Attachment 4 - PPW Amd 02.xlsx
XLSX spreadsheet 34 KB Posted
- Attached to
- Alaska - Systems O&M and Remediation Federal contract opportunity
- Solicitation number
- SPE603-20-R-0509
- Issued by
- Defense Logistics Agency Energy
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Eielson PPW
| Eielson Air Force Base Price Proposal | ||||||
| COMPANY & LOCATION: | PROPOSAL VERSION NO.: | |||||
| PREPARER NAME: | DATE PREPARED: | |||||
| TASK | REF # | ITEM DESCRIPTION | EST QTY | UNIT | UNIT PRICE | TOTAL PRICE |
| Eielson Air Force Base: Known Specific PWS Tasks | ||||||
| Initial Project Initiation IAW PWS 3.1 Task 1 | 001 | The Contractor will identify the primary POC to DLA. Activities included within the project initiation task include but are not limited to the project kickoff meeting and the documents associated with the Contract sites. | 1 | EA | $0.00 | |
| Project Mgmt Review Meetings & Quarterly Status Meetings IAW PWS Task 4.3.1 | 002 | Beginning 3 Months post award: quarterly status meetings, generally 2 hours long; includes information per PWS Para. 4.3.1. | 16 | EA | $0.00 | |
| Quality Control Plan IAW PWS Task 2.12 | 003 | Per PWS 2.12, prepare and submit an initial written QCP. | 1 | EA | $0.00 | |
| PMP and IMS IAW PWS 4.2.1 and 4.2.3 | 004 | Initial Project Management Plan & Integrated Management Schedule | 1 | EA | $0.00 | |
| Quarterly updates to PMP and IMS IAW PWS 4.2.1 and 4.2.3. | 005 | Provide quarterly updates as set forth ein PWS 4.2.1 and 4.2.3 IGCE INFO: 8 hours Proj Manager | 15 | EA | $0.00 | |
| Attachment 2 Appendix C Task 10-Moose Creek Semiannual Groundwater Monitoring | 006 | Moose Creek Groundwater Monitoring (Low or High) | 8 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 11-Tanker Row Annual Groundwater Monitoring | 007 | Tanker Row Groundwater Monitoring annual event | 4 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 12-Moose Creek Stakeholder Meetings | 008 | Moose Creek Stakeholder meetings | 8 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 13-Eielson Take Off Pad Groundwater Monitoring | 009 | ETOP Groundwater Sampling 2022 | 1 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 14-Manchu Road Groundwater Monitoring Event | 010 | Manchu Road Groundwater Monitoring 2022 | 1 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 15-O&M/Electricity Moose Creek Remedial System | 011 | Remedial System O&M including electricity | 4 | YEARS | $0.00 | |
| Attachment 2 Appendix C Task 16-Decision Document Addendums: Moose Creek and Manchu Road Sites | 012 | Decision Document Addendums - Moose Creek & Manchu Rd. sites | 2 | LUMP SUM | $0.00 | |
| Attachment 2 Appendix C Task 17-Moose Creek Five-Year Review (5YR) | 013 | Moose Creek Five-Year Review | 1 | LUMP SUM | $0.00 |
| Eielson Air Force Base: Items Reference List for Unknown Requirements | |||||
| Develop a Health & Safety (HASP) IAW Sec 4.2.4 of the PWS | 014 | HASP detailing the safe work practices as set forth | 1 | EA | $0.00 |
| Conduct soil gas survey IAW PWS 3.0 - Task 5 | 015 | Price per unit (10 points/unit) <=4' depth | 1 | EA | $0.00 |
