SOW Attachemnt 01 - Section 013200 Construction Documentation - AutoDesk.docx
DOCX document 20 KB Posted
- Solicitation number
- 36C24225B0007
About this file
This is a Statement of Work section that outlines requirements for using Autodesk Build Construction management platform (ACC) for VISN 2 VA facilities construction projects. The document specifies that contractors and A/E design firms must use this cloud-based platform for all Non-Recurring Maintenance, Minor Program projects, Feasibility Studies, and Commissioning contracts at no cost to the contractor.
Key requirements include requesting ACC platform access within 14 days of contract award, completing required training within 12 calendar days through ProductivityNOW eLearning, and submitting completion certificates within 2 business days. All official project correspondence must be conducted through ACC, including RFIs, submittals, schedules, shutdown requests, tasks, reports, testing, safety inspections, photos, and site surveys. Staff changes must be reported within 2 business days, and contractors cannot begin work without meeting all ACC platform requirements. The related contract opportunity is for Commissioning services for SPS Construction at the Buffalo VA Medical Center, set aside for SDVOSBs under NAICS 541690, with an estimated value between $5-10 million and anticipated award in January 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SPS Mod Construction - RFIs -4.docx | DOCX document | |
| 3rdFloor-Access Hatches-RV 2022-07-12.pdf | ||
| Copy of Buffalo VAMC Standard Finishes 1.pdf | ||
| S02 36C24225B0007 0004 - SPS CONS SOLICITATION.docx | DOCX document | |
| 3. STERIS Mobile SPD Deployment Guide 8-1-2023.pdf | ||
| S02 36C24225B0007 0003 - SPS CONS SOLICITATION.docx | DOCX document | |
| zipped RFI dwg.zip | ZIP file | |
| SPS Mod Construction - RFIs rev1.docx | DOCX document | |
| S02 36C24225B0007 0002 - SPS CONS SOLICITATION.docx | DOCX document | |
| RFI section 31 20 11.docx | DOCX document | |
| VAAR 852.219-77 SEPT 2021 Deviation - LIMITATIONS OF SUBCONTRACTING.pdf | ||
| RFI SECT 22 05 33.docx | DOCX document | |
| 2. STERIS Mobile SPD Facility Requirements 1-8-2024.pdf | ||
| S02 36C24225B0007 0001 - SPS CONS SOLICITATION.docx | DOCX document | |
| SIte Visit Sign in Sheet.pdf | ||
| VA TRAILER DRAWINGS -REV-3.pdf | ||
| 36C24225B0007_1.docx | DOCX document | |
| SPEC BINDER.pdf | ||
| P07 WAGE DETERMINATION.pdf | ||
| FULL DWG SET for 528-17-s38 SPS Modifications.pdf |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
09-01-23
SECTION 01 32 00
CONSTRUCTION DOCUMENTATION
PART 1- GENERAL
1.1 DESCRIPTION:
A. Construction contractors and A/E design firms, selected by award to perform work at VISN 2 VA facilities, are required to utilize VISN 2 Autodesk Build Construction management platform, also called Autodesk Construction Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative (COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.
1.2 REQUIREMENTS:
| A. | Contractor shall accomplish and complete the following tasks upon award of contract: |
| 1. | Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award. |
| 2. | Only staff that shall utilize the platform to be granted access. Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc. |
3. The access request shall be in writing and include a list of staff. The list shall include the following information:
| • | Full Name |
| • | Company Name |
| • | Email Address |
| • | Role/Position on the project (i.e., Project manager, site super) |
| 4. | Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days. |
| 5. | Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 Business days. |
| B. | Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period. |
| C. | Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above. |
| D. | The contractor shall only use the ACC platform for all contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys. |
| E. | Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform. |
| F. | Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training. |
E N D 01 32 00 - 1