This document outlines stipulations for the redevelopment of wildlife water catchments in Game Management Unit (GMU) 13A, involving two specific sites: AGFD # 758 'Hurricane Cliffs' and BLM # 9716 'Saltbush'. The project is a collaborative effort between the Arizona Game and Fish Department (AGFD) and the Bureau of Land Management (BLM), with detailed requirements for a contractor undertaking site improvements.

The contract specifies that the contractor will provide 224 bags of 60# 4000 P.S.I. bagged concrete per site, along with hydraulic cement, PVC primer and glue, pipe thread tape, pipe sealant, and welding rod. AGFD will supply all tanks, tank parts, wildlife troughs, plumbing components, apron materials, and fencing. The project involves precise installation requirements, including specific depths for fence and support structure posts, with alternatives for solid rock encounters. Key stipulations include strict adherence to existing road access, limited equipment movement, proper debris disposal, compliance with federal and state regulations, and a final inspection by AGFD before payment is authorized.

View the file

Other files

File Type Posted
STAZ__Mail_-_Wildlife_Waters_RFP_Ed_s_Edits_2-3-21.pdf PDF
Sam_and_AZ_Corp_Commission_for_Spencer_Construction.pdf PDF
STAZ_Mail_-_FROM_Spencer_Construction__BPM003283_Price_Negotiations_due_4-15-21.pdf PDF
Sign_in_sheet_RFP_Eval_Meeting.pdf PDF
Legal_Ad_Request_BPM003283.pdf PDF
STAZ_Mail_-_JOC_2-9-21.pdf PDF
STAZ_Mail_-_Legal_Ad_Request_BMP003283_2-17-21.pdf PDF
PDS_Kmetz.pdf PDF
STAZMail_-_Spencer__BPM003283._Price_Negotiations.pdf PDF
WOODARD-53-459212-1_legal_ad.pdf PDF
BPM003283_Evaluation_Consensus_Score_Nara_Sin.pdf PDF
BPM003283_Evaluation_Consensus_Score.xls XLS spreadsheet
Legal_Add_Proof_WOODARD-35-459212-1.pdf PDF
Certificate_6-1-22_to_6-1-23.pdf PDF
STAZMail_-TO_Evaluation_Committee___BPM003283___3-9-21.pdf PDF
PDS_Ed.pdf PDF
STAZ__Mail_-_attached_picture_2-9-21.pdf PDF
CTR055131_Spencer_Construction__Amendment_Renewal_Yr_3_DB_Signed.pdf PDF
Due_Diligence_Check_List_RFP_5-10-21.pdf PDF
AZGF_Wildlife_Waters_Construction_and_Redevelopment_Score_and_Narrative_Jeff_Green.pdf PDF
BPM003283_from__Spencer_Construction_LLC-_due_4-19-21.pdf PDF
STAZ_Mail_-_Request_for_Best_and_Final_Offer-BPM003283__RESPONSE-_Spencer_Construction.pdf PDF
STAZMail_-to__Spencer_Construction___Price_Negotiations_due_4-15-21.pdf PDF
Guidelines_for_Evaluation_for_Committee_Members.pdf PDF
Evaluation_Committee_Member_Statement_Nara_Sin.pdf PDF
AZGF_Wildlife_Waters_Construction_and_Redevelopment_Score_and_Narrative_Ed_Jahrke.pdf PDF
BAFO-Spencer.pdf PDF
STAZ_Mail_-_Re__Phone_Call_with_E_Jahrke.pdf PDF
STAZ_Mail_-_Term_Contract_-water_catchment_-Eval_Committee_requirements_1-27-21.pdf PDF
STAZ_Mail_-_Wildlife_Waters_RFP_2-4-21_Conversations_with_E_Jahrke.pdf PDF
STAZMail_-_Award_approval_Coppertree_and_Spencer_BPM003283_4-26-21.pdf PDF
20_21_LIAC_AUTC_WCMC_XLIC_w-_AI_-_Insurance_Spencer_Const.pdf PDF
Sam___AZ_Copr_Yr_2_renewal_Spencer_Construction_LLC_CTR055131.pdf PDF
Spencer_Construction_O_A_signed_BPM003283.pdf PDF
DNS20210223_30_legal_ad_affidavit.pdf PDF
State_of_Arizona_Mail_-_Legal_ad_proof_BPM003283.pdf PDF
WILDLIFE_WATERS_CONSTRUCTION_AND_REDEVELOPMENT_Eds_Edits_02-03-2021.pdf PDF
CTR055131_YR5_Contract_Renewal_AZGFD_Signed.pdf PDF
Certificate__1_.pdf PDF
STAZMail_-_Spencer_Construction__BPM003283_Price_Negotiations_INVITE.pdf PDF
COI_Spencer_Construction.pdf PDF
CTR055131_Contract_Renewal_YR3_Vendor_Signed__1_.pdf PDF
STAZ_Mail_-_Conversations_Re__draft_2-17-21.pdf PDF
Certificate.pdf PDF
STAZ_Mail_-_NOTICE_OF_ANTICIPATED_AWARD_BPM003283_-_Spencer_Construction_LLC_insurance.pdf PDF
Conflict_of_Interset_form_Jeff_Green.pdf PDF
COI2023.06.01_GL_AL_UMBRELLA_WC_EQ_FLOATER.pdf PDF
BABA_Amendment_Contract__CTR055131_Spencer_executed.pdf PDF
CTR055131_Spencer_Construction__Amendment_Renewal_Yr_3_fully_Executed.pdf PDF
COI_6-1-2023_Spencer_Construction_LLC.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stipulations for the Redevelopment of Wildlife Water Catchments AGFD #

