SOW - Bangor Imaging and Dental Xray Prep.pdf
PDF 170 KB Posted
- Solicitation number
- 36C24124Q0806
About this file
This document is a Contractor Scope of Work (SOW) for a construction project to prepare an imaging suite and dental x-ray room at the Bangor Community-Based Outpatient Clinic (CBOC) of the VA Maine Healthcare System.
The SOW requires the contractor to provide all labor, materials, and equipment necessary to install radiation shielding for new dental imaging equipment in Room 1404, as well as perform electrical modifications to Room 1709 in preparation for new x-ray equipment. Key tasks include demolishing existing finishes and walls, installing lead-lined drywall, replacing a window and door, and coordinating work with the government-provided x-ray equipment installation. The contractor must comply with applicable codes and regulations, provide submittals and warranties, and complete the work within 180 calendar days of the Notice to Proceed. The work is restricted to normal business hours and requires coordination with the Contracting Officer's Representative.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bangor Dental XRay pre-bid sign in sheet.pdf | ||
| 36C24124Q0806_2.docx | DOCX document | |
| Bangor 3D Shielding Plan.pdf | ||
| Bangor - Elec.zip | ZIP file | |
| Bangor - Struct.pdf | ||
| Drawing.pdf | ||
| Bangor - Arch.pdf | ||
| 36C24124Q0806.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR SCOPE OF WORK
VA MAINE HEALTHCARE SYSTEM – BANGOR CBOC
35 State Hospital Dr. Bangor, ME 04401
Project Title: Bangor – Imaging Suite and Dental Xray Room Prep
1.0 GENERAL:
Provide construction services to include all labor, transportation, materials, tools, equipment and permits necessary to install radiation shielding in preparation for the new dental imaging equipment to be installed Rm. 1404 and perform electrical modifications to Rm. 1709 which are associated with the installation of new x-ray equipment (to be installed by others).
2.0 PROJECT SCOPE OF WORK:
Dental Rm 1404:
2.1 Remove all finishes from walls in Rm. 1404. Drywall- must be demolished to the metal framing from floor level to at least 7 ft. above finished floor. Door 1401.1 and its frame must be demolished as it is not lead lined. There is a window located within the room that must be demolished as well.
2.2 Install 1/16” lead backed drywall on all interior walls. Drywall and joints must be installed according to manufacturer specifications. Drywall must be installed from floor level to at least 7 ft. above finished floor. If the existing drywall remains above the 7 ft. mark, then the new drywall must butt against the existing, and joints must be installed to manufacturer specifications.
2.3 Install a new window of the same size that contains 1/16” lead glass equivalent.
2.4 Door 1401.1 must be replaced with a door of the same size and finish and must contain
1/32” lead. Door must have an astragal that is a minimum of 16 ga. thick.
2.5 Door 1401.1 frame must be replaced with a door frame which contains 1/16” lead.
2.6 All finished must match the existing to what was originally installed prior to demolition.
Imaging Suite Rm 1709:
2.7 Contractor shall refer to SOW Attachment 1; Pages SD4, SD5, EN, EL, E1, E2, ED1, ED2. Please note SOW Attachment 1 references both work to be accomplished by this contract as well as work to be done by others. Contractor is responsible for all items that refer to customer and/or contractor.
2.8 Contractor will coordinate with project COR on mounting locations for devices not shown on drawings.
3.0 SUBMITTALS
The Contractor shall submit to the VAMC Togus, ME the following:
• Certification from the Contractor/Installer that the system specified meets all identified code and insurance requirements as required by the Government.
• Material Safety Data Sheets (MSDS)
• Cut sheets.
• Shop drawings for approval as requested by the COR.
• Operation and Maintenance Manuals for new equipment
• As-built drawings
• Release of claims at completion of project.
4.0 CODE REQUIREMENTS
Work performed shall meet all applicable code requirements.
5.0 WARRANTIES
All work and equipment supplied shall be warranted for a minimum period of one year from VA acceptance, or the manufacturer’s standard term, whichever is greater.
6.0 PROPOSED SCHEDULE:
Work shall commence upon receipt of a Notice to Proceed from the government and shall be completed within 180 calendar days after receipt of Notice to Proceed.
