About this file
This is a Statement of Work (SOW) for crane rental services supporting a shelter replacement project at an Airport Traffic Control Tower (ATCT) facility.
The vendor shall provide complete crane rental with a licensed operator to lift tools, materials, specialized equipment, and replacement glass units from ground level to the ATCT cab. The work is scheduled for one day with 8 hours of weekday service plus 2 hours of overtime. The crane must be capable of lifting/lowering a shelter with a maximum weight of X,XXX pounds and meet specific technical requirements including: trailer elevation at +/- XX' above ground level (AGL), top of shelter foundation elevation at +/- XX' AGL, crane tip height not to exceed XXX' AGL, lift radius of +/- XXX' (360°), and crane load not exceeding 65% of capacity. The vendor is responsible for all mobilization/demobilization, fuel, tolls, and permits. Documentation required includes CAD-generated plan and elevation view drawings, detailed lift plan data with crane specifications (make, model, tonnage, load chart data, boom angles, counterweights, and percent load to chart load), and time estimates for crane assembly and disassembly. The vendor must provide proof of the licensed operator's current certifications and crane inspection reports prior to operations, install a white and orange checkered flag on the boom in compliance with airport regulations, furnish and install appropriate crane mats and blocking, and provide spreader bars to prevent slings from contacting the shelter. The vendor assumes liability for any damage to pavements, blacktop, concrete, curbs, sidewalks, and landscaping during crane operations. The FAA Team Lead Technician will inspect and accept the completed work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_6973GH-26-R-00122_Amd_0002.pdf | ||
| 6973GH-26-R-00122 P0001.pdf | ||
| RFI.docx | DOCX document | |
| 6973GH-26-R-00122.pdf | ||
| SMR4 Crane SOW Sample.pdf | ||
| Cab Glass Crane SOW Sample.pdf | ||
| Offeror Organizational Experience Questionnaire.pdf | ||
| Wage Determinationp1.pdf | ||
| Wage Determinationp2.pdf | ||
| Crane Locations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6/24/2026
P a g e 1 | 2
Statement of Work (SOW)
CRANE RENTAL
Crane Rental for [LOCid FACid] Shelter Replacement Project
1. Introduction and Overview Service Order XXXXX is for the replacement of shelter on for [LOCid FACid]the Airport Traffic Control Tower (ATCT) utilizing a temporary mobile crane with operator services in support of these efforts.
2. Purpose Provide complete crane rental with operator service to support Cab Glass Replacement Project.
3. Scope of Work Vendor shall provide complete crane rental service with a licensed operator as required to lift tools, materials, specialized equipment, and replacement glass units from ground level to the ATCT Cab.
4. Period of Performance Month Day through Month Day for 1 day.
8Hrs for 1 Weekdays + 2Hrs Overtime
5. Deliverables Vendor shall provide a mobile crane capable of lifting/lowering a shelter (L x H x W at XXXXXLBS), in accordance with the requirements specified in Section 8 below. Vendor may perform a site visit and shall provide a lift plan in accordance with the requirements specified in Section 8 below.
6. Location of Work The crane service shall take place at:
Address
7. Inspection, Compliance and Acceptance The FAA Team Lead Technician will ensure all work has been completed prior to releasing the crane service.
8. Additional Notes & Requirements As-built drawings and other information provided to the vendor shall be considered part of this SOW.
Crane vendor shall provide a mobile crane capable of lifting/lowering shelter (L x H x W at XXXXXLBS) in accordance with the following:
a) Trailer elevation +/- XX’ above ground level (AGL)
b) Top of shelter foundation elevation +/- XX’ AGL
c) Not to Exceed Height (NEH) Crane Tip Height Not to Exceed XXX’ AGL
d) Lift weight of shelter is X,XXX pounds max.
e) Lift radius +/- XXX’ (360°) (crane vendor to determine based on Lift Survey & Lift Plan)
f) Crane load to capacity percent shall not exceed 65%
Crane vendor shall provide the following documentation:
(a) Crane Lift Plan, drawings, and information:
1) CAD-generated drawings of site-specific “plan view” of Tower and crane location including boom/jib length, radius, boom swing path, tail swing radius, outriggers, mats / blocking, and reference dimensions of crane location to tower.
2) CAD-generated drawings of site-specific “elevation view” of Tower and crane location including tip height, boom angle, radius, and reference dimensions of crane location to tower.
3) Lift Plan Data of proposed / recommended crane location including crane make, model number, tonnage, load chart data, radius, main boom length, boom angle, jib length, jib angle, tip height, tip to ground distance overall, counterweights, ball weight, rigging weight, lift load, total load, chart load and percent load to chart load.
6/24/2026
P a g e 2 | 2
4) An estimate of time required to mobilize and assemble the crane, and an estimate of time required to disassemble and de-mobilize the crane.
Crane vendor shall:
a) Be responsible for all crane mobilization / demobilization, fuel, tolls and permits required.
b) Provide to FAA prior to the start of operations documentation showing the licensed operator’s certifications and proof of current crane inspection reports.
c) Furnish and install a white and orange checkered flag at the end of the crane boom and be in full compliance with airport regulations prior to any lifting operations.
d) Furnish and install crane mats and blocking as required.
e) Be responsible for damage caused during crane mobilization and demobilization to pavements, blacktop, concrete, curbs, sidewalks, and landscaping.
f) Furnish and provide spreader bars appropriate for the shelter size listed above, to keep slings from contacting the shelter sides
Point of Contact (POC) Information:
For technical questions:
Shelter Lead Technician POC NAME NUMBER, or
For scheduling a lift survey / site survey visit, contact the local site personnel:
Address
Below is a typical shelter: INSERT PIC
File details come from the government source that posted it. Updated .