Specifications for the PIT ARSR Envelope Seal and Roof Guardrail Upgrades.pdf
PDF 3 MB Posted
- Solicitation number
- 6973GH-20-R-00093
About this file
This solicitation describes requirements for building envelope sealing, roof guardrail upgrades, and miscellaneous work at the PIT ARSR facility in Oakdale, Pennsylvania. The Federal Aviation Administration is seeking a firm-fixed price construction contract to perform work including perimeter roof guardrail replacement, building envelope sealing through wall opening infill, installation of wall exhaust fans, and exterior defect repairs. Proposals are due by May 22, 2020. The solicitation provides instructions for site visits and requires questions in writing by May 15. Offerors must be registered in SAM and complete and return required forms with their responses.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS
ENVELOPE INFILL AND ROOF GUARDRAIL
UPGRADES
AT PIT ARSR (PIT)
DECEMBER 2019
ARSR Facility (PIT), Oakdale, PA DEC 2019 Envelope Infill & Guardrail Replacement
TABLE OF CONTENTS 00 01 10 - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL CONDITIONS
01 10 00 SUMMARY OF WORK
01 14 10 PROJECT MANAGEMENT
01 33 00 SUBMITTAL PROCEDURES
01 40 00 CONTRACTOR QUALITY CONTROL
01 50 00 TEMPORARY FACILITIES AND CONTROLS
01 52 16 SAFETY REQUIREMENTS
01 58 13 POSTING OF NOTICES
01 71 33 PROTECTION OF WORK AND PROPERTY
01 74 13 CONSTRUCTION CLEANING
01 77 00 CLOSEOUT PROCEDURES
01 77 10 FINAL CLEANING
01 78 36 WARRANTIES AND GUARANTEES
DIVISION 02 - EXISTING CONDITIONS
02 41 10 SELECTIVE DEMOLITION
02 82 33 REMOVAL AND DISPOSAL OF ASBESTOS CONTAINING MATERIALS
DIVISION 03 - CONCRETE
03 30 00 MODIFIED POLYMER CONCRETE
DIVISION 04 – MASONRY
04 20 00 UNIT MASONRY
DIVISION 05 - METALS
05 50 00 METAL FABRICATIONS
05 52 13 PIPE AND TUBE RAILINGS
DIVISION 08 - OPENINGS
08 91 00 LOUVERS AND VENTS
DIVISION 09 - FINISHES
09 29 00 GYPSUM BOARD
09 91 00 PAINTING
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
23 05 13 MOTOR REQUIREMENTS
23 34 23 POWER VENTILATORS
APPENDIX
Appenix-1: FAA-C-1217H ELECTRICAL WORK, PREMISES WIRING Appenix-2: ORDINANCE NO. 16782 ALLEGHENY COUNTY HEALTH DEPARTMENT
RULES AND REGULATIONS ARTICLE XXI AIR POLLUTION CONTROL
ASBESTOS ABATEMENT
Appenix-3: PLM BULK ASBESTOS LABORATORY REPORT
Summary of Work 01100 - 1
SECTION 01100 – SUMMARY OF WORK
PART 1 -
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. Facility Description:
1. Facility: The Pittsburgh ARSR facility is on a campus located in the town of Oakdale, Pa., Allegheny County. The facility consists of a 60 ‘x 60’ square (3600 SF footprint) concrete building that is approximately 86 ft high. Atop the roof is a 50’ high, spherical shaped fiberglass enclosure (Radome) that rests atop a 3’ high radome ring wall comprised of structural steel.
B. Project Description:
1. Perimeter Roof Guardrail Upgrade & Miscellaneous Items
a. Approximately 240 linear feet of perimeter roof guardrail will be removed and replaced with an OSHA compliant guardrail system to be anchored to the facade of the concrete structure. This work shall be coordinated with the temporary removal and reinstallation of guardrail grounding and lightning protection systems by FAA.
b. Provide dedicated post supports for mounting four existing BUEC antennas at an antenna base height of 44.5 inches above the roof. FAA will remove and remount the BUEC antennas and related cables in coordination with the guardrail replacement.
c. Replace two BUEC cable enclosures (splice boxes) with new stainless steel enclosures per drawings. Coordinate with FAA for removal and rerouting the BUEC cables through the new enclosures.
d. Remove abandoned and unused communication switches, receptacle, cables, J-boxes and conduits per the drawings. Two existing conduits penetrating the roof shall be cut and capped above the roof line.
e. Remove four abandoned tripod dish support stanchions as follows:
(1) Cut/grind all tripod legs just below the top of the existing pitch pockets; (2) Top off pitch pockets with new pitch; (3) Cap pitch pockets with material to match the existing roof membrane; (4) Paint potential trip hazards yellow.
f. All roof work will be performed during Radome shutdown. Provide a coordinated and detailed Phasing Plan and Schedule for all work per drawings and specifications.
2. Seal Building Envelope & Install Wall Exhaust Fans
a. Remove exterior louvers, vent hoods/canopies and anchors at existing unused exterior wall openings, and repair resulting concrete damage using approved methods. Related unused air handlers inside shall have their intake duct sections removed per drawings. Remaining ductwork shall be blanked off using sheet metal.
b. The existing unused ventilation openings of varying sizes (approx. 160 sq.ft) through the 10” exterior walls shall be infilled with CMU block mortared and secured to the existing steel channels that frame the openings using welded studs and interior/exterior finished to match their respective adjacent surfaces.
