Amendment 0001- SP060424R0405.pdf

PDF 324 KB Posted

Attached to
Notice of Opportunity (NOO) for Energy Savings Performance Contract (ESPC) - Aviano Air Base, Italy
Solicitation number
SP060424R0405
Issued by

About this file

This amendment modifies the terms of a Notice of Opportunity for an Energy Savings Performance Contract at Aviano Air Base in Italy. The page limit for Factor 2 - Past Performance is increased from two to three single-sided pages to allow Energy Service Companies to describe up to six past performance references in their responses. Additionally, the selected Energy Service Company must provide designs signed and stamped by an Italian certified project engineer to comply with local construction norms at the base. Responses to the Notice of Opportunity are due no later than January 22, 2024 at 3:00pm EST and shall be submitted electronically to the Defense Logistics Agency Energy for an indefinite delivery, indefinite quantity task order award under the Department of Energy's Super Energy Savings Performance Contracts.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Previous Edition Unusable STANDARD FORM 30 (REV. 11-2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

J

PAGE OF PAGES

1 3

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

02 JAN 2024

4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE SP0604 7. ADMINISTERED BY (If other than Item 6) CODE SP0604

DEFENSE LOGISTICS AGENCY ENERGY

DLA Energy–FEA

8725 JOHN J. KINGMAN ROAD, STP 3950

FORT BELVOIR, VA 22060-6222

BUYER/SYMBOL: MaryLee Huerta /DLA Energy-FEAGB

PHONE: (202) 989-5971

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

UEI# Cage Code:

(X) 9A. AMENDMENT OF SOLICITATION NUMBER

Notice of Opportunity/SP0604-24-R-0401

9B. DATED (SEE ITEM 11)

06 DEC 2023

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

Choose an item

10B. DATED (SEE ITEM 13)

Click or tap to enter a date. CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

☒The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers ☐ is extended. ☒ is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required) See Section G

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A. ☐

☐ B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

☐ C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

☐ D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor ☐ is not ☒ is required to sign this document and return 01_ copies to the issuing office

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

AVIANO AIR BASE, AVIANO, ITALY NOTICE OF OPPORTUNITY-SP0604-24-R-0405

Amendment 001 addresses Request for Information (RFI) 0001 and 0002, and modifies Factor 2 – Past Performance in response to an RFI.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Christine Bond Jawish

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

SP0604-24-R-0405

Amendment 0001

This amendment is issued to all 20 ESCOs addressing a Request for Information (RFI) from industry regarding the subject Notice of Opportunity for Aviano, AB.

FIRST: The following RFIs were received from industry and are addressed as follows:

RFI 001: Recent Air Force ESPC NOOs have requested up to four (4) past projects and provided two (2) single-sided pages for Factor 2. This NOO requests up to six (6) projects while still providing two (2) single-sided pages. Would the government consider extending the page limit for Factor 2 to three (3) single-sided pages?

RFI 001 RESPONSE: Factor 2 – Past Performance page limitations is hereby modified as follows:

FROM:

Factor 2 – Past Performance: (Two (2) single-sided pages maximum)

The ESCO’s response to this factor shall include up to six (6) references illustrating the ESCO’s past performance as the prime contractor or prime subcontractor on any ESPC or Utility Energy Service Contracting (UESC) project. The ESCO shall provide a brief project description, the agency/owner point of contact (name, title, phone number, and email address), location of each project, contract number, date of task order or contract award, and actual or anticipated project construction completion date. The Government will use its discretion to determine the sources of past information used in the Past Performance evaluation. The information may be obtained from the Government’s knowledge of contractor performance, other government agencies or commercial entities, or past performance databases. It is not a requirement that the ESCO have past performance history in the execution of its recommended ECMs for this project. The DOE Fourth Generation ESPC IDIQ has already determined each ESCO responsible for the sound implementation of each of the technical categories.

TO:

Factor 2 – Past Performance: (Three (3) single-sided pages maximum)

The ESCO’s response to this factor shall include up to six (6) references illustrating the ESCO’s past performance as the prime contractor or prime subcontractor on any ESPC or Utility Energy Service Contracting (UESC) project. The ESCO shall provide a brief project description, the agency/owner point of contact (name, title, phone number, and email address), location of each project, contract number, date of task order or contract award, and actual or anticipated project construction completion date. The Government will use its discretion to determine the sources of past information used in the Past Performance evaluation. The information may be obtained from the Government’s knowledge of contractor performance, other government agencies or commercial entities, or past performance databases. It is not a requirement that the ESCO have past performance history in the execution of its recommended ECMs for this project. The DOE Fourth Generation ESPC IDIQ has already determined each ESCO responsible for the sound implementation of each of the technical categories.

SP0604-24-R-0405

Amendment 0001

RFI 0002: Will the government require an Italian certified project engineer (or equivalent) to review and stamp drawings for the Aviano Air Base ESPC project?

RFI 0002 RESPONSE: The selected ESCO must provide designs signed and stamped by an Italian certified project engineer for the Aviano Air Base ESPC project. Aviano Air Base is an Italian base and all construction (civil, electrical, mechanical, structural, etc.) projects must comply to Italian norms.

SECOND: All other terms and conditions remain as previously stated.

END OF AMENDMENT

END OF AMENDMENT