| 016 | Price per unit (10 points/unit) >10' but <=14' depth | 1 | EA | $0.00 | |
| 017 | Mobilization cost for soil gas survey | 1 | LUMP SUM | $0.00 | |
| Conduct geophysical survey IAW PWS 3.0 Task 5 | 018 | Price per unit (10,000 linear feet) to include in report of findings | 1 | LUMP SUM | $0.00 |
| Locate, install, and sample soil borings IAW PWS 3.0 Task 5 | 019 | Price per boring <=10' | 1 | LUMP SUM | $0.00 |
| 020 | Price per foot of boring >=11 and <=20' | 1 | EA | $0.00 | |
| 021 | Price per foot of boring >= 21' and <=60' | 1 | EA | $0.00 | |
| 022 | Price per foot of boring >=61 and <=150' | 1 | EA | $0.00 | |
| 023 | Mobilization cost for soil boring | 1 | LUMP SUM | $0.00 | |
| Locate, Install and sample monitoring wells IAW PWS 3.0 Task 5 (Includes decommissioning of wells) | 024 | Price per 2" Monitoring Well <=10' | 1 | LUMP SUM | $0.00 |
| 025 | Cost per foot of 2" monitoring well >= 11' and <= 21' | 1 | EA | $0.00 | |
| 026 | Cost per foot of 2" monitoring well >=21 and <=60' | 1 | EA | $0.00 | |
| 027 | Cost per foot of 2" monitoring well >= 61 and <=150' | 1 | EA | $0.00 | |
| 028 | Price per 4" monitoring well <=10' | 1 | LUMP SUM | $0.00 | |
| 029 | Cost per foot of 4" monitoring well from >=11' and <=20' | 1 | EA | $0.00 | |
| 030 | Cost per foot of 4" monitoring well from 21 to 60 feet | 1 | EA | $0.00 | |
| 031 | Cost per foot of 4" monitoring well from 61 to150 feet | 1 | EA | $0.00 | |
| 032 | Cost per foot to Close/Decommission 2" dia. well | 1 | EA | $0.00 | |
| 033 | Cost per foot to Close/Decommission 4" dia. well | 1 | EA | $0.00 | |
| 034 | Mobilization cost for monitoring well installation/decommissioning | 1 | LUMP SUM | $0.00 | |
| Conduct well development IAW PWS 3.0 Task 5 | 035 | Price for one well development | 1 | LUMP SUM | $0.00 |
| Conduct Direct Push Testing (DPT) IAW PWS 3.0 Task 5 | 036 | Cost per unit of DPT (5 bores per unit) | 1 | EA | $0.00 |
| 037 | Mobilization for DPT testing | 1 | LUMP SUM | $0.00 | |
| Perform soil boring survey IAW PWS 3.0 Task 5 | 038 | Price of 10 soil borings/unit | 1 | EA | $0.00 |
| Conduct analytical testing IAW PWS 3.0 Task 3; Cost per test for the following procedures: | 039 | 6010 (Individual metal) | 1 | EA | $0.00 |
| 040 | 8081 (Organochlorine Pesticides) | 1 | EA | $0.00 | |
| 041 | 8082 (PCBs) | 1 | EA | $0.00 | |
| 042 | 8151 (Chlorinated Herbicides) | 1 | EA | $0.00 | |
| 043 | 8260 (Full List Volatile Organic Compounds) | 1 | EA | $0.00 | |
| 044 | 8260 (BTEX/MTBE/Naphthalene) | 1 | EA | $0.00 | |
| 045 | 8270 (Semi-Volatile Organic Compounds) | 1 | EA | $0.00 | |
| 046 | 8270-SIM (Polyaromatic Hydrocarbons) | 1 | EA | $0.00 | |
| 047 | 9065 | 1 | EA | $0.00 | |
| 048 | 624 (Purgeables) | 1 | EA | $0.00 | |
| 049 | 625 (Semivolatile Organic Compounds) | 1 | EA | $0.00 | |
| 050 | TCLP Metals | 1 | EA | $0.00 | |
| 051 | 9045 (pH) | 1 | EA | $0.00 | |
| 052 | 1010 (Ignitability) | 1 | EA | $0.00 | |
| 053 | AK 101 (GRO) | 1 | EA | $0.00 | |
