Special_Provisions.pdf
PDF 2 MB Posted
- Attached to
- Franklin Road, McDermott Road to Black Cat Road
- Solicitation number
- CT227-07
- Issued by
- Ada County, Idaho
About this file
Special Provisions Summary
This Special Provisions document outlines requirements and conditions for the Franklin Road widening project in Idaho, extending from McDermott Road to Black Cat Road. The project encompasses roadway expansion to five lanes, installation of multi-use pathways on both sides, stormwater and irrigation facilities, continuous street lighting, and signalization at the McDermott Road intersection. Contractors must coordinate with all utility contractors operating on the project site and comply with all specified provisions to ensure successful project completion and integration of infrastructure components.
The special provisions establish the contractual framework and performance standards required of the awarded contractor. Key requirements include adherence to project specifications, coordination protocols with utility providers, and compliance with all applicable state and local regulations governing the construction process. The document serves as a binding supplement to the primary contract documents and defines the contractor's obligations regarding quality standards, safety requirements, and project-specific conditions necessary for the roadway, pathway, stormwater, irrigation, lighting, and signalization components of this transportation improvement initiative.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
100% SPECIAL PROVISIONS
FRANKLIN ROAD, McDERMOTT ROAD TO BLACK CAT
ROAD
PROJECT NO. 523011 and 323021 GIS No. 102497 and 200570
This stamp certifies the attached modifications to the ISPWC and ACHD supplemental provisions. It does not certify the ISPWC or ACHD supplemental provisions.
Special Provisions to modify the 2017 Idaho Standards for Public Works Construction (ISPWC)
Ada County Highway District Supplemental Specifications to the ISPWC
ACHD SPs and SSPs for Green Stormwater Infrastructure
10/2/2026
GENERAL NOTES
1. ACHD OWNED CONDUIT IMPACTS
ACHD-owned conduit may be shallow and located directly behind the curb or under the sidewalk. The Contractor’s method of sidewalk and/or curb removal shall be done in a manner to avoid damage to conduit and fiber. Any damage shall be repaired at the Contractor’s expense.
2. AMERICANS WITH DISABILITY ACCESS (ADA) DURING CONSTRUCTION
The needs and control of all road users (motorists, bicyclists, and pedestrians within the highway and/or public right-of-way, including persons with disabilities in accordance with the Americans with Disabilities Act of 1990 (ADA), Title II, Paragraph 35.130) through a temporary traffic control “TTC” zone shall be an essential part of highway construction, utility work, maintenance operations, and the management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient movement of road users through or around TTC zones while reasonably protecting workers, responders to traffic incidents, and equipment.
Temporary facilities, including reasonably safe pedestrian routes around work sites, are also covered by the accessibility requirements of the Americans with Disabilities Act of 1990 (ADA) (Public Law 101-336, 104 Stat.327, July 26, 1990. 42 USC 12101-12213 (as amended)). Implementation of TTC plans and installation and maintenance of devices shall be the responsibility of the contractor performing the construction, alteration and/or maintenance of the highway or public right-of-way. Temporary traffic control for pedestrians shall meet the accessibility requirements (Standards) set forth in Part 6 of the MUTCD. When an existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of construction, either temporary walkways with curb ramps are to be provided, or the construction shall be phased to maintain access to the affected addresses. Contractors shall be allowed flexibility as long as the requirements are met.
The location of the construction project and whether or not accessible facilities are present shall also determine the extent of the needed temporary facilities. The contractor is only required to maintain practical continuity where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by bicyclists, no additional measures are needed as the bicycles can share the available travel lanes with other traffic. On moderate to higher speed rural roads, if a bike lane exists then it should be properly detoured, complete with signage, to provide a safe route through or around the work area. If a road or bridge project affects vehicular traffic to a business, residence, school or any other type of pedestrian generating location with existing accessible facilities, then pedestrian and handicapped access must be maintained.
A continuous route for all pedestrians, including the disabled and bicyclists, shall be maintained at all times. When existing pedestrian facilities are disrupted, closed, or relocated in a TTC zone, the temporary facilities shall be detectable and include accessibility features consistent with the features present in the existing pedestrian facility. The temporary route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or going significantly out of their way.
Additional consideration must be given to the disabled since they may not have the physical or cognitive ability to improvise (e.g., balancing along the curb or a very narrow path) or use unofficial alternatives (e.g. using an adjacent grass surface). Temporary routes must meet the accessibility guidelines of the ADA for permanent facilities and shall be marked with the proper signage. Should existing crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted in an accessible location. Temporary signals should include pedestrian phases.
Contractors shall not block temporary walkways with contractor parking, materials piles, signs, rubble or rubbish. Construction equipment and equipment operation must be separated from the temporary walkways. At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other protective barriers may be needed to prevent access into the construction area.
Detour and diversion routes, when used for pedestrians and bicyclists, should be evaluated for the following items:
• Direct conflicts between pedestrians and vehicular traffic, work vehicles, and other work activities must be reduced with protective barriers or continuous high contrast fencing (min 36” high with a 6” high toe board). See MUTCD 6F.68 and 6D.02
• Temporary pedestrian facilities should provide safe, accessible routes that replicate as nearly as practical the most desirable characteristics of the existing facility, and parallel the disrupted route whenever possible. A smooth, continuous hard surface should be provided throughout the entire length of the temporary pedestrian facility. There should be no curbs or abrupt changes in grade or terrain that could cause tripping or be a barrier to wheelchair use. The geometry and alignment of the facility should meet the applicable requirements of the Americans with Disabilities Act Accessibility Guidelines (ADAAG) for Buildings and Facilities.
