Supplemental_General_Notes_.pdf

PDF 52 KB Posted

Attached to
Franklin Road, McDermott Road to Black Cat Road
Solicitation number
CT227-07
Issued by
Ada County, Idaho

About this file

This is a Supplemental General Notes document for the Franklin Road, McDermott Road to Black Cat Road project in Idaho. The project encompasses the widening of Franklin Road to five lanes between McDermott Road and Black Cat Road, including the addition of multi-use pathways on both sides of the roadway, installation of stormwater facilities, irrigation facilities, and continuous street lighting. The scope of work also includes signalizing the intersection of McDermott Road and Franklin Road. Contractors must coordinate with all utility contractors throughout the project execution to ensure seamless integration of existing and new utility infrastructure.

No specific pricing terms, set asides, incumbent information, funding sources, response dates, due dates, site visit schedules, or bidders' conference details are provided in this supplemental notes document. The document appears to serve as clarifying guidance for contractors regarding project requirements and coordination obligations related to the Franklin Road improvement initiative.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Supplemental General Notes Franklin Rd, McDermott Rd to Black Cat

Project # 323021 / 523011

1. Right-of-Way Acquisition Pending

Parcel #1 at 15861 McDermott Road: Right-of-way negotiations for this property are ongoing. Any construction shown within Parcel #1 is contingent upon ACHD obtaining the necessary property rights and access. Contractor shall not enter or perform work within this property until authorized by ACHD.

2. Demolition of structures at Parcel #26 by Others

Demolition of the (2) residential structures at Parcel #26, 5035 W Franklin Road, will be performed by a separate contractor under contract with ACHD. The structures will be completely removed by 04/30/2027. The Contractor shall coordinate their work with ACHD and the demolition contractor to avoid conflicts and ensure proper sequencing of work within the limits of Parcel #26.