Summary of Work 01100 - 2
1) For openings in walls where interior GWB finish exists, infill will consist of 8” CMU covered with 2” rigid board (polyisocyanurate) insulation, furred, and then covered with GWB. Finishes shall match the adjacent walls.
Associated asbestos containing GWB joint compound will be removed per drawings.
2) For openings in walls where exposed CMU/concrete interior finish exists, infill shall consist of 10” CMU with the interior parged and finished to match the adjacent walls.
3) If a cable passes through the existing opening, it shall be routed through a 1” PVC conduit and sealed.
4) A stainless steel exterior drip edge shall be installed above the exterior of each sealed opening to protect the existing steel channel from corrosion.
The exterior of all infilled openings will be parged to match the color and texture of the adjacent concrete wall.
c. Existing exterior wall openings to be sealed were approximated as follows:
1) Southeast Elevation:
a) First Floor: 26”x26”, 40”x24” and 48”x24”
b) Second Floor: 24”x24” and 118”x 48”
c) Third Floor: 42”x36”
d) Fourth Floor: 23”x22”and 23”x22”
e) Fifth Floor: 23”x22”
2) Southwest Elevation:
a) Second Floor: 77”x35”
3) Northeast Elevation:
a) Third Floor: 42”x36” (partial closure)
b) Fifth Floor: 82”x32”
4) Northwest Elevation:
a) Third Floor: 42”x36”
b) Fourth Floor: 29”x24” and 18”x12” and 12”x24” (existing CMU infilled - exterior parge coat only)
c) Fifth Floor: 23”x22”, 23”x22”.
ci. Three defunct 24”x24” wall exhaust fans will be removed and replaced in kind on the 1st, 2nd and 3rd floors to provide ventilation for the building. Gravity backdraft dampers, louvers/hoods shall be provided per drawings. During warm weather conditions, thermostat in automatic mode, will cycle exhaust fan operation. Exhaust fan controls shall also provide for manual operation for continuous ventilation when necessary. Exhaust fans shall be wired to the nearest available power panel on their respective floors.
3. Repair Exterior Defects
a. Contractor shall remove (1) steel platform and canopy, and (1) caged ladder from the northwest exterior wall. Remove all associated anchors and repair resulting concrete damage using approved methods.
b. From visual inspection, the FAA has established a baseline repair area of 960 sq.ft. for surface defects at the exterior of the ARSR tower. Contractor shall repair visible exterior concrete defects including but not limited to spalling and rebar pop-outs in accordance with the drawings and specifications. All areas of loose and/or cracked concrete shall be removed, all exposed rebar shall be cleaned all around, wire brushed, primed with rust inhibitor per the concrete patch manufacturer directions (see specifications for details).
Summary of Work 01100 - 3
c. Perform concrete inspection/sounding services as necessary to identify additional concrete surface defects that are to be repaired by the contractor on a unit cost basis. CONTRACTOR SHALL PROVIDE A SEPARATE UNIT COST BID FOR REPAIRS BEYOND THE BASELINE REPAIRS (refer to drawings).
d. Exterior asbestos caulking and backer rod shall be removed and replaced for all exterior joints. (Refer to Allegheny Global PLM Bulk Asbestos laboratory Report dated July 1 ,2014). Vertical joints each measuring 90 lineal feet in height at the sides of each of the twelve pilasters for a total of 2,160 lineal ft. of joint abatement and remediation. Contractor shall provide third party air monitoring for ACM abatement in accordance with FAA standards.
4. Note: Although abatement is limited to asbestos containing caulking and backer rod, the contractor is advised of the presence of asbestos containing materials used in the existing roofing materials, caulking and GWB joint compound. The contractor shall take all precautions to protect personnel from exposure to asbestos containing materials during this project. The contractor shall comply with USEPA 40 CFR763,Sub part E-Asbestos Hazard Emergency Response Act (AHERA) 40 CFR 61, Subpart M National Emissions Standards for Hazardous Air Pollutants (NESHAP) and OSHA-29 1926.1101 Besides the backer rod, caulking and GWB joint compound, the overall intent is to manage any other asbestos in place.
5. Contractor shall provide a coordinated phasing plan and schedule for all work per drawings and specifications.
1.2 WORK SCHEDULE
A. All work on the Roof shall be completed within 20 calendar days of outage from Notice to Proceed, based on scheduled daily Radome outages. Prior to commencement of this work, the Contractor shall submit a coordinated and detailed phasing plan and schedule to the FAA Contracting Officer and to the FAA System Support Center Manager. Acceptable hours of work are M-F, 7:00am –4:00pm (9 hour days during outages). All project construction work shall be completed within 75 calendar days from Notice to Proceed, excluding holidays.
1.3 ACCESS TO JOBSITE
A. Contractor personnel shall contact an FAA escort at the site perimeter gate for daily access to the jobsite. Contractor personnel will be continually escorted by FAA. All contractor personnel working on this project shall be US citizens and must have a valid government issued form of identification and available upon request.
