PRICE_PAGE.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
Los Reales Landfill Cell 4B Construction
Solicitation number
230059
Issued by
Pima County, Tucson City, Arizona

About this file

This document is a detailed bid tabulation worksheet for the Los Reales Landfill Cell 4B Construction project, issued by the City of Tucson, Arizona. The project involves comprehensive landfill cell construction, including mass excavation, grading, liner installation, and infrastructure development. Key components include approximately 447,000 cubic yards of cut and 23,700 cubic yards of fill, installation of geosynthetic liners covering 979,850 square feet, placement of HDPE geomembrane on 1,001,600 square feet, and various supporting infrastructure such as leachate collection systems, culvert pipes, and water truck filling stations.

The bid worksheet provides a line-by-line breakdown of 27 distinct construction items, with each item having a designated unit of measurement and quantity, though the unit prices are not completed in this document. The project scope encompasses complex environmental engineering tasks, including stormwater pollution prevention, liner subgrade preparation, pipe installations, and electrical services. While no specific pricing is indicated, the comprehensive nature of the bid suggests a significant municipal infrastructure investment focused on expanding and modernizing the Los Reales Landfill's operational capacity through the construction of Cell 4B.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Worksheet

LOS REALES LANDFILL CELL 4B CONSTRUCTION

(BID TABLULATION)

BID ITEM UNIT OF MEASUREMENT QUANTITY BID UNIT PRICE BID ITEM TOTAL COST

1Mobilization/DemobilizationLS1$ - 0
2AZPDES Construction Stormwater Pollution Prevention Plan, Notice of Intent, Permit and ImplementationLS1$ - 0
3Demolition, Salvage, Removal, and Disposal per Plan Sheet 4LS1$ - 0
4Mass Excavation and Grading - Includes Excavation, Stockpiling of Cut Material, Placement and Compaction of Fill, Rough Grade, and Fine Grade of Cell 4B Subgrade and Perimeter Infrastructure as shown on Sheet 5 of the Plans, and Pump and Treat Pond Grading as Shown on Sheet 10 of the Plans. [Note: estimated cut quantities shown are bank and fill quantities are compacted in place] [Quantities are based on preconstruction topographic survey from 1/17/22 and are subject to change]CY (CUT)447,000$ - 0
CY (FILL)23,700$ - 0
5Purchase and Install Four (4) Parallel 24-inch Corrugated Culvert Pipes (40 LF Each)LF160$ - 0
6Purchase and Install 12-24-inch Rip Rap Aprons as Located on Sheet 5 of the Plans, 18-inches thick minimum, includes geotextile underlayment per Specifications.SY470$ - 0
7Purchase and Install Asphalt Milling Road Surfacing (quantity is compacted in place)CY3,120$ - 0
8Liner Subgrade Preparation - Includes smooth drum rolling, filling/ leveling/removing surface voids, ruts, undulations, cracks, and debris in excess of 1-inch in maximum diameter within the areas to be lined only.LS1$ - 0
9Expose, Clean and Connect to Existing Cell 4A Liner Tie-in Edge
(Detail 2 on Sheet 11 and Detail 4 on Sheet 12)LF1,030$ - 0
10Purchase and Install Geosynthetic Clay LinerSF979,850$ - 0
11Purchase and Install 60-mil HDPE Double Sided Textured Geomembrane (Cell 4B and Pump and Treat Water Storage Pond)SF1,001,600$ - 0
12Purchase and Install 16-oz Non-Woven Needle Punched Geotextile
(Cell 4B and Pump and Treat Water Storage Pond)SF459,100$ - 0
13Purchase and Install 8-oz Non-Woven Needle Punched GeotextileSF374,000$ - 0
14Excavate and backfill anchor trench
a- North Slope with Soil Berm (Detail 3 on Sheet 11)LF1,340$ - 0
b- West Slope with Asphalt Millings Berm and Plywood
(Detail 4A on Sheet 11)LF730$ - 0
c- South Slope with Asphalt Millings Berm
(Detail 4B on Sheet 11)LF860$ - 0
d- Stability Slope Bench
(Detail 3 on Sheet 12)LF2,475$ - 0
e- Pump and Treat Pond AnchorLF600$ - 0
15Purchase and Install Cell 4B LCRS Drainage Gravel LayerCY14,000$ - 0
16Place and Spread Cell 4B Protective Soil LayerCY34,300$ - 0
17Purchase and Install 6-inch HDPE SDR-11 perforated leachate collection piping per Detail 1 on Sheet 12, includes connection to existing Cell 4A stubout per Detail 6 on Sheet 11.LF855$ - 0
18Purchase and install 18-inch HDPE SDR-17 sump pump riser pipe. Includes Connection to Existing Riser Flange per Detail 6 on Sheet 12 and Side Slope Trenching and Backfill Per Detail 5 on Drawing 12.LF110$ - 0
19Construct leachate sump pump riser pipe concrete headwall
per Detail 7 Sheet 12.LS1$ - 0
20Purchase and install leachate pump system, includes pump, control panel, and pressure sensor and programming.LS1$ - 0
21Purchase and Install leachate pump discharge assembly and connect to new forcemain, per Detail 7 on Sheet 12.LS1$ - 0
22Install 3"x6" HDPE Dual Contained Leachate Forcemain Pipe, Includes trenching and bedding per Detail 2 on Sheet 13, bends, and valves needed to extend below grade forcemain to new Frac Tank.LF320$ - 0
23Construct Cell 4A Water Truck Filling Station (Detail 3 on Sheet 13)
Includes Purchase and Placement of Frac Tank; Connection assembly of leachate forcemain to frac tank; Relocation of Existing 7HP pump (including construction of new reinforced concrete pump pad), Truck Filling J-Stand, and Cattle Guard; Mechanical Piping Connections and assembly between Frac Tank, Pump and J-Stand.LS1$ - 0
24Construct Pump and Treat Pond Water Truck Fill Station (Sheet 10)
Purchase and Installation of 7HP Pump, J-Stand and Cattle Guard (including mechanical connections between pond, pump, and J-stand ; Relocation of existing 5-hp pump (including construction of new reinforced concrete pump pad); relocation of Existing Inclined Tank and Cattle Guard; Puchase and Install Piping and Mechanical connetions between 5HP Pump and Inclined Tank; Purchase and Install Piping Connections between existing potable water valve and Inclined Tank.LS1$ - 0
25Cut and redirect existing Pump and Treat Discharge Line to New Pond, Includes capping of existing line on east side of pond.LS1$ - 0
26Purchase and Install Electrical Services and Connections per Electrical Plans.LS1$ - 0
27Construction TaxesIncurred Cost1$ - 0
BID TOTAL$ - 0

&"Arial,Italic"&8Bid Form "A" Page &P of &N

&"Arial,Italic"&8Bid Form "A" Page &P of &N

&"Arial,Italic"&8Bid Form "A" Page &P of &N

&"Arial,Italic"&8Bid Worksheet Page &P of &N

File details come from the government source that posted it. Updated .