See MUTCD 6D.01 and 6D.02
• Advance information placed at appropriate distances before the work zone allowing pedestrians to make timely decisions about routes through or around the work zone. See MUTCD 6F.14
• Transition information allowing pedestrians to find a safe path through and around work zones, which is critical when the pathway is restricted, diverted or detoured.
See MUTCD 6F.14
• Work area information assisting in safe passage of pedestrians through the work zone. This information is needed on all pedestrian routes except detours. See
MUTCD 6F.14
• Exit information directing pedestrians back to the original route. See MUTCD 6F.14
• Crosswalk placement at intersections may need additional signage, temporary striping, traffic signal modification, pedestrian signals with audible alarms if justified, proper push button height, and ramps. See MUTCD 6H.29, 6F.80, and 4E.06
• Accommodations for other transit forms (busses, trains etc.) are made. See
MUTCD 6D.02
• Requirements of the ADAAG and MUTCD are adhered to.
• Access is maintained to the affected businesses and residences.
3. ASPHALT AND CONCRETE CUTTING
Asphalt pavement and concrete cutting shall be incidental to other items of this contract. Contractor shall ensure that cuts made in asphalt and concrete for trenches are parallel and do not wander or diverge from the intended line.
Dust produced by asphalt or concrete saw cuts shall be collected using a high-powered vacuum dust control system, eliminating the dust from entering the atmosphere. The suction device shall be attached to the cutting equipment or positioned to assure a maximum amount of dust will be collected before it can be released into the atmosphere. The cost to ensure dust is collected during asphalt and concrete cutting shall be considered incidental to the cost of the project and no additional compensation will be made.
4. BASIS OF PAYMENT
Except as modified herein, the various roadway work called for on the Bid Schedule shall be performed, measured, and paid for as indicated on said Bid Schedules and as provided in the 2017 IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (ISPWC) and the 2017 supplements. The Contractor is required to have the 2017 edition of the ISPWC standards to perform this work. Unless otherwise specified herein, all plan quantities are based upon in-place, completed and accepted units.
5. CONFLICTING PAVEMENT MARKINGS
All conflicting pavement markings shall be completely obliterated using an ACHD approved method prior to applying permanent pavement markings. The cost of performing all obliteration shall be considered incidental to other items and no separate pay item will be included for obliteration of pavement markings.
6. CONNECTING PIPES
Connecting new pipes, manholes, irrigation structures\ditches and catch basins to existing pipes, manholes, irrigation structures\ditches and catch basins is incidental to other work and no additional compensation will be made.
7. CONSTRUCTION STAGING
The Contractor shall furnish ACHD with a detailed construction staging plan based on their anticipated approach to construction activities. This plan and implementation will be the responsibility of the contractor. Final approval of the staging plans and revisions thereof must be granted by ACHD prior to implementation.
Staging plans that may be contained within the project plans are primarily for bidding purposes only. The contractor may utilize any staging plans contained within the bid documents as a basis for staging but the final staging plan will be provided by the contractor prior to construction activities.
The cost associated with providing the necessary staging plans will be considered incidental to the project and no additional compensation will be made.
8. DAMAGED AREAS BEYOND SPECIFIED CONSTRUCTION LIMITS
Damage to any areas or items not specifically identified for removal, including the existing pavement, sod, sprinklers and landscaping in the contract documents shall be promptly repaired by the contractor. The contractor is also liable for dust damage to crops. The cost to complete such repairs shall be considered incidental to the cost of the project and no additional compensation will be made.
9. EXCESS SITE MATERIAL
The Contractor shall be responsible for providing a site for the disposal of excess or unsuitable materials. If bituminous material is to be disposed of, the site shall meet the requirements of the Idaho Department of Environmental Quality. All excess material sites shall be approved by ACHD. No separate payment will be made for the acquisition or operation of the sites, or for loading, hauling or unloading the materials at the site.
10. INFORMATION GIVEN PRIOR TO AWARD
Oral explanations, instructions and interpretations given to bidders prior to award of contract will not be binding. It is the ACHD’s intent to provide all bidders equal opportunity to access and acquire all available pertinent information necessary to formulate a responsive bid. Any information, specifications, plans, data, or interpretations that ACHD discovers is lacking and may be important to all bidders will be furnished in the form of an addenda, the receipt of which shall be acknowledged by the bidder.
11. PROPERTY OWNER COORDINATION
Contractor shall coordinate items of work affecting adjacent property owners, including but not limited to landscape removal and replacement, sprinklers, irrigation facilities, fencing, sod care, and trees. Property access coordination shall be conducted according to General Condition 49 – PROPERTY ACCESS POINTS.
12. PAY QUANTITIES
By the 25th of each month the Contractor shall supply quantities that are to be paid for that month. Each bid item shall be accompanied with the appropriate backup documentation on how the pay quantity was calculated. This shall include such documentation as, but not limited to; stationing, location, tallied weight tickets, sketch of calculated areas, and/or any other appropriate documentation to verify the pay quantity request. ACHD will verify quantities prior to remitting payment. Items failing to have the appropriate backup supporting documentation will not be paid until the information is supplied. The cost associated with providing the above outlined documentation shall be considered incidental to the project and no additional compensation will be granted.
All Pay quantities shall also adhere to the criteria outlined in General Condition 41 –
MANNER OF PAYMENT.
13. POWER SUPPLY
If indicated on the plans or directed by ACHD, the contractor shall install a three-wire electrical service to be used at 120/240 volts, single phase, 60 hertz AC between the power supply and the service cabinet. The contractor shall install a junction box a maximum of two (2) feet from the power supply. The distance from the power source to the service cabinet shall not exceed 300’ without approval from the ACHD Signal Coordinator. The contractor shall coordinate with Idaho Power for the power connection location. The District shall be responsible for all Idaho Power fees related to power supply and connection. The contractor shall have Idaho Power submit paperwork to the ACHD Utility Coordinator for the connection a minimum of sixty (60) working days prior to activating the new power supply. The contractor shall be responsible for all electrical permit fees.
