This document is an Exhibit "B" Special Conditions file for Volusia County's Deland IT Restroom Energy Conservation Measures project, identified by Contract No. C2031 and ITB No. 25-B-90LL. The project involves renovating four existing restroom spaces in an active, occupied County IT facility, with work primarily scheduled after normal business hours (Monday through Friday, 8:00 am to 5:00 pm). The contractor will be responsible for complete demolition and removal of existing equipment, ensuring minimal disruption to the facility's daily operations, and maintaining at least one restroom for each gender during business hours.
The special conditions outline critical requirements for the project, including strict security protocols where contractors must be escorted throughout the building, maintaining a secure work environment, and ensuring all tools remain secured in public areas. The County project manager will collaborate with the awarded contractor to determine dumpster and storage locations. The contractor must be prepared to immediately halt work if construction activities disrupt the facility's functionality, with the option to resume after business hours. All unused materials will be removed, and the contractor bears responsibility for any arrangements needed to meet the County's operational continuity requirements.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No. C2031 ITB No. 25-B-90LL
SC 1
EXHIBIT “B”
SPECIAL CONDITIONS
The following special conditions are supplementing, not replacing nor deleting the corresponding paragraphs in the general conditions.
1. The bulk of work for this project shall be scheduled for after normal business hours; Normal Business hours are Monday through Friday 8:00 am to 5:00 pm.
2. You will be working in an active and occupied County building. Any excessive noise, debris, or construction activity that disrupts the functionality will not be permitted. The contractor will be asked to stop work immediately and may continue after business hours.
3. The IT Facility is a secure building. All contractors must be escorted in and out of the building and may be required to go through security, and a county escort will be provided throughout the construction.
4. The awarded contractor shall be responsible for the demolition and removal of all equipment outlined in the scope of work. The County does not wish to retain any unused materials.
5. At no time during normal business hours shall the facility be without one restroom for each gender, each the men's and women’s (it is not permitted to have all bathrooms on-site offline during normal business hours). Any arrangement and costs needed to maintain this request shall be the responsibility of the awarded contractor.
6. The County project manager and the awarded contractor will determine locations for the contractor's dumpster and storage (if needed). Locations for any other construction items can be determined at this time.
7. All tools must remain secure while working in public areas.
File details come from the government source that posted it. Updated .