This document contains questions and answers related to solicitation number 6973GH-20-R-00093 issued by the Federal Aviation Administration. The solicitation requires building envelope sealing, upgrading an existing roof guardrail system, and other miscellaneous upgrades at the PIT ARSR facility located in Oakdale, Pennsylvania. The Federal Aviation Administration will remove and reinstall any lightning protection or grounding materials attached to the existing guardrail as part of the upgrade. The selected contractor will be responsible for coordinating this electrical work and furnishing all other labor, materials, equipment, insurance, permits and supervision to complete the required upgrades within 110 calendar days from the notice to proceed date. Questions regarding the solicitation were due by May 15, 2020, and proposals must be received by May 22, 2020 to be considered for award of a firm-fixed-price construction contract.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers for SIR 6973GH-20-R-00093
Q. Please clarify that the FAA’s own forces will provide and install all necessary Lightning Protection and Grounding with Regards to the Statement of Work – page 3, Item 1, L. 1-6? And will the contractor be responsible to perform any work relating to this other than the supply and installation of the Guard Rail System?
A. FAA-TSOG will remove and install lightning and grounding materials per drawings as these are mounted to the guardrail. The contractor shall coordinate with COR and FAA-TSOG for the removal and installation of said materials mounted on the guardrail. The contractor shall refer to the drawing notes for electrical work and coordination related to guardrail removal and installation.
Q. The solicitation form paragraph 11 states 110 calendar days to complete work from Notice to Proceed. Spec Section 01100, 1.2 states 75 days?
A. Due to the added complexities included in the design, the project will need to be completed within 110 calendar days from Notice to Proceed.