Franklin Road, McDermott Road to Black Cat Road
Solicitation number
CT227-07
Issued by
Ada County, Idaho

About this file

This is a Utility Information Sheet related to the Franklin Road widening project in Idaho, extending from McDermott Road to Black Cat Road. The project scope encompasses widening Franklin Road to five lanes, installing multi-use pathways on both sides of the roadway, constructing stormwater facilities, irrigation facilities, and continuous street lighting, as well as signalizing the intersection of McDermott Road and Franklin Road. Contractors are required to coordinate with all utility contractors involved in the project to ensure proper integration of utility work with the primary construction activities.

The document serves as a reference guide for utility providers and contractors to understand existing utility locations and requirements along the project corridor. This coordination document is essential for contractors bidding on or executing the roadway expansion project to identify potential conflicts with existing utilities and establish necessary communication protocols with utility service providers who maintain infrastructure within the project limits.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Utility Information

Franklin Road, McDermott to Black Cat Franklin Road and McDermott Intersection

Project #523011, 323021

Utility Company Work Duration and Contact Information:

Utilities require approx. 75 working days from NTP date to complete their relocations, adjustments, and installations after clearing, grubbing, tree trimming and removal. These utility windows may impact the Contractor’s critical path schedule by that amount of time, and utilities may be working on site for every phase of the project. Project phasing may have a significant effect on the schedule for utility relocations, adjustments, and installations.

Contractor shall coordinate and accommodate work with utility companies and schedule required construction windows throughout the project.

ACHD General Conditions Section 26 applies. Contact ACHD Utility Coordinator, Scott Bennett, at (208) 387-6259, with questions.

Utilities within project:

• Sparklight – Michael Stephen – (208) 615-0338 – michael.stephen@cableone.biz

• Lumen – James Hayes – (208) 350-1645 – James.P.Hayes@lumen.com

• City of Meridian Public Works – Micah Bandurraga – (208) 489-0352 – mbandurraga@meridiancity.org

• Idaho Power – Dan Hammerquist – (208) 388-2629 – dhammerquist@idahopower.com

• Intermountain Gas – Jordan Garcia – (208) 793-1528 – jordan.garcia@intgas.com

• Zayo – Ryan Goins (3C) - (208) 590-6681 - 3c.ryang@gmail.com mailto:michael.stephen@cableone.biz mailto:James.P.Hayes@lumen.com mailto:mbandurraga@meridiancity.org mailto:dhammerquist@idahopower.com mailto:jordan.garcia@intgas.com mailto:3c.ryang@gmail.com

File details come from the government source that posted it. Updated .