Exhibit 3

View the file

Other files

File Type Posted
Amendment_0004_RFP_SP3300-15-R-0009.pdf PDF
SF_30_Amendment_SP3300_15_R_0009_0003.pdf PDF
Attachment_9_Past_Performance_Questionnaire_DLA_Fire_Protection.docx DOCX document
Exhibit_3_-_Fire_Suppression_Systems _Inspection_ _Testing_Requirements_Rev1 _8-7-15.docx DOCX document
SF_30_Amendment_SP3300_15_R_0009_0001.pdf PDF
Building_750_-_Available_Contractor_Space _8-6-15.pdf PDF
Amendment_0001.pdf PDF
Exhibit_7_-_United_Facilities_Guide_Specifications_(UFGS)_Referenced_List.docx DOCX document
Exhibit_5_-_Impairment_Procedure.docx DOCX document
Exhibit_4_-_Fire_Alarm_Systems_Inspection_and_Testing_Requirements.docx DOCX document
Exhibit_6_-_Work_Authorization_Form.xlsx XLSX spreadsheet
Exhibit_8_-_Fire_Protection_Drawings_Schedule.docx DOCX document
Exhibit_2_-_Building-Systems_Fire_Alarm_Inventory.docx DOCX document
Exhibit_1_-_Building-Systems_Fire_Suppression_Inventory.docx DOCX document
Attachment_L_-_SF25A_(Payment_Bond).pdf PDF
Attachment_J_-_SF24_-_Bid_Bond.pdf PDF
Attachment_I_-_DLA_SP_Camera_Pass_Request_Form.pdf PDF
Attachment_A_New_Personnel_Notification_Form.docm DOCM document
Attachment_B_-_Short_Form2.pdf PDF
Attachment_G_-_Combined_Modified_UFGS_Specifications _3-9-15.pdf PDF
Attachment_F_-_SOW_DES-SP_Fire_Systems_Maint.docx DOCX document
Attachment_K_-_SF25_(Performance_Bond).pdf PDF
Attachment_M_-_WD_PA150131_20150626.pdf PDF
Attachment_E_Deliv_Notification_Form.docm DOCM document
Attachment_C_-_Long_Form.pdf PDF
SP3300-15-R-0009.pdf PDF
Attachment_D_Badge_Renewal.doc DOC document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WET PIPE SPRINKLER SYSTEMS (including Antifreeze Systems)

Combined Recommendation for Wet Pipe Sprinkler Systems

Cycle
System Component
* Work
Annually
All Control Valves

(Lock, Unlocked, Supervised, or Unsupervised) Test 13.3.3.1: Operate valve through its full range and return to its normal position.

- Confirm valve position after operation.

Waterflow Alarm Devices (Water motor gong, vane-type and pressure switch-type water flow devices) Inspect 13.2.6:

-Operate to verify function and alarm at panel.

-Verify alarm test valve alignment and tamper switch (if applicable)

Supervisory Signal Devices
Inspect 5.2.5: Inspect to verify devices are free from physical damage.
Main Drain
Test 13.2.5, 13.2.5.1:

- Conduct Main Drain Test.

- Read and record static and residual pressure.

- Attach readings to gauge with a tag.

- Compare resulting test pressures with previous test pressures and verify results are within acceptable limits or identify corrective measures.

Alarm valve and trim
Inspect 13.4.1.1:

-Visual inspection of alarm valve exterior, trim, gauges.

- Verify and record valve pressure and legibility of hydraulic placard (if applicable).

Fire Department Connections
Inspect 13.7.1:

- Verify accessibility and condition.

- If caps are missing, check for obstructions.

Hydraulic Placard
Inspect 5.2.6:
Spare Sprinklers
Inspect 5.2.1.4:
Information Signs
Inspect 5.2.8:
Pipe and Fittings
Inspect 5.2.2:
Backflow Preventers
Test 13.6.2:

Test backflow preventers and record results (where systems permits this type of testing). Repair leaking check valves.