14. SHOP DRAWING REVIEW
Plans show details of all structures, lines, grades, typical cross sections of the roadway, location and design of all structures and a summary of items appearing on the proposal.
The Contractor shall keep one set of plans available on the work site at all times.
The Contractor will supplement the plans by such working drawings necessary to adequately control the work. Working drawings shall be submitted to the Engineer for review in advance of the start of the proposed work. The Contractor shall allow sufficient Engineer review time and corrections resubmitted by the Contractor without impacting the approved construction schedule. The drawings shall be on sheets measuring 22 in. x 34 in. Unless otherwise stated in the contract, the Engineer will require up to 15 business days from the date the submittals or re-submittals are received until they are returned to the Contractor. No extension to contract time will be given due to re-submittals or the failure of the Contractor to provide any information necessary in a timely fashion. If necessary, drawings will be signed and sealed by a Professional Engineer licensed to practice in the State of Idaho.
This review time will increase if the drawings submitted do not meet the contract requirements or contain sufficient details.
For structures, six sets of working drawings shall be furnished and shall include stress sheets, shop drawings, erection plans, coffer dam plans, bending diagrams for reinforcing steel, or any other supplementary plans or similar data required of the Contractor. All structural drawings provided shall be sealed by a Professional Engineer licensed to practice in the State of Idaho.
Working drawings shall be approved before beginning the work covered by the submitted drawings. Such approval is only for general conformance with the information given in the contract documents and does not relieve the Contractor of responsibility for correctness of the details and dimensions, nor does it waive any requirements of the specifications.
The contract price shall include the cost of furnishing all submitted shop and/or working drawings.
15. STORMWATER FLOWS
The Contractor is responsible for transmitting existing stormwater and irrigation flows during construction. All costs associated with transmitting existing flows, including flows from the temporary water quality best management practices on the project, shall be considered incidental to other items of work and no additional compensation will be made.
16. STORM WATER MANAGEMENT
Contractor shall implement Best Management Practices (BMPs) controls to protect storm sewer systems and Waters of the United States located on or near project limits.
Contractor shall follow the requirements of the Idaho Pollutant Discharge Elimination System (IPDES) Construction General Permit (CGP) and/or ACHD’s Construction Site Discharge Control (CSDC) Program as required. The contractor is required to implement and maintain BMPs through life of contract. The removal of all temporary construction BMPs after completion of all required work to final stabilization is considered incidental to this project.
The ACHD CSDC Plan shall meet the CSDC Program requirements listed in Sections 8305 to 8306 of the ACHD Policy Manual https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_ ConstructionSiteDischargeControlProgram.pdf.
https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_ConstructionSiteDischargeControlProgram.pdf https://www.achdidaho.org/Documents/ACHDpolicyManual/7000to9000/Section8300_ConstructionSiteDischargeControlProgram.pdf
The CSDC Plan shall include measures to protect the existing ACHD storm drain systems inside and outside the project boundaries from mud, dust, debris, and other pollutants generated or transported due to this project. All measures will also be implemented to protect any “Waters of the United States” inside or outside of the project boundaries.
“Pollutants” are defined in Section 8302 of the ACHD Policy Manual.
The IPDES CGP Stormwater Pollution Prevention Plan (SWPPP) shall meet the CGP requirements. The CGP can be found on the Idaho Department of Environmental Quality (IDEQ) website at:
https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509.
BMPs for controlling pollutant transport from the construction site and activities can be found in a number of publications and locations including, but not limited to:
• Idaho Department of Environmental Quality, Idaho Catalog of Storm Water Best
Management Practices at: https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ or Phone: (208) 373-0502
• United States Environmental Protection Agency – Region 10, Resources and Tools at: https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates or Phone: (800) 424-4372
• Idaho Transportation Department, Best Management Practices (BMP) Manual at:
https://itd.idaho.gov/env/?target=resources or Phone: (208) 334-8476
Payment for this item will be made under the appropriate bid item numbers.
17. SUBGRADE
It shall be the Contractor’s responsibility to maintain the integrity for the exposed subgrade. Degradation due to his operations or weather shall be remedied under the guidance of a geotechnical engineer.
All costs to maintain and repair including, geotechnical engineering, etc. shall be incidental to the project and no additional compensation will be made.
18. TRAFFIC CONTROL
Contractor shall furnish ACHD with a detailed traffic control plan based on their anticipated approach to construction activities. This plan and implementation will be the https://www2.deq.idaho.gov/admin/LEIA/api/document/download/16509 https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ https://www.deq.idaho.gov/water-quality/wastewater/storm-water/ https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates https://www.epa.gov/npdes/construction-general-permit-resources-tools-and-templates https://itd.idaho.gov/env/?target=resources responsibility of the contractor. Final approval of the traffic control plan and revisions thereof must be granted by ACHD prior to implementation. It will be the sole discretion of the ACHD Resident Engineer, or designated representative, to determine if the advanced construction signing plan contained in the contract documents shall be approved as a traffic control plan.
Traffic control plans and/or advanced construction signing plans that may be contained within the project plans are primarily for bidding purposes only.
Local and emergency vehicle access shall be maintained at all times, unless otherwise indicated in the contract documents. All traffic control items not specifically listed in the bid schedule shall be incidental to this contract, and no additional compensation will be made. Short term lane closures shall be only as approved by the Resident Engineer.
