FULL DWG SET for 528-17-s38 SPS Modifications.pdf

PDF 33 MB Posted

Attached to
Z1DA--SPS Modification - Construction WNY HEALTHCARE SYSTEMS - BUFFALO VAMC
Solicitation number
36C24225B0007
Issued by

About this file

This is a drawing set related to SPS (Sterile Processing Services) modifications at the Buffalo VA Medical Center. The drawings are referenced in a solicitation for commissioning services (36C24225Q0184) to be released around December 20, 2024, by the Western New York Healthcare Systems.

The solicitation is a 100% SDVOSB set-aside under NAICS 541690 (Other Scientific and Technical Consulting Services) with a size standard of $19M. The project, valued between $5-10 million, requires a Commissioning Agent to verify installation and performance of systems, develop commissioning specifications and plans, and produce a commissioning report. The work focuses on upgrading HVAC capacity and equipment that has exceeded its service life in the Sterile Processing Department. Award is anticipated around January 2025. Quotes will be accepted electronically only, and interested vendors should contact Contracting Officer Idalia Algarin at the VA's Cheektowaga, NY office.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOLF

COURSE

BAILEY AVE

SPS

TEMP

TRAILER

STERILE PROCESSING

EQUIPMENT REPLACEMENTV.A. WESTERN NEW YORK

BUFFALO, NEW YORK 14215

9A

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

ISSUED FOR CONSTRUCTION

DRAWING INDEX:

GI-001 COVER SHEET

GI-002 GENERAL NOTES, SYMBOLS, AND ABBREVIATIONS

GI-003 PHASING SEQUENCE

GI-004 ICRA AND LIFE SAFETY PLAN

GI-005 ICRA AND LIFE SAFETY PLAN

1-HA-103 ASBESTOS ABATEMENT 3rd FLOOR PLAN 1-HA-104 ASBESTOS ABATEMENT 4th FLOOR PLAN

1-AD-103 3rd FLOOR ARCHITECTURAL DEMOLITION PLAN 1-AD-104 3rd FLOOR CEILING DEMOLITION PLAN 1-AD-105 4th FLOOR ARCHITECTURAL DEMOLITION PLAN 1-AI-103 3rd FLOOR ARCHITECTURAL FLOOR PLAN 1-AI-104 3rd FLOOR SPS EQUIPMENT LAYOUT PLAN 1-AI-105 4th FLOOR ARCHITECTURAL PLANS 1-AI-203 3rd FLOOR REFLECTED CEILING PLAN

AI-001 INTERIOR ELEVATIONS AND SECTIONS

AI-002 DOOR & ROOM FINISH SCHEDULES AND DETAILS

AI-003 ARCHITECTURAL DETAILS

SS-001 GENERAL NOTES

1-SS-103 3rd FLOOR FRAMING PLAN 1-SS-104 4th FLOOR FRAMING PLAN

SS-002 SECTIONS AND DETAILS

1-FD-103 3rd FLOOR FIRE PROTECTION DEMOLITION PLAN 1-FX-103 3rd FLOOR FIRE PROTECTION PLAN

PP-001 PLUMBING LEGEND AND SCHEDULES

1-PD-102 2nd FLOOR PLUMBING DEMOLITION PLAN 1-PD-103 3rd FLOOR PLUMBING DEMOLITION PLAN 1-PL-102 2nd FLOOR PLUMBING PLAN 1-PL-103 3rd FLOOR PLUMBING PLAN

P-501 PLUMBING DETAILS

P-502 PLUMBING DETAILS

P-503 PLUMBING DETAILS

M-001 MECHANICAL LEGEND

1-MD-103 3rd AND 4th FLOOR MECHANICAL DUCTWORK DEMOLITION PLAN

1-MD-200 SUB-BASEMENT MECHANICAL PIPING DEMOLITION PLAN

1-MD-203 3rd FLOOR MECHANICAL PIPING DEMOLITION PLAN 1-MH-103 3rd AND 4th FLOOR MECHANICAL DUCTWORK PLAN

1-MH-200 SUB-BASEMENT MECHANICAL PIPING PLAN

1-MH-203 3rd AND 4th FLOOR MECHANICAL PIPING PLAN 1-MH-403 3rd AND 4th FLOOR ENLARGED MECHANICAL ROOM PLANS 1-MH-412 12th FLOOR MECHANICAL PLAN

1-MI-401 SPS AIR DISTRIBUTION AND PIPING SCHEMATIC DIAGRAMS

1-MI-402 SPS POINTS LISTS AND SEQUENCE OF OPERATIONS

M-501 MECHANICAL DETAILS

M-502 MECHANICAL DETAILS

M-503 MECHANICAL DETAILS

M-701 MECHANICAL SCHEDULES

E-001 ELECTRICAL SYMBOLS & ABBREVIATIONS

1-ED-103 ELECTRICAL DEMOLITION PLANS

1-EP-103 3rd FLOOR PLAN - POWER & SYSTEMS 1-EP-104 4th & 12th FLOOR PLAN - POWER & SYSTEMS 1-EL-203 3rd FLOOR PLAN - LIGHTING

E-501 ELECTRICAL DETAILS

E-601 ELECTRICAL SCHEDULES

COVER SHEET

GI-001

EHALLJ 1

BUILDING SCHEDULE

No. BUILDING

1 MAIN HOSPITAL BLDG.

2 OFFICE OF DISTRICT COUNCIL

3 DAYCARE & CONTRACTING OFFICE

4 PERSONNEL GARAGE

5 OFFICES

6 GARAGE & BOILER HOUSE

7 SNOW REMOVAL EQUIP. STORAGE

8 FLAG POLE

9 5 KV SWITCH GEAR STA.

10 23 KV TRANSFORMERS

11 GENERATOR / SWITCH GEAR

GENERATOR & TANK

13 OXYGEN TANK - EAST

17 COOLING TOWER - NORTH

18 1000 KVA SUB STATION

20 MEDICAL RESEARCH BLDG

21 EMEG. GENERATOR BLDG.

25 BUS SHELTER

26 SAFETY STORAGE BLDG #1

27 SAFETY STORAGE BLDG #2

28 HVAC CHILLER BLDG.

24 SOUTH WATER METER BLDG

23 F.P. BACKFLOW PREVENT BLDG

22 NORTH WATER METER BLDG.

9A 23 KV SUBSTATION/5 KV SWITCH GEAR

16 NOT USED

19 NOT USED

29 PARKING GARAGE

COOLING TOWERS - SOUTH

1. REFER TO ROOM FINISH SCHEDULE, REFLECTED CEILING PLANS, AND INTERIOR ELEVATION

SHEETS FOR INFORMATION ON NEW FLOOR, WALL AND CEILING FINISHES.

2. SEE PLUMBING DRAWINGS FOR NEW PLUMBING FIXTURE SCHEDULE.

3. IN THE EVENT THAT THE CONTRACTOR DISCOVERS A DISCREPANCY ON THE CONSTRUCTION

PLANS, HE SHALL CONTACT THE COR OR PM IMMEDIATELY FOR CLARIFICATION, PRIOR TO

PROCEEDING WITH CONSTRUCTION OF THE PORTION IN QUESTION.

4. WHERE INCIDENTAL WORK IS REQUIRED TO ACCOMPLISH WORK SHOWN ON DRAWINGS, THIS

WORK IS IMPLIED AND SHALL BE INCLUDED AS PART OF THE BID.

5. PRIOR TO ANY WORK COMMENCING IN AN AREA, THE CONTRACTOR SHALL NOTIFY THE CO OF

HIS INTENTION TO WORK IN THE AREA AND SHALL SCHEDULE A WALKTHROUGH WITH THE CO

TO DETERMINE EXISTING CONDITIONS. AFTER THE WORK, THE EXISTING WORK AREAS SHALL

BE RETURNED TO THEIR ORIGINAL STATE BEFORE FINAL APPROVAL SHALL BE GIVEN.

6. AFTER THE COMPLETION OF CONSTRUCTION, THE CONTRACTOR SHALL COMPLETELY CLEAN

ALL SURFACES OF CONSTRUCTION DEBRIS. SURFACES SHALL BE WIPED CLEAN OF DUST,

INCLUDING FIXTURES, WINDOW SILLS, DOOR FRAMES, ETC.. ANY TOILETS OR SINKS WITHIN

THE CONSTRUCTION AREA SHALL BE COMPLETELY CLEANED AFTER THE CONSTRUCTION HAS

BEEN COMPLETED USING NATURAL CLEANSER.

