SPECS.pdf
PDF 893 KB Posted
- Solicitation number
- 5-S176-Q-00616-00
- Issued by
-
Department of Energy Office of Science
About this file
These are technical specifications for an outdoor double-ended unit substation for Argonne National Laboratory's Building 206 Substation C/D Replacement Project. The specifications detail requirements for a 1500 KVA, 13,200V delta primary/480/277V wye secondary dry-type cast coil transformer system with low voltage switchgear, including specific technical requirements for transformer construction, electrical ratings, enclosure design, and performance characteristics. The unit substation must be manufactured by Square D, Powell, or SAI Advanced Power Solutions, with a NEMA 3R outdoor walk-in enclosure measuring 438"L x 121"W x 118"H, featuring integrated power monitoring systems, surge protection devices, and comprehensive environmental and operational controls.
The specifications outline extensive technical requirements including transformer specifications with four 2.5% voltage taps, 80°C temperature rise, copper windings, and specific insulation and thermal expansion characteristics. The switchgear must be a double-ended radial type with main-tie-main configuration, 2000A bus, microprocessor trip units, digital power monitoring, and integration capabilities with Argonne's existing electrical monitoring systems. Additional requirements include space heaters, interior and exterior lighting, receptacles, emergency lighting, and a 10-year warranty. The project involves pre-purchase of equipment with manufacturer's field service installation as a delayed service, targeting compliance with multiple IEEE, ANSI, and DOE electrical standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum and Acknowledgement Doc 02.doc | DOC document | |
| Addendum and Acknowledgement Doc.doc | DOC document | |
| Instructions to Offerors_G5-188019.doc | DOC document | |
| ANL-70 Request for Quotation.doc | DOC document | |
| Special Cl-Progress Pmts-02-SEP-2015.PDF | ||
| ANL-70B Reps and Certs Long-14-FEB-2025.PDF | ||
| SOW.docx | DOCX document | |
| Property Questionnaire-08-SEP-2023.PDF | ||
| Appendix A-71COM-13-FEB-2023.PDF | ||
| Appendix D8C-12-DEC-2023.PDF | ||
| Property Requirements-08-MAY-2025.PDF |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page: Cover Revision: 0
PROJECT MANAGEMENT ORGANIZATION (PMO)
INFRASTRUCTURE SERVICES DIRECTORATE (IS)
EQUIPMENT SPECIFICATIONS
FOR
BUILDING 206
SUBSTATION C/D REPLACEMENT PROJECT
ARGONNE NATIONAL LABORATORY
9700 SOUTH CASS AVENUE
ARGONNE, ILLINOIS 60439
ANL DOCUMENT NUMBER J206-119-W-T001
Approved, Project Manager (PM) S. Manasra Date
Approved, Construction Management Program Manager (CPM) Date
Concurred, Quality Assurance Representative (QAR)
C. Baltas
Date
Revision # 0
Date
Approved, Project Manager
P. Matton
6/26/25
6/26/25
7/01/2025
07/01/2025
SECONDARY UNIT SUBSTATION
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 1
SECTION 26 1100
SECONDARY UNIT SUBSTATION
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Secondary unit substation consisting of, transformer section, and low voltage switchgear secondary distribution section. US-C-D
1.2 RELATED SECTIONS AND WORK
A. Refer to the One-Line Diagram for size, rating, and configuration.
1.3 REFERENCES
A. ANSI/IEEE C57.12 - Switchgear and Transformers - Enclosure Integrity
B. ANSI/IEEE C57.13 - Requirements for Instrument Transformers
C. IEEE 48 - Test Procedures and Requirements for High-Voltage Alternating-Current Cable Terminations 2.5 kV Through 765 kV
D. NETA ATS - Acceptable Testing Specifications for Electrical Power Distribution Equipment
E. ANSI/IEEE C37.121- American National Standard for Switchgear - Unit Substations - Requirements
F. Department of Energy 10 CFR Part 431 (DOE 2016) – Energy Conservation Program for Commercial Equipment: Distribution Transformers Energy Conservation Standards;
Final Rule.
G. ANSI C37.13 - IEEE Standard for Low-Voltage Power Circuit-Breakers Used in Enclosures
H. ANSI C37.17 - Trip devices for AC and General Purpose DC Low-Voltage Power Circuit-Breakers
I. ANSI C37.20.1 - IEEE Standard for Metal-Enclosed Low-Voltage Power Circuit-Breaker Switchgear
J. IEEE C57.12.01 - General Requirements for Dry-Type Distribution and Power Transformers Including Those with Solid Cast and/or Resin Encapsulated Windings
K. IEEE C57.12.28 - Standard for Pad-Mounted Equipment - Enclosure Integrity
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 2
L. IEEE C57.12.50 - Requirements for Ventilated Dry-Type Distribution Transformers, 1- 500 kVA Single-Phase and 15-500 kVA Three-Phase, with High Voltage 601-34,500 Volts, Low Voltage 120-600 Volts
M. IEEE C57.12.51 - Standard for Ventilated Dry-Type Power Transformers, 501 kVA and Larger Three-Phase, with High Voltage 601 to 34500 Volts, Low Voltage 208Y/120 to 4160 Volts – General Requirement
N. IEEE C57.12.55 - Conformance Standard for Transformers – Dry-Type Transformers Used in Unit Installations, Including Unit Substations
O. IEEE C57.12.56 - Standard Test Procedure for Thermal Evaluation of Insulation Systems for Ventilated Dry-Type Power and Distribution Transformers
P. IEEE C57.12.58 - Guide for Conducting a Transient Voltage Analysis of a Dry-Type Transformer Coil
Q. IEEE C57.12.59 - Guide for Dry-Type Transformer Through-Fault Current Duration
R. IEEE C57.12.80 - IEEE Standard Terminology for Power and Distribution Transformers
S. IEEE C57.12.91 - Standard Test Code for Dry-Type Distribution and Power Transformers
T. IEEE C57.94 - IEEE Recommended Practice for Installation, Application, Operation, and Maintenance of Dry-Type General Purpose Distribution and Power Transformers
U. IEEE C57.96 - Guide for Loading Dry-Type Distribution and Power Transformers
V. NEMA 260 - Safety Labels for Pad-Mounted Switchgear and Transformers Sited in Public Areas
W. NEMA SG-5 - Power Switchgear Assemblies
X. NEMA SGH-3 - Low Voltage Circuit Breakers
Y. UL-1066 - UL Standard for Safety For Low-Voltage AC and DC Power Breakers Used in Enclosure
Z. UL-1558 - UL Standard for Safety for Metal-Enclosed Low-Voltage Circuit Breaker Switchgear
1.4 SUBMITTALS
A. Include front and side views of enclosures with overall dimensions shown; conduit entrance locations and requirements; nameplate legends; size and number of bus bars per phase, neutral, and ground; substation instrument details; instructions for handling and installation of switchgear; and electrical characteristics including voltage, frame size and trip ratings, withstand ratings, and time-current curves of all equipment and components.
B. Manufacturer’s installation instructions for switchgear and all components including circuit breakers, trip units, and external communication devices.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 3
C. All of the transformer nameplate information shall be supplied on the submittal drawings. The transformer impedance information shall be part of the submittal information.
1.5 DELIVERY, STORAGE, AND HANDLING
A. Accept products on site in factory shipping splits and verify damage.
B. Protect products from moisture and debris by storing in a clean, dry heated space.
Maintain factory wrapping or provide an additional heavy canvas or heavy plastic cover to protect units. Provide auxiliary heating in switchgear and transformer sections in accordance with manufacturer instructions.
1.6 OPERATION AND MAINTENANCE DATA
A. Include overcurrent protective device adjusting and testing instructions.
B. Test Reports: Indicate procedures and results for specified factory and field testing and inspection.
C. Include bus tightening intervals and procedures and overcurrent protective device maintenance procedures.
PART 2 - PRODUCTS
2.1 ACCEPTABLE MANUFACTURERS
A. Square D
B. Powell
C. SAI Advanced Power Solutions
2.2 SECONDARY UNIT SUBSTATION
A. Description: Secondary unit substation manufactured to NEMA 210.
B. Service Conditions:
1. Maximum Temperature: 104°F (40°C).
2. Altitude: 1000 feet.
C. Construction: Outdoor. NEMA 3R
D. Load Current Harmonic Factor: 0.05 per unit, maximum.
E. Configuration: Double-Ended Radial type, with secondary main-tie-main.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 4
2.3 TRANSFORMER SECTION EQUIPMENT
A. Description: 3-Phase, dry-type cast coil distribution transformer. Double-ended unit substation requires two identical transformers.
B. Capacity: 1500 KVA, AA (self-cooled).
C. Voltage: 13,200V delta primary, secondary voltage 480/277 wye.
D. Voltage Taps: Four 2-1/2% voltage taps, 2+ 2-.
E. Temperature Rise: 80°C rise over 40°C ambient.
F. High Voltage Basic Impulse Level: 95 KV for 15 KV Class.
G. Low Voltage Basic Impulse Level: 30kV
H. Impedance: 5.75 percent. The impedance tolerance shall be plus or minus 7.5 percent.
I. Construction
1. The transformer shall comply with DOE 2016 Energy Efficiency Requirements.
2. The transformer construction type shall be dry type, solid-cast, with high and low voltage windings separately cast in a mineral-filled epoxy that is reinforced with fiberglass. The cast shall provide complete, void-free resin impregnation throughout the entire insulation system. The insulating materials shall be rated for the service in accordance with UL insulation system ratings. The transformer shall have an average temperature rise of 80°C in a 40°C maximum, 30° average ambient as defined by IEEE C57.12.01.
3. Both high and low voltage windings shall be of copper conductors.
a. Each winding shall be separately cast as one rigid tubular coil, and arranged coaxially.
b. Each cast coil shall be fully reinforced with glass cloth, and cast under vacuum to provide complete, void-free resin impregnation throughout the entire insulation system.
c. Coils shall be supported by cast epoxy bottom supports and space blocks and spring loaded top blocks in order to absorb thermal expansion and contraction of the coils. Reinforcement with suspended particulate matter (filled-resin) is not acceptable.
d. The coil supports shall maintain constant pressure during thermal expansion and contraction of the coils. There shall be no rigid mechanical connection between high and low voltage coils.
e. The windings must not absorb moisture, and shall be suitable for both storage and operation in adverse environments, including prolonged storage in 100% humidity at temperature from -40oC to 40oC and shall be capable of immediately being switched on after such storage without pre-drying.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 5
4. The transformer core shall be constructed of high grade, grain-oriented silicone steel laminations, with high magnetic permeability. Magnetic flux density is to be kept well below the saturation point. The core shall be cruciform in shape, with mitered joints to keep core losses, excitations current and noise level at a minimum. The outside surfaces of the core shall be protected against corrosion by painting with a suitable coating after assembly. Core dipping is not acceptable.
5. Transformer percent impedance, as measured at the rated, nominal voltage connection, shall be per the target impedance of 5.75%. The tolerance on the target impedances shall be ± 7.5-percent of nominal value. Manufacturer shall submit target impedance on submittal.
6. The impulse rating of the high voltage windings must be at least equal to the basic impulse level specified by ANSI C57.12.90 for oil-filled transformers of the same voltage class, without the use of supplemental surge arresters.
7. Primary/High Voltage Termination Enclosure:
a. Full Length Air Terminal Chamber/Cabinet: A full height air terminal chamber in a weather-resistant metal enclosure around the transformer sidewall mounted bushings shall be provided. The enclosure shall extend downward to the transformer base level and extend above the top of the bushing centerline as required for bottom conduit/cable entry. The chamber/cabinet shall be provided with a hinged cover. The chamber/cabinet shall completely enclose all terminations. The chamber/cabinet shall be 20” deep or as necessary to allow the termination of shielded, medium voltage power cable with termination means for the type of bushings provided
8. Secondary/Low Voltage Termination Enclosure:
a. Flange: A flange shall be provided to connect the transformer low voltage terminals to switchgear as part of the unit substation.
9. Low voltage bus shall be silver plated copper. Ground bus shall be tin plated.
10. Surge Arresters: Metal-oxide, gapless-type distribution class surge arresters shall be installed by the manufacturer on the high voltage side of the transformer to provide additional protection against high voltage lightning or switching surges.
Arrester ratings shall be 15 kV suitable for a high voltage rating of 13.2 kV, delta windings.
11. Transformers shall be mounted in a suitable, ventilated, outdoor, NEMA 3R enclosure. All ventilating opening shall be in accordance with NEMA and NEC standards for ventilated enclosures. The transformer shall be provided with lifting devices and jacking pads designed to be flush with the transformer enclosure.
Provisions shall be provided for lifting the core and coil assembly. Refer to Unit Substation Enclosure section for additional requirements.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 6
2.4 LOW VOLTAGE SWITCHGEAR SECTION EQUIPMENT
A. Substation supplier shall provide transition section enclosure, bus bar, flexible bus, wiring, bus bar connector links, etc. from transformer secondary to secondary equipment.
B. Conform to requirements of ANSI C57.12.28.
C. The switchgear for this project shall be fully rated unless otherwise specifically noted in the specifications. Fully rated equipment shall be defined as equipment where all devices in that equipment shall carry a minimum of the short circuit current rating that is specified.
D. Factory-assembled, dead-front, metal-enclosed, and self-supporting switchgear assembly, and complete from incoming line terminals to load-side terminations.
E. Switchgear electrical ratings and configurations as shown on the drawings. The entire assembly shall be suitable for 600 volt maximum AC service.
F. Load Terminations: Accessible, NEMA 2 hole lugs suitable for copper conductors up to #600KCM, rated at 75°C.
G. Bus Material: Copper with silver plating, sized in accordance with ANSI temperature rise criteria of 65°C over a 40°C ambient. Bus shall be extended to the maximum vertical height in each section.
H. Bus Connections: Bolted, with Belleville-type washers. The bus arrangement shall be designed to permit future additions.
I. Bus bars shall be fully insulated, braced for minimum ANSI 4-cycle short-circuit withstand rating of 100,000 ampere rms symmetrical.
J. Provide a copper ground bus through the length of the switchboard, with a short time withstand rating equal to the largest circuit breaker in the assembly.
K. Each breaker compartment shall be isolated completely from other breaker compartments by grounded metal barriers. A front-hinged door with quarter-turn lath and padlock provisions shall be provided for each breaker and metering compartment.
L. Engraved identification nameplates for each breaker compartment and each control switch. Owner shall provide designation for breakers.
M. Terminals for all alarm, status, metering, etc. shall be located in a separate/barriered compartment for access without de-energizing equipment.
N. Future Provisions: Fully equip spaces indicated for future devices with bussing and bus connections.
O. Manual transfer interlocking: Provide a trapped key mechanical interlocking scheme to prevent the tie breaker from being closed while the two main breakers are closed. The opening of one of the main breakers will lock out the breaker in an open position, then allow the transfer of the key to the tie breaker and allow the closing of the tie breaker.
Keys shall not be reproducible to prevent copying.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 7
2.5 OVER-CURRENT PROTECTIVE DEVICES
A. Low-voltage Power Circuit Breakers with Microprocessor Trip Units: Provide Square D low-voltage power circuit breakers with Micrologic trip units. All power circuit breakers shall be UL listed for application in their intended enclosures for 100% of their continuous ampere rating. Provide power circuit breaker with two-step stored energy closing. Provide manual charging handle and electric charging motor where indicated as electrically operated. Electrically operated breakers shall be complete with 120V AC motor operators. The charging time of the motor shall not exceed six (6) seconds.
Provide with rating plug as required on drawings and electronic circuits for true rms current sensing, timing, and tripping for fully adjustable time current characteristics as indicated on the drawings including ground fault trip, instantaneous trip, long time trip, and short time trip. Trip settings shall be field programmable with a sealable clear cover. Provide draw-out construction with safety shutters to isolate breaker connections to the main bus when the breaker is removed. The primary contacts shall have an easily accessible wear indicator to indicate contact erosion.
B. Solid-state Microprocessor-based Trip Unit: Non-volatile memory, continuously adjustable, true RMS sensing with three current sensors. The trip unit shall be front mounted and shall allow access to all information without opening the cell door. The trip unit shall have information system that indicates mode of trip following an automatic trip operation. All circuit breakers shall have adjustments for long delay pickup and time, individual adjustments for short delay pickup and time, and adjustable instantaneous pickup. The trip unit shall have 4-character display, showing phase, neutral, and ground current. The metering accuracy shall be ± 2% of full scale. Trip unit shall have Modbus IP communications to communicate all status conditions, settings, and metering parameters per Section 26 0913.
C. Circuit breakers shall have arc energy reducing maintenance switching with local status indicators.
2.6 ACCESSORIES
A. Control Power Transformer(s): Fused primary and 240/120 volt fused secondary, UL RK1 current limiting fuses. Size the transformer to supply power for electronic metering and other internal auxiliary equipment. Provide a load center for power distribution as required. Primary power shall be derived from each transformer/bus.
B. Provide a traveling, rail-mounted breaker lifting trolley and winch.
C. Portable test kit for secondary injection testing and verification of trip units.
D. Mimic bus painted on front of switchgear showing power distribution and interlock controls. Minimum text size shall be 1/4” lettering.
E. Provide a surge protection device for each bus per Section 26 4300.
F. Provide a digital power quality meter for each bus per Section 26 0913.
G. Provide a voltage test station and indicator in the face of switchgear. Device shall be factory installed and wired.
1. Approved Manufacturer: Grace Engineered Products Safe-Side VTS #P-S11S21-
M3RX
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 8
2.7 EXTERNAL COMMUNICATION
A. Facility Monitoring and Control System (FMCS) Integration (final interconnect in future phase).
B. Circuit breakers shall have individual terminal points to report status and alarms for future connection to the FMCS, also known as building automation system.
C. At a minimum, the following shall be provided:
1. Breaker status (open, closed, tripped).
D. Electrical SCADA Integration:
1. Power quality meter and circuit breakers shall have MODBUS IP based network connection to interface with Argonne’s Electrical SCADA system to report status and alarms. Refer to Specification Section 26 0913 for additional information.
Equipment manufacturer to provide full data/register map and support as necessary to contractor for integration.
2. At a minimum, the following shall be displayed by the Electrical SCADA:
a. Power quality meter status, history, and metering per Specification Section 26 0913.
b. Electronic trip unit status, history, and metering per Specification Section 26 0913.
2.8 UNIT SUBSTATION ENCLOSURE
A. Construction: NEMA 3R outdoor, weatherproof housing with integral structural framing anchored to a concrete foundation. Stainless steel fasteners and hardware. Provide an complete bottom enclosure and elevated base to exclude rodents, water, snow, dirt, and debris.
B. Structural Design and Anchorage: Wind resistant up to 100 mph.
C. The exterior finish shall be unpainted aluminum or steel painted ANSI 49 medium gray using a phosphating process with baker polymer coating. The interior of the transformer and switchgear cabinets shall be painted for corrosion resistance or plated with cadmium or zinc. The cabinet interior shall be painted a light color for ease of viewing. The paint process shall be suitable for the installation environment.
D. All transformer and switchgear cable and bus compartments shall have hinged, gasketed doors with locking provisions.
E. Walk-in design at circuit breaker side of switchgear shall allow for NEC compliant working space with minimum 42” clear. Provide one door on each side with locking provisions. Door shall be minimum 36" wide and 72" high and equipped with panic hardware.
F. Provide space heaters in each transformer and each switchgear compartment (circuit breaker, cable, bus). All heaters shall be controlled by a thermostat and humidistat for outdoor operation. Power for the heaters shall be supplied from the accessory panel.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 9
G. Provide air conditioning and heating in the walk-in enclosure. All air conditioning and heating shall be controlled by a thermostat. Power for the air conditioning and heating shall be supplied from the accessory panel.
H. Provide two NEMA 5-20R GFI duplex receptacles with weatherproof covers inside the enclosure, located at each end. Provide two NEMA 5-20R GFI weather resistant duplex receptacles with extra duty while-in-use weatherproof covers on the exterior of the enclosure, located at each end.
I. Lighting:
1. Provide 4000K LED lensed striplights (Metalux SNLED or equal) inside the enclosure to provide average illumination of 300 lux measured at the floor. All interior lighting shall be connected to two three-way switches located inside each door.
2. Provide an emergency lighting unit with nickel cadmium battery and adjustable LED lamps (Sure-Lites AP2SQLED or equal) centered inside the enclosure.
3. Outside each door provide a 1400 lumen, 4000K LED wall pack with integral photocell, color to match enclosure (Lumark XTOR1B or equal). All exterior lighting shall be connected to a single pole switch located inside one door. Switch shall be clearly labeled “Exterior Lights”.
4. Power for lighting shall be supplied from the accessory panel.
J. Accessory Panel: 120/208V 3PH, 4W distribution system via integral stepdown transformer located within incoming cable compartment of switchgear. Distribution system shall provide power for accessory equipment/loads, and have spare breakers to accommodate miscellaneous loads. Panel shall be located and installed by manufacturer's field service, scheduled as a delayed service. The transformer shall be pre-wired by the factory.
K. Provide manual pushbuttons to activate maintenance mode for all circuit breakers shall be located on the exterior of the switchgear at each door. Pushbuttons shall be weather resistant and clearly labeled.
L. MAXIMUM OVERALL DIMENSIONS: 438”L X 121“W X 118“H.
2.9 ADDITIONAL REQUIREMENTS
A. Provide reasonable Perfluoralkyl and Polyfluoralkyl Substances (PFAS) free alternatives to products. PFAS compounds, following EPA's Safer Choice Standard or similar EPA-endorsed certification program. Reasonable determination will be based on PFAS-free product availability, performance and cost.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 10
PART 3 - EXECUTION
3.1 FATORY TESTING
A. The switchgear section shall be completely assembled, wired, adjusted and tested at the factory. After assembly, the complete switchgear shall be tested to ensure the accuracy of the wiring and the functioning of all equipment. The main bus system shall be given a dielectric test of 2200 volts for one minute between live parts and ground and between opposite polarities.
B. The wiring and control circuits shall be given a dielectric test of 1500 volts for one minute, or 1800 volts for one second, between live parts and ground, in accordance with ANSI C37.20.1.
C. A certified test report of all standard production tests shall be shipped with each assembly.
D. Factory Standard Tests: The transformer shall be factory tested in accordance with IEEE C57.12.91. Tests include:
1. Ratio tests using all tap settings.
2. Polarity and phase relation tests.
3. No-load losses tests.
4. Load loss tests.
5. Excitation current tests.
6. Percent Impedance at rated current.
7. Winding resistance measurement tests.
8. Induced and applied potential tests.
9. Partial discharge test.
10. Mechanical leak test.
E. Certification of Transformer Tests: Provide certification of all design, routine, and other tests listed in C57.12.01.
3.2 MANUFACTURER’S CERTIFICATION (DELAYED SERVICE)
A. Provide the services of a qualified, factory-trained manufacturer’s representative to assist the Contractor in installation and startup of the equipment specified under this section. The manufacturer’s representative shall provide technical direction and assistance to the Contractor in general assembly of the equipment, connections and adjustments, and testing of the assembly and components contained therein.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 1100 - 11
B. A qualified, factory-trained manufacturer’s representative shall certify in writing that the equipment has been installed, adjusted, and tested in accordance with the manufacturer’s recommendations as a delayed service
END OF SECTION
POWER MONITORING AND CONTROL SYSTEM
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 0913 - 1
SECTION 26 0913
POWER MONITORING AND CONTROL SYSTEM
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Power monitoring and control system
1.2 REFERENCES
A. ANSI C12 - Code for Electrical Metering
B. ANSI C57.13 - Requirements for Instrument Transformers
1.3 SUBMITTALS
A. Provide product data showing the type, size, rating, catalog number, manufacturer's names, and/or data sheets for all items to ensure compliance with these specifications.
Submit operation and programming manual.
1.4 REGULATORY REQUIREMENTS
A. System: UL listed.
1.5 SYSTEM DESCRIPTION
A. The power monitoring and controls (PMCS) shall consist of electronic power monitoring devices as designated on the project drawings and described herein. The system shall be capable of monitoring, displaying, logging, and communicating the true RMS measurements in this specification as a minimum level of performance. The system shall be designed so the maximum response time from an event or reading to displaying shall be 5 seconds.
B. Performance Statement: This specification section and the accompanying design documents describe the minimum material quality, required features, and operational requirements of the system. These documents do not convey every wire that must be installed and every equipment connection that must be made. Based on the equipment described and the performance required of the system, as presented in these documents, the Vendor and the Contractor are solely responsible for determining all wiring, programming and miscellaneous equipment required for a complete and operational system.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 0913 - 2
C. This section of the specifications includes the furnishing and manufacturer installation of the power monitoring and control system (PMCS) equipment required to form a complete coordinated system that is ready for connection and operation. It shall include, but is not limited to, remote devices for monitoring, communication interface hardware, and intercommunications wiring, indicated on the drawings and specified herein. It shall not include installation or connection to existing PMCS system, or update of software and programming
D. All meters on electrical distribution equipment shall be suitable for integration with Argonne’s ION system. Integration shall be by the installing contractor.
E. The following instantaneous and peak demand data shall be monitored, displayed, and communicated by the meter: Current (A), Voltage (V), Frequency (Hz), Real power (kW), Real energy (kW-h), Reactive power (kVAR), Reactive energy (kVAR-h), Apparent power (kVA), Apparent energy (kVA-h), Power factor. All measurements shall be taken per phase, phase-to-phase, phase-to-neutral, and/or three-phase total as appropriate to the measurement. Meters shall have revenue grade accuracy.
F. Meters shall be equipped with a display to provide local access to all metered quantities.
G. Provide current transformers compatible with the load being monitored (voltage, ampacity, cable size/quantity, etc.).
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Schneider Electric ION
B. Any other manufacturer meeting the specified requirements and capable of proper communication with Argonne National Laboratory’s existing ION system.
2.2 POWER MONITORING NETWORK
A. Ethernet communication ports shall be provided and have provisions for for future connection to the Argonne network. The installation shall include all power supplies, gateways, network drops, switches, routers, IP addressing, programming, software updates, etc. as required to incorporate the new monitoring devices into the existing ION PCMS at Argonne National Laboratory.
B. The PMCS shall be connected by means of the facilities ethernet backbone. Provide Ethernet gateway or communication cards as required to connect system to network jacks installed as part of the facility’s Ethernet network. Future network connections shall be established using industry standard Ethernet protocol, such as TCP/IP. All components shall work with facility’s Ethernet switches, router, and hub technology.
2.3 POWER MONITORING DEVICES
A. Power Quality Meter (ION 9000 Series):
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 0913 - 3
1. The following instantaneous readings shall be monitored, displayed, and communicated by the power quality meter:
a. Frequency, monthly maximum and minimum
b. Current, per phase RMS, 3-phase average RMS, apparent RMS, peak demand (15 minute sliding window)
c. Voltage, phase-to-phase and phase-to-neutral
d. Power factor, per phase and 3-phase total
e. Real power (kW), 3-phase total, peak demand, cumulative (kWH)
f. Reactive power (kVAR), 3-phase total
g. Total harmonic distortion (current and voltage)
h. Power analysis values
2. The current and voltage signals shall be digitally sampled at a rate high enough to provide true-RMS sensing through the 85th harmonic (minimum 128 times per cycle). All setup parameters required by the power quality meter shall be stored in nonvolatile memory and retained in the event of a control power interruption.
The meter shall maintain, in nonvolatile memory, maximum and minimum values for each of the instantaneous values reported, as well as the time and date of the highest peak for all peak demand readings.
3. The power quality meter shall be equipped with a display to provide local access to the all metered quantities.
4. Reset of the following electrical parameters shall also be allowed from the front of the meter:
a. Peak demand current
b. Peak demand power
c. Energy (MWH)
d. Reactive energy (MVARH)
5. Waveform Capture Capability: Waveform capture shall be for 60 cycles and initiated either manually using software or by user-defined alarm conditions. The data points shall be sampled in a manner that allows the original power signals with proper magnitude and phase relationships to be reconstructed.
Reconstruction of the original power signal from the stored data points shall have sufficient accuracy to allow steady-state power harmonic analysis that provides valid information on harmonic content for up to the 81st harmonic of the fundamental power frequency.
6. Disturbance Detection: Shall have sag and swell detection capability and log the waveform event.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 0913 - 4
7. The power meter shall have four (4) digital inputs and one (1) digital solid state output/KY pulse output.
8. Ancillary components associated with the power quality meter shall be as recommended by the manufacturer and shall be installed and wired inside enclosures. Ancillary components typically include the following:
a. Current transformers (CTs) and associated shorting block for the current inputs to the meter.
b. Disconnects and fuses for the voltage inputs to the meter.
c. If potential transformers (PTs) are used for the voltage inputs to the meter:
disconnects and fuses on the primary side of the PTs; fuses on the secondary side of the PTs.
d. Disconnects and fuses in the control power wiring to the meter.
e. If a control power transformer (CPT) is used: disconnects and fuses on the primary side of the CPT; fuses on the secondary side of the CPT.
B. Electronic Trip Units:
1. Electronic trip units shall be provided for all circuit breakers in the low voltage switchgear.
2. They shall provide the following breaker/trip unit information to the PMCS network:
a. Breaker sensor rating
b. Rating plug
c. Date/time of last trip
d. Type of last trip (overload, short circuit, ground fault)
e. Magnitude of phase and ground fault at time of last trip
f. Number of overload trips
g. Number of short circuit trips
h. Number of ground fault trips
3. The electronic trip units shall provide equivalent information to the digital power meter specified above.
4. Trip unit display shall be field selectable to display current, power, and energy.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 0913 - 5
PART 3 - EXECUTION
3.1 INSTALLATION
A. PMCS components, including system display units, metering devices, electronic trip units and transformer temperature monitors, shall be installed by the manufacturer, and wired and tested in the equipment as indicated on the drawings. All control power, CT, PT, and data communications wire shall be factory wired and harnessed within the equipment enclosure.
B. Where external circuit connections are required, terminal blocks shall be provided and the manufacturer's drawings must clearly identify the interconnection requirements, including wire type to be used.
SURGE PROTECTION DEVICES
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 4300 - 1
SECTION 26 4300
SURGE PROTECTION DEVICES
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Surge Protection Devices
1.2 QUALITY ASSURANCE
A. The specified unit shall be designed, manufactured, tested and installed in compliance with the above references. The unit shall be "Listed by Underwriters Laboratories" to
UL 1449.
B. Each unit shall be designed and manufactured by a qualified manufacturer of power conditioning equipment. The qualified manufacturer must have been engaged in the design and manufacturer of such products for a minimum of five years.
