sandy silt with gravel and a lower layer of reddish and tannish brown clayey silt and silty clay, sometimes with angular gravel

Consistency: stiff to hard

N-value: 20 to 59 bpf

2 to 4 ft

Saprolite

Reddish and tannish brown clayey silt and silty clay, sometimes clayey silty sand, with oxidized planes

Consistency: stiff to very stiff

N-value: 6 to 55 bpf (most ≥11 bpf)

2 to >60 ft

2 to 48 ft (21-04)

Found underlying the existing fill

Highly weathered volcanic rock

Recovered as greenish gray cemented silty sand and sandy silt and cemented weathered rock fragments (broken by the sampler)

Relative density: dense

N-value: >100 bpf

Found beneath the saprolite in boring 21-04

Comments

The depth range and consistency of the existing soil layers may vary at other road locations

Loose debris was observed along the descending slope

Section TWO | page 6

The N-values from the existing fill (20 to 59 bpf) indicated that the fill was compacted when being deposited.

The saprolite N-values were variable (most of them ≥11 bpf). There were pockets with N-values of 6 bpf and 8 bpf in borings 21-03 to 21-05.

Relatively thin fill was found with the borings. However, based on the morphology of the site and its surroundings, a thicker fill seemed to have been deposited at the road sector where the landslide occurred.

A thick fill seemed to have been deposited at the road sector where the landslide occurred

Several soil samples from those recovered with the borings were selected as representative of the soil layers identified with the borings.

These samples were subjected to laboratory testing to obtain the soil grain-size distribution, the liquid (LL) and plastic (PL) limits, and the plasticity index (PI). The following table shows the test results and the soil classification (according to the Unified Soil Classification System, USCS):

Section TWO | page 7

Summary of Laboratory Test Results from Selected Soil Samples

Soil Borings Depth

(ft)

USCS

Class.

Gravel

Sand

Fines

PL

LL

PI

Existing fill 21-02 0-2 SM 12 59 29 31 56 25

Saprolite

21-01 21-01 21-01 21-02 21-02 21-03 21-03 21-03 21-04 21-04 21-05 21-05

4-10 23-28 48-55 4-15 15-35 2-10 13-25 43-50 2-15 23-30 2-15 33-40

MH

MH

SM

ML

ML

MH

MH

SM

MH

MH

MH

MH

NP

Highly weathered volcanic rock

21-04 48-55 SM 8 58 34 - - NP

Most of the tested soil samples from the saprolite classified as silt of high plasticity (MH) indicating the presence of clay. The presence of clay was confirmed by results from the unconfined compression tests (qu) obtained for several samples. A great deal of the cementation present in the highly weathered volcanic rock was broken by the sampler.

No groundwater was found when drilling borings. Taking into consideration the topographic conditions of the general area, the groundwater level should be at deeper depths than the depth reached by the borings. Temporary groundwater may emanate along the existing slope due to percolation of rainwater in areas of higher elevation.

Groundwater Not found during drilling

Section TWO | page 8

The specific conditions encountered at the borings are indicated on the enclosed boring logs (see Appendix 4). The stratification or change lines shown in the logs and in the soil profile of Fig. 5 are based upon visual-manual descriptions of the samples and information recorded on the field logs. For this reason, these lines are approximate and thus schematic. The in-situ transition between various soil/rock types may be gradual. The depths mentioned in the report refer to the existing ground surface at the time of opening the borings.

Geotechnical Assessment

Section THREE | page 1

3. GEOTECHNICAL ASSESSMENT

3.1 Alternatives of Corrective Measures

Taking into consideration the landslide morphology contained in Section

1.2, the site existing topography, and the soil information obtained from the site reconnaissance and borings, several alternatives of corrective measures for this landslide were evaluated and discussed with the project designers. Figures 6, 7, and 8 schematically show three feasible alternatives from a geotechnical point of view. The purpose of these alternatives is to reconstruct the road pavement to its previous conditions to the landslide occurrence. The road pavement reconstruction will be achieved by providing lateral support on the downslope side to the ground underlying the road pavement.

Sections 3.1.1 to 3.1.3 include a description of each alternative. The alternatives are the following:

Alternatives of Corrective Measures

Alternative Figure

1. Gabion retaining wall 6

2. Gravity concrete wall 7

3. Secant pile wall (CFA pile wall)

Section THREE | page 2

Alternatives 1 and 2 will require the following:

• Removal of the existing failed groundmass

• An overexcavation within the underlying in-situ ground to found the wall bases (the actual size and depth of the overexcavation will have to be determined in the field during construction)

• A protection against erosion (e.g. gabion revetment, anchored geomesh, etc.) along the descending slope located in front of the wall base

• Temporary support of excavation walls during construction

• Wall construction be performed in short alternating sections to reduce the risk of additional failures

• Installation of a surficial and underground drainage system that takes into account the upslope and downslope sides of the road and disposes of percolating water that may tend to accumulate along the wall base

Alternative 3 will require the following:

• A protection against erosion (e.g. gabion revetment, anchored geomesh, etc.) along the descending slope located in front of the secant wall

• Installation of a surficial and underground drainage system that takes into account the upslope and downslope sides of the road and disposes of percolating water that may tend to accumulate at the bottom of the backfill of the secant wall

All alternatives will require the following:

• Improvement of the stability conditions of the adjacent cut (along the road southern side) to prevent local failures from reaching the

Section THREE | page 3 road pavement. This cut has significant instability problems in localized sectors and existing structures constructed along the cut crest. The construction of a retaining wall will be required for this improvement.

