Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx

DOCX document 40 KB Posted

Attached to
JB Charleston Multiple Award Construction Contract
Solicitation number
FA441826R0009
Issued by

About this file

This is a Statement of Work template for construction projects at Joint Base Charleston. The document provides a standardized framework for defining work scope, project locations, occupancy conditions, existing work requirements, and government-furnished materials for construction contracts supporting the Air Force. The work covers new construction, alterations, repairs, and demolition of buildings, structures, roads, grounds, and utilities across multiple JBC locations including the Air Base, Weapons Station, North Auxiliary Air Field, and Short Stay Recreational Area.

Key requirements outlined in the template include: contractors must coordinate with the Contracting Officer regarding work sequences, material storage, and access to facilities; contractors are responsible for protecting existing structures and utilities, with repairs required to match pre-construction conditions; government-furnished materials and equipment will be clearly identified and must be picked up within 30 days of the required date; contractors must develop salvage plans for designated materials and maintain property control records for salvaged items stored at government-designated locations; and buildings may or may not be occupied during performance. The template uses bracketed placeholders for project-specific details such as project summaries, delivery locations, notification timelines, and occupancy status, indicating this document serves as a reusable format for multiple construction task orders under the broader Multiple Award Construction Contract vehicle.

View the file

Other files

File Type Posted
Solicitation Amendment FA441826R00090003.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf PDF
Solicitation Amendment - FA441826R00090002.pdf PDF
Attachment YU - Seed Project Schedule B.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings.pdf PDF
Solicitation Attachment - Salvage Storage List.docx DOCX document
Solicitation Attachment - Site Visit Sign-In Sheet.pdf PDF
Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx XLSX spreadsheet
B464 Photos.pdf PDF
Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf PDF
Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf PDF
Solicitation Attachment - B466 Mechanical RFIs.pdf PDF
Solicitation Attachment - Geotechnical Report 14 April 2025.pdf PDF
Solicitation Attachment - Pre-Proposal Conference Slides 2026.pptx PPTX presentation
Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf PDF
B466 Photos.pdf PDF
Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf PDF
Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf PDF
Solicitation Attachment - Hydrant Flow Test Data.pdf PDF
Solicitation Amendment FA441826R00090001.pdf PDF
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.pdf PDF
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf PDF
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf PDF
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Solicitation - FA441826R0009.pdf PDF
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf PDF
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx XLSX spreadsheet
Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule- Pay Calendar Example 1.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

[Type here]

DRAFT – DO NOT USE

SECTION 01 11 00

SUMMARY OF WORK

JB Charleston (Dec 2021)

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes [INSERT PROJECT SUMMARY HERE] and incidental related work.

1.1.2 Location

The work shall be located on Joint Base Charleston (JBC) [Air Base (AB)][Weapons Station (WS)][North Auxiliary Air Field (NAAF)][Short Stay (SS)], approximately as indicated. The exact location will be shown by the Contracting Officer.

1.2 OCCUPANCY OF PREMISES

Building(s) [will][will not] be occupied during performance of work under this Contract.

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.3 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer or Contracting Officer’s Representative. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

[DELETE BELOW IF NOT REQUIRED]

1.4 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish material and equipment per the drawings for the [Contractor][Government] to install.

1.4.1 Delivery Schedule

Government-furnished materials shall be clearly indicated as an activity on the Critical Path Method Schedule. Notify the Contracting Officer in writing at least [_____] calendar days in advance of the date on which the materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such date.

1.4.2 Delivery Location

The materials and equipment are located at [_____].

1.5 GOVERNMENT-INSTALLED WORK

1.6 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located on Joint Base Charleston.

Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section -- Section 01 11 00 Page 1