7. THE CONTRACTOR SHALL PROVIDE A MINIMUM OF ONE (1) HARD COPY AND ONE (1) CD OF

OPERATING AND SERVICE MANUALS FOR EACH MECHANICAL, ELECTRICAL, ELECTRONIC,

HVAC OR OTHER EQUIPMENT INSTALLED AS PART OF THE PROJECT.

8. THE CONTRACTOR SHALL RECEIVE ALL DELIVERIES OF MATERIALS, EQUIPMENT, TOOLS, OR

OTHER GOODS OFF OF STATION AND BRING THEM TO THE JOB SITE. THE BUFFALO VA SHALL

NOT ACCEPT DELIVERIES FOR PROJECT PURPOSES.

9. THE KNOWN CONSTRUCTION AND SIMILAR FEATURES LOCATED ON OR ADJACENT TO THE

WORK AREA ARE SHOWN ON THE PLANS. THIS INFORMATION HAS BEEN COMPILED FROM

SEVERAL SOURCES AND IS SHOWN FOR THE CONVENIENCE OF THE CONTRACTOR. THIS

INFORMATION IS NOT GUARANTEED TO BE COMPLETE OR WITHOUT ERRORS. THE SIZE AND

LOCATION OF CONSTRUCTION MAY BE INACCURATE, OTHER OBSTRUCTIONS MAY BE

ENCOUNTERED.

10. THESE PLANS HAVE BEEN PREPARED USING THE MOST ACCURATE INFORMATION AND DATA

AVAILABLE AT THE TIME OF PREPARATION. FIELD CONDITIONS MAY BE ENCOUNTERED

DURING CONSTRUCTION WHICH VARIES FROM THOSE DEPICTED HEREIN. AS SUCH, THESE

PLANS SHOULD BE USED AS A CONSTRUCTION CONTROL REFERENCE, NOT A PRECISE

CONSTRUCTION DOCUMENT. MODIFICATIONS TO THE IMPROVEMENTS AS SHOWN MAY BE

REQUIRED BASED ON FIELD CONDITIONS AT THE TIME OF CONSTRUCTION.

11. WATER, SANITARY SEWER, STORM SEWER, ELECTRIC, COMMUNICATION, STEAM, AND GAS

LINES DAMAGED DURING CONSTRUCTION SHALL BE IMMEDIATELY REPAIRED BY THE

CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER. THE CONTRACTOR SHALL NOT BE

PERMITTED TO CONTINUE UNTIL DAMAGED PIPE IS REPAIRED.

12. RESTORE ALL DISTURBED AREAS TO EQUAL OR BETTER THAN PRE-PROJECT CONDITION.

13. IT SHALL BE THE CONTRACTORS RESPONSIBILITY TO PROTECT EXISTING FEATURES.

DAMAGED FEATURES SHALL BE REPAIRED BY THE CONTRACTOR AT NO ADDITIONAL COST TO

THE OWNER.

14. ANY CONTRACTOR PERFORMING WORK IN A CONFINED SPACE (I.E. PIPE CHASES), MUST

CERTIFY THAT THEY HAVE THEIR OWN CONFINED SPACE ENTRY PROGRAM THAT MEETS OR

EXCEEDS OSHA'S REGULATIONS. CERTIFICATION MUST BE NOTARIZED BY A PUBLIC NOTARY.

15. THE CONTRACTOR AND SUBCONTRACTORS SHALL BE SOLELY RESPONSIBLE FOR COMPLYING

WITH ALL FEDERAL, STATE, AND LOCAL SAFETY REQUIREMENTS, TOGETHER WITH

EXERCISING PRECAUTIONS AT ALL TIMES FOR THE PROTECTION OF PERSONS (INCLUDING

EMPLOYEES) AND PROPERTY. THE CONTRACTOR SHALL COMPLY WITH THE OCCUPATIONAL

SAFETY AND HEALTH ACT OF 1970 DURING THE CONDUCT AND PERFORMANCE ON AND IN

CONNECTION WITH THIS PROJECT. IT IS ALSO THE SOLE RESPONSIBILITY OF THE

CONTRACTOR TO INITIATE, MAINTAIN, AND SUPERVISE ALL SAFETY REQUIREMENTS,

PRECAUTIONS, AND PROGRAMS IN CONNECTION WITH THE WORK.

16. THE CONTRACTOR SHALL BE THOROUGHLY FAMILIAR WITH THE REGULATIONS OF THE U.S.

DEPARTMENT OF LABOR, OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA), THE

U.S. DEPARTMENT OF TRANSPORTATION (DOT), THE U.S. ENVIRONMENTAL PROTECTION

AGENCY (EPA), AND SIMILAR STATE AND OTHER AGENCIES HAVING JURISDICTION OVER THE

WORK BEING PERFORMED.

17. THE CONTRACTOR SHALL PROVIDE NECESSARY HEALTH AND SAFETY TRAINING FOR ALL OF

THE CONTRACTOR'S ON-SITE PERSONNEL. REQUIREMENTS IN SAFETY SPECIFICATIONS FOR

SSHO AND CSP SITE SAFETY & HEALTH OFFICER AND COMPETENT SAFETY PROFESSIONAL.

18. THE CONTRACTOR SHALL HAVE A HEALTH AND SAFETY PLAN (HASP), WHICH DESCRIBES THE

WORK BEING UNDERTAKEN, THE RISKS INVOLVED IN PERFORMING THE REQUIRED TASKS,

THE MEASURES BEING TAKEN TO MITIGATE THE RISKS/HAZARDS, AND EMERGENCY

RESPONSE PLANS. THE FOLLOWING TOPICS MUST BE COVERED IN THE CONTRACTOR'S HASP,

AT A MINIMUM:

A. EMERGENCY RESPONSE PLANS (CLOSEST HOSPITAL INFORMATION/DRIVING ROUTE)

B. SITE AUTHORITIES AND ADDITIONAL EMERGENCY CONTACT PHONE NUMBERS

C. SPECIFIC TASK JOB SAFETY ANALYSIS (JSA) FOR ALL WORK TASKS

D. REQUIRED PERSONAL PROTECTIVE EQUIPMENT (PPE)

E. DESIGNATED EMERGENCY MEETING LOCATION

F. KICK-OFF TAILGATE MEETING OUTLINE (TAILGATE TO BE CONDUCTED DAILY)

G. SIGN-OFF LINES (ALL ON-SITE REQUIRED TO SIGN DAILY)

H. PCRA RESULTS FROM VA REVIEW OF 90% DRAWINGS

19. THE CONTRACTOR SHALL AT ALL TIMES MEET ALL SAFETY REQUIREMENTS SET FORTH IN

THEIR HEALTH & SAFETY PLAN (HASP) FOR THE SITE. THE CONTRACTOR SHALL BE SOLELY

RESPONSIBLE FOR CONDITIONS AT THE SITE, INCLUDING SAFETY OF ALL PERSONS AND

PROPERTY WHILE PERFORMING THE WORK. THIS REQUIREMENT WILL APPLY CONTINUOUSLY

AND NOT BE LIMITED TO NORMAL WORKING HOURS. THE CONTRACTOR SHALL COMPLY WITH

THE CONSTRUCTION SAFETY COMMISSION "GENERAL SAFETY RULES AND REGULATIONS FOR

THE CONSTRUCTION INDUSTRY", 29 CFR 1926 AND SAFETY RULES. THE CONTRACTOR SHALL

REQUIRE ALL PERSONNEL TO WEAR APPROPRIATE PROTECTIVE CLOTHING, HARD HATS, ETC.,

AS REQUIRED BY LAW.

20. IN ACCORDANCE WITH GENERALLY ACCEPTED PRACTICES, THE CONTRACTOR SHALL BE

RESPONSIBLE FOR ALL MATTERS RELATING TO THE HEALTH AND SAFETY OF ITS PERSONNEL

AND EQUIPMENT AND THE PUBLIC IN PERFORMANCE OF THE WORK. THIS INCLUDES

RECOGNITION OF THE POTENTIAL HEALTH AND SAFETY HAZARDS ASSOCIATED WITH THE

WORK AND INCLUDES COMPLIANCE WITH THE MINIMUM REQUIREMENTS OF THE HEALTH AND

SAFETY PLAN IN FORCE FOR THE WORK, IF APPLICABLE. IT IS UNDERSTOOD THAT

PROTECTIVE MEASURES SPECIFIED IN ANY HEALTH AND SAFETY PLAN ARE MINIMUM

REQUIREMENTS FOR THE WORK.