3.1.1 Gabion Retaining Wall

The alternative of the gabion wall will consist of a stepped-face or stepped-backface gabion wall with a horizontal or inclined backfill. If stepped-face wall is selected, the wall shall be constructed with a 1:6

(Horizontal:Vertical, H:V) batter towards the road (Fig. 6). Given below are the pros and cons of this alternative:

Pros and Cons – Gabion Retaining Wall

Pros

• Relatively easy and fast to construct

• Probably only partial closure of road required during construction

• Permeable to allow drainage

• Flexible enough to tolerate ground settlements

Cons will require:

• Compacted select backfill

• 8 to 12 courses of gabion elements

• A wide base (probably an area larger that the road right-of-way)

• Construction in short segments

Section THREE | page 4

3.1.2 Gravity Concrete Wall

The alternative of the gravity concrete wall will consist of a near trapezoidal wall probably with toe and heel projections at the base. The wall shall be constructed with a batter back face and a backfill having a maximum inclination of 2:1 (H:V) (Fig. 7). Given below are the pros and cons of this alternative:

Pros and Cons – Gravity Concrete Wall

Pros

• Relatively easy to construct

• Probably partial closure of road required during construction

• Can be probably built within the road right-of-way

▪ will require:

• Compacted select backfill

• A wide base

• More time for construction (due to concrete required curing time)

• Construction in short segments

▪ Rigid structure that do not tolerate differential settlements or ground movements without cracking

3.1.3 Secant Pile Wall (CFA Pile Wall)

A third alternative of corrective measures is installing a wall made of secant CFA piles along the affected ground (Fig. 8). Given below are the pros and cons of this alternative:

Section THREE | page 5

Pros and Cons –Secant Pile Wall (CFA Piles)

Pros

• Relatively easy to construct

• Less site preparation

• Probably only partial closure of road required during construction

• Can be probably built within the road right-of-way will require:

• Specific equipment for installation

• Special workmanship for installation

• Use of casing at the upper portion

• More time for construction (due to concrete required curing time)

▪ May require additional lateral support (e.g. tiebacks)

▪ Rigid structure that does not tolerate differential settlements or ground movements without undergoing cracking

3.1.4 Preferred Alternative – Secant Pile Wall

The preferred alternative of corrective measures for this landslide, from a geotechnical point of view, is the secant pile wall due to the topographic characteristics of the site. This alternative will probably require less site preparation and only a partial closure of the road during construction. The alternative may likely require additional lateral support, such as tiebacks.

The following parameters shall be used for the secant pile wall design:

Section THREE | page 6

Summary of Design Parameters for the Secant Pile Wall (CFA Piles)

Depth Range Ka Kp γ

(pcf) ɸ (o) δ (o) c (psf)

Soil

0-4 ft 0.27 - 115 32 21 - Backfill

4-30 ft 0.27 0.50 120 32 21 250 Saprolite

30-80 ft 0.27 0.50 120 32 21 350 Saprolite where

Ka = coefficient of active earth pressure

Kp = coefficient of passive earth pressure (it takes into account the inclination of the descending slope) γ = soil unit weight ɸ = soil angle of internal friction δ = friction angle along wall/soil contact c = cohesion intercept

Depth Range = measured with respect to the road pavement elevation

The CFA pile installation shall follow the specifications provided by the

PRHTA for these piles.

3.2 New Fill

Unless otherwise stated in this report, any fill or backfill required for the project shall consist of the soil specified as fill in Appendix 3. The soil shall be placed and compacted following the recommendations provided for fill in this appendix.

Section THREE | page 7

3.3 Construction Considerations

The following considerations shall be taken into account for the construction of this project. Appendix 3 includes additional recommendations.

1. All earthwork operations in the project shall be conducted under our supervision.

2. One of our Geotechnical Engineers (or his representative) shall examine the bottom of any excavation to verify its conditions with respect to those obtained with the soil exploration program.

Proof-rolling of the excavation bottom may be required depending on the exposed ground conditions (this shall be determined in the field during construction). As the project area was previously subjected to construction, debris and buried abandoned utilities may appear beneath the site as earthwork operations progress.

Any detected soft soil spot, debris, remnants of buried previous structures, doubtful fill, or deleterious material within any excavation shall be removed and replaced with compacted fill, as specified in Section 3.2.

3. The project excavations shall be expedited to prevent disturbance of the foundation soils. All excavations shall be performed under dry conditions. The contractor shall take the required provisions to prevent seepage into and accumulation of water (runoff, percolating water, or temporary groundwater) in all excavations.