19. TACK COAT
Tack Coat is required between lifts of asphalt and between existing and overlayed lifts of asphalt. Tack Coat shall be CSS-1 Diluted Emulsified Asphalt with an application rate of
0.12 Gallons/SY. Tack Coat shall be incidental to other pay items and no additional payment made.
20. TRENCHING
All excavation and trenching shall meet OSHA requirements. Trenches shall be backfilled and properly compacted, closed at the end of each day, and barricaded, as needed.
21. WARNING AND REGULATORY SIGNS
Existing warning and regulatory signing shall be retained and protected throughout the project limits unless otherwise noted. This may require multiple relocations, which will be incidental to other bid items. Existing warning and regulatory signs that are designated for removal and replacement and do not conflict with construction traffic control signs shall be maintained during construction and, if necessary, relocated to locations where the signs are visible to traffic and serve their original purpose.
22. CONSTRUCTION OF IRRIGATION IMPROVEMENTS
All irrigation improvements shall be constructed during the irrigation off-season, generally October 15th to March 15th. All irrigation improvements shall be completed prior to the first March 15th following the when construction begins. Contractor shall meet all requirements stated in License Agreements obtained from Irrigation Districts and/or Irrigation users.
23. WORKING HOURS
Unless otherwise specified here the Regular working hours for this contract shall adhere to the criteria outlined in General Condition 40 – WORK HOURS/TIME OF COMPLETION.
24. QUALITY CONTROL/QUALITY ASSURANCE
SECTION 100 – General Conditions
Add the following:
Ada County Highway District Quality Control and Quality Assurance Procedure
Definitions
Quality Assurance (QA) is defined as the process or set of processes used to measure and assure the quality of a product and/or workmanship. This encompasses ACHD’s oversight of the Developer’s/Contractor’s processes and materials. This includes review of the inspector, sampler, tester and laboratory qualifications (per ACHD Independent Assurance Program defined below); verifying the results of the quality control and process control testing; and inspecting for conformance to plans and specifications.
Quality Control (QC) is defined as the actions necessary to produce quality workmanship and materials. QC includes, but should not be limited to, inspection of the production and placement operations, quality control and process control testing and inspection of the finished product. QC is the responsibility of the Developer/Contractor.
No separate payment will be made for this work. If quality control testing is not being performed at the required frequency, ACHD may stop production of work until the tests are supplied, or ACHD determines the work can proceed.
Quality Control Testing and Process Control Testing are defined as the testing and inspections conducted by the Developer/Contractor to determine if the construction materials have been produced and placed in compliance with the project specifications and applicable standards. Process control testing is conducted to demonstrate that the construction materials being produced and used continue to meet the requirements for the product.
Independent Assurance Program (IAP) is the process provided by ACHD, through trained and certified staff, to ensure that all testing is performed correctly and testing equipment is functioning and calibrated properly.
Acceptance is determined by the QA test results, in combination with the assurance that the Developer/Contractor has satisfied the specification requirements for materials quality and workmanship, with the exception of Superpave Hot Mix, as specified below.
In addition to the specified testing results, visual inspection of the end product is also taken into consideration in determining acceptance. Acceptance will be determined by ACHD. All samples required for QA testing will be supplied by the Developer/Contractor to ACHD. Prior to obtaining a sample for QA testing, ACHD shall be notified of when and where the sample will be taken from. ACHD will determine if it needs to witness the obtaining of the QA sample. Superpave Hot Mix acceptance shall be based on ACHD’s supplement to the ISPWC Section 814 under Part 4.2.
Construction Testing and Inspection Responsibilities
Quality Control
A. The Developer/Contractor shall be responsible for the Quality Control of all construction processes and materials quality. The Developer/Contractor will be responsible for quality throughout the construction process. Therefore, the
Developer/Contractor must ensure that the materials and workmanship provided by themselves, Subcontractors, Suppliers, and Producers meet all pertinent specifications. All tests listed under Quality Control in the Minimum Testing
Frequency Table are required for quality control, however only tests listed as
Acceptance shall be used in determining pay.
B. The Quality Control laboratory must be approved by the Idaho Transportation
Department. All testing personnel and facilities used by the Developer/Contractor must be currently certified by the Western Alliance for Quality Transportation
Construction (WAQTC) and by the ACHD Independent Assurance Program. All test results must be supplied to ACHD the next working day after the test was performed. All Quality Control tests will be supplied to ACHD directly from the lab performing the tests. Tests results shall have the ACHD project/permit number listed and be sequential.
C. Quality Control Testing must occur in a random frequency and at a minimum, at the intervals specified in the table provided in the corresponding ISPWC sections. The
Developer/Contractor shall determine the random locations. Upon request, documentation must be supplied showing how the random numbers/locations were determined by the Developer/Contractor. All random sampling for ACHD will be done by the Developer/Contractor and witnessed by an ACHD representative.
D. For gradation testing by the Developer/Contractor during production, each sample size shall be taken per AASHTO T2, except the sample size shall be doubled. The sample obtained shall be split in accordance with AASHTO T248, and half of it shall be marked with an ID number and tested by the Developer/Contractor. The other half of the sample shall be sealed in a canvas sack or plastic bucket, and marked with the ID number, stored in a weather protected container, and reserved for use in retesting if needed. Material shall be retained until written notification is given by
ACHD that it can be discarded.
E. Acceptance, gradation, binder content and volumetrics for plant mix pavement and/or Superpave Hot Mix asphalt shall be performed on the loose mix sampled from the roadway, haul unit, or an approved sampling method at the Hot Plant. At the start of each project the location for sampling shall be determined by ACHD and all samples for the project shall be obtained from that determined location. The hot mix sample used for asphalt binder content, gradation and volumetric testing shall be doubled in size. The sample shall be split in accordance with AASHTO R47 and half of the sample shall be used for the appropriate testing. The other half of the sample shall be sealed in a box, marked with the sample ID number, stored in a weather protected enclosure, and reserved for use in retesting if needed. Material shall be retained until written notification is given by ACHD that it can be discarded.