1.4 COORDINATION WITH FACILITY
A. Contractor shall closely coordinate all work activities with the Contracting Officer’s Technical Representative (COTR) and FAA System Support Center Manager (SSC Mgr.) so as not to impact the operation of the facility.
1.5 OTHER WORK
Amanda J Garen Highlight
Summary of Work 01100 - 4
A. Contractor will be made aware of other ongoing maintenance and/or construction activity that may be underway at this facility.
B. Cooperate fully with separate entities so work on other activities can be carried out smoothly, without interfering with or delaying work under this Contract.
1.6 IMPACT TO FACILITY
A. Contractor is made aware that this facility is responsible for the control and navigation of air traffic. Contract work or workers cannot impact operations at this facility. Unauthorized and/or unexpected interruption to the operation of this facility may jeopardize the safety of the flying public. Closely coordinate all proposed activities with the Contracting Officers Technical Representative (COTR) and FAA System Support Center Manager.
B. This facility will be under temporary outage in order to provide safe access to the work area.
1.7 IMPACT TO SURROUNDING AREAS
A. Contractor is advised that this facility is located adjacent to the Oakdale community and the Contractor shall not impact the surrounding areas in any way during the project. Contractor shall assure that the habitat of the area is not adversely impacted.
1.8 PROTECTION DURING CONSTRUCTION
A. Contractor is responsible for providing the proper protection of the facility during construction to include protection from moisture, rain, noise, fumes, dust, damage to existing walls, floors, roofs and adjacent areas of the site. Contractor cannot leave area exposed to the elements for any duration that could potentially damage existing work.
1.9 TEMPORARY FACILITIES
A. The Contractor shall provide temporary equipment for construction needs to ensure safe working conditions, public safety and security in compliance with the requirements of 29 CFR
1926.26 and subpart D.
B. The contractor shall be permitted to use facility building service power. UNDER NO
CIRCUMSTANCES SHALL THE CONTRACTOR BE ALLOWED TO HOOK INTO
THE CRITICAL POWER SOURCE or UPS POWER SOURCE. Closely coordinate temporary electrical requirements with on site FAA personnel.
C. The contractor is advised that running water and sanitary facilities are not available at this location.
1.10 CLEANUP AND RESTORATION
Summary of Work 01100 - 5
A. Contractor is responsible for maintaining the worksite in a clean and safe condition during the work shift as well as after work hours. The contractor shall restore the site to it’s original condition upon completion of the project.
1.11 PRE-BID SITE VISIT
A. A pre-bid site visit is highly recommended. Site visits can be arranged by contacting Russ Classi, FAA Project Engineer, russell.classi@faa.gov, 718-553-3376 and Fran Wyrick, FAA Site SSC Technician, Francis.J.Wichryk@faa.gov, 724-693-8964.
1.12 PERMITS
A. If permits are required, the General Contractor will secure the necessary permits.
END OF SECTION 01100
mailto:russell.classi@faa.gov mailto:Francis.J.Wichryk@faa.gov
PROJECT MANAGEMENT 01 14 10 - 1
SECTION 011410 – PROJECT MANAGEMENT
PART 1 - GENERAL
1.1 SUMMARY
A. This section describes the required performance of administrative project related requirements necessary for the proper conduct of the work as indicated in this section.
1.4 SUBMITTALS
A. Show temporary facilities, temporary egress paths, utility hookups, staging areas, and parking areas for construction personnel.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Materials used on this project shall be in accordance with the requirements of the individual sections of these specifications and drawings.
2.2 MATERIALS CONTAINING ASBESTOS
A. No materials or products, which contain asbestos in any form, shall be introduced for use on this project.
2.3 LEAD FREE PAINT AND FLASHING
A. Only lead free paint and flashing materials may be used on this project.
PART 3 - EXECUTION
3.1 WORK SCHEDULE
A. Normal working hours are 0700 to 1600, Monday through Friday (except U.S. Federal holidays).
Contractor requests to work outside normal working hours require RE approval. However, the RE has full discretion to approve or disapprove, or withdraw approval of, requests. If the contractor desires to work outside normal hours (including Saturdays, Sundays, and holidays), he shall submit his written request to the RE at least 48 hours in advance. Some typical constraints on working outside normal working hours are:
PROJECT MANAGEMENT 01 14 10 - 2
1. The Contractor’s request must be made at least two days in advance (e.g., request received by close of business Wednesday for work on following Saturday). Prior to submitting the request, the Contractor must coordinate as needed (such as utility outages) and have all required people and materials for the work that will be performed.
2. A Contractor with quality or safety problems (as determined by the RE) will be restricted to normal working hours.
3. A Contractor who fails to correct deficiencies within a reasonable time (as determined by the RE) will be restricted to normal working hours or may be allowed to work outside normal working hours only to correct those deficiencies.
4. The Contractor shall schedule his work to cause the least amount of interference to normal activities.
3.2 FIELD MEASUREMENTS
A. Contractor is responsible for making complete field measurements. Check all dimensions at the job site for components requiring fit to existing conditions. Check shop drawings and indicate the actual dimension available at all locations.