21. CONTRACTOR WARRANTS WHEN REQUIRED BY A PROJECT THAT ALL ITS EMPLOYEES

PERFORM WORK ON SAID PROJECT ARE PERMITTED TO ENGAGE IN HAZARDOUS WASTE

OPERATIONS THAT COULD EXPOSE THEM TO HAZARDOUS SUBSTANCES, SAFETY, OR HEALTH

HAZARDS, AND SHALL PROVIDE EVIDENCE PRIOR TO COMMENCING WORK THAT ALL

WORKERS HAVE OBTAINED THE NECESSARY HEALTH AND SAFETY TRAINING AND MEDICAL

SURVEILLANCE AS REQUIRED BY OSHA 1910.120.

22. THE CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR MAINTAINING A SECURE AND SAFE

SITE DURING THE ENTIRE PROJECT.

23. ALL INSPECTIONS/SITE ASSESSMENTS MUST BE PERFORMED BY A QUALIFIED PROFESSIONAL.

24. PROVIDE ACCURATE, FIELD CERTIFIED AS-BUILT DRAWINGS AT COMPLETION OF

CONSTRUCTION TO INCLUDE BUT NOT LIMITED TO: ANY FIELD CHANGES MADE DURING

CONSTRUCTION.

25. ANY CHANGES OR SUBSTITUTIONS MUST RECEIVE PRIOR APPROVAL FROM THE

CO. THESE SHALL USE THE RFI PROCESS FOR FULL DOCUMENTATION.

26. THE CONTRACTOR IS RESPONSIBLE FOR ALL REQUIRED SURVEYS AND FIELD

MEASUREMENTS TO COMPLETE THE PROJECT.

27. ALL REQUIREMENTS DESCRIBED WITHIN THE GENERAL NOTES SECTION AND CONTRACT

DOCUMENTS, UNLESS OTHERWISE INDICATED, SHALL BE CONSIDERED INCIDENTAL TO THE

PROJECT WITH NO ASSOCIATED PAY ITEM AND NO ADDITIONAL COMPENSATION TO BE

AWARDED TO THE CONTRACTOR.

28. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE CONDITION OF ALL WORK PERFORMED

WITHIN THE WORK LIMITS FOR A PERIOD OF ONE (1) YEAR FROM THE FINAL ACCEPTANCE OF

THE WORK, AND SHALL MAKE ANY NECESSARY REPAIRS AT NO COST TO THE OWNER.

29. CONSTRUCTION STAGING AREA SHALL BE LOCATED WHERE DIRECTED BY VA. PROVIDE

DESIRED SIZE TO VAMC AND COORDINATE WITH CO TO DETERMINE FINAL LOCATION.

CONSTRUCTION STAGING AREA SHALL BE SURROUNDED WITH TEMPORARY CHAIN LINK FENCE.

30. THE CONTRACTOR WILL BE RESPONSIBLE FOR CONSTRUCTION MEANS, METHODS,

PROCEDURES, AND/OR TECHNIQUES.

31. ANY MODIFICATION TO THE SPECIFICATIONS OR CHANGES TO THE WORK AS SHOWN ON THE

DRAWINGS MUST HAVE PRIOR WRITTEN APPROVAL BY THE CO.

32. SURFACE DEBRIS SHALL BE PICKED UP AND DISPOSED OF PRIOR TO DEMOBILIZATION.

33. DEMOLITION AND REMOVAL WORK AND NEW WORK SHALL BE STAGED TO MINIMIZE IMPACT TO

VAMC OPERATIONS. STAGING/PHASING MUST BE REVIEWED AND APPROVED BY CO.

34. DUST CONTROL SHALL BE INTEGRATED THROUGHOUT THE PROJECT. REFER TO ICRA AND LIFE

SAFETY PLANS AND SECTION 01 35 26, SAFETY REQUIREMENTS FOR PROJECT SPECIFIC ICRA

REQUIREMENTS.

35. CONTRACTOR SHALL PROVIDE DETAILED PLANS AND PROCEDURES TO VA FOR REVIEW AND

APPROVAL FOR THE FOLLOWING ITEMS:

A. DUST CONTROL

B. DEMOLITION PLAN

C. PHASING

36. THE CONTRACTOR SHALL BE RESPONSIBLE TO OBTAIN ALL NECESSARY PERMITS ASSOCIATED

WITH THE WORK AS DESCRIBED WITHIN THE PROJECT SPECIFICATIONS AND DRAWINGS.

37. SCHEDULE SYSTEMS SHUTDOWNS WITH CO. SUBMIT SHUTDOWN REQUEST TWO (2) WEEKS

PRIOR TO VA ENGINEERING DEPARTMENT. SYSTEM SHUTDOWNS SHALL NOT INTERFERE WITH

BUILDING OPERATIONS. MAINTAIN EXISTING SYSTEMS PER CO.

38. THE CONTRACTOR SHALL BE ALLOWED ACCESS TO THE ELEVATORS DURING CONSTRUCTION,

COORDINATE WITH CO.

39. SEVERAL AREAS ARE KEPT LOCKED AT ALL TIMES FOR SECURITY, THE CONTRACTOR WILL BE

REQUIRED TO PASS THROUGH A SERIES OF LOCKED DOORS TO ACCESS THE PROJECT AREAS.

COORDINATE WITH CO FOR REQUIRED KEYS. CONSTRUCTION AREAS SHALL BE LOCKED AND

KEYED BY VA BUFFALO WITH CONSTRUCTION/CONTRACTOR KEY 7C-14.

40. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REPAIR AND PROPER FIRE SEALING OF

ALL ABOVE CEILING THRU-WALL PENETRATIONS/ OPENINGS BETWEEN PROJECT AREA WALLS

AND ADJACENT SPACES/CORRIDORS, INCLUDING ANY PENETRATIONS/OPENINGS THAT

EXISTED PRIOR TO CONSTRUCTION.

41. ITEMS CALLED OUT SPECIFICALLY BY MANUFACTURER, MODEL NUMBER, NAME, ETC. ARE TO BE CONSIDERED THE "BASIS OF DESIGN". SUBSTITUTE ITEMS WILL BE CONSIDERED ON AN "OR

EQUAL" BASIS. IT IS THE CONTRACTORS RESPONSIBILITY TO PROVIDE EVIDENCE THAT

SUBSTITUTE ITEMS ARE EQUAL TO OR BETTER THAN ITEM SPECIFIED. IT IS THE CONTRACTORS

RESPONSIBILITY TO ATTAIN APPROVAL PRIOR TO ORDERING OR PURCHASING SUBSTITUTE

ITEMS.

42. NO SUPPORTS, ATTACHMENTS, ANCHORS OR PENETRATION ARE TO BE MADE TO THE

CONCRETE BEAMS OR COLUMNS WITHOUT EXPRESS PERMISSION FROM COR. ALL MEP RUNS

ARE TO BE SUPPORTED FROM THE DECK OR WALLS.

43. INITIAL PHOTOS AND RETURN TO EQUAL OR BETTER CONDITION OF NON-WORK AREAS BEHIND

CONSTRUCTION BARRIER. DAMAGE AND POOR CONDITIONS NOT CAPTURED WILL BE

CONSIDERED TO OCCUR DURING CONSTRUCTION AND REPAIRED.

X

PLAN

NORTH

N

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

ISSUED FOR CONSTRUCTION

GENERAL NOTES AND

ABBREVIATIONS

GI-002

EHALLJ 2

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

AREA OF WORK

ISSUED FOR CONSTRUCTION

REV. 1 - 50% REVIEW COMMENTS 05/07/19

PHASING SEQUENCE

GI-003

EHALLJ/BFW 3

PHASE 0 - SUBMITTALS, APPROVALS, AND ORDERING

1. ALL SCHEDULES AND SUBMITTALS SHALL BE PROVIDED, REVIEWED,

AND APPROVED.

2. ALL MATERIALS SHALL BE ORDERED. OFF-SITE WAREHOUSE SPACE

FOR STORAGE IS SECURED.

