Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx
XLSX spreadsheet 775 KB Posted
- Solicitation number
- FA441826R0009
About this file
This file is a Schedule-Pay Calendar Example template in Excel format designed for use in federal construction contracting under the Joint Base Charleston Multiple Award Construction Contract (MACC).
The document serves as an instructional template demonstrating how contractors should format and present their payment schedules and financial calendars when submitting proposals or managing contract execution. As an appendix to the Statement of Work for specification section 01 32 00 (Construction Progress Documentation), this example provides standardized guidance for organizing project payment schedules, likely showing the structure for milestone-based or time-phased payment distributions across construction phases. The template is not specific to particular products or services but rather provides a formatting reference that vendors responding to the JB Charleston MACC solicitation (FA441826R0009) should follow when developing their cost and schedule documentation. This is applicable to the Air Force's multiple award construction contract supporting Joint Base Charleston and associated installations in South Carolina, which encompasses new construction, alterations, repairs, demolition, design-build services, and emergency support to other Air Force bases.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Schedule and Pay Request Calendar |
| Project Name |
| 2016 |
| Notice to Proceed: | 01-Jan-21 |
| Contract Completion: | 01-Jan-24 |
Data Date: Last Day of the Month, Close-of-Business
| Contractor Provides Draft Monthly Cost Loaded CPM Schedule Update and Narrative to JB Charleston |
| Contractor Conducts Monthly Periodic Schedule Meeting with JB Charleston |
| Contractor Submits Final Monthly Cost Loaded CPM Schedule Update and all Reports |
| Contractor Provides Approved Monthly Cost Loaded CPM Schedule Update and Submits Invoice Payment to JB CHS |
| Contractor Submits Approved Invoice for Payment in Wide Area Work Flow (WAWF) |
This calendar is a visualization tool for the monthly schedule updating and payment process and does not supersede contract requirements. Dates may need to shift based on holidays.