3.3 PROJECT SAFETY AND HEALTH PROGRAM REQUIREMENTS
A. All on-site work under this Contract shall be performed in compliance with the requirements of all Federal and State Occupational Safety and Health laws and regulations as they apply to construction site activity.
1. Comply with applicable Occupational Safety and Health Standard (29 CFR 1910 and 1926) promulgated pursuant to authority of the Occupational Safety and Health Act of 1970.
2. Comply with any other applicable Federal, State, or local regulations governing workplace safety to the extent that they do not conflict with other clauses of this contract. If a conflict exists between sections of this Contract, the more stringent requirement takes precedence.
3. Take all other proper precautions to protect the safety and health of the contractor’s employees, Federal Aviation Administration employees, and the public. Provide and maintain barricades, warning signage, PPE, guard rails, lighting devices and other protective devices necessary to warn and protect the workmen and general public from hazards at the construction site.
4. Contractor shall maintain a Project Safety and Health Plan which shall address site-specific safety and health requirements and procedures to include, but not limited to fall protection, electrical safety, scaffold safety, cranes, steel erection, welding, burning and cutting safety, concrete and roofing work.
5. In addition to compliance with applicable statutory and regulatory requirements, the Project Safety and Health Plan shall contain provisions for mandatory safety orientation for every contractor, subcontractor, and vendor employee assigned or sent to the site. Safety orientation shall cover as a minimum the rules and regulations governing on-site construction activities, special known hazards, accident prevention, emergency procedures, and personal protection equipment requirements. Upon completion of the safety orientation, each attendee will be issued a hard hat sticker. No contractor, subcontractor or vendor employee will be
PROJECT MANAGEMENT 01 14 10 - 3
allowed to enter or remain on-site without a hard hat bearing a valid safety orientation sticker.
6. As work progresses, the Plan shall be updated to adapt to new situations and new conditions.
Changes to the Project Safety and Health Plan shall be made only with full concurrence of the COTR.
7. If any unforeseen hazard should become evident during the performance of the work, bring such information to the attention of the COTR, verbally and in writing. Take the necessary action to re-establish and maintain safe working conditions.
8. The Project Safety and Health Plan shall include MSD sheets for materials and products to be used on the project. MSD sheets shall be maintained at the project site where all employees will have access.
B. The Project Superintendent shall act as Safety Director and be responsible for the implementation, execution and oversight of the Project Safety and Health Plan. The Superintendent shall have authority from the contractor to stop work to abate hazardous conditions should they arise or unsafe practices, and to eject any contractor, subcontractor, or vendor employee from the project site for failure to comply with safety requirements. The Project Superintendent’s authority, responsibilities, and duties in the capacity of Safety Director shall be incorporated as part of the written Project Safety and Health Plan. These responsibilities shall include, but not be limited to conducting subcontractor pre-construction safety program reviews, conducting the employee safety orientation training, conducting weekly safety meetings, conducting daily site safety inspections, auditing subcontractor safety compliance, conducting accident investigations, and preparing required periodic and special safety reports.
C. When the Contractor is notified by the COTR of non-compliance with the safety or health provisions of this contract, the contractor shall immediately, unless otherwise instructed, correct the unsafe or unhealthy condition. If the Contractor fails to comply promptly, all or part of the Work will be stopped by notice from the COTR. There will not be any allowance for time or compensation due to work stoppage for an unsafe condition.
D. The contractor will maintain an accurate record of exposure data and all accidents incidental to work performed under this Contract. The contractor must report the exposure data and accidents to the COTR.
E. All subcontracts and vendor purchase orders related to this project shall contain provisions requiring compliance with the contractor’s approved Project Safety and Health Plan.
F. Prior to commencing construction, representatives of the Contractor, including the Project
Superintendent, shall hold a Safety Meeting with designated representatives of the Contracting Officer for the purpose of reviewing the approved Project Safety and Health Plan and discussing the implementation of the plan.
G. The Contractor shall take all necessary precautions to prevent injury to the public, occupants, or damage to property of others. The public and occupants include all persons not employed by the Contractor or a subcontractor.
H. Wherever practical, the work area shall be fenced, barricaded or otherwise blocked off from public or occupants to prevent unauthorized entry into the work area.
PROJECT MANAGEMENT 01 14 10 - 4
5. Provide traffic barricades and traffic control signage where construction activities occur in vehicular areas.
6. Corridors, aisles, stairways, doors and exitways shall not be obstructed or used in a manner to encroach upon routes of ingress or egress utilized by the public or occupants, or to present an unsafe or unhealthy condition to the public or occupants.
7. Store, position and use equipment, tools, materials, scraps and trash in a manner that does not present a hazard to the public or occupants by accidental shiftings, ignition or other hazardous activity.
8. Store and transport refuse and debris in a manner to prevent unsafe and unhealthy conditions for the public and occupants. Cover refuse containers, and remove refuse on a frequent regular basis acceptable. Use tarpaulins or other means to prevent loose transported materials from dropping from trucks.
