Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx
DOCX document 40 KB Posted
- Solicitation number
- FA441826R0009
About this file
This is a Statement of Work template for construction projects at Joint Base Charleston. The document provides a standardized framework for defining work scope, project locations, occupancy conditions, existing work requirements, and government-furnished materials for construction contracts supporting the Air Force. The work covers new construction, alterations, repairs, and demolition of buildings, structures, roads, grounds, and utilities across multiple JBC locations including the Air Base, Weapons Station, North Auxiliary Air Field, and Short Stay Recreational Area.
Key requirements outlined in the template include: contractors must coordinate with the Contracting Officer regarding work sequences, material storage, and access to facilities; contractors are responsible for protecting existing structures and utilities, with repairs required to match pre-construction conditions; government-furnished materials and equipment will be clearly identified and must be picked up within 30 days of the required date; contractors must develop salvage plans for designated materials and maintain property control records for salvaged items stored at government-designated locations; and buildings may or may not be occupied during performance. The template uses bracketed placeholders for project-specific details such as project summaries, delivery locations, notification timelines, and occupancy status, indicating this document serves as a reusable format for multiple construction task orders under the broader Multiple Award Construction Contract vehicle.
View the file
Other files
Show all 50
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
[Type here]
DRAFT – DO NOT USE
SECTION 01 11 00
SUMMARY OF WORK
JB Charleston (Dec 2021)
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes [INSERT PROJECT SUMMARY HERE] and incidental related work.
1.1.2 Location
The work shall be located on Joint Base Charleston (JBC) [Air Base (AB)][Weapons Station (WS)][North Auxiliary Air Field (NAAF)][Short Stay (SS)], approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Building(s) [will][will not] be occupied during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer or Contracting Officer’s Representative. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
[DELETE BELOW IF NOT REQUIRED]
1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish material and equipment per the drawings for the [Contractor][Government] to install.
1.4.1 Delivery Schedule
Government-furnished materials shall be clearly indicated as an activity on the Critical Path Method Schedule. Notify the Contracting Officer in writing at least [_____] calendar days in advance of the date on which the materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such date.
1.4.2 Delivery Location
The materials and equipment are located at [_____].
1.5 GOVERNMENT-INSTALLED WORK
1.6 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located on Joint Base Charleston.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section -- Section 01 11 00 Page 1