TE 39 PWO Format.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- W5168W23R0004
- Issued by
-
Department of the Army
About this file
This document contains a tracking worksheet for ongoing public works projects and a related federal contract solicitation for base operation support services. The tracking worksheet lists several ongoing and recently completed projects for various government buildings, including paint and carpet replacement, expanding an unmanned aerial vehicle compound, replacing a failed chiller, concrete impoundment repair, and safety line painting. It provides details on each project such as work order number, task order number, building location, RFP and proposal dates, notice to proceed dates, construction start and completion dates, material procurement status, overall status percentage, and comments. The related federal contract solicitation is for base operation support services at Yuma Proving Ground in Arizona. It seeks these services under solicitation number W5168W23R0004 and is issued by the Department of the Army.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ALL
| TECHNICAL EXHIBIT 39 | ||||||
| PWO Format | ||||||
| PWO TRACKING WORKSHEET | ||||||
| IN PROGRESS | ||||||
| 9 | COMMENTS | |||||
| ITEM | ||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 4945 | |||||||||
| 37585 | Paint and Carpet Replacement | 6071 | 10/24/13 | 11/22/13 | 1/30/14 | Rec'd | 65% | Carpet Received XX Installing Carpet | ||
| WAITING SCHEDULING | ||||||||||
| PROJECT | COMMENTS | |||||||||
| ITEM | ||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 4869 | ||||||||||
| 18220 | Expand North UAV Compound | N UAV | 8/30/12 | 5/14/13 | 3/28/14 | Sub Contract | 45% | Existing Fence Removed for Customer's Contractor to Begin work. Work will be completed after power upgrade project is complete, IJO 4738. Waiting on outside contractor to complete their work - 2 weeks from 3/4 | |||
| WAITING MATERIALS | |||||||||||
| PROJECT | COMMENTS | ||||||||||
| ITEM | |||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 6493 | ||||||||||
| 29740 | Replace Failed 40 Ton Chiller | 3125 | 5/14/13 | 7/8/13 | 9/23/13 | 3/13/14 | ETA 02/28/14 | 0% | Waiting Materials / Chiller On Site | ||
| CHANGE ORDER STATUS | |||||||||||
| PROJECT | COMMENTS | ||||||||||
| ITEM | |||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 4898 | ||||||||||
| 25099 | Concrete Impoundment Repair | KADS | 1/28/13 | 2/27/13 | 9/17/13 | 1/16/14 | Rec'd | 0% | Project On Hold until Permit is updated / Working with environmental to update permit w/ new epoxy | ||
| RECENTLY COMPLETED PROJECTS | |||||||||||
| PROJECT | COMMENTS | ||||||||||
| ITEM | |||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 4887 | ||||||||||
| 22439 | Paint Safety Lines on Floor | 2344 | 12/10/12 | 1/9/13 | 9/23/13 | 2/28/14 | Rec'd | 100% | Completed | ||
| FY XX QC AND GOV INSPECTED/APPROVED | |||||||||||
| PROJECT | COMMENTS | ||||||||||
| ITEM | |||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 6537 | ||||||||||
| 33649 | Install Split HVAC Unit | 3013 | 7/10/13 | 8/5/13 | 9/17/13 | 10/1/13 | 100% | Completed | |||
| IN FOR RFP | |||||||||||
| PROJECT | COMMENTS | ||||||||||
| ITEM | |||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 6616 | |||||||||
| 42786 | Repair/Replace PIV Valve | 3027 | 2/25/14 | 3/5/14 | 3/6/14 | 2 | 20% | Developing Estimate / Extension Approved | ||
| SUBMITTED PROPOSAL | ||||||||||
| PROJECT | COMMENTS | |||||||||
| ITEM | ||||||||||
| # | WO # | TASK ORDER NUMBER | DESCRIPTION OF WORK | BLDG | RFP |
RECEIVED
DATE DATE PROPOSAL DUE NOTICE TO PROCEED CONST. START DATE POP DATE MATERIAL STATUS STATUS % COMPLETE
| 1 | 4962 | |||||||
| 42765 | F8477 EHP Roller Test | KFR | 2/24/14 | 3/25/14 | 3/25/14 | 100% | Estimate Complete |
&"Arial,Bold"&20
UPDATED: &D
&P of &N