2 Years
In addition to the annual requirements listed above, perform the following:
Control Valves
- Maintenance 13.3.4: Lubricate valves and stems.
Antifreeze Solution
Test 5.3.4:
Gauges
- Recalibrate or replace gauges.
5 Years
Obstruction Inspection
Inspection, 14.2
Sprinklers (Extra-High or greater temp heads)
Test 5.3.1.1.1.4

Alarm Valve and Appurtenances (Strainers, Filters, Orifices) Inspect 13.4.1.2: Clean and inspect internals of alarm valve and appurtenances.

Check Valves
Inspect 13.4.2.1: Internal inspection and operability
Sprinklers (Subject to Corrosion Environment)
Test 5.3.1.1.2:
10 Years
Sprinklers (Dry Heads)
Test 5.3.1.1.1.6
Gauges
- Recalibrate or replace gauges.
20 Years
Fast Response and High Temperature Sprinkler Heads
Test 5.3.1.1.1.3

- Test sample sprinklers to verify response characteristics.

50 years
Standard Sprinkler Heads
Test 5.3.1.1.1

- Replace or test a sample of sprinkler heads to verify response characteristics.

Following System Repair or Modification
Valve Supervisory Switch
Inspect: 13.3.2.1.2
Main Drain
- Conduct a main drain test to verify supply.
As Part of Building Inspections
Entire System
- Visually check pipe hangars, sprinkler heads for obstructions, piping for leaks, riser condition.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Exhibit 3 Fire Suppression Systems Maintenance Task Tables

Wet Pipe Sprinkler System RequirementsPage 1 of 21
DRY PIPE SPRINKLER SYSTEMS

Combined Recommendation for Dry Pipe Sprinkler Systems

Cycle
System Component
* Work
Annually
All Control Valves

(Lock, Unlocked, Supervised, or Unsupervised) Test 13.3.3.1:

- Operate valve through its full range and return to its normal position.

Waterflow Alarm Devices

Inspect 13.2.6:

- Operate to verify function and alarm at panel.

- Verify alarm test valve alignment and tamper switch (if applicable)

Supervisory Signal Devices
Inspect 5.2.5:

- Inspect to verify devices are free from physical damage.

Main Drain
Test 13.2.5, 13.2.5.1:

- Conduct Main Drain Test.

- Read and record static and residual pressure.

- Compare resulting test pressures with previous test pressures and verify results are within acceptable limits or identify corrective measures.

Dry Pipe Alarm Valve and Trim
Test 13.4.4.2.2:

- Visual inspection of alarm valve exterior, trim, gauges.

- Verify and record valve pressure

- Perform full flow trip test

Priming Water Level
Test 13.4.4.2.1:

- Check priming water level (before and after trip test).

Quick Opening Device
Test 13.4.4.2.4:
Fire Department Connections
Inspect 13.7.1:
Low Air Pressure Alarm, Dry Pipe Valve
Test 13.4.4.2.6:
Low Point/Auxiliary Drains
- Drain all low points to remove condensation prior to cold season.
Water Motor Gong
Inspect: 13.5.1.1:
Gauges
Inspect 5.2.4.2 - 5.2.4.4:
Pipe and Fittings
Inspect 5.2.2:
Spare Sprinklers
Inspect 5.2.1.4:
Hydraulic Placard
Inspect 5.2.6, Verify legibility
Information Signs
Inspect 5.2.8:
Dry Pipe Valve and Riser Enclosure
Inspect 13.4.3.1 / 13.4.3.2.14:

- Verify operability of the heating system at the beginning of the heating season.

- Verify operability of low temperature alarms and alarm at panel.

Backflow Preventers
Test 13.6.2:

Test backflow preventers and record results (where systems permits this type of testing). Repair leaking check valves.

2 Years
In addition to the annual requirements listed above, perform the following:
Dry Pipe Alarm Valve and Trim
Maintenance 13.4.3.3.2:

Inspect 13.4.3.1.7:

- Verify that manual actuators are operable.

- Inspect internal condition and clean valve seat before resetting.

Control Valves
Maintenance 13.3.4:

- Exercise valve through entire range.

- Lubricate valves and stems.

Gauges
- Recalibrate or replace gauges.
Air Maintenance Devices
- Inspect to verify proper operation.
5 Years
Obstruction Inspection
Inspection, 14.2
Gauges
Test 5.3.4, 13.2.7.2:

- Recalibrate or replace gauges.