Quality Assurance
A. ACHD shall oversee the Developer’s/Contractor’s fulfillment of the QC requirements, and independently verify that the QC test results being submitted by the
Developer/Contractor are representative of the workmanship and product quality.
ACHD will also be responsible for determining general project acceptance based on conformance to the approved plan and specifications.
B. ACHD will perform random Quality Assurance testing at the intervals specified in
Minimum Testing Frequency table.
C. Acceptance of material will be based on the Quality Assurance test performed by
ACHD. If no QA test is performed, acceptance will be based on the QC tests results and inspections as determined by ACHD.
D. ACHD will perform random inspections of material storage and handling practices.
Dispute Resolution
A. The dispute resolution process is to resolve differences between the
Developer/Contractor and ACHD when a disagreement regarding the test results occurs.
B. When a failing QA test occurs, production may be suspended until the differences are resolved and ACHD is satisfied.
C. ACHD may run one or more tests of the split material from the QC process to help resolve differences.
D. When ACHD and the Developer/Contractor are unable to resolve the differences, a
Third Party prequalified independent lab shall be brought in to verify testing.
E. ACHD will hire the Third Party independent lab. If ACHD tests are found to coincide with the independent lab, ACHD will not grant additional contract time due to any delays in production and the Developer/Contractor shall bear the costs associated with the Third Party resolution. Likewise, if the Developers/Contractors tests are found to coincide with the independent lab, ACHD will bear the costs associated with Third Party resolution and will grant additional time for any delay caused by this additional testing.
F. For hot mix density dispute testing, cores shall be obtained by the Third Party from the same locations as the nuclear gauge tests.
Independent Assurance Program
A. ACHD practices the standards of the Western Alliance for Quality Transportation
Construction (WAQTC).
B. ACHD Independent Assurance personnel may observe testers and verify that the equipment and techniques used for the required testing are calibrated and performing accurately, per WAQTC. During construction, it may be necessary for an
IAP representative to verify the reliability of the tester by witnessing sampling and testing, and by splitting samples and comparing results.
C. All independent testing laboratories to be used shall be pre-qualified by ACHD prior to construction. To request an inspection and certification, contact the ACHD Lab
Coordinator at 387-6310 to schedule. Laboratories that are currently certified by the
Idaho Transportation Department (ITD) can provide ACHD with their current certification as confirmation of qualification. In the event that the lab is ITD certified;
a facility inspection by ACHD IAP personnel may still be required.
Price Adjustment for Non- Compliant Materials or Products
A. When material fails to meet the required specifications, they will be subject to a price adjustment or rejection. ACHD may also request a lengthened warranty period.
B. ACHD will, in its sole, discretion determine the price adjustment or rejection.
C. The determined price adjustment or rejection of material shall be applied to the quantity of material that is represented by the non-compliant test results, as outlined in the Minimum Testing Frequency table.
Minimum Testing Requirements
A. The requirements outlined herein are the established minimum acceptance requirements for materials used in standard applications and paid for under standard bid items. For special provision items, material used in non-standard, non-roadway, temporary applications, or small quantities of materials, alternative materials acceptance requirements will be determined as discussed herein or as specified in the contract documents, or as otherwise approved by ACHD. Material placed without appropriate testing shall be subject to a price deduction or rejected as determined by
ACHD.
B. Minimum testing frequencies are included in the Minimum Testing Frequency table.
The Developer/Contractor frequencies may only be altered by Change Order approved by ACHD. ACHD may elect to increase its own testing frequency at any time. Testing frequency should be increased when accepting material from newly developed sources or those with varying results.
C. Material source approval requirements are not listed in this document. All fill and aggregate material imported to the project must be obtained from ACHD or ITD approved materials sources.
D. Based on inspection and without regard for testing frequency, ACHD may isolate and reject obviously defective material.
E. When the material is not listed in the Minimum Testing Frequency table and not identified in the ISPWC, acceptance shall be determined by ACHD.
F. When the material is required by the Contract to meet a given specification, such as
ASTM or AASHTO, acceptance of material will, at a minimum, require a manufacturer’s certification. A partial list of such material is outlined in the List of Miscellaneous
Material Accepted on the Basis of Manufacturer’s Fabricator’s Certification.
Small Quantities
A. ACHD may accept small quantities of certain materials without sampling and testing.
The determination to accept materials using this provision rest solely with ACHD.
B. The following are not eligible for small quantity acceptance:
i. Concrete with a specified strength of greater than 3000 psi.
ii. Paving on the roadway with quantities above 100 ton.
C. Materials may be accepted as a small quantity if the estimated quantity is less than the minimum QC testing frequency. The small quantity exception may be used on pavement items such as; small patches, utility repairs, pavement placed outside the traveled way (driveways, approaches, mailbox turnouts, asphalt sidewalk and curb), and temporary pavement.
D. The minimum requirements that must be met for small quantities includes; approved sources, mix design, material certifications, inspection, and a core for density acceptance of mainline and intersection paving less than 100 tons.
CONTINGENCY BID ITEMS
The following item(s) are contingency items to be used as directed or approved by ACHD. The Contractor must have prior written/email approval from ACHD to received payment for utilizing the following contingency item(s):
• 0202.4.5.A.1- Unsuitable Material Excavation
SECTION 202
EXCAVATION & EMBANKMENT
Amend Part 3.7 to include E
E. If suitable material is not encountered after removing unsuitable material to a depth 2-ft below proposed subgrade. The Contractor shall stop over excavation and install subgrade geotextile meeting the requirements outlined in Section 2050 and place repair material suitable for construction to meet the compaction and density requirements of Class A. All work and materials associated with the installation of the geotextile shall be considered incidental to other 202 bid items.