9. All personnel shall be made aware of all temporary alternate egress paths during construction activities.
3.4 FIRE PROTECTION
A. Maintain fire extinguishers at construction site in sufficient number to adequately protect the structures during construction. Provide at least one 20 pound ABC fire extinguisher at intervals not to exceed 500 feet. Provide at least one fire extinguisher for welders or other trades using open flames in the execution of their work. All construction trailers shall possess at least one 10 pound ABC fire extinguisher. Maintain “Fire Watch” personnel, with fire extinguisher in hand, during all welding/cutting or other open flame operations on, within, or near existing facility.
B. Maintain the telephone number of the local fire department and emergency services. Keep number posted conspicuously near telephones throughout site
3.5 DISRUPTION TO SERVICES
A. The loss or shut down of existing FAA air traffic control equipment or associated support equipment for any amount of time will jeopardize safety of the flying public. Scheduled outages to existing radar and radio equipment shall be closely coordinated with COTR. FAA reserves the right to suspend the outages as deemed necessary at anytime. Contractor shall have an evacuation plan in place in the event of a suspension of an ongoing or scheduled outage.
B. Disruption to existing utilities, piping, or electrical services must be held to a minimum.
Carefully plan work in a manner to minimize disruptions and coordinate all activities with the COTR. Any operation which requires shut down of some portion of the facilities operation must be closely coordinated 10 days in advance with the COTR.
C. Temporary lighting: Provide exterior illumination around field offices, storage, shop, work and other construction areas, and circulation areas for personnel. Security lighting during hours of low visibility.
D. As determined by COTR, permanent or temporary wall openings are closed with permanent construction or substantial temporary closures complete and weathertight.
PROJECT MANAGEMENT 01 14 10 - 5
E. Sanitary Facilities: Temporary Sanitary Facilities shall comply with the requirements of the State and County health standards. Enclosed portable self-contained units or temporary water closets and urinals, secluded from public view.
F. Water Service: Provide connections and extensions of services as required for construction operations.
G. Contractor shall provide and pay for all temporary facilities as necessary for the proper and expeditious execution of the work. Contractor shall provide all labor, materials, equipment and appurtenances necessary for the complete installation, operation and maintenance of all temporary facilities. Contractor shall pay costs of all utilities consumed. All work under this Section shall comply with applicable laws, rules, regulations, codes, ordinances and orders of all federal, state and local authorities having jurisdiction for the safety of persons, materials and property. Contractor shall remove all such temporary installations and connections when no longer necessary for the project work.
H. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.
I. Temporary Stairs: Until permanent stairs are available, provide temporary stairs where ladders are not adequate.
J. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.
K. Temporary Partitions: Provide floor-to-ceiling dustproof partitions to limit dust and dirt migration and to separate areas occupied by FAA from fumes and noise.
1. Construct dustproof partitions with gypsum wallboard with joints taped on occupied side, and fire-retardant plywood on construction operations side.
2. Construct dustproof partitions with 2 layers of 3-mil polyethylene sheet on each side.
Cover floor with 2 layers of 3-mil polyethylene sheet, extending sheets 18 inches up the sidewalls. Overlap and tape full length of joints. Cover floor with fire-retardant plywood.
3.6 ENVIRONMENTAL PROTECTION AND POLLUTION CONTROL
A. The contractor shall perform all work necessary to implement and accomplish a program to prevent environmental pollution during or as a result of construction performed under this contract.
B. Take necessary precautions to prevent contamination of soil or atmosphere by the discharge of noxious substances resulting from construction operations. Provide equipment and personnel and perform emergency measures necessary to contain any spillage. If contamination of the soil does occur, excavate contaminated soil and dispose of at an off-site location in accordance with
PROJECT MANAGEMENT 01 14 10 - 6
applicable Federal, State and local regulations. Fill resulting excavations with suitable backfill and compact to the density of the surrounding undisturbed soil.
C. Take measures to prevent dispersal of pollutants into the atmosphere. Do not dump or otherwise discharge noxious, volatile or harmful fluids into drains or sewers.
3.7 HANDLING OF HAZARDOUS MATERIALS
A. The known presence of lead containing coatings and asbestos containing building components have been identified in other sections of the specification. If other suspect hazardous materials are encountered during this project notify the COTR immediately. Do not disturb suspect hazardous materials. All waste shall be stored in secure containers on site until it is properly transported off site and disposed and documented as required.
3.8 WEATHER PROTECTION
A. Structure: If required, provide and maintain weather protection with tarpaulins or polyethylene film supported on and secured to temporary framework and scaffolding to protect all parts of the structure and contents from damage by the elements.
B. Weather protection methods shall be subject to approval by the COTR.
3.9 MATERIALS AND EQUIPMENT
A. Ordering of Materials: Orders for materials and equipment shall be made promptly after approval of submittal, when required, in order to avoid any delay to project schedule.
B. Transportation and Delivery: Arrange for delivery to avoid impact to project schedule and to avoid impact to the operation of the existing facility. Deliver materials and equipment in their original, unopened containers bearing the manufacturers label.
C. Storage: Store materials and equipment to provide protection from damage from damage, dust and moisture. Store all flammable or volatile materials properly outdoors.
D. Arrange storage in a manner to provide easy access for inspection.
E. Manufacturer’s Instructions: When contract documents require that the installation of the work shall comply with the manufacturer’s printed instructions, obtain and distribute copies of such instructions to those involved in the installation, including (2) copies to the COTR. Maintain one set of instructions at the job site. Strict adherence to the manufacturer’s instructions is required.