Sprinklers (Extra-High or greater temp heads)
Test 5.3.1.1.1.4
Alarm Valve Appurtenances
Inspect 13.4.4.1.6:

- Inspect strainers, filters, restricting orifices

Check Valves
Inspect 13.4.2.1: Internal inspection and operability
Sprinklers (Subject to Corrosion Environment)
Test 5.3.1.1.2:
10 Years
Sprinklers (Dry Heads)
Test 5.3.1.1.1.6:
20 Years
Fast Response and High Temperature Sprinkler Heads
Test 5.3.1.1.1.3:

- Test sample sprinklers to verify response characteristics.

50 years
Standard Sprinkler Heads
Test 5.3.1.1.1:
Following System Repair or Modification
Valve Supervisory Switch
Inspect 13.3.2.1.2:
Main Drain
- Conduct a main drain test to verify supply.
As Part of Building Inspections
Entire System
- Visually check pipe hangars, sprinkler heads for obstructions, piping for leaks, riser condition.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Dry Pipe Sprinkler System RequirementsPage 5 of 21
DELUGE SPRINKLER SYSTEMS

Combined Recommendations for Deluge Sprinkler Systems

Cycle
System Component
*Work
Annually
All Control Valves

(Lock, Unlocked, Supervised, or Unsupervised) Test 13.3.3.1:

Waterflow Alarm Devices

Inspect 13.2.6, 13.5.1.1:

Supervisory Signal Devices
Inspect 5.2.5:
Main Drain
Test 13.2.5, 13.2.5.1:

- Conduct Main Drain Test.

- Read and record static and residual pressure.

- Compare resulting test pressures with previous test pressures and verify results are within acceptable limits or identify corrective measures.

Deluge Alarm Valve and Trim
Test 13.4.3.2.2:

- Visual inspection of alarm valve exterior, trim, gauges.

- Verify and record valve pressure.

Priming Water Level
Test 13.4.3.2.1:
Fire Department Connections
Inspect 13.7.1:
Low Air Pressure Alarm, Deluge Valve
Test 13.4.3.2.13:
Low Point/Auxiliary Drains
- Drain all low points to remove condensation prior to cold season.
Gauges
Inspect 5.2.4.2 - 5.2.4.4:
Pipe and Fittings
Inspect 5.2.2:
Spare Sprinklers
Inspect 5.2.1.4:
Hydraulic Placard
Inspect 5.2.6:
Information Signs
Inspect 5.2.8:
Deluge Valve and Riser Enclosure
Inspect 13.4.3.1 / 13.4.3.2.14:
Backflow Preventers
Test 13.6.2:

Test backflow preventers and record results (where systems permits this type of testing). Repair leaking check valves.

2 Years
In addition to the annual requirements listed above, perform the following:
Deluge Alarm Valve and Trim
- Inspect 13.4.3.1.7:

- Maintenance 13.4.3.3.2:

Control Valves
- Maintenance 13.3.4:
Air Maintenance Devices
- Inspect to verify proper operation.
5 Years
Obstruction Inspection
Inspection 14.2:
Gauges
Test 5.3.4, 13.2.7.2:
Sprinklers (Extra-High or greater temp heads)
Test 5.3.1.1.1.4:
Deluge Valve Appurtenances
Inspect 13.4.3.1.8:

- Clean and inspect internals of alarm valve and appurtenances.

Inspect 13.4.2.1: Internal inspection and operability
Check Valves
Pressure Reducing and Relief Valves (Sprinklers)
Test 13.5.1.2:
Sprinklers (Corrosion Resistant)
Test 5.3.1.1.2:
10 Years
Sprinklers (Dry Heads)
Test 5.3.1.1.1.6:
20 Years
Sprinklers (Fast Response)
Test 5.3.1.1.1.3:
50 years
Standard Sprinkler Heads
Test 5.3.1.1.1:
20 Years
Fast Response and High Temperature Sprinkler Heads
Test 5.3.1.1.1.3:

- Test sample sprinklers to verify response characteristics.