| 054 | AK 102 (DRO) | 1 | EA | $0.00 | |
| 055 | AK 103 (RRO) | 1 | EA | $0.00 | |
| 056 | TO 15 Air sample | 1 | EA | $0.00 | |
| Install and maintain recovery well IAW PWS 3.0 Task 5 | 057 | Price per 6" recovery well up to 10 Feet (including water table depression and free product recovery pump) | 1 | LUMP SUM | $0.00 |
| 058 | Price per foot of 6" recovery well from 11 to 20 Feet | 1 | EA | $0.00 | |
| 059 | Price per foot of 6" recovery well from 21 to 60 Feet | 1 | EA | $0.00 | |
| 060 | Price per foot of 6" recovery well from 61 to 120 Feet | 1 | EA | $0.00 | |
| 061 | Mobilization cost for 6" recovery well | 1 | EA | $0.00 | |
| 062 | Monthly price for 6" recovery well system O&M | 1 | EA | $0.00 | |
| 063 | Cost of installing water table depression and free product recovery pump system on an existing 4” monitoring well | 1 | EA | $0.00 | |
| 064 | Mobilization cost for pump installation on existing 4" monitoring well | 1 | EA | $0.00 | |
| 065 | Monthly price for 4" recovery well system O&M | 1 | EA | $0.00 | |
| Conduct pump testing IAW PWS 3.0 Task 5 | 066 | Lump sum price for pump test | 1 | EA | $0.00 |
| Report preparation, duplication and distribution IAW PWS 3.0 Task 4 | 067 | Lump sum price for report preparation, duplication, and distribution | 1 | EA | $0.00 |
| Additional Environmental Services Associated with PWS 3.0 Tasks 1-9 and Appendix C | 068 | Project Manager | 1 | PER HOUR | $0.00 |
| 069 | Engineer I | 1 | PER HOUR | $0.00 | |
| 070 | Engineer II | 1 | PER HOUR | $0.00 | |
| 071 | Engineer III | 1 | PER HOUR | $0.00 | |
| 072 | Chemist | 1 | PER HOUR | $0.00 | |
| 073 | Environmental Scientist I | 1 | PER HOUR | $0.00 | |
| 074 | Environmental Scientist II | 1 | PER HOUR | $0.00 | |
| 075 | Environmental Scientist III | 1 | PER HOUR | $0.00 | |
| 076 | Geologist I | 1 | PER HOUR | $0.00 | |
| 077 | Geologist II | 1 | PER HOUR | $0.00 | |
| 078 | Geologist III | 1 | PER HOUR | $0.00 | |
| 079 | Hydrogeologist I | 1 | PER HOUR | $0.00 | |
| 080 | Hydrogeologist II | 1 | PER HOUR | $0.00 | |
| 081 | Hydrogeologist III | 1 | PER HOUR | $0.00 | |
| 082 | Toxicologist I | 1 | PER HOUR | $0.00 | |
| 083 | Toxicologist II | 1 | PER HOUR | $0.00 | |
| 084 | Toxicologist III | 1 | PER HOUR | $0.00 | |
| 085 | Drafter | 1 | PER HOUR | $0.00 | |
| 086 | Traffic Control Engineer | 1 | PER HOUR | $0.00 | |
| 087 | Cost Accountant | 1 | PER HOUR | $0.00 | |
| 088 | Secretary | 1 | PER HOUR | $0.00 | |
| 089 | Buyer | 1 | PER HOUR | $0.00 | |
| 090 | Site Labor Foreman | 1 | PER HOUR | $0.00 | |
| 091 | Remediation System Operator | 1 | PER HOUR | $0.00 | |
| 092 | Heavy Equipment Operator | 1 | PER HOUR | $0.00 | |
| 093 | Laborer | 1 | PER HOUR | $0.00 | |
| 094 | Drill Rig Operator | 1 | PER HOUR | $0.00 | |
| 095 | Environmental Technician | 1 | PER HOUR | $0.00 | |
| 096 | Utility Truck | 1 | PER DAY | $0.00 | |
| 097 | O2 Explosimeter | 1 | PER DAY | $0.00 | |
| 098 | Groundwater Sampling Pump | 1 | PER DAY | $0.00 | |
| 099 | Flame Ionization OCA | 1 | PER DAY | $0.00 | |
| 100 | Air Velocity Meter | 1 | PER DAY | $0.00 | |