Section THREE | page 8

4. Any water collected from the road pavement shall be properly disposed of into the storm drainage system of the project. No accumulation of water shall be allowed adjacent to the road pavement.

5. No trees with a large, thick, superficial tabular root system shall be planted or exist close to the new retaining wall. Any tree of this type shall be placed at a minimum distance of 50 feet away from the wall.

6. This report is submitted for the project design and it includes construction considerations that shall be reviewed by any bidding contractor. However, the bidding contractors shall not use this report as the only information to base their bid for the project.

GEO-Engineering shall not be held responsible if the contractors use without limitations the information contained herein. Any bidding contractor should conduct a careful review of the geotechnical data and comments presented in this report. In addition, GEO-Engineering will not be responsible for the contractor’s interpretation and conclusions made from these data. The bidding contractor shall visit the project site prior to submitting a bid to become acquainted with the site actual conditions.

7. The contractor shall take care to prevent damaging surrounding structures and utilities due to the construction operations. Claims are frequently presented commonly based on vibration effects

Section THREE | page 9 derived from the construction operations (especially those due to earthwork equipment). A notarization of an overall evaluation of the conditions of nearby structures is recommended prior to starting the project construction.

8. The contractor will be solely and completely responsible for his method of construction, his method of excavation, the working conditions at the job site, and the project safety measures. This requirement applies continuously, and it is not limited to normal working hours.

According to existing regulations, any excavation exceeding a depth of 5 ft must be shored, braced, or be cut with adequate slopes to provide safety to workers. The adequacy of the required shoring or bracing system or the inclination of the excavation walls and the stability of the complete excavation is a responsibility of the contractor.

9. The contractors and/or subcontractors bidding for this project shall be pre-qualified, since the earthwork, the construction of retaining structures, and their associated activities are all specialized operations.

General Comments

Section FOUR | page 1

4. GENERAL COMMENTS

4.1 General Comments

1. This report has been prepared to evaluate the project site from a geotechnical point of view and provide recommendations for the project design and construction.

2. The scope of this report is limited to the specific project and locations described herein.

3. Our description and analysis of the project represent our understanding of the significant aspects relevant to soil/rock characteristics.

4. In the event that any changes in the project are made, we should be informed so that the changes can be reviewed, and the conclusions of this report be modified as necessary in writing by us.

5. Geotechnical aspects of design and construction are specialized activities. As a result, we should be consulted and should participate in the preparation of the final design plans and specifications for the project. In addition, we recommend that we be authorized to review the project construction plans and specifications to confirm that the findings and conclusions contained in this report have been interpreted in accordance with our intent. Without this review, we will not be held responsible for

Section FOUR | page 2 the misinterpretation of our data and/or our analysis, nor how these are or have been incorporated into the final design.

6. The analysis and recommendations submitted in this report are based upon data obtained from borings performed at the locations indicated and from any other information discussed in the report. The report does not reflect any soil/rock variations, which may occur between the borings and other project locations.

If variations appear evident, it will be necessary to re-evaluate the conclusions and recommendations after performing on-site observations during construction and noting the characteristics of the variations.

As requested by PRHTA, we are including the following statement:

“In our geotechnical reports for the subsoil investigations, evaluations and recommendations regarding Landslide

Evaluation Projects throughout Puerto Rico, we have evaluated the stability of the proposed geotechnical alternatives based on our experience, subsurface conditions encountered at each site and evaluation of allowable soil bearing pressures on the recommended strata. Additional analysis regarding the stability of the final selected alternative at each site will also be performed during the final design stage of the selected alternative when final dimensions and depth of the retaining structures are established”

(signature on next page)

Section FOUR | page 3

Submitted by, GEO-Engineering

Carlos E. Rodríguez Pérez, PhD, PE Geotechnical Engineer

May 10, 2019

GEO-925-2018

D:\Proyectos Vigentes\Kimley-Horn-Landslides-ACT-apr2018\21\Report-Landslide ER-HWY-21-KH.docx

AASHTO AAP

Accredited

Laboratory

Validated

Laboratory

PR/FL DTOP

Certified

Disadvantaged

Business Enterprise

DBE

SBA Certified

HUBZone

MBE Certified

FIGURES

Landslide Schematic Location – Las Marías, PR

FIGURE 1 GEOTECHNICAL EVALUATION

LANDSLIDE ID# ER-HWY-21

PRHTA DESIGN AREA

Views of Landslide ER-HWY-21

FIGURE 2 GEOTECHNICAL EVALUATION

LANDSLIDE ID# ER-HWY-21

PRHTA DESIGN AREA

Views of Landslide ER-HWY-21

FIGURE 2 Cont. GEOTECHNICAL EVALUATION

LANDSLIDE ID# ER-HWY-21

PRHTA DESIGN AREA

Landslide Location on USGS Geologic Map (I- 660)

FIGURE 3

Ky

GEOTECHNICAL EVALUATION

LANDSLIDE ID# ER-HWY-21

PRHTA DESIGN AREA

Schematic Location of Borings

FIGURE 4 GEOTECHNICAL EVALUATION

LANDSLI…

This is the start of the file's text. The full file is on GovTribe.