50 years
Standard Sprinkler Heads
Test 5.3.1.1.1:
Following System Repair or Modification
Valve Supervisory Switch
Inspect 13.3.2.1.2:
Main Drain
- Conduct a main drain test to verify supply.
As Part of Building Inspections
Entire System
- Visually check pipe hangars, sprinkler heads for obstructions, piping for leaks, riser condition, spare sprinkler heads. - Ensure detectors are unblocked, panels are secured and indicator lamps are functional, notification appliances are in place, and manual stations are in place and unobstructed.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Deluge Sprinkler System RequirementsPage 8 of 21
PREACTION SPRINKLER SYSTEMS

Combined Recommendations for PreAction Sprinkler Systems

Cycle
System Component
*Work
Annually
All Control Valves

(Lock, Unlocked, Supervised, or Unsupervised) Test 13.4.3.1:

Waterflow Alarm Devices

Inspect 13.2.6:

Supervisory Signal Devices
Inspect 5.2.5:
Main Drain
Test 13.2.5, 13.2.5.1:

- Conduct Main Drain Test.

- Read and record static and residual pressure.

- Compare resulting test pressures with previous test pressures and verify results are within acceptable limits or identify corrective measures.

PreAction Alarm Valve and Trim
Test 13.4.3.2.2:

- Visual inspection of alarm valve exterior, trim, gauges. - Verify and record valve pressure.

Priming Water Level
Test 13.4.3.2.1:
Fire Department Connections
Inspect 13.7.1:
Low Air Pressure Alarm, PreAction Valve
Test 13.4.3.2.13:
Low Point/Auxiliary Drains
- Drain all low points to remove condensation prior to cold season.
Water Motor Gong
Inspect 13.5.1.1:
Gauges
Inspect 5.2.4.2 - 5.2.4.4:
Pipe and Fittings
Inspect 5.2.2:
Spare Sprinklers
Inspect 5.2.1.4:
Hydraulic Placard
Inspect 5.2.6:
Information Signs
Inspect 5.2.8:
PreAction Valve and Riser Enclosure
Inspect 13.4.3.1 / 13.4.3.2.14:
Backflow Preventers
Test 13.6.2:

Test backflow preventers and record results (where systems permits this type of testing). Repair leaking check valves.

2 Years
In addition to the annual requirements listed above, perform the following:
PreAction Alarm Valve and Trim
- Inspect 13.4.3.1.7:

- Maintenance 13.4.3.3.2:

Control Valves
- Maintenance 13.3.4:
Air Maintenance Devices
- Inspect to verify proper operation.
5 Years
Obstruction Inspection
Inspection 14.2:
Gauges
Test 5.3.4, 13.2.7.2:
Sprinklers (Extra-High or greater temp heads)
Test 5.3.1.1.1.4:
PreAction Valve Appurtenances
Inspect 13.4.3.1.8:

- Clean and inspect internals of alarm valve and appurtenances.

Pressure Reducing and Relief Valves (Sprinklers)
Test 13.5.1.2:
Sprinklers (Corrosion Resistant)
Test 5.3.1.1.2:
10 Years
Sprinklers (Dry Heads)
Test 5.3.1.1.1.6:
20 Years
Sprinklers (Fast Response)
Test 5.3.1.1.1.3:
50 years
Standard Sprinkler Heads
Test 5.3.1.1.1:
20 Years
Fast Response and High Temperature Sprinkler Heads
Test 5.3.1.1.1.3:

- Test sample sprinklers to verify response characteristics.

50 years
Standard Sprinkler Heads
Test 5.3.1.1.1:

- Replace or test a sample of sprinkler heads to verify response characteristics.

Following System Repair or Modification
Valve Supervisory Switch
Inspect 13.3.2.1.2:
Main Drain
- Conduct a main drain test to verify supply.
As Part of Building Inspections
Entire System
- Visually check pipe hangars, sprinkler heads for obstructions, piping for leaks, riser condition, spare sprinkler heads. - Ensure detectors are unblocked, panels are secured and indicator lamps are functional, notification appliances are in place, and manual stations are in place and unobstructed.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Preaction Sprinkler System RequirementsPage 11 of 21
STANDPIPE SYSTEMS/HOSE SYSTEMS

Combined Recommendations for Standpipe/Hose Systems

Cycle
System Component
*Work
Annually
Piping
Inspect 6.2.1:

-Inspect for damage, leaks, missing caps, and obstructions.

Cabinet
Inspect, NFPA 1962
Hose
Inspect, NFPA 1962
Hose Nozzle
Inspect, NFPA 1962
Hose Storage Device
Test, NFPA 1962
Pressure Reducing and Relief Valves (Hose Connections)
Inspect, 13.5.2.1
Control Valves
-Operate to verify function and alarm at panel.

-Lubricate valves and stems.

Pressure Reducing and Relief Valves (Hose Racks)
Inspect, 13.5.3.1
Hose Connections
Maintenance, Table 6.1.2
5 Years
Hose
Test, NFPA 1962
Hydrostatic Test
Test 6.3.2:

- Hydrostatic test to ensure integrity (for dry standpipe systems only)

Control Valves
-Lubricate valves and stems.
Flow Test
Test, 6.3.1

- Conduct flow test to verify flow capacity and minimum discharge pressure.

Pressure Reducing and Relief Valves (Hose Connections) Test, 13.5.2.2

Pressure Reducing and Relief Valves (Hose Racks) Test, 13.5.3.2

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Standpipe System RequirementsPage 12 of 21
MAINS AND HYDRANTS

Combined Recommendations for Mains and Hydrants

Cycle
System Component
*Work
Annually
Hydrants
Maintenance, 7.4.2.2

- Keep hydrants free of snow and ice or other materials

Hydrants Flow Test
Test 7.3.2:

- Open fully and run water until water is clear or 1 minutes, whichever is longer.

- Verify drainage of the barrel after all operations and before cold weather.

Hydrants (Dry-Barrel)
Inspect 7.2.2.4:

- Take corrective action as necessary, see Table 7.2.2.5

Hydrants (Wet-Barrel)
Inspect 7.2.2.5:

- Take corrective action as necessary, see Table 7.2.2.5

2 Years
Hydrants
Maintenance 7.4.2:

- Lubricate hydrant.

- With caps on all outlets, operate not less than five full cycles to ensure operation and to distribute lubrication.

5 Years
Piping Flow Test
Test 7.3.1:

-Conduct flow test. Test should be coordinated with the 2-year tasks whenever possible. 20 percent of the site's hydrants should be tested each year so that every hydrant has had a flow test conducted and recorded at the end of the 5-year cycle.

- Document flow tests and provide results to the Fire Department.

After Flow Test
Strainers
- Inspect and clean after each flow test.
As Required
Hydrants
- Apply protective coatings to prevent corrosion.

- Identify by hydrant barrel color code the water distribution system to which the hydrant is connected;

1) Potable Water

2) Non-Potable Fire Protection Water

3) Non-Potable Reuse (Gray) Water. Locate or confirm on existing plans.

- Identify by hydrant bonnet color code the water flow available from the hydrant.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Mains and Hydrants RequirementsPage 13 of 21
FIRE PUMPS

Combined Recommendations for Fire Pumps

Cycle
System Component
*Work
Monthly
Pump House
Inspect 8.2.2 (1):

-Inspect for proper condition, ventilation, and heating

Control Valves and Isolation Valves
Inspect 8.2.2 (2):

-Verify proper valve position.

Pressure Gauges
Inspect 8.2.2 (2):

- Check reading and verify gauge operability.

Controllers
Inspect 8.2.2 (3):

- Verify that automatic controllers are in the AUTO setting.

- Inspect electronic connections.

- Operate manual and automatic stations.

Diesel Engine
Inspect 8.2.2 (4):

- Verify proper charge.

- Controller switch set to Auto

- Verify fuel level for Engine-Driven Pumps (minimum 2/3 full).

- Alarm pilot lights are off

- Crankcase oil level acceptable

- Cooling water level acceptable

- Water jacket heater is operating

Pump Electric Motor
Inspect 8.2.2 (3)

- Transfer switch normal pilot light is on

- Reverse phase alarm pilot light off

- Oil level in motor sight glass is acceptable

- Power to jockey pressure maintenance (jockey) pump is available and pump is functioning normally.

Pump with Electric Motor
Test 8.3.2.8 (1,2):

- Start and churn to verify operability. Electric Pumps shall operate for 10 minutes

- Verify operation of relief valves.