3. OFFICIAL NOTICE TO PROCEED TO CONSTRUCTION.

PHASE A - ENABLING PHASE

* NOTE: PHASE A SHALL NOT COMMENCE UNTIL PHASE 0 IS COMPLETED

AND OFFICIAL NOTICE-TO-PROCEED IS PROVIDED TO THE

CONTRACTOR BY VA.

1. 4TH FLOOR:

a. DEMOLITION OF UTILITIES AND MEP EQUIPMENT ON 4TH

FLOOR MECHANICAL ROOM 437-C.

b. DEMOLITION OF ARCHITECTURAL ELEMENTS (WINDOW, LOUVER, ETC.).

c. DEMOLITION OF ELECTRICAL ITEMS.

d. DEMOLITION OF MECHANICAL AND PLUMBING ITEMS FOR

RELOCATION.

2. SUB-BASEMENT:

a. EXCAVATION OF SOIL TO PREP FOR NEW PRV.

b. CONCRETE PAD INSTALLATION IN SUB-BASEMENT TO

SUPPORT NEW PRV INSTALLATION.

c. NEW STEAM PRV INSTALLATION, EXCLUDING TIE-IN TO HIGH

PRESSURE STEAM MAIN.

3. UTILITIES TO TEMPORARY SPS TRAILER:

a. PROVIDE COLD WATER, HOT WATER, AND HOT WATER

RE-CIRCULATION SERVICE FROM POTABLE WATER MAINS

ADJACENT TO BASEMENT KITCHEN.

b. PROVIDE WATER FILTRATION SKIDS ON WALL TO CONDITION

DOMESTIC COLD AND HOT WATER.

c. PROVIDE NEW SANITARY LATERAL TO THE 12” MAIN

ADJACENT TO TEMPORARY TRAILER LOCATION.

d. PROVIDE NEW FIRE PROTECTION CONNECTION TO THE

EXISTING FIRE PROTECTION LOOP.

e. PROVIDE TEMPORARY POWER SERVICE TO SPS TRAILER, INCLUDING TRENCHING AND UNDERGROUND INSTALLATION.

f. PROVIDE TEMPORARY DATA CONNECTIONS TO THE SPS

TRAILER BASEMENT.

g. PROVIDE TEMPORARY FIRE ALARM CONNECTIONS TO THE SPS

TRAILER FROM BASEMENT.

PHASE B - TEMPORARY SPS TRAILER INSTALLATION :

1. PREP LANDING AREA FOR TEMPORARY TRAILER:

a. INSTALL TEMPORARY ANCHORS AT FOUR CORNERS OF THE

TRAILER.

b. PROVIDE LEVEL STONE LANDING AREA FOR TRAILER.

2. PROVIDE TEMPORARY CONCRETE SIDEWALKS (5'-0” WIDE) FOR

INGRESS / EGRESS OF WHEELED CASE CARTS.

3. DELIVER TRAILER TO THE SITE.

4. PLACE AND LEVEL TRAILER AND INSTALL STRAPPING TO ANCHOR

POINTS.

5. INSTALL ACCESS RAMPS AND LANDINGS.

6. PROVIDE OVERHEAD COVER IN THE FORM OF SCAFFOLDING WITH

PLYWOOD AND PLASTIC.

7. CONNECT ALL UTILITIES FROM PHASE A TO CONNECTION POINTS

AT TRAILER.

8. STARTUP, TESTING, AND COMMISSIONING OF TRAILER TO PUT SPS

INTO SERVICE.

a. INCLUDING 2 WEEKS OF FULL OPERATION WITH SPS STAFF.

* NOTE THE SPS TRAILER MUST BE FULLY OPERATIONAL PRIOR TO

COMMENCING ON SUBSEQUENT PHASES.

PHASE C - SPS DEMOLITION:

* NOTES:

· PHASE B SHALL NOT COMMENCE UNTIL PHASE A IS COMPLETED AND

OFFICIAL NOTICE-TO-PROCEED IS PROVIDED TO THE CONTRACTOR BY

VA.

· PHASES C, D, AND E MAY BE ACCOMPLISHED IN PARALLEL WITH ONE

ANOTHER.

· ALL DEMOLITION WILL OCCUR WITH SPS SHUTDOWN AND ALL

STERILIZATION BEING PERFORMED IN THE TEMPORARY TRAILER.

· DOMESTIC WATER SHUTDOWNS SHALL OCCUR AT RISERS S23, S24,

S30, AND S50 FOR NEW PLUMBING TIE-INS. DOMESTIC WATER

SHUTDOWNS ARE ALSO REQUIRED FOR RELOCATIONS OF PLUMBING

PIPING ON CLEAN SIDE FOR SPS EXHAUST FAN DUCTWORK

INSTALLATION. REFER TO 1-PD-103 AND 1-PL-103.

· FIRE PROTECTION WATER SHUTDOWNS SHALL OCCUR ON 3RD FLOOR

SPS FOR SPRINKLER MODIFICATIONS FOR NEW SPS LAYOUT.

CONTRACTOR SHALL SUBMIT INTERIM LIFE SAFETY MEASURES FOR

SPRINKLER SHUTDOWN TO THE VA. REFER TO 1-FD-103 AND

1-FX-103.

· A SHUTDOWN OF THE GLYCOL HOT WATER SYSTEM IN MECHANICAL

ROOM A 316-C WILL BE REQUIRED FOR NEW TIE-INS FOR

1-AHU-SPS-3C AND 1-AHU-SPS-4C. REFER TO 1-MD-203 AND

1-MH-203.

· THE EXISTING COMPRESSED AIR SYSTEM WILL NEED TO BE

SHUTDOWN FOR THE NEW TIE-INS IN THE SPS. REFER TO 1-PD-103

AND 1-PL-103.

1. OFFICIAL SPS SHUTDOWN AFTER MOBILE SPS TRAILER HAS

SUCCESSFULLY BEEN IN SERVICE FOR TWO WEEKS.

2. INSTALL ICRA MEASURES / TEMPORARY BARRIERS AT SPS SUITE

AND 4TH FLOOR MECHANICAL ROOM.

3. REMOVE EXISTING SPS EQUIPMENT AND STORE IN LOCATION

DESIGNATED BY VA. REFER TO CONTRACT DRAWING 1-AD-103

FOR EQUIPMENT REMOVALS.

4. CEILING AND WALL DEMOLITION THROUGHOUT SPS.

5. FLOOR FINISH DEMOLITION.

6. DEMOLISH WALLS OF UTILITY CHASE WITHIN SPS SUITE.

7. ACM ABATEMENT.

8. DEMOLITION OF DUCTWORK.

9. DEMOLITION OF AHU IN 3RD FLOOR MECHANICAL ROOM.

10. DEMOLITION OF MECHANICAL PIPING.

11. DEMOLITION OF PLUMBING, WITH THE EXCEPTION OF THE FLOOR

DRAINS.

12. RELOCATE EXISTING ELECTRICAL PANEL FROM HAC 305-C TO

SOILED RECEIVING PPE ALCOVE 306-C-2

13. DEMOLITION OF TEMPORARY ELECTRICAL AND DATA

INFRASTRUCTURE.

PHASE D - STRUCTURAL FRAMING FOR 3RD FLOOR AHU ABOVE MEN'S

OR LOCKER ROOM

(SERIES OF WEEKEND SHUTDOWNS)

* NOTES:

· ALL WORK IN 2ND FLOOR CEILINGS (OR LOCKER ROOM) SHALL

OCCUR DURING A SERIES OF WEEKEND SHUTDOWNS TO BE

SCHEDULED WITH VA. WEEKEND WORK SHALL ONLY OCCUR

STARTING ON A FRIDAY AT 6:00 PM AND SHALL BE COMPLETED WITH

ALL AREAS CLEANED UP BY 6:00 PM SUNDAY EVENING. THE

EXCEPTION WOULD BE FOR A THREE-DAY WEEKEND WHERE THIS

COULD EXTEND UNTIL 6:00 PM ON A MONDAY. REFER TO FEDERAL

HOLIDAY SCHEDULE FOR AVAILABILITY OF THREE-DAY WEEKENDS.

· PHASES C, D, AND E MAY BE ACCOMPLISHED IN PARALLEL WITH ONE

ANOTHER.

1. INSTALL ICRA BARRIERS - ICRA MEASURES WILL NEED TO BE

INSTALLED AT THE BEGINNING OF EACH WEEKEND SHIFT AND

REMOVED PRIOR TO PUTTING SPACE BACK IN TO SERVICE.

