This document is a transmittal form (JB CHS TRANSMITTAL FORM 4025) used for submitting shop drawings, equipment data, material samples, and manufacturer's certificates of compliance to the Air Force Civil Engineer Squadron (628CES/CEN) for approval during construction or project execution.

The form serves as the primary vehicle for contractors to request approval of submittal items and for approving authorities to document their review and authorization. Section I requires contractors to provide detailed information about each submittal item, including item number, description (model/catalog numbers, manufacturer, nomenclature), submittal type code (SD-01 through SD-11, ranging from preconstruction to closeout documentation), number of copies submitted, relevant specification and drawing references, any variations from contract requirements, and time/cost impacts if applicable. Contractors must also indicate whether the transmittal is new or a resubmittal and identify the approval source required (For Information Only, Government Approval, Designer of Record Approval, Government Conformance Review, or combinations thereof). Section II requires certification by a Quality Control Manager and signature approval by an authorized approving official, with remarks documenting any conditions or exceptions. Each transmittal must address items from only one specification section, and expedited submittals require separate forms. The approving authority assigns action codes (A through X and K, R for design-build contracts) indicating approval status, required resubmissions, or disapproval.

View the file

Other files

File Type Posted
Solicitation Amendment FA441826R00090004.pdf PDF
Statement of Work - JBLG Rev01.pdf PDF
Solicitation Amendment FA441826R00090003.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf PDF
Solicitation Amendment - FA441826R00090002.pdf PDF
Solicitation Attachment - 1999 As-Built Drawings.pdf PDF
Solicitation Attachment - B466 Mechanical RFIs.pdf PDF
Attachment YU - Seed Project Schedule B.pdf PDF
Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf PDF
Solicitation Attachment - Pre-Proposal Conference Slides 2026.pptx PPTX presentation
Solicitation Attachment - Geotechnical Report 14 April 2025.pdf PDF
B464 Photos.pdf PDF
Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx XLSX spreadsheet
Solicitation Attachment - Site Visit Sign-In Sheet.pdf PDF
Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf PDF
Solicitation Attachment - Salvage Storage List.docx DOCX document
Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf PDF
Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf PDF
Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf PDF
B466 Photos.pdf PDF
Solicitation Attachment - Hydrant Flow Test Data.pdf PDF
Solicitation Amendment FA441826R00090001.pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf PDF
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Solicitation - FA441826R0009.pdf PDF
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx XLSX spreadsheet
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA, MATERIAL SAMPLES, OR

MANUFACTURER'S CERTIFICATES OF COMPLIANCE

The proponent agency is 628CES/CEN.

DATE TRANSMITTAL NO.

SECTION I - REQUEST FOR APPROVAL OF THE FOLLOWING ITEMS (This section will be initiated by the contractor)

TO:

PROJECT TITLE AND LOCATIONSPECIFICATION SEC. NO. (Cover only one section with each transmittal)

FROM: CONTRACT NO. CHECK ONE:

THIS TRANSMITTAL IS FOR: (See Note 8)

THIS IS A NEW TRANSMITTAL

THIS IS A RESUBMITTAL OF

TRANSMITTAL

FIO GA DA CR DA/CR DA/GA

ITEM

NO.

(See

Note 3)

GOV

ACTION

CODE

(Note 10)

SUBMITTAL

TYPE CODE

(See Note 9)

TYPE

OF

COPIES

(See Note 1)

SPEC.

PARA. NO.

DRAWING

SHEET NO.

VARIATION

(See Note 6) g.

TIME/COST

IMPACT

(See Note 7)

DESCRIPTION OF SUBMITTAL ITEM

(Model Number, Catalog Number, Manufacturer, Nomenclature of Material, etc.)

a. i.c. d. e. f.b.

CONTRACT DOCUMENT

REFERENCE

REMARKS

SECTION II - APPROVAL ACTION

I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.

NAME OF QC MANAGER SIGNATURE OF QC MANAGER

NAME AND TITLE OF APPROVING AUTHORITY

SIGNATURE OF APPROVING AUTHORITY DATE

REMARKS

REPLACES AF IMT 3000, WHICH IS OBSOLETE.JB CHS TRANSMITTAL FORM 4025, 20210421

h.

NOTES

9. When submittal items are transmitted, indicate the "Submittal Type" (SD-01 through SD-11) in column c of Section I.

Submittal types are the following:

SD-01 - Preconstruction SD-02 - Shop Drawings SD-03 - Product Data SD-04 - Samples SD-05 - Design Data SD-06 - Test Reports

SD-07 - Certificates SD-08 - Manufacturer's Instructions SD-09 - Manufacturer's Field Reports SD-10 - O&M Data SD-11 - Closeout

10. For each submittal item, the Contractor will assign Submittal Action Codes in column g. The approving authority will assign Submittal Action Codes in column i.

The Submittal Action Codes are:

A -- Approved as submitted.

B -- Approved, except as noted. Resubmission not required.

C -- Approved, except as noted Refer to attached comments.

Resubmission required.

D -- Will be returned by separate correspondence.

E -- Disapproved. Refer to attached comments.

11. Approval of items does not relieve the contractor from complying with all the requirements of the contract.

F -- Receipt acknowledged.

X -- Receipt acknowledged, does not comply with contract requirements, as noted.

G -- Other action required (Specify)

K -- Government concurs with intermediate design. (For D-B contracts)

R -- Design submittal is acceptable for release for construction. (For D-B contracts)

JB CHS TRANSMITTAL FORM 4025, MAR 2021

1. Indicate "E" For Electronically Submitted or "H-#” for hard copy (replacing “#” with the quantity)

2. Each Transmittal shall be numbered consecutively. If the Transmittal is a resubmittal, then add a decimal point to the end of the original Transmittal Number and begin numbering the resubmittal packages sequentially after the decimal.

3. The "Item No." for each entry on this form will be the same "Item No." as indicated on the submittal register.

4. Submittals requiring expeditious handling will be submitted on a separate Transmittal Form.

5. Items transmitted on each transmittal form will be from the same specification section. Do not combine submittal information from different specification sections in a single transmittal.

6. If the data submitted are intentionally in variance with the contract requirements, indicate a variation in column g, and enter a statement in the Remarks block describing he detailed reason for the variation.

7. If the variation causes an impact to time or cost indicate the type of impact in column h, and enter the associated RFI number in the remarks

8. Select one of the following depending on which approval source is required.

FIO – For Information Only GA – Government Approval DA - Designer of Record Approval CR - Government Conformance Review of Design DA/CR - Designer of Record Approval/Government Conformance Review DA/GA - Designer of Record Approval/Government Approval

Reason: Off
Transmittal: Off
Previous Transmittal:
Transmittal No:
Project Title:
Spec No:
Item No:
0:
1:
2:
3:
4:
5:
6:
7:
Submittal Code:
0:
1:
2:
3:
4:
5:
6:
7:
Submittal Discription:
0:
1:
2:
3:
4:
5:
6:
7:
No of Copies:
0:
1:
2:
3:
4:
5:
6:
7:
Spec para:
0:
1:
2:
3:
4:
5:
6:
7:
Sheet No:
0:
1:
2:
3:
4:
5:
6:
7:
Contractor Review Code:
0:
1:
2:
3:
4:
5:
6:
7:
Variation:
0:
1:
2:
3:
4:
5:
6:
7:
USACE:
0:
1:
2:
3:
4:
5:
6:
7:
Contractor Name:
Date:
1:
Authority Remarks:
Authority Name:
Authority Date:
Contractor Remarks:
Contract No:
From:
To: