This document is a Request for Quotation (RFQ) issued by Argonne National Laboratory for a Building 206 Substation C/D Replacement Project. The solicitation seeks an outdoor double-ended substation with components and accessories, with acceptable manufacturers including Square D, Powell, and SAI Advanced Power Solutions. The RFQ is structured around four primary tasks: detailed shop drawings, substation fabrication and assembly, equipment shipment, and optional field testing and commissioning.
The solicitation is structured with a lowest price, technically acceptable (LPТА) evaluation methodology and requires submission by July 25, 2025. The contract is associated with the Department of Energy Office of Science and operates under Contract No. DE-AC02-06CH11357. Vendors must provide supporting documentation including a published price list or customer invoice, complete the attached representations and certifications, and adhere to specific requirements regarding country of origin (with U.S. component percentages increasing from 60% to 75% across different calendar years). The RFQ includes multiple attachments such as terms and conditions, intellectual property provisions, a statement of work, and technical specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum and Acknowledgement Doc 02.doc | DOC document | |
| Addendum and Acknowledgement Doc.doc | DOC document | |
| Instructions to Offerors_G5-188019.doc | DOC document | |
| SPECS.pdf | ||
| Special Cl-Progress Pmts-02-SEP-2015.PDF | ||
| SOW.docx | DOCX document | |
| Property Questionnaire-08-SEP-2023.PDF | ||
| Appendix A-71COM-13-FEB-2023.PDF | ||
| Appendix D8C-12-DEC-2023.PDF | ||
| Property Requirements-08-MAY-2025.PDF | ||
| ANL-70B Reps and Certs Long-14-FEB-2025.PDF |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ANL-70 (February 22, 2013)
UCHICAGO ARGONNE, LLC
OPERATOR OF
ARGONNE NATIONAL LABORATORY
BLDG. 201 OCF, 9700 S. Cass Ave., Lemont, IL 60439
(CONTRACT NO. DE-AC02-06CH11357)
REQUEST FOR QUOTATION
| TO ALL PROSPECTIVE OFFERORS: |
| THIS IS NOT AN ORDER |
NOTICE:
1. The right is reserved to accept or reject quotations on each item separately unless your quotation states otherwise.
2. The right is reserved to accept minor deviations from specifications herein listed or referenced.
3. Firm prices are requested. If other than firm prices are quoted, conditions of escalation are to be stated.
4. If material is packaged in returnable containers the amount of deposit, if any, is to be stated together with instructions for returning.
5. Terms and Conditions referenced below will apply to any resulting Purchase Order.
| Address Reply To: |
| MOLLY HUNTER |
| PHONE: |
| (630)252-3094 |
| Date |
| 07/09/2025 |
| Inquiry No. |
| 5-S176-Q-00616-00 |
| Quotation must be received by: |
| 07/25/2025 |
| ITEM NO. |
| QUANTITY |
| DESCRIPTION |
| UNIT PRICE |
| TOTAL |
THE ENCLOSED BOOKLET OF Argonne Representations and Certifications is included as part of this request and must be completed, signed and returned with your quotation.
Please furnish quotation to supply the materials and/or services indicated on page two(2). Please send any inquiries to Molly Hunter at mollyhunter@anl.gov Offeror is requested to furnish the following to support the offered price:
a. A published price list that is available to all customers.
b. If a published pricelist is not available, please furnish a copy of an invoice to another Customer (Customer name can be removed) for the same or similar products/services as being requested by Argonne.
*EVALUATION IS BASED ON LOWEST PRICE, TECHNICALLY ACCEPTABLE METHODOLOGY*
Any resulting Purchase Order will be subject to the Argonne Terms and Conditions attached hereto and made part of hereof and will be exempt from Illinois Occupation and Use Taxes and from Manufacturers and Retailers Excise Taxes.
We quote you F.O.B. Destination. Shipment can be made in days from receipt of order. Country of Origin*: ________________
| Cash Terms |
| Net 30 days |
| Will Ship Via* |
NAICS:
*If Shipment will not be made via FedEX, UPS, or USPS, Please provide estimate of weight and volume _________________________________________ cft
COMPLETE AND RETURN ONE COPY
PLEASE MARK “NO BID” IF YOU CANNOT QUOTE
AUTHORIZED SIGNATURE
| ITEM |
| NAME |
| QTY |
| UNIT |
| UNIT PRICE |
| EXTENDED PRICE |
| DESCRIPTION |
| TIMELINE IN WEEKS FROM PO |
| 0001 |
| Task 1: Drawings |
| 1 |
| Each |
Substation Detailed Shop drawings
| 0002 |
| Task 2: Fabrication and Assem. |
| 1 |
| Each |
Substation fabrication and assembly completed for onsite inspection of hardware at manufacturer
| 0003 |
| Task 3: Substation Shipment |
| 1 |
| Each |
Substation equipment and all associated OEM manuals and documentation delivered to Argonne.
The Laboratory may increase the quantity of supplies or extend the term of this contract in accordance with option items quantities and option prices indicated herein.
| OPTION ITEM |
| NAME |
| QTY |
| UNIT |
| UNIT PRICE |
| DESCRIPTION |
| TIMELINE IN WEEKS FROM OPTION EXECUTION |
| 0004 |
| Task 4: Testing and Commissioning |
| 1 |
| Each |
Substation field testing, operational verification, and commissioning.
*Country of Origin should be consistent with the definition stated in FAR 52.225-I for Buy American-Supplies, in which "the cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind as those that the agency determines are not mined, produced, or manufactured in sufficient and reasonably available commercial quantities of a satisfactory quality are treated as domestic. Components of unknown origin are treated as foreign."
Applicable Documentation:
The following applicable documentation is attached hereto and made a part hereof:
1. Appendix “A” Argonne Terms and Conditions for Commercial Items and Services, ANL-71-COM, dated 2/13/2023 (REVIEW)
2. D-08-C Intellectual Property Provisions, Commercial Supplies and Services Requiring Delivery of Data, ANL 562IP dated 06/2020 (REVIEW)
3. Statement of Work, “Building 206 C/D Substation” dated 5/27/2025 (REVIEW)
4. Specifications, “BUILDING 206 SUBSTATION C/D REPLACEMENT PROJECT” dated 6/26/2025 (REVIEW)
5. Progress Payments Based on Milestones, PD-133, dated 9/2/2015 (REVIEW)
6. Control of Government-Owned Property – Contractor Requirements, PD-150, dated 08/31/2023 (REVIEW)
7. Property Management Self-Evaluation Questionnaire, ANL-642, dated 09/08/2023 (SIGN AND RETURN)
8. Pre-Award Information, ANL-70B (Long Version) – Reps & Certs, dated 1/13/2025 (SIGN AND RETURN)
Please note, inapplicable clauses are self-deleting.
All quotations shall be responsive to the terms and conditions made a part of this solicitation. Any exceptions taken shall be detailed and refer to specific Articles of the Applicable Documentation.
PAGE
File details come from the government source that posted it. Updated .