| 101 | Field GC | 1 | PER DAY | $0.00 | |
| 102 | Furnish and fill with soil or water DOT approved 55 gallon drum | 1 | EA, DRUM | $0.00 | |
| 103 | Furnish and fill with soil roll-off bin | 1 | EA, BIN | $0.00 | |
| 104 | Shipping of soil and water samples for analytical testing price for each 25 lb shipping container | 1 | EA, COOLER | $0.00 | |
| 105 | Disposable Bailers | 1 | EACH | $0.00 | |
| 106 | Tedlar Bags | 1 | PER DOZEN | $0.00 | |
| 107 | Pickup Truck 1/2 ton | 1 | PER DAY | $0.00 | |
| 108 | Air Compressor (7CFM) | 1 | PER DAY | $0.00 | |
| 109 | Generator (4000K watt) | 1 | PER DAY | $0.00 | |
| 110 | CAD Equipment Use Charge | 1 | PER DAY | $0.00 | |
| 111 | Photoionization Detector | 1 | PER DAY | $0.00 | |
| 112 | Groundwater Multimeter | 1 | PER DAY | $0.00 | |
| 113 | Deionized Water | 1 | CASE | $0.00 | |
| Multiple: Generally associtated with Task 5 requirements | 114 | Oil/water interface probe rental, per day | 1 | EA | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 115 | Nitrile gloves, case | 1 | CASE | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 116 | Alconox, 50 1/2 ox packets (box) | 1 | BOX | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 117 | Drum storage locker, 14', rental per day | 1 | EA | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 118 | Disposable Tubing, 3/8", 500' roll | 1 | ROLL | $0.00 |
| Appendix C Task 13-Eielson Take Off Pad Groundwater Monitoring | 119 | Investigative Disposal of Waste IDW for ETOP sampling | 1 | LUMP SUM | $0.00 |
| Total By CLIN | |
| CLIN 0001 - Environmental Assessment, Remediation, Response | $0.00 |
| CLIN 0002 - O&M of Remediation System | $0.00 |
| CLIN 0003 - DLA HQ Environmental Support Services | N/A |
| Total Offered Price | $0.00 |
Whittier PPW
| DFSP Whittier Price Proposal | |
| COMPANY & LOCATION: | PROPOSAL VERSION NO.: |
| PREPARER NAME: | DATE PREPARED: |
| TASK | REF # | ITEM DESCRIPTION | EST QTY | UNIT | UNIT PRICE | TOTAL PRICE |
| DFSP Whittier: Known Specific PWS Tasks | ||||||
| Initial Project Initiation IAW PWS 3.1 Task 1 | 001 | The Contractor will identify the primary POC to DLA. Activities included within the project initiation task include but are not limited to the project kickoff meeting and the documents associated with the Contract sites. | 1 | EA | $0.00 | |
| Project Mgmt Review Meetings & Quarterly Status Meetings IAW PWS Task 4.3.1 | 002 | Beginning 3 Months post award: quarterly status meetings, generally 2 hours long; includes information per PWS Para. 4.3.1. | 16 | EA | $0.00 | |
| Quality Control Plan IAW PWS Task 2.12 | 003 | Per PWS 2.12, prepare and submit an initial written QCP. | 1 | EA | $0.00 | |
| PMP and IMS IAW PWS Tasks 4.2.1 and 4.2.3 | 004 | Initial Project Management Plan & Integrated Management Schedule | 1 | EA | $0.00 | |
| Quarterly updates to PMP and IMS IAW PWS Tasks 4.2.1 and 4.2.3 | 005 | Provide quarterly updates as set forth in PWS 4.2.1 and 4.2.3 IGCE INFO: 8 hours Proj Manager | 15 | EA | $0.00 | |