ITEM 29, “VARIATIONS IN QUANTITIES”, ON PAGE GC16 OF THE ACHD GENERAL
CONDITIONS, PARAGRAPH, shall not apply to this bid item.
END OF SECTION
SECTION 703
CAST-IN-PLACE CONCRETE
Amend Part 3 to include Section 3.9
3.9 GRADING CANAL SLOPES
A. Work shall include all costs associated with the grading of the canal slopes after the installation of cast-in-place concrete headwall and rip rap. Where canals are disturbed from construction activity and no proposed grading is indicated on the construction plans, the canal slopes shall be returned to existing grade.
B. Grading material shall be free of organic material, concrete, asphalt, and other deleterious construction waste. All materials shall meet the applicable ISPWC Sections and City of Nampa Construction Standards.
C. Contractor shall grade canal slopes in accordance with the project plans and geotechnical report’s recommendation. Backfill and compaction of the canal slopes shall adhere to ISPWC Section 202.
Amend Part 4 to include Section 4.2
4.2 There shall be no measurement and payment for Grading Canal Slopes and shall be considered incidental to other bid items.
SECTION 706
OTHER CONCRETE CONSTRUCTION
Amend Part 4.1 to include:
I. Pedestrian Ramp, No Detectable Warning Domes, Type Bike Ramp
1. Bid Schedule Payment Reference: 706.4.1.I.1
2. Bid Schedule Description: Pedestrian Ramp, No Domes, Type Bike Ramp …each (EA)
J. Concrete Curb Drain per each, to include all materials, labor, and appurtenances necessary for construction per the approved construction drawings.
1. Bid Schedule Payment Reference: 706.4.1.J.1
2. Bid Schedule Description: Curb Drain… each (EA)
SECTION 1003
SEDIMENT COLLECTION
Amend Part 4.1 include:
B. Fiber Rolls
1. Bid Schedule Payment Reference: 1003.4.1.G.1
2. Bid Schedule Description: Fiber/Straw Wattles Fiber Wattle….Linear foot (LF)
1131.01.01.A1 – TRAFFIC SIGNAL AND ILLUMINATION SYSTEM COMPLETE (TRAFFIC SIGNAL –
FRANKLIN/MCDERMOTT)
ON PAGE 8 OF SECTION 1130 (GENERAL CONDITIONS) OF ACHD’S TRAFFIC SPECIFICATIONS,
SUBSECTION 1130.03.E – USE TAX, add the following:
TRAFFIC SIGNAL AND ILLUMINATION SYSTEM COMPLETE MATERIAL LIST
Item
Number Item Description Quantity Supplied
By 1 Econolite Cobalt TS2-1 Traffic Signal Controller and Size 6
Cabinet: supplied with all related equipment, relays, load switches, and MMU. (Includes anchor bolts, does not include Opticom).
Cost = $18,333.00 each
1 ACHD
2 Electric Service Pedestal with UPS: 200 AMP, 120/240 volt (traffic signal and lighting service) to include dual meter bases. Manufacturer and model number to be determined. (Includes anchor bolts).
Cost = $11,177.00 each
1 ACHD
3 Pole, steel, 40-foot combination traffic signal and luminaire pole (includes anchor bolts). To be furnished with one 35-foot mast arm, one 15-foot luminaire mast arm and one 6-foot CCTV camera mast arm. Pole A.
Cost = $14,472.00 each
1 ACHD
4 Pole, steel, 25-foot combination traffic signal and luminaire pole (includes anchor bolts). To be furnished with one 50-foot mast arm, one 15-foot luminaire mast arm. Pole C.
Cost = $13,732.00 each
1 ACHD
Number Item Description Quantity Supplied
By 5 Pole, steel, 35-foot combination traffic signal and luminaire pole (includes anchor bolts). To be furnished with one 35-foot mast arm and one 15-foot luminaire mast arm. Poles E.
Cost = $13,143.00 each
1 ACHD
6 Pole, steel, 35-foot combination traffic signal and luminaire pole (includes anchor bolts). To be furnished with one 50-foot mast arm and one 15-foot luminaire mast arm. Poles G.
Cost = $14,301.00 each
1 ACHD
7 Pole, steel, 12-foot pedestrian signal pole (includes anchor bolts). Poles B, D, F, and H.
Cost = $1,862.00 each
4 ACHD
8 Traffic signal head, four-section, 12-inch, LED three-color left-arrow (red left-arrow, yellow left-arrow, flashing yellow left-arrow, green left-arrow) with 5-inch backplate. Manufacturer and model number to be determined. (Includes Astro bracket).
Cost = $556.00 each
4 ACHD
9 Traffic signal head, three-section, 12-inch, LED three-color ball (red, yellow, green) with 5-inch backplate.
Manufacturer and model number to be determined.
(Includes Astro bracket).
Cost = $443.00 each
10 ACHD
10 Traffic Signal Bracket: for side of posts, terminal compartment mounting of pole mounted signals. To be Crouse Hinds Arm Set, or equal.
Cost = $260.00 each
4 ACHD
11 Accessible Pedestrian Pushbutton Assembly: to include mounting assemblies, APS pushbutton and sign decals.
To be Campbell Company, Type AGPS or approved equal.
Cost = $440.00 each
8 ACHD
12 Pedestrian Signal: LED "Count Down" 16-inch, 2-section, one-way. Manufacturer and model number to be determined.
Cost = $180.00 each
8 ACHD
13 Pedestrian Signal Bracket: for side of post terminal compartment mounting for 16-inch, 2-section, one-way pedestrian heads.
Cost = $240.00 each
8 ACHD
Number Item Description Quantity Supplied
By
Luminaire: Leotek 100 watt class, catalog model: GCM2- 60J-MV-30K-3F-BK-145-SC or approved equal.