When project conditions or unique circumstances require deviation from the printed instructions, consult with the COTR for further guidance. Do not proceed until clear direction has been obtained.
END OF SECTION 01141
SUBMITTAL PROCEDURES 01 33 00 - 1
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Submittals listed or specified in this Contract shall conform to the provisions of this section, unless explicitly stated otherwise.
1.2 REFERENCES
NOT USED
1.3 DEFINITIONS
A. Submittal Definition: Shop drawings, product data, samples, administrative and closeout submittals, and additional data presented for review and approval. Contract clauses referring to material, workmanship specifications and drawings for construction shall apply to all submittals.
B. Types of Submittals
1. Shop Drawings. As used in this Section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by the Contractor or through the Contractor by way of a subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate a portion of the work.
2. Product Data. Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate a portion of the work, but not prepared exclusively for this Contract. Information such as mix design, material characteristics, and similar data is included herein.
3. Samples. Physical examples of products, materials, equipment, assemblies, or workmanship, physically identical to a portion of the work, illustrating a portion of the work or establishing standards for evaluating the appearance of the finished work or both.
4. Administrative and Closeout Submittals. Submittals of data for which reviews and approval will be to ensure that the administrative requirements of the project are adequately met but not to ensure directly that the work is in accordance with the design concept and in compliance with the contract documents.
C. Approving Authority: Contracting Officer's Representative (COR) or Resident Engineer (RE).
D. Work: As used in this Section, the construction required by the contract documents, including labor necessary to produce the construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction and including materials, products, equipment, and systems produced both on-and off-site.
SUBMITTAL PROCEDURES 01 33 00 - 2
1.4 SUBMITTALS
A. Submit the following in accordance with the requirements of this section.
1. Submittal status log: List each submittal. Include for each submittal the specification section number; description of item for which the submittal is required; and the Contractor's scheduled date for the submittal. Submit the log within 15 days after notice to proceed. Indicate required approval date to maintain project schedule.
1.5 PROCEDURES FOR SUBMITTALS
A. Limits and Constraints Regarding Submittals
1. Submittals shall be complete for each portion of the work; components of the work interrelated as a system shall be submitted at the same time.
2. When submittal acceptability is dependent on conditions, items, or materials included in separate subsequent submittals, the submittal will be returned without review.
3. Submittals of information not required as a submittal, or covering work for which the submittals have been returned as “No Exceptions Taken” will be returned without review.
4. Approval of a separate material, product, or component does not imply approval of assembly in which the item functions.
5. The work shall conform to approved submittals, except contractor shall conform to the contract requirements and resubmit the submittal if a previously approved submittal has an error or omission.
6. When submitting for approval material which is other than that cited in the contract, submit the necessary scale drawings, wiring and control diagrams, cuts or entire catalogs, pamphlets, descriptive literature, and performance and test data of both the material specified and the material he wishes to substitute in the number of copies of each as required under the contract.
B. Scheduling of Submittals
1. Coordinate preparation and processing of submittals with performance of the work so that work will not be delayed by submittal processing. Coordinate and sequence different categories of submittals for same work, and for interfacing units of work, so that one will not be delayed for coordination with another.
2. Except as specified otherwise, allow a review period, beginning with receipt by the approval authority, that includes at least 20 working days.
C. Substitutions: Substitutions from contract requirements require Government approval and will be considered where advantageous to the Government. Where substitutions are proposed for consideration, submit a written request, with documentation of the nature and features of the substitution and why the substitution is desirable and beneficial to the Government. The proposed substitution shall be identified separately and included along with the required submittal for the item. When a substitution is submitted for approval, the Contractor warrants the following:
SUBMITTAL PROCEDURES 01 33 00 - 3
1. Substitution Is Compatible: The Contract has been reviewed to establish that the substitution, when incorporated, will be compatible with other elements of the work.
2. Contractor is Responsible: The Contractor shall take action and bear the additional cost, including review costs by the Government, necessary because of the proposed substitution.
D. Resubmittal Costs: Initial submittals requiring Government approval will be reviewed at no cost to the Contractor. The cost of reviewing resubmittals, for reason of failure of the initial submittal to meet contract requirements, shall be the responsibility of the Contractor. The COR will issue a deductive contract modification to reduce the contract price by $350.00 for each resubmittal of items requiring Government review and approval. The contract completion date will not be extended due to non-compliance with submittal requirements.
E. Contractor's Responsibilities:
1. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and Contract documents.
2. Ensure that material is clearly legible. Ensure required specialty stamps are affixed and signed.
3. Stamp each sheet of each submittal with the Contractor's certificating stamp, except that data submitted in bound volume or on one sheet printed on two sides may be stamped on the front of the first sheet only. Word the submittal stamp as follows:
"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated into Contract Number ________________, is in compliance with the contract drawings and specification, can be installed in the allocated spaces, and is submitted for Government approval.
Certified by_______________________ Date ______________________"
4. Sign the Contractor's certification. The person signing the certification shall be one designated in writing by the Contractor as having that authority. The signature shall be in original ink. Stamped signatures are not acceptable.