758 ‘Hurricane Cliffs’ and BLM # 9716 ‘Saltbush’ in GMU 13A

Access to project sites is by existing roads only.

No vehicles/equipment allowed 10’ outside of existing perimeter fence lines.

Only trees and shrubs within the project sites identified by a representative from the

Arizona Game and Fish Department (AGFD) can be removed.

In the event of any game cameras being present at the sites, contact AGFD immediately for instructions with how to proceed.

All construction debris will be disposed of by the contractor at their cost, at an appropriate landfill or recycling center – no burying construction debris on project sites or leaving it on the ground. Do not burn concrete bags on site.

AGFD will supply all tanks and tank parts, wildlife trough and trough parts, all connective plumbing and associated plumbing parts, all apron materials including gutter and gutter basket, and fence and substructure pipe for both projects.

Contractor supplies 224 bags of 60# 4000 P.S.I. bagged concrete per site, hydraulic cement (if needed), all PVC primer and glue, pipe thread tape and pipe sealant, and welding rod.

All new perimeter fence posts have to be 18” deep from existing grade. If solid rock is encountered, a 2” hole drilled 12” deep into the rock will suffice, using hydraulic cement as the bonding medium.

All apron support structure posts have to be 24” deep from tank floor grade. If solid rock is encountered, a 2” hole drilled 12” deep into the rock will suffice, using hydraulic cement as the bonding medium.

An inspection will be conducted by AGFD when all of the connective plumbing has been installed and charged with water between the tanks and the trough. Plumbing will remain uncovered until that inspection takes place.

All spoils/overburden need to be dispersed and contoured to match existing site grades.

Federal NEPA, OSHA and state laws, including AGFD policies and rules, need to be adhered to at all times.

Contractor is responsible to adhere to all NWS Red Flag Warnings where a project is occurring, along with adherence to AGFD Hot Works Policy D4.9.

All work must cease and the AGFD contacted immediately if any artifacts or other objects of an historical nature are uncovered

At the completion of each project, all vehicle/equipment tracks and ruts on the project site are to completely filled-in and raked out.

Payment will be made only after a final inspection is conducted by AGFD, and all of the above listed stipulations have been followed.