1.3 REFERENCES
A. ANSI/IEEE C62.33 - IEEE Guide on Testing of MOV components
B. ANSI/IEEE C62.35 - IEEE Guide on Testing of SAD components
C. ANSI/IEEE C62.41 - IEEE Recommended Practice on Surge Voltage in Low Voltage AC Power Circuits
D. ANSI/IEEE C62.45 - IEEE Guide on Surge Testing for Equipment Connected to Low Voltage AC Power Circuits
E. ANSI/UL 1449 Latest Edition - UL Standard for Safety for Surge Protective Devices
F. CBEMA - Computer Business Equipment Manufacturers Association
G. IEC 664 - International Engineering Consortium, Standard for Clamping Voltage
H. NFPA 70 - National Electrical Code (NEC)
I. UL 67 - Listed for Internal Panelboard Transient Voltage Surge Suppressors
J. UL 96A - Devices listed as approved for secondary surge arrestors (VZCA)
K. UL 248-1 - Fusing
L. UL 1283 - Electromagnetic Interference Filters, Fifth Edition
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 4300 - 2
1.4 SUBMITTALS
A. Shop Drawings: Should include device dimensions, mounting requirements including wire size and over-current protection device rating, nameplate nomenclature, electrical ratings, short circuit current rating, and test results as indicated below under "Testing, Warranty and Life Expectancy" as provided by an independent test lab or a UL certified test lab for the category(ies) of suppression device(s) specified using the appropriate IEEE test wave. Product data sheets with installation instructions for each size and type of device are required. Shop drawings submitted without the testing data as required by section this section will be rejected.
1.5 TESTING, WARRANTY AND LIFE EXPECTANCY
A. Manufacturer must provide independent testing on repetitive capability and maximum surge current rating of service entrance suppressor units. This shall be performed at a nationally recognized lab not affiliated with the manufacturer.
1. Single pulse surge current capacity: Single pulse surge current tested in a mode at rated surge currents.
2. Single pulse surge current capacity test: An initial UL 1449 defined 1.2 x 50µs, 6000V open circuit voltage waveform and an 8 x 20µs, 500A and 3kA short circuit current waveform shall be applied to benchmark the unit's suppression voltage (VPR).
3. A single 8 x 20µs waveform pulse of maximum rated surge current per mode shall then be applied. To complete the test, another UL 1449 surge shall be applied to verify the unit's survival. Survival is achieved if the suppression voltage measured from the two UL1449 surges does not vary by more than 10%.
B. Minimum Repetitive Surge Current Capacity:
1. Service entrance suppressor units should be tested repetitively at an independent lab to verify repetitive capacity.
2. Minimum Repetitive Surge Current Capacity Test:
a. An initial UL 1449 surge defined as 1.2 x 50µs, 6000V open circuit voltage waveform and an 8 x 20µs, 500A and 3kA short circuit current waveform shall be applied to benchmark the unit's suppression voltage.
b. A repetitive number of ANSI/IEEE C62.41.2-2002 (Category C3) surges, defined as a 1.2 x 50µs 10kV or 20kV open circuit voltage waveform and an 8 x 20µs 10,000A short circuit current waveform, shall then be applied at one-minute intervals.
c. To complete the test, another UL 1449 surge shall be applied to verify the unit's survival.
3. Survival is achieved if the suppression voltage (VPR) does not vary by more than 10%.
4. Proof of such testing shall be the test log generated by the surge generator.
C. Provide UL 1449 classification white sheet pages indicating the VPR (voltage protection rating) for each SPD unit submitted for this product using the 6kV/3kA combination wave surge.
D. Warranty: Ten (10) years. Includes workmanship, installation and programming.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 4300 - 3
E. No scheduled parts replacement or preventative maintenance shall be required.
PART 2 - PRODUCTS
2.1 DESCRIPTION
A. General: The unit shall provide transient voltage suppression, surge current diversion and high-frequency noise attenuation, when connected in parallel to the facilities distribution system. The unit MCOV shall not be less than 115% of the nominal system voltage. Operating frequency shall be for a 60 Hz system. The unit shall provide protection in all normal modes for "wye" and "delta" systems.
2.2 RATINGS
A. SPD-1; Service Entrance Suppressors:
1. 480-volt, 3 phase, wire, type 2, category C3 unit.
a. Surge current capacity: 100,000/200,000 amps per protection mode/phase
b. Nominal Discharge Current: 20 kA.
c. Mounting: Inside unit substation. Internal or external to low voltage switchgear.
d. Voltage Protection Rating: Refer to requirements below.
e. Components: Minimum component size of 20mm thermally protected metal oxide varistors (MOV).
f. Disconnect: Surge-rated disconnect with 200,000 SCCR.
2. Manufacturers:
a. Selected by manufacturer of unit substation.
B. Voltage Protection Rating:
1. Protection modes and UL 1449 voltage protection rating for surge suppression units per each mode (L-N, L-L, L-G, and N-G as appropriate).
a. 277/480 Volt, 3 phase, 4 wire. 1200 Volt L-N, L-G, N-G. 1800 Volt L-L.
C. Indication:
1. Each unit shall include solid-state indicators with externally mounted LED visual status indicators that indicate on-line status of each protection mode of the unit.
2. Each unit shall include an audible alarm with silencing switch to indicate when protection has failed.
3. Each unit shall contain form "C" contacts for remote indication of an alarm status.
06/13/2025 Bldg. 206 Substation C/D Replacement - Pre-Purchase 26 4300 - 4
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine equipment for size and type of surge protection device to be used to ensure physical compatibility.
B. Inspect surge protection device for any signs of physical damage due to shipping or handling before installing surge protection device.
3.2 INSTALLATION
A. The unit shall be pre-installed by the manufacturer.
B. Mounting Location:
1. The unit shall be installed as close as practical to the protected bus in accordance with applicable national/Local Electrical Codes and the manufacturer's recommended installation instructions. Connect the unit to the equipment using a conduit nipple.
2. Device shall be installed in a barrier compartment isolated from other components.
C. Connections:
1. Conductors from the protected bus to the unit shall not be any longer than necessary avoiding unnecessary bends. The conductor leads shall be twisted together and as short as possible. Connection shall be with mechanical lugs for each phase, neutral, and ground if applicable. Contractor shall provide wire and circuit breakers sized per the approved manufacturer's requirements. Maximum lead length from protected bus to surge protection device shall be per manufacturer's requirements, but no greater than 5'-0".
2. The surge protection unit shall be isolatable from the electrical distribution system via 3 pole circuit breaker.
D. General:
1. Check unit for proper operation of protection and indication under start-up.
2. Check unit to ensure all MOVs for each mode of protection are operational.
Verify integral fuse links are operational and have not melted.