| Attachment 3 Appendix D Task 10-Whittier Summer/High Groundwater Monitoring Events | 006 | Whittier High/Summer Groundwater Sampling inc. AKRR Ins. Requirements | 4 | LUMP SUM | $0.00 | |
| Attachment 3 Appendix D Task 11-Whittier Winter/Low Groundwater Monitoring Events | 007 | Whittier Low/Winter Groundwater Sampling | 4 | LUMP SUM | $0.00 | |
| Attachment 3 Appendix D Task 12-O&M/Electricity Whittier Remedial System Operation | 008 | Remedial System O&M including electricity | 4 | EA | $0.00 | |
| Attachment 3 Appendix D Task 13-Alaska Railroad Annual Fee for Site Access at Whittier, AK | 009 | Annual payment of AK Railroad Right of Entry Fee | 4 | ANNUAL | $0.00 | |
| Attachment 3 Appendix D Task 14-Decision Document Addendum: Former DFSP Whittier | 010 | Revision/Update of Decision Document | 1 | LUMP SUM | $0.00 | |
| Attachment 3 Appendix D Task 15-Former DFSP Whittier Well Maintenance and Assessment | 011 | Well Maintenance and Assessment | 1 | LUMP SUM | $0.00 | |
| Attachment 3 Appendix D Task 16-Five Year Review (5YR), FORMER DFSP Whittier | 012 | Five Year Review | 1 | LUMP SUM | $0.00 |
| DFSP Whittier: Items Reference List for Unknown Requirements | |||||
| Develop a Health & Safety (HASP) IAW Sec 4.2.4 of the PWS | 013 | HASP detailing the safe work practices as set forth | 1 | EA | $0.00 |
| Conduct soil gas survey IAW PWS 3.0 - Task 5 | 014 | Price per unit (10 points/unit) <=4' depth | 1 | EA | $0.00 |
| 015 | Price per unit (10 points/unit) >10' but <=14' depth | 1 | EA | $0.00 | |
| 016 | Mobilization cost for soil gas survey | 1 | LUMP SUM | $0.00 | |
| Conduct geophysical survey IAW PWS 3.0 Task 5 | 017 | Price per unit (10,000 linear feet) to include in report of findings | 1 | LUMP SUM | $0.00 |
| Locate, install, and sample soil borings IAW PWS 3.0 Task 5 | 018 | Price per boring <=10' | 1 | LUMP SUM | $0.00 |
| 019 | Price per foot of boring >=11 and <=20' | 1 | EA | $0.00 | |
| 020 | Price per foot of boring >= 21' and <=60' | 1 | EA | $0.00 | |
| 021 | Price per foot of boring >=61 and <=150' | 1 | EA | $0.00 | |
| 022 | Mobilization cost for soil boring | 1 | LUMP SUM | $0.00 | |
| Locate, Install and sample monitoring wells IAW PWS 3.0 Task 5 (Includes decommissioning of wells) | 023 | Price per 2" Monitoring Well <=10' | 1 | LUMP SUM | $0.00 |
| 024 | Cost per foot of 2" monitoring well >= 11' and <= 21' | 1 | EA | $0.00 | |
| 025 | Cost per foot of 2" monitoring well >=21 and <=60' | 1 | EA | $0.00 | |
| 026 | Cost per foot of 2" monitoring well >= 61 and <=150' | 1 | EA | $0.00 | |
| 027 | Price per 4" monitoring well <=10' | 1 | LUMP SUM | $0.00 | |
| 028 | Cost per foot of 4" monitoring well from >=11' and <=20' | 1 | EA | $0.00 | |
| 029 | Cost per foot of 4" monitoring well from 21 to 60 feet | 1 | EA | $0.00 | |
| 030 | Cost per foot of 4" monitoring well from 61 to150 feet | 1 | EA | $0.00 | |
| 031 | Cost per foot to Close/Decommission 2" dia. well | 1 | EA | $0.00 | |
| 032 | Cost per foot to Close/Decommission 4" dia. well | 1 | EA | $0.00 | |