- Record time motor requires to obtain full speed.

- Record pumps starting pressure

- Check for unusual noise or vibration

- Check pump packing boxes, bearings, and pump casing for overheating

Diesel Engine
Test 8.3.2.8 (3):

- Operate engine-driven pump for 30 minutes

- Inspect exhaust system for leaks for Engine-Driven Pumps.

- Start engine-driven pump again using second battery set and churn to verify operability.

- Observe/record time for engine to crank to start

- Observe/record time for engine to reach running speed

- Observe/record engine oil pressure gauge, speed indicator, water and oil temperature

- Check heat exchanger to confirm cooling water flow.

2 Years
Control Valves
- Operate and lubricate valves. To ensure operability
Controllers
- Calibrate pressure switches.

- Exercise circuit breakers and switches to verify operability.

- Inspect fuses.

Pumps
- Check coupling alignment to ensure that the shaft is aligned.

- Check pump shaft end play.

- Lubricate bearings.

- Lubricate couplings.

- Lubricate right-angle drives.

Fuel
- Sample fuel to verify quality.
Relief Valves
- Calibrate valves.
Emergency Power Supply
- Test to verify availability and capacity for pump motor
5 Years
Pumps
- Conduct flow test to verify pump output. Test may be through a flow meter returning the water to a storage reservoir or through the test header. Recirculation of water to the suction piping is not permitted. In a multi-pump installation, each pump may be tested separately at not less than 100 percent capacity for 30 minutes.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Fire Pump System RequirementsPage 15 of 21
WATER SUPPLY TANKS

Combined Recommendations for Water Supply Tanks

Cycle
System Component
*Work

Weekly (during cold weather season)

Tank Heating System without electronic supervision
Inspect 9.2.3.2

- Verify water temperature.

- Verify operation of tank heaters.

Water Temperature, Low Temp Alarm not supervised
Inspect 9.2.4.3
Temperature Alarm, not connected to a supervised location
Inspect 9.2.4.3
Monthly
Heating System, Tank Water Temperature Low Temp Alarm
Inspect: 9.2.3.1, 9.2.4.2
Temperature Alarm, connected to a supervised location
Inspect, 9.2.4.2
Low Water Temperature Alarms
Test 9.3.3
High Temperature Limit Switches
Test 9.3.4
Annually
Control Valves with locks or electronic supervision
- Verify proper valve position
Tank Exterior
Inspect 9.2.5.1:

- Inspect exterior for condition, damage, corrosion, and accessibility.

Support Structure
Inspect 9.2.5.1:
Catwalks and Ladders
Inspect 9.2.5.1:
Surrounding Area
Inspect 9.2.5.2:
Tank Heating System with electronic supervision
- Verify operation of tank heater prior to cold weather season.

- Test temperature alarms to verify operation.

All Control Valves (Lock, Unlocked, Supervised, or Unsupervised) Test 13.3.3.1:

Hoops and Grillage
Inspect 9.2.5.4:
Painted / Coated Surfaces
Inspect 9.2.5.5:
Expansion Joints
Inspect 9.2.5.3:
2 Years
Control Valves including Drain Valves
Maintenance 13.3.4:

- Exercise valve through operating range.

- Lubricate valves.

Water Level Alarms and Indicators
- Test water level alarms to verify operation and set points.
Tank Vent
- Inspect and clean tank vents.
Tanks Without Cathodic Protection
- Conduct internal tank inspection to determine condition and amount of corrosion.
5 Years
Pressure Gauges
Test 9.3.6:

- Calibrate gauges.

Check Valves
- Inspect interior of valves.
Level Indicator Test
Test 9.3.1:

- Calibrate level indicator.

Interior, Tanks with Corrosion Protection
Inspect 9.2.6.1.2:

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Water tank will be added to service contract later. Requirements are included for information only.

Water Supply Tank / System RequirementsPage 17 of 21
DRY CHEMICAL SYSTEMS

Combined Recommendations for Dry Chemical Systems

Cycle
System Component
*Work
Semi-Annually
Piping and Nozzles
- Inspect piping, pipe hangers, and nozzles for obstructions and proper support.

- Conform nozzle covers are in place.

Storage Vessels
- Inspect agent container for condition.

- Verify storage pressure of propellant is within operating range.

Agent
- Verify quantity and quality of agent.
Actuators
- Inspect manual actuators for accessibility.

- Inspect detection devices for contamination and clean.

- Test actuation system without agent release. Coordinate with annual replacement of fixed temperature sensing elements.

- Verify that interfaces (gas shutoff, power shutoff) operate properly.

Fusible Metal Alloy Link Detectors
Replace 11.3.2:
Detectors (other than Metal Alloy)
Inspect 11.3.3.1:

- Ensure that detectors are unblocked

Detectors (other than Metal Alloy)
Test 11.3.3.1:
Control System
Ensure that panels are secured and indicator lamps are functional, notification appliances are in place, manual stations are in place and unobstructed.
Annually
Actuators
- Replace fixed temperature sensing elements (fusible links/metal alloy type).
Pressure Regulators
Test 11.3.1.6:
5 Years
Storage Vessels
Hydrostatic Test 11.5:

- Conduct hydrostatic test for pressure cylinders in accordance with OSHA and DOT standards.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Dry Chemical System RequirementsPage 18 of 21
WET CHEMICAL SYSTEMS

Combined Recommendations for Wet Chemical Systems

Cycle
System Component
*Work
Semi-Annually
Piping and Nozzles
- Inspect piping, pipe hangers, and nozzles for obstructions and proper support.

- Conform nozzle covers are in place.

Storage Vessels
- Inspect agent container for condition.

- Verify storage pressure of propellant is within operating range.

Agent
- Verify quantity and quality of agent.
Actuators
- Inspect manual actuators for accessibility.

- Inspect detection devices for contamination and clean.

- Test actuation system without agent release. Coordinate with annual replacement of fixed temperature sensing elements.

- Verify that interfaces (gas shutoff, power shutoff) operate properly.

Fusible Metal Alloy Link Detectors
Replace 11.3.2:
Detectors (other than Metal Alloy)
Inspect 11.3.3.1:

- Ensure that detectors are unblocked

Detectors (other than Metal Alloy)
Test 11.3.3.1:
Control System
Ensure that panels are secured and indicator lamps are functional, notification appliances are in place, manual stations are in place and unobstructed.
Annually
Actuators
- Replace fixed temperature sensing elements (fusible links/metal alloy type).
Pressure Regulators
Test 11.3.1.6:
5 Years
Storage Vessels
Hydrostatic Test 11.5:

- Conduct hydrostatic test for pressure cylinders in accordance with OSHA and DOT standards.

* Where paragraph sections are referenced, refer to NFPA 25 to locate these section numbers.

Wet Chemical System RequirementsPage 19 of 21
Nitrogen Generation Systems
Cycle
Work
Monthly
- Clean filter bowls.

- Calibrate oxygen analyzer per manufacturer's instructions.

Every 3 Months
- Change Particulate pre filter element.

- Operate safety valves.

- Operate manual valves.

- Check for leaks and repair as necessary.

Every 6 Months
- Change Coalescing pre filter element.
Annually
- Test all air pilot valves.

- Install valve repair kits on flow control valve and equalizer valves when necessary.

- Disassemble and inspect all air-operated valves; install repair kits if required.

- Check for air and product leaks.

- Change Absorber pre filter element.

- Check O2 analyzer sensor for proper operation as per manufacturer's instructions and order replacement.

Every 3 Years
- Install repair kits in all pneumatically operated valves.
Nitrogen Generation System RequirementsPage 20 of 21
Dry and PreAction System Air Compressors
Cycle
Work
Weekly
- Check Oil Level

- Drain condensate from receiver and traps

- Check for usual noise or vibration

- Clean air filters

- Clean all external parts of the compressor and motor

Quarterly
- Change oil

- Change filters

Monthly
- Manually test safety relief valve

- Inspect air system for leaks

- Inspect oil for contamination and change if necessary

- Check for belt tension and wear

- Check pulley set screws for tightness

- Tighten nuts and cap screws as required

Dry-Pipe and Preaction System Air Compressors Requirements Page 21 of 21