3. Surge suppression devices shall not be installed ahead of the main service disconnect(s).
4. Coordinate location of surge protection device to allow adequate clearances for maintenance.
SCCR RATINGS LISTED FOR EQUIPMENT ARE MINIMUM REQUIREMENTS FOR BUS BRACING AND DEVICE RATING. ALL EQUIPMENT SHALL BE FULLY RATED UNLESS SPECIFICALLY NOTED AS SERIES RATED.
1.
2.
3.
8.
9.
10.
11.
13.
15.
16.
17.
18.
19.
20.
INDICATES DIRECT CONNECTION OF GROUND CONDUCTOR TO GROUND BUS.
CONDUCTOR AND CONDUIT SIZES ON THE LINE AND LOAD SIDES OF ALL NON-FUSIBLE
DISCONNECT SWITCHES SHALL BE IDENTICAL UNLESS NOTED OTHERWISE.
INDICATES DIGITAL POWER MONITOR.
INDICATES CURRENT TRANSFORMER, SIZE AS SPECIFIED.
MEDIUM LOAD BREAK ARROW / DEAD BREAK ELBOW.
MEDIUM VOLTAGE TERMINATIONS.
INDICATES LIGHTNING ARRESTORS.
DPM
LA
ONE LINE DIAGRAM NOTES
CIRCUIT BREAKER CHARACTERISTICS:
a. [LSIG] INDICATES FEATURES PROVIDED WITH SOLID STATE CIRCUIT BREAKER. [LONG
TIME (W/DELAY), SHORT TIME (W/DELAY), INSTANTANEOUS, GROUND FAULT].
b. [AF] INDICATES MOLDED/INSULATED CASE BREAKER FRAME SIZE, FOR ADJUSTABLE
TRIP BREAKERS.
c. [AT] INDICATES MOLDED/INSULATED CASE BREAKER TRIP UNIT, FOR ADJUSTABLE TRIP
BREAKERS.
D. [100% RATED] INDICATES MOLDED/INSULATED CASE BREAKER RATED FOR FULL
CONTINUOUS CAPACITY OF CIRCUIT BREAKER NAMEPLATE.
MEDIUM VOLTAGE SWITCH
DRAW-OUT CIRCUIT BREAKER
INDICATES POTENTIAL TRANSFORMER, SIZE AS SPECIFIED
INDICATES TRANSFORMER, SIZE AS SPECIFIED
KIRK KEY INTERLOCKK1
ELECTRICAL EQUIPMENT TAGS
TAG: DESCRIPTION:
RELATED
SPECIFICATION
MVSG-# MEDIUM VOLTAGE SWITCHGEAR 26 13 15
US-# UNIT SUBSTATION 26 11 00
SPD-# SURGE PROTECTION DEVICE 26 43 00
ELECTRICAL ABBREVIATION KEY
N.C. NORMALLY CLOSED
NIC NOT IN CONTRACT
N.O. NORMALLY OPEN
ABBR: DESCRIPTION:
TYP TYPICAL
UON UNLESS OTHERWISE NOTED
GFI GROUND FAULT INTERRUPTER
CPT CONTROL POWER TRANSFORMER
Argonne
NATIONAL LABORATORY
PROJECT TITLE
DRAWING TITLE
DESIGNED
DRAWN
CHECKED
FACILITY NUMBER
CADD NUMBER
APPROVED
FACILITY DOCUMENT NO. REV. NO.DRAWING NO.
JMLT-269-W-
211 WEST WACKER DR,
#1650
CHICAGO, ILLINOIS 60606
312.642.2600
FAX 312.642.6916
225 W Ohio Street - Suite 400; Chicago, IL 60654
(T) 312-467-0123 l (F) 312-467-0220
T. BALA
C. DEPPEN
J. LEESMAN J. LEESMAN
ELECTRICAL COVERSHEET
B206 - Electrical Pre-purchase
E-000
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
Illinois Design Firm Registration #184007637-0014
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2025 IMEG CORP.
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
2400220.04
ELECTRICAL SHEET INDEX
E-000 ELECTRICAL COVERSHEET
E-301 ELECTRICAL ONE-LINE DIAGRAM
E-302 UNIT-SUBSTATION FLOOR PLAN
GRAND TOTAL: 3
REV. NO. DESCRIPTION BY APVD DATE
ISSUED FOR BID 06.13.2025
MVSG-1, NEW 4-WAY 13.2KV SOURCE TRANSFER
SWITCHGEAR
600A/3P
FAULT
INTERRUPTER
600A/3P
FAULT
INTERRUPTER
N.C.
50/51 SEL751A 50/51 SEL751A
N.C.
1200AF
LSI
US-C-D, NEW UNIT SUBSTATION 'C' & 'D'
TRANSFORMERS AND SWITCHGEAR SHALL BE AN OUTDOOR
DOUBLE-ENDED UNIT SUBSTATION IN NEMA 3R WALK-IN ENCLOSURE.
TRANSFORMERS: 1500KVA, 13.2KV:480/277V, DRY TYPE CAST COIL,
CU WINDINGS, 80C RISE
SWITCHGEAR: 2000A, 480/277V, 3PH, 4W,100,000 SCCR, MAIN-TIE-MAIN
1200AF
LSI
#4/0 EQUIPMENT BOND
TO GROUND GRID
(PART OF FUTURE PHASE)
(TBD)AT
LSI
1200AF
2000AF
2000AT
100% RATED
[LSIG]
#500KCM TO GROUNDING
ELECTRODE
(PART OF FUTURE PHASE)
12KV
3 LA'S
1500 KVA, 13.2KV:480/277V
TRANSFORMER, DRY TYPE
CAST COIL, CU WINDINGS,
80C RISE, ENCLOSURE PER
SPECIFICATIONS
DPM
SPD-1
DPM
SPD-1
12KV
3 LA'S
EXISTING S&C VISTA 13.2KV
SWITCHGEAR 'B1-203'
600A/3P
FAULT
INTERRUPTER
600A/3P
FAULT
INTERRUPTER
N.C.
50/51 SEL751A 50/51 SEL751A
N.C.600A/3P LOAD
BREAK SWITCH
N.C.
EXISTING FEEDER
'B-1' FROM S&C
VISTA 13.2KV
SWITCHGEAR
'B1-203'
600A/3P LOAD
BREAK SWITCH
N.C.
EXISTING FEEDER
'B-1' TO S&C
VISTA 13.2KV
SWITCHGEAR
'B2-200'
EXISTING FEEDER
'B-1' TO BUILDING
208 13.2KV
SWITCHGEAR
600A/3P LOAD
BREAK
SWITCH
N.O.
VT
600A/3P LOAD
BREAK
SWITCH
N.C.
VT
#4/0 EQUIPMENT BOND
TO GROUND GRID
(PART OF FUTURE PHASE)
EXISTING S&C VISTA 13.2KV
SWITCHGEAR 'B3-203'
600A/3P
FAULT
INTERRUPTER
600A/3P
FAULT
INTERRUPTER
N.C.
50/51 SEL751A 50/51 SEL751A
N.C.600A/3P LOAD
BREAK SWITCH
N.C.
EXISTING FEEDER
'B-3' FROM S&C
VISTA 13.2KV
SWITCHGEAR
'B3-203'
600A/3P LOAD
BREAK SWITCH
N.C.
EXISTING FEEDER
'B-3' TO S&C
VISTA 13.2KV
SWITCHGEAR
'B2-200'
EXISTING FEEDER
'B-3' TO BUILDING
208 13.2KV
SWITCHGEAR
HATCH AREA INDICATES NOT IN
PROJECT SCOPE OF WORK.
GROUND NEUTRAL
#4/0 EQUIPMENT BOND
TO GROUND GRID
(PART OF FUTURE PHASE)
1500KVA, 13.2KV:480/277V
TRANSFORMER, DRY TYPE
CAST COIL, CU WINDINGS,
80C RISE, ENCLOSURE PER
SPECIFICATIONS
REMOVABLE LINK
(TBD)AT (TBD)AT
800AF
LSI
(TBD)AT
800AF
LSI
(TBD)AT
800AF
LSI
(TBD)AT
1200AF
LSI
(TBD)AT
800AF
LSI
(TBD)AT
1200AF
SPACE
LSI
800AF
(TBD)AT
LSI
800AF
(TBD)AT
LSI
1200AF
(TBD)AT
LSI
800 AF
(TBD) AT
LSI
1200AF
(TBD)AT
LSI
800AF
(TBD)AT
1200AF
SPACE
2000AF
2000AT
100% RATED
[LSIG]
2000AF
2000AT
100% RATED
[LSIG]
K1 K1 K1
KIRK KEY
INTERLOCK
2000 AMP BUS 2000 AMP BUS
15kVA LOCATED IN
INCOMING CABLE SECTION
(INSTALLED IN FACTORY)
PANEL L
60A, 120/208V, 3PH, 4W
INSTALLED BY MFR
FIELD SERVICES TEAM
AS A DELAYED
SERVICE
LOCATED INSIDE
WALK-IN
ENCLOSURE
NEUTRAL GROUND
REMOVABLE LINK
CIRCUIT BREAKER TRIP RATINGS TO BE
DETERMINED UPON SHOP DRAWING
APPROVAL. ALLOW FOR TRIP RATINGS
EQUAL TO THE FRAME RATING (TYPICAL).
Argonne
NATIONAL LABORATORY
PROJECT TITLE
DRAWING TITLE
DESIGNED
DRAWN
CHECKED
FACILITY NUMBER
CADD NUMBER
APPROVED
FACILITY DOCUMENT NO. REV. NO.DRAWING NO.
JMLT-269-W-
211 WEST WACKER DR,
#1650
CHICAGO, ILLINOIS 60606
312.642.2600
FAX 312.642.6916
225 W Ohio Street - Suite 400; Chicago, IL 60654
(T) 312-467-0123 l (F) 312-467-0220
T. BALA
C. DEPPEN
J. LEESMAN J. LEESMAN
ELECTRICAL ONE-LINE DIAGRAM
B206 - Electrical Pre-purchase
E-301
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
Illinois Design Firm Registration #184007637-0014
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2025 IMEG CORP.
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
2400220.04
NO SCALE
ONE LINE DIAGRAM - B206 - MVSG-1 & US-C-D
FLOOR
MOUNTED
CPT
FLOOR
MOUNTED
CPT
WALK-IN ENCLOSURE
REFER TO SPECIFICATIONS FOR DETAIL ON ACCESSORIES
DOUBLE-ENDED SWITCHGEAR
TRANSFORMER
INCOMING CABLE SECTION INCOMING CABLE SECTION
15kVA
TRANSFORMER
31'-5 55/64"438" MAXIMUM
M A
X
IM
U M
TRANSFORMER
NOTES:
1. ENTIRE UNIT SUBSTATION SHALL BE TYPE 3R ENCLOSURE.
Argonne
NATIONAL LABORATORY
PROJECT TITLE
DRAWING TITLE
DESIGNED
DRAWN
CHECKED
FACILITY NUMBER
CADD NUMBER
APPROVED
FACILITY DOCUMENT NO. REV. NO.DRAWING NO.
JMLT-269-W-
211 WEST WACKER DR,
#1650
CHICAGO, ILLINOIS 60606
312.642.2600
FAX 312.642.6916
225 W Ohio Street - Suite 400; Chicago, IL 60654
(T) 312-467-0123 l (F) 312-467-0220
T. BALA
C. DEPPEN
J. LEESMAN J. LEESMAN
UNIT-SUBSTATION FLOOR PLAN
B206 - Electrical Pre-purchase
E-302
REFERENCE SCALE IN INCHES
0 1 2 3
PROJECT #
Illinois Design Firm Registration #184007637-0014
IMEG CORP RESERVES PROPRIETARY RIGHTS, INCLUDING COPYRIGHTS, TO THIS
DRAWING AND THE DATA SHOWN THEREON. SAID DRAWING AND/OR DATA ARE
THE EXCLUSIVE PROPERTY OF IMEG CORP AND SHALL NOT BE USED OR
REPRODUCED FOR ANY OTHER PROJECT WITHOUT THE EXPRESS WRITTEN
APPROVAL AND PARTICIPATION OF IMEG CORP. © 2025 IMEG CORP.
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
263 Shuman Boulevard, SUITE 550
NAPERVILLE, IL 60563
630.527.2320 FAX: 630.527.2321
www.imegcorp.com
2400220.04
NO SCALE
UNIT SUBSTATION 'US-C-D' FLOOR PLAN
| 20250613 Drawings B206 Pre-Purchase.pdf |
| Sheets |
| E-000 - ELECTRICAL COVERSHEET |
| E-301 - ELECTRICAL ONE-LINE DIAGRAM |
| E-302 - UNIT-SUBSTATION FLOOR PLAN |
File details come from the government source that posted it. Updated .