| 033 | Mobilization cost for monitoring well installation/decommissioning | 1 | LUMP SUM | $0.00 | |
| Conduct well development IAW PWS 3.0 Task 5 | 034 | Price for one well development | 1 | LUMP SUM | $0.00 |
| Conduct Direct Push Testing (DPT) IAW PWS 3.0 Task 5 | 035 | Cost per unit of DPT (5 bores per unit) | 1 | EA | $0.00 |
| 036 | Mobilization for DPT testing | 1 | LUMP SUM | $0.00 | |
| Perform soil boring survey IAW PWS 3.0 Task 5 | 037 | Price of 10 soil borings/unit | 1 | EA | $0.00 |
| Conduct analytical testing IAW PWS 3.0 Task 3; Cost per test for the following procedures: | 038 | 6010 (Individual metal) | 1 | EA | $0.00 |
| 039 | 8081 (Organochlorine Pesticides) | 1 | EA | $0.00 | |
| 040 | 8082 (PCBs) | 1 | EA | $0.00 | |
| 041 | 8151 (Chlorinated Herbicides) | 1 | EA | $0.00 | |
| 042 | 8260 (Full List Volatile Organic Compounds) | 1 | EA | $0.00 | |
| 043 | 8260 (BTEX/MTBE/Naphthalene) | 1 | EA | $0.00 | |
| 044 | 8270 (Semi-Volatile Organic Compounds) | 1 | EA | $0.00 | |
| 045 | 8270-SIM (Polyaromatic Hydrocarbons) | 1 | EA | $0.00 | |
| 046 | 9065 | 1 | EA | $0.00 | |
| 047 | 624 (Purgeables) | 1 | EA | $0.00 | |
| 048 | 625 (Semivolatile Organic Compounds) | 1 | EA | $0.00 | |
| 049 | TCLP Metals | 1 | EA | $0.00 | |
| 050 | 9045 (pH) | 1 | EA | $0.00 | |
| 051 | 1010 (Ignitability) | 1 | EA | $0.00 | |
| 052 | AK 101 (GRO) | 1 | EA | $0.00 | |
| 053 | AK 102 (DRO) | 1 | EA | $0.00 | |
| 054 | AK 103 (RRO) | 1 | EA | $0.00 | |
| 055 | TO 15 Air sample | 1 | EA | $0.00 | |
| Install and maintain recovery well IAW PWS 3.0 Task 5 | 056 | Price of 6" recovery well up to 10 Feet (including water table depression and free product recovery pump) | 1 | LUMP SUM | $0.00 |
| 057 | Price per foot of 6" recovery well from 11 to 20 Feet | 1 | EA | $0.00 | |
| 058 | Price per foot of 6" recovery well from 21 to 60 Feet | 1 | EA | $0.00 | |
| 059 | Price per foot of 6" recovery well from 61 to 120 Feet | 1 | EA | $0.00 | |
| 060 | Mobilization cost for 6" recovery well | 1 | EA | $0.00 | |
| 061 | Monthly price for 6" recovery well system O&M | 1 | EA | $0.00 | |
| 062 | Cost of installing water table depression and free product recovery pump system on an existing 4” monitoring well | 1 | EA | $0.00 | |
| 063 | Mobilization cost for pump installation on existing 4" monitoring well | 1 | EA | $0.00 | |
| 064 | Monthly price for 4" recovery well system O&M | 1 | EA | $0.00 | |
| Conduct pump testing IAW PWS 3.0 Task 5 | 065 | Lump sum price for pump test | 1 | EA | $0.00 |
| Report preparation, duplication and distribution IAW PWS 3.0 Task 4 | 066 | Lump sum price for report preparation, duplication, and distribution | 1 | EA | $0.00 |
| Additional Environmental Services Associated with PWS 3.0 Tasks 1-9 and Attachment 3 Appendix D | 067 | Project Manager | 1 | PER HOUR | $0.00 |
| 068 | Engineer I | 1 | PER HOUR | $0.00 | |
| 069 | Engineer II | 1 | PER HOUR | $0.00 | |
| 070 | Engineer III | 1 | PER HOUR | $0.00 | |
| 071 | Chemist | 1 | PER HOUR | $0.00 | |
| 072 | Environmental Scientist I | 1 | PER HOUR | $0.00 | |