5. Transmit submittals to the approving authority in orderly sequence, in accordance with the Submittal Status Log, and to prevent project delays and delays in work by the Government or separate contractors.
6. Advise the approving authority of substitution, as required by the paragraph entitled " Substitutions."
7. Correct and resubmit submittal as directed by the approving authority. Direct specific attention, in writing or on resubmitted submittal, to revisions not requested by the approving authority on previous submissions.
8. Retain a copy of approved submittals at the project site, including the Contractor's copy of approved samples.
9. Furnish additional copies of submittals if requested by the COR.
10. Ensure no work is begun until the submittals for that work have been returned with a review comment other than “Revise and Resubmit” or “Rejected”.
F. Approving Authority's Responsibilities:
1. Submittals will be reviewed for approval with reasonable promptness and only for conformance with project design concepts and compliance with the contract documents.
SUBMITTAL PROCEDURES 01 33 00 - 4
If a substitution is not identified as required by the paragraph entitled " Substitution ", then the approval of the submittal SHALL NOT be an approval of the substitution.
2. The checking, marking or approval of the shop drawings and/or product data by the COR shall not be construed as a complete check, but will indicate only that the general method of construction and detailing is satisfactory. Approval will not relieve the contractor of the responsibility for any error which may exist. The contractor shall be responsible for the dimensions and design of adequate connections, details, and satisfactory construction of all work.
3. Submittals will be returned with one of the following notations:
a. Submittals marked ”As Submitted” indicate the work may proceed as presented in the submittal.
b. Submittals marked “Not Approved” indicate the submittal has failed to meet the specification requirements and work may not proceed.
c. Submittals marked “As Noted” indicate there are markings in the submittal that must be included to result in an acceptable submittal. Contractor may proceed with the work by accepting and incorporating the markings in the finished work unless the “Revise and Resubmit” box is checked.
d. Submittals marked “Revise and Resubmit” must be modified and resubmitted.
The revised submittal number must indicate that it is a resubmittal of a rejected submittal.
G. The transmittal sheet returning the submittal will be initialed.
1.6 FORMAT AND QUANTITY OF SUBMITTALS
A. Transmittal Form: Transmit each submittal, except sample installations and sample panels, to the office of the approving authority. Transmit submittals with a transmittal form approved by the COR and standard for the project. The transmittal form shall identify the Contractor, indicate the date of the submittal, and include information prescribed by the transmitted form and required in the paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations.
B. Identifying Submittals: Identify submittals, except sample panel and sample installation, with the following information permanently adhered to or noted on each separate component of each submittal and noted on the transmittal form. Mark each copy of each submittal identically, with the following:
1. Project title and location.
2. Construction contract number.
3. The Section number and paragraph number of the Section by which the submittal is required and the paragraph to which it conforms.
4. The name, address, and telephone number of the subcontractor, supplier, manufacturer and any other second tier contractor associated with the submittal.
5. Product identification and location in project.
C. Format and Quantity for Shop Drawings
SUBMITTAL PROCEDURES 01 33 00 - 5
1. For shop drawings presented on sheets larger than 11-inches by 17 inches, submit two printed copies and one Portable Document Format (PDF) file transmitted on 700 MB compact disks (CD) of each shop drawing prepared for this project.
2. For shop drawings presented on sheets 11-inches by 17 inches or less, submit two printed copies with each bound in a separate volume and a PDF file transmitted on 700 MB compact disks (CD) of each shop drawing prepared for this project.
3. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to the information required in the paragraph entitled "Identifying Submittals."
4. Dimension drawings, except diagrams and schematic drawings; prepare dimensioned drawings to scale. Identify materials and products for work shown.
5. Shop drawings shall be not less than 8 1/2 by 11 inches or more than 36 by 42 inches.
6. After review, the approving authority will return a PDF file and a marked original.
D. Format and Quantity for Product Data
1. Submit two printed copies with each, bound in a separate volume and a PDF file transmitted on compact disk (CD) or diskette of each Product Data prepared for this project.
2. Present submittals for each Section as a complete, bound volume. Include a table of contents listing page and catalog item numbers for product data.
3. Indicate, by prominent notation, each product that is being submitted; indicate the Section and paragraph numbers to which it pertains.
4. Supplement product data with material prepared for the project to satisfy submittal requirements for which product data does not exist. Note that the material is developed specifically for the project.
E. Format and Quantity of Samples:
1. Furnish samples in the sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of equipment or device: Full size.
b. Sample of materials less than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of materials exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of linear devices or materials such as conduit and handrails: 10-inch length or length to be supplied, if less than 10 inches.
e. Sample of non-solid materials such as sand and paint: Pint.
f. Color selection samples: 2 inches by 4 inches.
g. Sample panel: 4 feet by 4 feet.
h. Sample Installation: 100 square feet.
2. Samples showing range of variation: Where variations are unavoidable due to the nature of the materials, submit sets of samples of not less than three units showing the extremes and middle of the range.
