The document is a set of Standard Specifications and Details for Public Improvements from the City of Tucson and Pima County, specifically the 2003 edition. These specifications are incorporated into contract documents and are available for purchase from Duck Press Media Solutions in Tucson, Arizona. The document provides a comprehensive list of errata and revisions to the original standard specifications, covering various technical and procedural updates across multiple sections including labor costs, equipment rentals, force account work, manhole frame resets, construction materials, and technical requirements.

The revisions address specific technical details such as adjusting labor and travel allowance rates, modifying equipment rental payment calculations, updating subcontractor markup procedures, and revising specifications for tension wire coatings, aggregate composition, and manhole frame resets. Key changes include limiting subsistence and travel allowance rates to state-published levels, establishing a 0.933 adjustment factor for equipment rental rates, allowing a 10% markup for outside rented equipment, and specifying precise coating weight requirements for tension wire and fabric fasteners. These modifications appear designed to provide clearer guidance, improve cost management, and standardize technical specifications for public improvement projects.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STANDARD SPECIFICATIONS AND DETAILS

STANDARD SPECIFICATIONS AND DETAILS

City of Tucson/Pima County Standard Specifications and Details for Public Improvements are on file in the City Clerk's Office. The 2003 edition of the above-referenced Standard Specifications and

Details are incorporated herein by this reference and are as much a part of the Contract Documents as if they were attached hereto or as they may be modified herein.

In the event of any conflict, seeming or real, between the Special Provisions contained herein and the above-referenced Standard Specifications and Details, these Special Provisions shall prevail.

Copies of the above-referenced Standard Specifications and Details may be obtained at the following location:

City/County Standard Specifications and Details for Public Improvements (including City

Traffic Engineering and Tucson Water Standard Specifications and Details)

Duck Press Media Solutions

4633 E. Broadway Boulevard

Tucson, AZ 85711

(520) 795-1700

Cost: Standard Specifications - Call

Standard Details - Call

ADDITIONS AND REVISIONS TO THE STANDARD SPECIFICATIONS (2003

EDITION):

STANDARD SPECIFICATIONS ERRATA:

The following changes shall be made to cover errors in the text of the Standard Specifications:

Page 105:

109-5 (B)(1) Labor: subparagraph (c) of the Standard Specifications is revised to read:

(c) Subsistence and travel allowances paid to workers as required by collective bargaining agreements, or as approved by the Agency. Rates for lodging, meals and mileage shall not exceed the rates published by the State at the time of the force account work. No markup will be allowed for profit and overhead.

Page 106:

109-5 (B)(3)(a) Rental Rates (Without Operators): is modified to add:

F = Adjustment factor for the Rental Rate Blue Book will be 0.933.

Page 107:

109-5 (B)(3)(c) Outside Rented Equipment: of the Standard Specifications is revised to read:

In cases where a piece of equipment to be used is rented or leased by the contractor from a third party exclusively for force account work, the contractor will be paid as follows:

[Rental Invoice x 1.10] + HOC

The above formula includes a 10 percent markup of the rental invoice for all overhead and incidental costs for furnishing the equipment.

109-5 (B)(3)(d) Owner-Operated Equipment: of the Standard Specifications is hereby deleted.

109-5 (B)(3)(e) Moving of Equipment: the subsection letter of the Standard Specifications is revised to read:

(d) Moving of Equipment.

Page 109:

109-5 (C) Force Account Work by Subcontractor: of the Standard Specifications is revised to read:

When force account work is determined by the Engineer to require specialized labor or equipment not normally utilized by the contractor, and such force account work is performed by subcontractors, the contractor will be allowed a supplemental markup of five percent of the subcontractor’s costs.

Such allowance will be applied to the subcontractor’s force account costs less markups for overhead and profit.

The contractor shall submit payrolls or other cost data documents for all force account work performed by subcontractors. There shall be no payments made for force account work until the receipt of proper and correct documentation.

Page 270:

505-3.05 Reset Manhole Frame and Cover: the first sentence of the Standard Specifications is revised to read:

Existing frames and covers to be reset shall be carefully removed and reset to the required grade in accordance with the requirements of Subsection 505-3.01; however, at the contractor's option and with approval of the Engineer, adjustable extension rings, of the type which do not require the removal of the existing frame, may be used.

Page 368:

601-3.02 (D) Removal of Falsework and Forms: the first sentence of the seventh paragraph of the Standard Specifications is revised to read:

Placement of backfill material shall be in accordance with Subsection 203-5.03 (B).

Page 689:

902-2.05 Tension Wire and Fabric Fasteners: the last paragraph of the Standard

Specifications is revised to read:

The minimum weight of zinc coating shall conform to the requirements of ASTM A641, Class 3.

The minimum weight of aluminum coating shall be 0.40 ounces per square foot of wire surface area.

Page 713:

909-2.02 Frames and Covers: of the Standard Specification is revised to read:

Frames and covers shall conform to the requirements of Subsection 505-2.06.

920-3.03 Reset Frames and Covers: of the Standard Specification is revised to read:

Existing frames and covers to be reset shall be carefully removed and reset as specified under

Subsection 909-3.01; however, at the contractor's option and with approval of the Engineer, adjustable extension rings conforming to the requirements of Subsection 505-3.05 may be used.

Frames and covers broken or damaged in removing and resetting shall be replaced at the contractor's expense. Page 752:

920-2.04 Aggregate: the table in the Standard Specifications is revised to read:

Sieve Size Percent Passing (Dry Weight)

1-1/2"

#4

#200

100%

60% - 90%

5% - 15%