| 073 | Environmental Scientist II | 1 | PER HOUR | $0.00 | |
| 074 | Environmental Scientist III | 1 | PER HOUR | $0.00 | |
| 075 | Geologist I | 1 | PER HOUR | $0.00 | |
| 076 | Geologist II | 1 | PER HOUR | $0.00 | |
| 077 | Geologist III | 1 | PER HOUR | $0.00 | |
| 078 | Hydrogeologist I | 1 | PER HOUR | $0.00 | |
| 079 | Hydrogeologist II | 1 | PER HOUR | $0.00 | |
| 080 | Hydrogeologist III | 1 | PER HOUR | $0.00 | |
| 081 | Toxicologist I | 1 | PER HOUR | $0.00 | |
| 082 | Toxicologist II | 1 | PER HOUR | $0.00 | |
| 083 | Toxicologist III | 1 | PER HOUR | $0.00 | |
| 084 | Drafter | 1 | PER HOUR | $0.00 | |
| 085 | Traffic Control Engineer | 1 | PER HOUR | $0.00 | |
| 086 | Cost Accountant | 1 | PER HOUR | $0.00 | |
| 087 | Secretary | 1 | PER HOUR | $0.00 | |
| 088 | Buyer | 1 | PER HOUR | $0.00 | |
| 089 | Site Labor Foreman | 1 | PER HOUR | $0.00 | |
| 090 | Remediation System Operator | 1 | PER HOUR | $0.00 | |
| 091 | Heavy Equipment Operator | 1 | PER HOUR | $0.00 | |
| 092 | Laborer | 1 | PER HOUR | $0.00 | |
| 093 | Drill Rig Operator | 1 | PER HOUR | $0.00 | |
| 094 | Environmental Technician | 1 | PER HOUR | $0.00 | |
| 095 | Utility Truck | 1 | PER DAY | $0.00 | |
| 096 | O2 Explosimeter | 1 | PER DAY | $0.00 | |
| 097 | Groundwater Sampling Pump | 1 | PER DAY | $0.00 | |
| 098 | Flame Ionization OCA | 1 | PER DAY | $0.00 | |
| 099 | Air Velocity Meter | 1 | PER DAY | $0.00 | |
| 100 | Field GC | 1 | PER DAY | $0.00 | |
| 101 | Furnish and fill with soil or water DOT approved 55 gallon drum | 1 | EA, DRUM | $0.00 | |
| 102 | Furnish and fill with soil roll-off bin | 1 | EA, BIN | $0.00 | |
| 103 | Shipping of soil and water samples for analytical testing price for each 25 lb shipping container | 1 | EA, COOLER | $0.00 | |
| 104 | Disposable Bailers | 1 | EACH | $0.00 | |
| 105 | Tedlar Bags | 1 | PER DOZEN | $0.00 | |
| 106 | Pickup Truck 1/2 ton | 1 | PER DAY | $0.00 | |
| 107 | Air Compressor (7CFM) | 1 | PER DAY | $0.00 | |
| 108 | Generator (4000K watt) | 1 | PER DAY | $0.00 | |
| 109 | CAD Equipment Use Charge | 1 | PER DAY | $0.00 | |
| 110 | Photoionization Detector | 1 | PER DAY | $0.00 | |
| 111 | Groundwater Multimeter | 1 | PER DAY | $0.00 | |
| 112 | Deionized Water | 1 | CASE | $0.00 | |
| 113 | Hydrasleeve sampling equipment | 1 | LUMP SUM | $0.00 | |
| 114 | utility vehicle for clearing site | 1 | WEEK | $0.00 | |
| Multiple: Generally associtated with Task 5 requirements | 115 | Oil/water interface probe rental, per day | 1 | PER DAY | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 116 | Nitrile gloves, case | 1 | CASE | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 117 | Alconox, 50 1/2 Box packets (box) | 1 | BOX | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 118 | Drum storage locker, 14', rental per day | 1 | PER DAY | $0.00 |
| Multiple: Generally associtated with Task 5 requirements | 119 | Disposable Tubing, 3/8", 500' roll | 1 | ROLL | $0.00 |
| Total By CLIN | |
| CLIN 0001 - Environmental Assessment, Remediation, Response | $0.00 |
| Total Offered Price | $0.00 |