7.0 WORK LOCATION AND RESTRICTIONS:
The work site location is at 35 State Hospital Dr. Bangor, ME 04401.
All work shall be coordinated with the COR. Notification of work commencing shall be sent to the COR in writing no earlier than 7 calendar days prior. All work shall be done between the hours of 7am and 4:30pm Monday through Friday, holidays excepted, unless other times are arranged in advance and approved in writing by the Project COR. When the contractor’s work interferes with facility functions, such as when work produces excessive noise, odors, dust, utility service interruptions, or other interferences with normal operations that cannot be contained within the area of work, the contractor shall schedule said work at other than normal hours and as directed by the Project COR.
8.0 STORAGE OF EQUIPMENT & MATERIALS:
The contractor shall arrange with the Project Manager for allocation of required workspace and for the storage of equipment and material to be used for this project. Storage space is very limited. Additionally, no space will be made available for the placement of a contractor trailer for this project. The Contractor should schedule delivery of materials to limit the amount of storage space and time.
9.0 DEBRIS REMOVAL
Contractor is required to remove waste materials and debris daily from the campus. All waste material and debris shall be removed off the site by the contractor and shall be disposed of in accordance with applicable State and Federal regulations.
10.0 SITE UTILITIES:
The Contractor/Installer should note this scope of work does not detail all existing structures, utilities, or components that may potentially interfere with the contract work required. The contractor shall note any obstruction, utility, or condition that may hinder or interfere with the execution of this contract and the contractor shall make provisions in their contract price to resolve such interferences and other conditions that may hinder the proper completion of the work. All proposed utility relocations, reallocations, and shutdowns shall be approved by the Project Manager prior to commencing such work. The contractor shall verify all existing utility installations and take appropriate action prior to working around any potential utility installation.
In the event a shutdown, restriction, or interruption of any utility services is required, a written request must be submitted (at least 2 weeks in advance) and approved by the VA Project Manager. All utility shutdowns must be reviewed and approved by the VA.
11.0 PROJECT SAFETY:
Contractor shall comply with 1926 OSHA Construction Industry Regulations and Standards
29CFR.
12.0 INTERIM LIFE SAFETY PROTECTION MEASURES:
Contractor shall participate with the VA in the preparation of an interim life safety measures that will be implemented during construction of this project. At a minimum, contractor shall comply with the following requirements of an interim life safety measures and fire protection plan:
• Ensure exits provide free and unobstructed egress for all building occupants. If required by contractor’s operations establish and mark alternate means of egress for all building occupants.
• Contractor shall always maintain escape facilities from the work area for construction workers. Means of egress in construction areas will be inspected daily.
• Ensure free and unobstructed access to all areas of the project site for emergency services and for emergency forces.
• Ensure that means of egress and existing fire alarm, detection, and suppression systems are not impaired by contractor’s operations.
• When required, a fire watch shall be by a qualified person provided by the contractor who shall maintain constant observation of the affected area and have no other duties. The person providing the fire watch shall be trained in fire prevention and in the use of fire extinguishers, occupant hose lines, occupant fire protection system, in sounding the building fire alarm and in notifying the local fire department, and in understanding the particular fire safety situation for the project.
• Provide written procedures and guidelines for construction personnel and post in the immediate areas of construction detailing what to do and who to call in the event of fire or emergency.
• Maintain the construction area to minimize the potential for fire or safety hazards resulting from storage of construction material, construction waste and debris during construction operations.
• All temporary construction shall be built of noncombustible/fire retardant materials and shall be smoke tight.
13.0 MATERIAL & WORKMANSHIP QUALITY:
All materials and workmanship shall comply with all codes, standards, and recommendations of all Authorities Having Jurisdiction (AHJ). All work shall be done in a first-class manner according to the best trade practices and to the satisfaction of the Project Manager.
14.0 SOW ATTACHMENTS
• SOW Attachment 1 – Augusta C90 VS N-EAS230245 Finals.pdf
| CONTRACTOR SCOPE OF WORK |
| Work shall commence upon receipt of a Notice to Proceed from the government and shall be completed within 180 calendar days after receipt of Notice to Proceed. |
File details come from the government source that posted it. Updated .