Cost = $205.00 each
4 ACHD
15 Photoelectric Control: multi-volt, with pole adaptor. To be Fisher Pierce #6690B or ACHD approved equal.
Cost = $60.00 each (estimated)
1 ACHD
16 Grid Smart Video Detection System: To include all materials for a complete install including mounting brackets, cabling and cabinet equipment required for a full install based on the manufacture specifications.
Cost = $17,096.00 each
1 ACHD
17 3-Conductor for Opticom. To be 3M Model 138 or equal.
Cost = $0.60/LF (estimated)
300 LF ACHD
18 3M Opticom Preemption Detection System to include one Model 764 four-direction phase selector and two Model 722 bi-direction preempt detectors or approved equal.
Cost = $3,778.00 for the system (estimated)
1 Meridian Fire Department
19 Mast arm and pole mounted signs with mounting brackets. Mounting brackets for mast arm mounted signs to be Pelco Astro Sign Bracket AB-0218 or an ACHD approved equal.
2 – R3-5R (30” x 36”) 2 – R3-4 (30” x 30”) 2 – Street Name Sign (McDermott Rd) (66" x 30") 2 – Street Name Sign (Franklin Rd) (60" x 30")
Per Plan Contractor
20 2-inch rigid plastic conduit (RPC) Per Plan Contractor
Wire copper, stranded, 600V, AWG No. 3/0 THWN, No. 6 THWN, No. 12 THWN and No. 6 Bare.
Per Plan Contractor
4-Conductor signal cable (600V, No. 14 stranded copper).
Per Plan Contractor
5-Conductor signal cable (600V, No. 14 stranded copper).
Per Plan Contractor
12-Conductor signal cable (600V, No. 14 stranded copper).
Per Plan Contractor
RJ-45 10/100 Base-TX Ethernet (High Power-over- Ethernet (High PoE) or PoE+ (IEEE 802.3at, class 4 standard) 21-30 VAC, 50/60 Hz power cable for CCTV Camera.
Per Plan Contractor
22 Concrete junction box, to be Idaho Precast Concrete Per Plan Contractor
Number Item Description Quantity Supplied
By Type S-40T/ADA or approved equal.
Concrete junction box, to be Idaho Precast Concrete Type S-45T/ADA or approved equal.
Per Plan Contractor
Concrete junction box, to be Idaho Precast Concrete Type S-45T/ADA with riser or approved equal.
Per Plan Contractor
23 Miscellaneous items to include foundations for poles, anchor bolts, conduit elbows, wire splices, connections, fuses, miscellaneous hardware, and other items necessary to complete the installation as depicted in the plans, ACHD supplemental provisions and these special provisions.
Per Plan
Contractor
Estimated TRAFFIC SIGNAL AND ILLUMINATION EQUIPMENT To Be Supplied By ACHD.
Total Cost = $125,376.00
Summary ACHD
Estimated TRAFFIC SIGNAL EQUIPMENT to be supplied by Meridian Fire Department.
Total Cost = $3,778.00
Summary Meridian Fire Department
1131.01.05 – INSTALL INTERCONNECT CABLE
INSTALL INTERCONNECT CABLE MATERIAL LIST
Number Item Description Quantity Supplied
By 1 12-Fiber cable for Interconnect to be Corning Altos
012RW4-14101A20 12-fiber cable or an ACHD approved equal. Cable shall be single mode, Gel free, loose tube and non-armored.
Cost = $0.34/ LF
6,508 ACHD
Estimated INSTALL INTERCONNECT CABLE To Be Supplied By ACHD.
Total Cost = $2,212.72
Summary ACHD
1131.01.06-INSTALL STREET LIGHT
INSTALL STREET LIGHT MATERIAL LIST
Number Item Description Quantity Supplied
By 1 Pole, steel, 30-foot mounting height, Davit arm style luminaire pole (includes anchor bolts). Refer to Valmont Industries drawing DB00372 for specifications. Poles 56740C - 56778C.
Cost = $2,800.00 each
37 ACHD
Luminaire: Leotek 100 watt class, catalog model: GCM2- 60J-MV-30K-3F-BK-145-SC or approved equal.
Cost = $205.00 each
ACHD
3 2-inch rigid plastic conduit (RPC) Per Plan Contractor
4 Wire copper, stranded, 600V, AWG No. 6 THWN and No.
12 THWN.
Per Plan Contractor
Concrete junction box, to be Idaho Precast Concrete Type S-40T/ADA or approved equal.
Per Plan Contractor
6 Miscellaneous items to include foundations for poles, anchor bolts, conduit elbows, wire splices, connections, fuses, miscellaneous hardware, and other items necessary to complete the installation as depicted in the plans, ACHD supplemental provisions and these special provisions.
Per Plan
Contractor
Estimated INSTALL STREET LIGHT To Be Supplied By
Total Cost = $111,185.00
Summary ACHD
1135.01.01 – ROADSIDE TRAFFIC SIGN INSTALLATION (ONE METAL POST)
ON PAGE 6 OF THE ACHD DIVISION 1100 SUPPLEMENTAL PROVISIONS, SUBSECTION 1135.02.E
– SIGN POST, DELETE THE FOLLOWING:
1. Metal Sign Support Upright – 2 Inch by 2 Inch (Typically Supplied by ACHD)
AND REPLACE WITH THE FOLLOWING:
1. Metal Sign Support Upright – 2 Inch by 2 Inch
(Supplied by Contractor) ON PAGE 6 OF THE ACHD DIVISION 1100 SUPPLEMENTAL PROVISIONS, SUBSECTION 1135.02.E
– SIGN POST, DELETE THE FOLLOWING:
2. Metal Sign Base (Typically Supplied by ACHD)
AND REPLACE WITH THE FOLLOWING:
2. Metal Sign Base
(Supplied by Contractor) ON PAGE 8 OF THE ACHD DIVISION 1100 SUPPLEMENTAL PROVISIONS, SUBSECTION 1135.02.E
– SIGN POST, DELETE THE FOLLOWING:
4. Mounting Hardware (Typically Supplied by ACHD)
AND REPLACE WITH THE FOLLOWING:
4. Mounting Hardware
(Supplied by Contractor)
SECTION 2040
FENCING
Amend Part 3 to include the following:
M. The contractor shall provide temporary fencing for dog park and homesite of Parcel No.
10. Fencing must be sufficient to contain large dogs and children. Contractor to maintain access to and parking for the dog park throughout the project, except when necessary to install irrigation pipe. Coordinate with owner on layout and timing. The fencing shall be removed at the cessation of construction. This includes 1 gate.
Amend Part 4.1 include:
D. Dog proof Fence installation and removal, Type – Type 4 Chain-Link Fence
1. Bid Schedule Payment References: 2040.4.1.D.1
2. Bid Schedule Description: Dog proof Fence installation and removal , Type 4
Gate & Chain-Link Fence...linear foot (LF)
1. SP 02020 – Gravel Repair
Description: This item shall include all costs associated with the repair of existing gravel driveway accesses abutting the project to match the grades of new back of sidewalk or driveway and existing gravel. Locations for repairs are shown on the plans or as directed in the field by the Engineer.
Materials & Workmanship: This item shall include excavation and/or borrow, construction of necessary embankment, labor, equipment, and materials necessary to complete placement of a 6-inch thickness of ¾” aggregate base course, on a compacted subgrade. Materials shall meet the requirements of Section 802.
Measurement and Payment:
ITEM 29, “VARIATIONS IN QUANTITIES”, ON PAGE GC16 OF THE ACHD GENERAL
CONDITIONS, SECOND PARAGRAPH, shall not apply to this bid item.
Payment for this item will be made under:
SP 02020 - Gravel Repair…………………………………………………………………………Per Square Yard
2. SP 02033 – Borrow Ditch (Typical)
Description: This item shall include all costs associated with the construction of borrow ditches in the specified locations shown on the plans or as directed in the field by the Engineer.
Materials & Workmanship: This item shall include all excavation, borrow, labor, filter sand, vegetation, and all appurtenances necessary for construction per the approved construction drawings. All materials shall meet the tolerances and specifications of the approved construction drawings.
Measurement and Payment:
SP 02033 – Borrow Ditch (Typical) .....................................................Per Linear Foot (LF)
3. SP 06004.A – NAMPA SEEPAGE BED
Description: Incorporated by reference, Part 1 of section 207 of the 2020 ISPWC and the 2023 Nampa Standard Construction Specifications Supplement to the 2020 ISPWC.
Materials: All materials including drainage rock and monitoring wells shall meet the requirements of the applicable ISPWC Sections and City of Nampa Construction Standards.
Workmanship: The Seepage Bed shall be placed at the location and elevation shown on the plans. Refer to the project plans for additional information. Workmanship shall meet the requirements of the applicable ISPWC Sections and City of Nampa Construction Standards.
Measurement and Payment: Unless specifically indicated in the bid schedule, all labor, material, and equipment required for seepage beds will be considered incidental to other Bid Items.
SP 06004.A – Seepage Bed 4.2'x15', 18" ...........................................Per Lineal Foot (LF)
4. SP 06004.B – ACHD SEEPAGE BED
Description: This item shall include all labor, equipment, and materials to construct and install infiltration beds and all appurtenances at the locations and as detailed on the plans. Infiltration beds shall be constructed in conformance with ACHD Section 8200 Standard Drawing BMP 20.
Materials: Contractor shall construct and install perforated piping, drain rock, filter sand, geotextile fabrics, backfill, observation wells, and appurtenances as detailed on the plans and SD BMP 20.
Measurement and Payment: Payment shall be on a linear foot basis to the dimensions shown on the plans. Any over excavation and associated drain rock, filter fabric, and backfill material shall be considered incidental to this item, and no additional payment will be made.
The cost of any utility service sleeve pipe or solid pipe for services is considered incidental to this bid item, and no additional payment will be made.
Shoring boxes may also be required for the construction of this item, and additional compensation will not be made.
Payment for this item will be made under:
SP 06004.B1 – Seepage Bed 2.5'x31', 18" ..........................................Per Lineal Foot (LF) SP 06004.B2 – Seepage Bed 2.5'x31', 18" ..........................................Per Lineal Foot (LF) SP 06004.C1– Seepage Bed 2.25'x22', 18".........................................Per Lineal Foot (LF) SP 06004.C2 – Seepage Bed 2.25'x22', 18" ........................................Per Lineal Foot (LF) SP 06004.C3 – Seepage Bed 2.25'x22', 18" ........................................Per Lineal Foot (LF)
SP 06004.D1 – Seepage Bed 2'x35', 18" ............................................Per Lineal Foot (LF) SP 06004.D2 – Seepage Bed 2'x35', 18" ............................................Per Lineal Foot (LF)
5. SP 11310 – INSTALL CONDUIT, 4-2” (TRENCH) WITH LOCATE WIRE
Description: This item includes all labor, equipment and materials necessary to install conduit in the locations shown on the plans or as directed.
Materials: Materials shall conform to Section 1131.05, Conduit, of the current version of the ACHD Supplemental Specifications, 1131 – Illumination, Traffic Signal Systems and Electrical.
Workmanship: This item includes trenching and installing conduit per Sections 1131.05, Conduit, and 1131.06,…