3. Quantity, unless otherwise specified:
a. Submit two samples, or two sets of samples showing range of variation, of each
SUBMITTAL PROCEDURES 01 33 00 - 6
required item. One approved sample or set of samples will be retained by the approving authority and one will be returned to the Contractor.
b. Submit one sample panel. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
4. Reusable samples: Incorporate returned samples into the work only if so specified or indicated. Incorporated samples shall be in undamaged condition at the time of use.
5. Recording of sample installation: Note and preserve the notation of the area constituting the sample installation but remove the notation at the final clean up of the project.
6. When a color, texture or pattern is specified in naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
7. Transmittal Form for samples shall identify manufacturer, model, type, color, etc.
sufficient to reorder or replace.
F. Format and Quantity of Administrative and Closeout Submittals
1. Unless otherwise specified, submit administrative and closeout submittals in the format and quantities required for shop drawings.
2. Comply with section entitled “Contract Closeout Procedures”.
G. A Portable Document Format (PDF) file for each shop drawing, product data, and sample transmittals shall be uploaded to FAA’s KSN website.
1.7 PROGRESS PHOTOGRAPHIC SUBMITTALS
A. Still Photographs: Before construction operations have started at the site, the contractor shall take and provide 25 color photographs showing the existing conditions and thereafter an average of 25 views shall be taken each month until completion of the work. An electronic file of each view shall be submitted to the RE promptly after taking the views.
1. Photographs shall be made using a digital camera of at least 4 mega pixel size. All digital images shall be submitted on CD along with the monthly photographs.
2. The contractor shall notify the RE 24 hours in advance of taking any photographs.
B. Ownership of Photographs: Any and all still photographs, digital files, and video tapes taken of the construction area are the property of FAA and shall not be released to any source whatsoever without the prior written permission from the RE. This provision shall prevail for the duration of the contract and indefinitely thereafter.
C. Video Photography: Refer to Section 01 32 33 for video photography requirements.
PART 2 - PRODUCTS
SUBMITTAL PROCEDURES 01 33 00 - 7
PART 3 - EXECUTION
END OF SECTION 01 33 00
SUBMITTAL PROCEDURES 01 33 00 - 8
THIS PAGE INTENTIONALLY BLANK
CONTRACTOR QUALITY CONTROL 01 40 00 - 1
SECTION 01 40 00 - CONTRACTOR QUALITY CONTROL
1.1 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
1.2 AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
A. ASTM D 3740 Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
B. ASTM E 329 Agencies Engaged in the Testing and/or Inspection of Materials Used in
Construction
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Contractor Quality Control Personnel
C. Daily Logs
NOT USED
3.1 GENERAL REQUIREMENTS
A. The Contractor is responsible for quality control and shall establish and maintain an effective quality control system. The quality control system shall consist of plans, procedures, and organization necessary to produce an end product that complies with the contract requirements.
The system shall cover all construction operations, both onsite and offsite, and shall be keyed to the proposed construction sequence. The site project superintendent will be held responsible for the quality of work on the job and is subject to removal by the RE for non-compliance with the quality requirements specified in the contract. The site project superintendent in this context shall be the highest level manager responsible for the overall construction activities at the site, including quality and production. The site project superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the RE, and shall be responsible for all construction and construction related activities at the site.
CONTRACTOR QUALITY CONTROL 01 40 00 - 2
3.2 COORDINATION MEETING
A. After the Preconstruction Conference, before start of construction, the Contractor shall meet with the RE and discuss the Contractor's quality control system. During the meeting, a mutual understanding of the system details shall be developed, including recording the CQC operations, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the FAA's Quality Assurance.
Minutes of the meeting will be prepared by the Contractor and signed by both the Contractor and the RE. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reconfirm mutual understandings and/or address deficiencies in the CQC system or procedures that may require corrective action by the Contractor.
3.3 REQUEST FOR INFORMATION (RFI’s) AND SUBMITTALS
A. Submittals shall be made as specified in Section 01 33 00 “SUBMITTAL PROCEDURES”.
The CQC shall be responsible for reviewing all RFI’s and submittals prior to submission to the
FAA.
3.4 CONTROL
A. Contractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract.
B. Daily checks shall be performed to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. The checks shall be made a matter of record in the CQC documentation. Final follow-up checks shall be conducted and all deficiencies corrected prior to the start of additional features of work that may be affected by the deficient work. The Contractor shall not build upon nor conceal non-conforming work.
3.5 TESTS
A. Testing Procedure: The Contractor shall perform specified or required tests to verify that control measures are adequate to provide a product that conforms to contract requirements. Testing acceptance tests when specified. The Contractor shall procure the services of an approved testing laboratory or establish an approved testing laboratory at the project site. The Contractor shall perform the following activities and record and provide the following data:
1. Verify that testing procedures comply with contract requirements.
2. Verify that facilities and testing equipment are available and comply with testing standards.
3. Check test instrument calibration data against certified standards.
4. Verify that recording forms and test identification control number system, including all of the test documentation requirements, have been prepared.
5. Results of all tests taken, both passing and failing tests, shall be recorded on the CQC report for the date taken. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test shall be given. If approved by the RE, actual test reports may be submitted later with a reference to the test number
CONTRACTOR QUALITY CONTROL 01 40 00 - 3
and date taken. An information copy of tests performed by an offsite or commercial test facility shall be provided directly to the RE.