2. DEMOLISH CEILING ABOVE MEN'S OR LOCKER ROOM.

3. PROVIDE TEMPORARY CEILING THAT CAN BE REMOVED DURING

WEEKEND SHUTDOWNS AND REPLACED PRIOR TO RESTORATION

OF SERVICE. NO OTHER WORK MAY OCCUR UNTIL TEMPORARY

CEILINGS ARE INSTALLED.

4. TEMPORARILY REMOVE LOCKERS AS NEEDED TO INSTALL

STRUCTURAL WORK.

5. RELOCATE SANITARY LINES IN CEILING TO FACILITATE

INSTALLATION OF NEW STRUCTURAL FRAMING.

6. INSTALL NEW STRUCTURAL STEEL FRAMING FOR AHU ABOVE.

7. RE-INSTALL HARD CEILING.

PHASE E - SANITARY DRAINAGE WORK ABOVE OR 2ND FLOOR

* NOTES:

· ALL WORK IN 2ND FLOOR CEILINGS (OR LOCKER ROOM) SHALL

OCCUR DURING A SERIES OF WEEKEND SHUTDOWNS TO BE

SCHEDULED WITH VA. WEEKEND WORK SHALL ONLY OCCUR

STARTING ON A FRIDAY AT 6:00 PM AND SHALL BE COMPLETED WITH

ALL AREAS CLEANED UP BY 6:00 PM SUNDAY EVENING. THE

EXCEPTION WOULD BE FOR A THREE-DAY WEEKEND WHERE THIS

COULD EXTEND UNTIL 6:00 PM ON A MONDAY. REFER TO FEDERAL

HOLIDAY SCHEDULE FOR AVAILABILITY OF THREE-DAY WEEKENDS.

· PHASES C, D, AND E MAY BE ACCOMPLISHED IN PARALLEL WITH ONE

ANOTHER.

1. INSTALL ICRA BARRIERS - ICRA MEASURES WILL NEED TO BE

INSTALLED AT THE BEGINNING OF EACH WEEKEND SHIFT AND

REMOVED PRIOR TO PUTTING SPACE BACK IN TO SERVICE.

2. CEILING DEMOLITION ABOVE OR SUITE.

3. PROVIDE TEMPORARY CEILING THAT CAN BE REMOVED DURING

WEEKEND SHUTDOWNS AND REPLACED PRIOR TO RESTORATION

OF SERVICE. NO OTHER WORK MAY OCCUR UNTIL TEMPORARY

CEILINGS ARE INSTALLED.

4. DEMOLISH SANITARY PIPING AND FLOOR DRAINS UP TO 3RD

FLOOR SPS SUITE.

5. INSTALL NEW SANITARY PIPING ABOVE OR CEILING AND FLOOR

DRAINS AT THE FLOOR OF 3RD FLOOR SPS SUITE.

6. DEMOLISH TEMPORARY CEILINGS AND RE-INSTALL PERMANENT

CEILINGS.

PHASE F - INSTALLATION OF NEW STEAM LINE TO PRV STATION

* NOTE: PHASE F AND G MAY BE COMPLETED IN PARALLEL WITH ONE

ANOTHER.

1. HIGH-PRESSURE STEAM SHUTDOWN:

a. ALL SHUTDOWNS WILL REQUIRE MINIMUM 6 WEEKS

COORDINATION WITH VA PRIOR TO COMMENCEMENT OF

WORK.

b. CONTRACTOR SHALL PROVIDE A DETAILED SHUTDOWN AND

RE-START PLAN THAT MUST BE REVIEWED AND APPROVED BY

VA PRIOR TO COMMENCEMENT OF WORK.

c. IN ORDER TO SHUTDOWN THE STEAM MAIN THE

CONTRACTOR MUST CONDUCT A FLAME-OUT BOILER PLANT

SHUTDOWN TO DEPRESSURIZE AND SAFE THE ENTIRE STEAM

SYSTEM.

d. SHUTDOWNS SHALL BE LIMITED TO THE HOURS OF 6PM ON A

SATURDAY AND THE STEAM SYSTEM SHALL BE BACK IN

OPERATION BY SUNDAY MORNING AT 6AM.

2. PROVIDE TIE-IN TO HIGH-PRESSURE STEAM MAIN DURING STEAM

SHUTDOWN.

3. PROVIDE NEW TIE-INS IN 3RD FLOOR SPS FOR STERILIZATION

EQUIPMENT AND AHUS WHILE STEAM IS SHUTDOWN.

4. PUT STEAM BACK INTO SERVICE.

5. DEMOLISH EXISTING PRV STATION ONCE NEW STATION IS IN

SERVICE.

PHASE G - MISCELLANEOUS REPAIRS & ADJUSTMENTS

* NOTE: PHASE F AND G MAY BE COMPLETED IN PARALLEL WITH ONE

ANOTHER.

1. PROVIDE ICRA ENCLOSURE AT 3RD FLOOR DUCT CHASE ADJACENT

TO SPS.

2. REPAIR EXHAUST DUCT RISER FROM DIRTY SIDE OF SPS WITHIN

CHASE. INSTALLATION OF EMERGENCY POWER CONDUIT AND

WIRING TO NEW PANEL ON 12TH FLOOR FROM SUB-BASEMENT

WITHIN CHASE.

PHASE H - INSTALLATION OF NEW WORK FOR SPS

1. INSTALL STRUCTURAL FRAMING IN HALLWAY TO SUPPORT THE

4TH FLOOR AHU.

2. INSTALL NEW AHU AND ALL APPURTENANCES AT 3RD FLOOR

MECHANICAL ROOM. CONFIRM ALL LARGE ITEMS ARE INSIDE

BUILDING BEFORE INTAKE IS BLOCKED, REFER TO DRAWING

1-MH-403.

3. INSTALL NEW AHU AND ALL APPURTENANCES AT 4TH FLOOR

MECHANICAL ROOM.

4. INSTALL NEW EXHAUST FAN IN SPS SUITE.

5. INSTALL THE STAINLESS-STEEL UTILITY ENCLOSURE AND ALL NEW

WALLS WITHIN THE SPS, INCLUDING NEW MEDIVATOR ROOM.

6. INSTALL NEW ELECTRICAL POWER AND DATA CONNECTION

INFRASTRUCTURE.

7. INSTALL STEAM SERVICE LINE FROM NEW PRV IN BASEMENT.

8. INSTALL NEW PLUMBING INFRASTRUCTURE.

9. INSTALL NEW MECHANICAL EQUIPMENT (HX, PUMPS, ETC.) AND

MECHANICAL PIPING.

10. INSTALL NEW STERILIZATION EQUIPMENT WITHIN THE UTILITY

CHASE.

11. COMPLETE DUCTWORK INSTALLATION.

12. INSTALL NEW CEILINGS.

13. INSTALL NEW DIFFUSERS AND RETURN GRILLES.

14. TEST AND BALANCE ALL HVAC SYSTEMS WITHIN SPS.

a. CONNECTION OVER TO EMERGENCY POWER 12TH FLOOR AND

SUB-BASEMENT. THIS WILL REQUIRE A SHUT-DOWN ON

WEEKEND OR HOLIDAY EFFECTING MOST OF THE HOSPITAL.

b. TEST AND BALANCE EXHAUST FAN AT THE 12TH FLOOR

MECHANICAL ROOM AS PART OF OVERALL TESTING OF THE

SPS SUITE HVAC SYSTEMS.

16. INSTALL LIGHTING FIXTURES THROUGHOUT THE SPS SUITE.

17. INSTALL NEW FIRE ALARM DEVICES.

18. INSTALL NEW SINKS.

19. INSTALL FLOORS AND FINISHES.

20. INSTALL REMAINDER OF STERILIZATION EQUIPMENT.

21. MAKE FINAL UTILITY CONNECTIONS TO STERILIZATION

EQUIPMENT.

22. COMMISSION ALL WORK.

23. INSTALL FURNISHINGS.

24. REMOVE ICRA ENCLOSURE / BARRIER.

PHASE I - PUT SPS SUITE BACK INTO OPERATION

1. PUNCH LIST INSPECTION AND FINAL CORRECTIONS COMPLETED.

2. RETURN ALL ANCILLARY SPACES TO PRE-USE CONDITION.

3. INCLUDE 2 WEEKS OF FULL OPERATION WITH SPS STAFF IN NEW

SUITE.

