Amendment SP3300-15-R-0009-0003

View the file

Other files

File Type Posted
Amendment_0004_RFP_SP3300-15-R-0009.pdf PDF
Attachment_9_Past_Performance_Questionnaire_DLA_Fire_Protection.docx DOCX document
Exhibit_3_-_Fire_Suppression_Systems _Inspection_ _Testing_Requirements_Rev1 _8-7-15.docx DOCX document
SF_30_Amendment_SP3300_15_R_0009_0001.pdf PDF
Building_750_-_Available_Contractor_Space _8-6-15.pdf PDF
Amendment_0001.pdf PDF
Exhibit_7_-_United_Facilities_Guide_Specifications_(UFGS)_Referenced_List.docx DOCX document
Exhibit_5_-_Impairment_Procedure.docx DOCX document
Exhibit_4_-_Fire_Alarm_Systems_Inspection_and_Testing_Requirements.docx DOCX document
Exhibit_6_-_Work_Authorization_Form.xlsx XLSX spreadsheet
Exhibit_8_-_Fire_Protection_Drawings_Schedule.docx DOCX document
Exhibit_2_-_Building-Systems_Fire_Alarm_Inventory.docx DOCX document
Exhibit_1_-_Building-Systems_Fire_Suppression_Inventory.docx DOCX document
Exhibit_3_-_Fire_Suppression_Systems_Inspection_and_Testing_Requirements.docx DOCX document
Attachment_L_-_SF25A_(Payment_Bond).pdf PDF
Attachment_J_-_SF24_-_Bid_Bond.pdf PDF
Attachment_I_-_DLA_SP_Camera_Pass_Request_Form.pdf PDF
Attachment_A_New_Personnel_Notification_Form.docm DOCM document
Attachment_B_-_Short_Form2.pdf PDF
Attachment_G_-_Combined_Modified_UFGS_Specifications _3-9-15.pdf PDF
Attachment_F_-_SOW_DES-SP_Fire_Systems_Maint.docx DOCX document
Attachment_K_-_SF25_(Performance_Bond).pdf PDF
Attachment_M_-_WD_PA150131_20150626.pdf PDF
Attachment_E_Deliv_Notification_Form.docm DOCM document
Attachment_C_-_Long_Form.pdf PDF
SP3300-15-R-0009.pdf PDF
Attachment_D_Badge_Renewal.doc DOC document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, Xs not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

SP3300 SP3300

DLA DISTRIBUTION

OFFICE OF PROCUREMENT - EBS

2001 MISSION DRIVE

NEW CUMBERLAND PA 17070-5000

DLA DISTRIBUTION

OFFICE OF PROCUREMENT - EBS

2001 MISSION DRIVE

NEW CUMBERLAND PA 17070-5000

SP3300-15-R-0009

08/14/2015

07/24/2015

See continuation sheet

0058574773

XX

RIFs for Inspection, Repair, and Maintenance of Fire Protection Systems Solicitation number SP3300-15-R-0009

8/14/2015

1. Since as of 8/11/15, the past performance questionnaire form is still not available, we would like to request a 2 week extension of the due date of this bid to allow adequate time for contractors to complete the form, submit it to their customers, and give the customers adequate time to complete the form and send it to the contracting officer. We do not feel even if received today that it allots adequate time to expect customers to turn around this document.

RESPONSE: A two day extension to the RFP closing date is hereby issued. The RFP closing date/time is Wednesday, August 26, 2015 at 1:00 PM EDT (1300 hours local).

2. NFPA 25 requires weekly inspections of Fire Pumps, however only monthly requirements are stated in the RFP exhibits. Please confirm if weekly operation and preventative maintenance are required per NFPA 25, 8.2.2, and 8.3.1.1.

RESPONSE: The Exhibits should be followed. In the case of the fire pumps referenced in the RFI, there is no weekly requirement. The most frequent task listed is monthly.

All other terms and conditions remain unchanged.