This Statement of Work (SOW) details a rubber removal and airfield markings project (FNWZ 25-0167) for a military airfield. The project requires two-phase rubber removal at runways 16/34 and 164/344, with weekend-only work during Phase 1 and a subsequent Phase 2 to be completed 6 months later. The contractor must also paint airfield markings according to attached contract drawings and specifications, with work spanning 220 calendar days.

Key requirements include coordinating with the Contracting Officer, Airfield Management, and Civil Engineering at least 45 days prior to approved work weekends. The project is located in a controlled airfield area, necessitating tower contact during controlled movement work, radio request from Airfield Management, and escort coordination. The Civil Engineering Point of Contact is Davis Matschek (325-696-5620), and the work is subject to ongoing airfield operations with limited access and strict coordination requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Rubber Removal and Airfield Markings, newest first.
File Type Posted
Solicitation Amendment FA466126Q00090002 SF 30.pdf PDF
Questions and Answers.pdf PDF
Solicitation Amendment - FA466126Q00090002.pdf PDF
Solicitation Amendment - FA466126Q00090001.pdf PDF
Questions and Answers.pdf PDF
Drawings.pdf PDF
Solicitation - FA466126Q0009.pdf PDF
Technical Factors.pdf PDF
Wage Determination.pdf PDF
Specifications_.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR OFFICIAL USE ONLY

Statement of Work November 25, 2025

Project: _FNWZ 25-0167 Rubber Removal & Airfield Markings

Civil Engineering Point of Contact (Name/phone #): Davis Matschek 325-696-5620__

Scope of Work: 1- Perform rubber removal as indicated in attached drawings C1 through C8 and per specifications at runways 16/34 and 164/344 (CLIN 0001). 2- Paint airfield markings as indicated in the attached contract drawings C1 through C8 and specifications (CLINs 0002- 0006).

Phasing Requirements: This contract shall be performed in several phases on coordination with the Contracting Officer (CO), Airfield Management (AM), and Civil Engineering (CE). Access to all work areas is limited by ongoing airfield operations. Contractor shall coordinate work at each location with the Airfield Manager. Rubber removal shall be completed in two phases:

Phase 1: Perform rubber removal at runways 16/34 and 164/344 (Tye LZ); weekend work only Phase 2: Perform rubber removal at runway 16/34, must be completed 6-months after the completion of Phase 1.

Special Requirements/Security/Submittals: Contractor shall coordinate with the Contracting Officer and Airfield Manager, at least 45 days prior, for approved weekends when rubber removal and markings will be allowed.

Project is in a General/Controlled Area: Work under this contract is located on the airfield.

Access to it is subject to operations requirements and only after it has been coordinated with the CO in conjunction with the AM and 7 CES. Airfield Markings - Contact with the Tower is required during work in controlled movements areas. Contractor to request radio from Airfield Management. Escorts are required within the Controlled Area (Airfield). Contractor to submit schedule to 7 CONs for escort coordination.

Performance Time/Desired Project Completion Date: 220 calendar days