PHASE J - DE-COMMISSION THE TEMPORARY SPS TRAILER.

1. REMOVE TRAILER.

2. DEMOLISH ALL TEMPORARY UTILITIES TO TRAILER, BACK TO

SOURCE.

3. REMOVE OVERHEAD WALKWAY PROTECTION.

4. LEAVE CONCRETE PAD LANDING AREA FOR FUTURE USE.

PHASE K - PROJECT CLOSE-OUT.

1. FINAL AS-BUILTS PROVIDED BY CONTRACTOR TO ENGINEER OF

RECORD FOR FINAL REVIEW.

2. CONTRACTOR PROVIDES FINAL TEST AND BALANCE,

PRESSURIZATION TESTING, AND ANY ADDITIONAL DATA

IDENTIFIED IN THE COMMISSIONING SPECIFICATIONS TO THE

COMMISSIONING AUTHORITY FOR REVIEW.

3. FINAL COMMISSIONING MANUAL PROVIDED BY COMMISSIONING

AUTHORITY.

4. WARRANTY DOCUMENTATION.

5. SEASONAL COMMISSIONING (1-YEAR FOLLOW-UP) AND

SUPPORT/CORRECTION OF ANY ISSUES IDENTIFIED.

SB

SB

SB

SBSB

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

ISSUED FOR CONSTRUCTION

ICRA AND LIFE SAFETY PLAN

PLAN

NORTH

2nd FLOOR LIFE SAFETY & ICRA PLAN

SCALE: 18" = 1'-0"

GENERAL ICRA AND LIFE SAFETY NOTES:

1. ALL SECOND FLOOR OPERATING (OR) SUITE DEMOLITION AND NEW

WORK MUST TAKE PLACE DURING PATIENT DIVERSION OVER A SINGLE

LONG WEEKEND OR 2 TO 3 NORMAL WEEKENDS. TIMES MUST BE

COORDINATED ONE (1) MONTH IN ADVANCE.

2. REFER TO ASBESTOS ABATEMENT DRAWINGS, 1-HA-103 AND 1-HA-104,

FOR "LEAD AWARENESS NOTES" AND "ASBESTOS AWARENESS NOTES".

KEYED LIFE SAFETY & ICRA NOTES:

1. LIMITED NEW WORK TO TAKE PLACE IN THIS AREA. UNSEAL AND OPEN

EXISTING DOOR WHEN WORK IN THIS AREA IS TO BE ACCOMPLISHED.

CLOSE DOOR AND SEAL WHEN NO WORK IS BEING PERFORMED.

2. 1-HOUR RATED TEMPORARY CONSTRUCTION BARRIER, SEE DETAIL

1/GI-003.

INFECTION CONTROL RISK ASSESSMENT

MATRIX OF PRECAUTIONS FOR CONSTRUCTION AND RELOCATION

TYPE CONSTRUCTION PROJECT ACTIVITY

TYPE A INSPECTION AND NON-INVASIVE ACTIVITIES.

INCLUDE, BUT ARE NOT LIMITED TO:

REMOVAL OF CEILING TILES FOR VISUAL INSPECTION LIMITED TO 1

TILE PER 50 SQUARE FEET.

PAINTING (BUT NOT SANDING).

WALL COVERING, ELECTRICAL TRIM WORK, MINOR PLUMBING, AND

ACTIVITIES THAT DO NOT GENERATE DUST OR REQUIRE CUTTING OF

WALLS OR ACCESS TO CEILINGS OTHER THAN FOR VISUAL

INSPECTION.

TYPE B SMALL SCALE, SHORT DURATION ACTIVITIES THAT CREATE MINIMAL

DUST.

INCLUDE, BUT ARE NOT LIMITED TO:

INSTALLATION OF TELEPHONE AND COMPUTER CABLING.

ACCESS TO CHASE SPACES.

CUTTING OF WALLS OR CEILING WHERE DUST MIGRATION CAN BE

CONTROLLED.

TYPE C WORK THAT GENERATES A MODERATE TO HIGH LEVEL OF DUST OR

REQUIRES DEMOLITION OR REMOVAL OF ANY FIXED BUILDING

COMPONENTS OR ASSEMBLIES.

INCLUDES, BUT IS NOT LIMITED TO:

SANDING OF WALLS FOR PAINTING OR WALL COVERING.

REMOVAL OF FLOOR COVERINGS, CEILING TILES, AND CASEWORK.

NEW WALL CONSTRUCTION.

MINOR DUCT WORK OR ELECTRICAL WORK ABOVE CEILINGS.

MAJOR CABLING ACTIVITIES.

ANY ACTIVITY THAT CANNOT BE COMPLETED WITHIN A SINGLE

WORK SHIFT.

TYPE D MAJOR DEMOLITION AND CONSTRUCTION PROJECTS.

INCLUDES, BUT IS NOT LIMITED TO:

ACTIVITIES THAT REQUIRE CONSECUTIVE WORK SHIFTS.

REQUIRES HEAVY DEMOLITION OR REMOVAL OF A COMPLETE

CABLING SYSTEM.

NEW CONSTRUCTION.

PATIENT RISK GROUPS

LOW RISK MEDIUM RISK HIGH RISK HIGHEST RISK

ICRA MATRIX CLASS OF PRECAUTIONS

PATIENT RISK GROUP TYPE A TYPE B TYPE C TYPE D

DESCRIPTION OF REQUIRED INFECTION CONTROL PRECAUTIONS BY CLASS - SEE "KEYED NOTE" THIS SHEET, FOR PROJECT SPECIFICS

CLASS DURING CONSTRUCTION/DEMOLITION PHASE UPON COMPLETION OF THE PROJECT/PHASE

CLASS I

CLASS II

CLASS III

CLASS IV

1. NOTIFY THE COR OR GOVERNMENT DESIGNATED AUTHORITY.

2. EXECUTE WORK BY METHODS TO MINIMIZE RAISING DUST FROM

CONSTRUCTION OPERATIONS.

1. NOTIFY THE COR OR GOVERNMENT DESIGNATED AUTHORITY.

2. PROVIDE ACTIVE MEANS TO PREVENT AIRBORNE DUST FROM DISPERSING

INTO ATMOSPHERE SUCH AS WET METHODS OR TOOL MOUNTED DUST

COLLECTORS WHERE POSSIBLE. WHERE DUST CONTROL IS SHOWN ON

ICRA PLAN, PROVIDE SHEET PLASTIC BARRIERS AS SPECIFIED IN SECTION

01 35 26, INFECTION CONTROL, PRODUCTS AND MATERIALS, DURING

DEMOLITION ACTIVITIES. REMOVE BARRIERS UPON COMPLETION OF

DEMOLITION WORK AND APPROVAL OF COR.

3. WATER MIST WORK SURFACES TO CONTROL DUST WHILE CUTTING.

4. SEAL UNUSED DOORS WITH DUCT TAPE.

5. BLOCK OFF AND SEAL AIR VENTS.

6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE WORK IS BEING

PERFORMED.

AS ABOVE AND:

1. OBTAIN PERMIT FROM THE COR OR GOVERNMENT DESIGNATED

AUTHORITY.

2. COMPLETE ALL CRITICAL BARRIERS (SHEETROCK, PLYWOOD, PLASTIC), TO

SEAL AREA FROM NON-WORK AREA OR IMPLEMENT CONTROL CUBE

METHOD (CART WITH PLASTIC COVERING AND SEALED CONNECTION TO

WORK SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT) BEFORE

CONSTRUCTION BEGINS. INSTALL CONSTRUCTION BARRIERS AND CEILING

PROTECTION CAREFULLY, COORDINATE TIMING OF INSTALLATION WITH VA

STAFF.

3. MAINTAIN NEGATIVE AIR PRESSURE, 0.01 INCHES OF WATER GAUGE,

WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS AND

CONTINUOUSLY MONITOR WITH A DIGITAL DISPLAY, RECORDING AND

ALARM INSTRUMENT, WHICH MUST BE CALIBRATED ON INSTALLATION AND

MAINTAINED WITH PERIODIC CALIBRATION AND MONITORED BY THE

CONTRACTOR.

4. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN TIGHTLY

COVERED CONTAINERS.

5. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE COVERING UNLESS

SOLID LID.

AS ABOVE AND:

1. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES APPROPRIATELY.

2. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL TO PASS

THROUGH THIS ROOM SO THEY CAN BE VACUUMED USING A HEPA VACUUM

CLEANER BEFORE LEAVING WORK SITE OR THEY CAN WEAR CLOTH OR

PAPER COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE THE

WORK SITE.

3. ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED TO WEAR SHOE

COVERS. SHOE COVERS MUST BE CHANGED EACH TIME THE WORKER

EXITS THE WORK AREA.

1. CLEAN WORK AREA UPON COMPLETION OF TASK.

2. NOTIFY THE COR OR GOVERNMENT DESIGNATED

AUTHORITY.

1. WET MOP/WIPE WORK SURFACES WITH

CLEANER/DISINFECTANT.

2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT IN

TIGHTLY COVERED CONTAINERS.

3. WET MOP AND/OR VACUUM WITH HEPA FILTERED VACUUM

BEFORE LEAVING WORK AREA.

4. UPON COMPLETION, RESTORE HVAC SYSTEM WHERE WORK

WAS PERFORMED.

5. NOTIFY THE COR OR GOVERNMENT DESIGNATED

AUTHORITY.

AS ABOVE AND:

1. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL

COMPLETED PHASE HAS BEEN INSPECTED BY THE COR OR

GOVERNMENT DESIGNATED AUTHORITY AND THOROUGHLY

CLEANED BY THE VA ENVIRONMENTAL SERVICES

DEPARTMENT.

2. REMOVE CONSTRUCTION BARRIERS AND CEILING

PROTECTION CAREFULLY TO MINIMIZE SPREADING OF DIRT

AND DEBRIS ASSOCIATED WITH CONSTRUCTION;

COORDINATE TIMING OF REMOVAL WITH VA STAFF.

3. RETURN PERMIT TO THE COR.

AS ABOVE

LEGEND:

DC

GI-004

EHALLJ 4

D C

DC DC DC DC

DC

DC

SB

DC

D C

D C

DC DC

DC

D C

D C

DC

DC

PLAN

NORTH

4th FLOOR LIFE SAFETY & ICRA PLAN

SCALE: 18" = 1'-0"

4'-0"

MIN.

1'-0"

BOTH SIDES

OF DOOR

PROVIDE 42" HIGH MINIMUM

CONSTRUCTION FENCE

EXISTING CEILING

EXISTING FLOOR

BACKER ROD AND

SEALANT, ENTIRE

PERIMETER

8" TYPE X GYPSUM WALL BOARD,

BOTH SIDES

3 58" STEEL STUDS @ 24" OC

WITH TOP AND BOTTOM

RUNNER TRACK

SOUND BATT INSULATION

SCALE: 11

2" = 1'-0" UL DESIGN NO. U419

315-C

314-C

FEMALE

STAFF

MALE

STAFF

309-C-1

OFFICE

NNW

311-C-1

ETO

ROOM311-C

TRAINING

ROOM

NNW

310-C

HAC

NNW

309-C

"CLEAN SIDE"

PREPARATION

STERILIZATION

CART

WASH

NNW

308-C

WOMEN'S

LOCKER

317-C

OFFICE

316-C

MECHANICAL

ROOM

300C-2

SERVICE

CORRIDOR

306-C

"DIRTY SIDE "

DECONTAMINATION

WORK AREA

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

ISSUED FOR CONSTRUCTION

ICRA AND LIFE SAFETY PLAN

PLAN

NORTH

3rd FLOOR LIFE SAFETY & ICRA PLAN

SCALE: 18" = 1'-0"

GI-005

EHALLJ 5

GENERAL ICRA AND LIFE SAFETY NOTES:

1. ALL SECOND FLOOR OPERATING (OR) SUITE DEMOLITION AND NEW

WORK MUST TAKE PLACE DURING EVENING OR WEEKEND HOURS.

2. REFER TO ASBESTOS ABATEMENT DRAWINGS, 1-HA-103 AND 1-HA-104,

FOR "LEAD AWARENESS NOTES" AND "ASBESTOS AWARENESS NOTES".

KEYED LIFE SAFETY & ICRA NOTES:

1. LIMITED NEW WORK TO TAKE PLACE IN THIS AREA. UNSEAL AND OPEN

EXISTING DOOR WHEN WORK IN THIS AREA IS TO BE ACCOMPLISHED.

CLOSE DOOR AND SEAL WHEN NO WORK IS BEING PERFORMED.

2. COVER AND SEAL TIGHT ENTRANCE TO AND CONTROL PANEL FOR CART

WASH.

3. 1-HOUR RATED TEMPORARY CONSTRUCTION BARRIER, SEE DETAIL

1/GI-003.

LEGEND:

DC

SB

DC

3'-0"

MIN.

DC

DC

DC

DC

DC DC

DC

DC

DC

DC

DC

DC

DC

ABBREVIATIONS:

NNW NO NEW WORK

DC

DC

122124

126127 washer sterilizer sterilizer blank eto

FD

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

AREA OF WORK

95 Perry Street, Suite 300 Buffalo, NY 14203

ISSUED FOR CONSTRUCTION

1/8" = 1'-0"1 PARTIAL 3RD FLOOR PLAN

GENERAL NOTES

A. PERFORM ALL WORK IN ACCORDANCE WITH ALL APPLICABLE LOCAL, STATE, AND FEDERAL RULES, REGULATIONS, GUIDELINES, AND THE CONTRACT

DOCUMENTS.

B. IF ANY PREVIOUSLY-UNIDENTIFIED OR OTHERWISE UNANTICIPATED SUSPECT MATERIAL IS IDENTIFIED DURING CONSTRUCTION, STOP WORK AND NOTIFY THE OWNER OR THEIR REPRESENTATIVE FOR FURTHER DIRECTION. UNDER NO CIRCUMSTANCES SHALL THE CONTRACTOR COLLECT AND/OR ANALYZE BULK SAMPLES OF SUSPECT MATERIALS WITHOUT THE APPROVAL OF THE OWNER OR THEIR REPRESENTATIVE.

C. THE DISTURBANCE OF ANY ASBESTOS-CONTAINING MATERIAL (ACM), OR SUSPECT ACM, SHALL BE PERFORMED BY A LICENSED ASBESTOS

ABATEMENT CONTRACTOR.

D. ALL MATERIAL MEASUREMENTS AND/OR QUANTITIES AND LOCATIONS ARE APPROXIMATE AND FOR GENERAL ORIENTATION ONLY.

E. THE LOCATION OF SITE STORAGE OF MATERIAL, EQUIPMENT, WASTE TRAILER/DUMPSTER(S), AS WELL AS CONTRACTOR PARKING, ETC. SHALL BE

COORDINATED WITH AND APPROVED BY THE OWNER/OWNER'S REPRESENTATIVE.

F. CONTRACTOR IS RESPONSIBLE FOR ALL TOOLS, EQUIPMENT, AND SUPPLIES. CONTRACTOR IS ALSO RESPONSIBLE FOR PROVIDING LADDERS, SCAFFOLDING, LIFTS, PLANKING, ETC. AS REQUIRED TO PERFORM WORK. THE OWNER OR THEIR REPRESENTATIVE WILL NOT BE RESPONSIBLE FOR

LOST, DAMAGED, OR STOLEN ITEMS.

G. THE CONTRACTOR IS RESPONSIBLE FOR KEEPING THE WORK AREA IN A CLEAN AND SAFE CONDITION, PROVIDING TEMPORARY PROTECTION, PROTECTING BUILDING MATERIALS SCHEDULED TO REMAIN, AND TO PREVENT UNAUTHORIZED ACCESS DURING THE DURATION OF THE PROJECT.

REPAIR OF DAMAGE CAUSED AS A RESULT OF INADEQUATE TEMPORARY PROTECTION OR CONTRACTOR ACTIVITIES WILL BE THE RESPONSIBILITY OF

THE CONTRACTOR.

H. ALL REMOVED ASBESTOS-CONTAINING MATERIALS AND ASBESTOS-CONTAMINATED WASTE SHALL BE PROPERLY PACKAGED PRIOR TO BEING REMOVED FROM THE WORK AREA(S). WARNING LABELS SHALL BE APPLIED TO ASBESTOS WASTE CONTAINERS AS APPROPRIATE. ALL ASBESTOS-CONTAINING MATERIALS/ASBESTOS-CONTAMINATED WASTE REMOVED FROM THE WORK AREA(S) SHALL BE ACCOMPANIED BY A WASTE SHIPMENT RECORD. COMPLETED WASTE SHIPMENT RECORDS MUST BE PROVIDED TO THE OWNER AS PART OF THE CLOSEOUT DOCUMENTATION.

ALL ORIGINAL WASTE SHIPMENT RECORDS MUST BE PROVIDED TO THE OWNER WITHIN 35 DAYS OF THE WASTE LEAVING THE SITE.

I. COORDINATE ALL WORK ACTIVITIES WITH THE OWNER/OWNER'S REPRESENTATIVE TO ENSURE ONSITE ACTIVITIES ARE ACCEPTABLE TO THE OWNER, AND THAT REMOVALS ARE SUFFICIENT TO ACCOMMODATE THE PROJECT ACTIVITIES.

J. REFER TO SPECIFICATION SECTIONS 028213.21 AND 028333.13 AND THE CONTRACT DOCUMENTS FOR ADDITIONAL INFORMATION AND COORDINATION.

K. ABATEMENT WORK SHALL BE PHASED. FOR PROJECT PHASING REFER TO DRAWINGS GI-004 AND GI-005.

L. REFER TO DRAWING AD-104 FOR ACCESS AFTER CEILING DEMOLITION.

ASBESTOS ABATEMENT NOTES

AA-1 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF ALL SECTIONS OF SHEET METAL DUCTWORK ABOVE THE THIRD FLOOR CEILING AND IN THE WALL CHASES AT THE BATHROOMS TO BE DEMOLISHED. THE DUCTS HAVE ASBESTOS-CONTAINING FLANGE SEALANT INTERMITTENTLY ON SEAMS AND EDGES. ALL SECTIONS OF DUCT TO BE REMOVED SHALL BE CUT INTO SECTIONS AND WRAPPED IN TWO LAYERS OF 6-MIL FIRE RETARDANT POLY SHEETING PRIOR TO REMOVAL FROM THE REGULATED ABATEMENT WORK AREA. REMOVE ALL ASBESTOS-CONTAINING FLANGE SEALANT 12 INCHES BEYOND THE LIMITS OF DEMOLITION ON DUCTS TO REMAIN AND PREPARE FOR INSTALLATION/CAPPING BY OTHER TRADES.

REFER TO MECHANICAL DEMOLITION DRAWINGS FOR APPROXIMATE LOCATIONS OF DUCT REMOVAL.

AA-2 CONTRACTOR SHALL PROPERLY MAKE ALL PENETRATIONS INTO EXISTING SHEET METAL DUCTS IN THE VERTICAL CHASE TO ACCOMMODATE NEW DUCT TIE-IN AND ACCESS DOOR INSULATION AND NEW ENERGY RECOVERY COIL INSTALLATION. THE EXISTING DUCTS HAVE ASBESTOS-CONTAINING FLANGE SEALANT INTERMITTENTLY ON SEAMS AND EDGES. WRAP REMOVED SECTIONS OF DUCT IN TWO LAYERS OF 6-MIL FIRE RETARDANT POLY SHEETING PRIOR TO REMOVAL FROM THE REGULATED ABATEMENT WORK AREA. PREPARE DUCT SURFACES FOR

INSTALLATION OF ACCESS DOORS OR CONNECTIONS WITH NEW DUCTS.

AA-3 NOT USED.

AA-4 NOT USED.

AA-5 NOT USED.

AA-6 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF ALL PIPE INSULATION ABOVE THE SUSPENDED CEILING AND IN THE WALL CHASE AT THE THIRD FLOOR BATHROOMS TO BE DEMOLISHED. THERE IS ASBESTOS-CONTAINING END-SEALANT ON THE FIBERGLASS PIPES INSULATION. REMOVE ALL PIPE INSULATION ON PIPING IN THE CHASES AND ABOVE THE CEILING AT THE LIMITS OF DEMOLITION AND SEAL THE ENDS OF REMAINING INSULATION WITH WETTED CLOTH. REFER TO PLUMBING DEMOLITION DRAWINGS FOR APPROXIMATE LOCATIONS AND EXTENT OF PIPING REMOVAL.

CONTRACTOR SHALL BE RESPONSIBLE FOR THE DEMOLITION OF THE CHASES AS REQUIRED TO ACCESS THE ASBESTOS INSULATION AND TO

ALLOW FOR THE CAPPING OF PLUMBING LINES.

AA-8 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF DESIGNATED SECTIONS OF SHEET METAL DUCTWORK WITH ASBESTOS-CONTAINING FLANGE SEALANT. SECTIONS INCLUDE BOTH BARE METAL AND FIBERGLASS INSULATED DUCTS ABOVE THE HARD CEILINGS, AND SUSPENDED CEILINGS. THE FLANGE SEALANT OCCURS ALONG EDGES AND SEAMS OF THE DUCTS. REMOVE ALL DESIGNATED SECTIONS OF DUCTS UNDER NEGATIVE AIR CONTAINMENT AS PART OF A REGULATED ASBESTOS ABATEMENT WORK AREAS. SECTIONS OF DUCTS WITH THE FLANGE SEALANT SHALL BE WRAPPED WITH 6-MIL POLY SHEETING PRIOR TO REMOVAL FROM THE ABATEMENT WORK AREA. REFER TO MECHANICAL DEMOLITION PLANS FOR PRECISE LOCATIONS AND EXTENT OF DUCTS TO BE REMOVED. ALL REMOVED SECTIONS FO DUCTS WITH TAN FLANGE SEALANT SHALL

BE DISPOSED OF AS ASBESTOS-WASTE.

LEAD AWARENESS NOTES

1. CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLYING WITH OSHA 29 CFR 1926.62: LEAD EXPOSURE IN CONSTRUCTION; INTERIM FINAL RULE FOR ALL ACTIVITIES DURING WHICH AN EMPLOYEE MAY BE OCCUPATIONALLY EXPOSED TO LEAD. ALL CONTRACTORS SHALL ENSURE THAT THEIR EMPLOYEES WEAR PROPER PERSONAL PROTECTIVE EQUIPMENT AND/OR UTILIZE APPROPRIATE WORK METHODS TO PREVENT ELEVATED BLOOD LEAD LEVELS OR EXPOSURE ABOVE THE PERMISSIBLE EXPOSURE LIMIT.

2. AREAS OF THE BUILDING HAVE BEEN INVESTIGATED FOR THE PRESENCE OF LEAD DURING PAST PROJECTS AND LEAD-BASED PAINT HAS

BEEN IDENTIFIED.

3. FURNISHING OF THIS INFORMATION IS NOT INTENDED TO RELIEVE THE CONTRACTOR OF ITS RESPONSIBILITIES UNDER OSHA TO DETERMINE THE PRESENCE, LOCATION, AND QUANTITY OF EXISTING LEAD-CONTAINING MATERIALS THAT THEIR EMPLOYEES AND SUBCONTRACTORS MAY BE EXPOSED TO, AND TO WARN THEIR EMPLOYEES OF THE POTENTIAL DANGERS OF THE DISTURBANCE OF

LEAD-CONTAINING MATERIALS.

VIEW OF ASBESTOS-CONTAINING FLANGE SEALANT ON SHEET METAL DUCTS

ABOVE THE SUSPENDED CEILING IN MEN'S TOILET 315C.

2 PHOTO 1

VIEW OF ASBESTOS-CONTAINING FLANGE SEALANT ON METAL DUCTS AND PIPE

INSULATION WITH ASBESTOS-CONTAINING END SEALANT ABOVE THE SUSPENDED

CEILING IN WOMEN'S TOILET 314C.

3 PHOTO 2

VIEW OF ASBESTOS-CONTAINING FLANGE SEALANT ON SHEET METAL DUCTS

ABOVE THE SUSPENDED HARD PLASTER CEILING IN THE STERILE PROCESSING

SERVICE ROOM 306C.

4 PHOTO 3

AA-1

AA-6

ASBESTOS AWARENESS NOTES

WATTS ARCHITECTS & ENGINEERS HAS PERFORMED A PRE-RENOVATION SURVEY FOR ASBESTOS-CONTAINING MATERIALS FOR THE STERILIZATION PROCESSING SERVICE EQUIPMENT REPLACEMENT PROJECT. A COPY OF THE REPORT IS INCLUDED IN THE CONTRACT DOCUMENTS. ADDITIONAL COPIES CAN BE OBTAINED FROM THE PROJECT MANAGER. FOR ADDITIONAL INFORMATION, REFER TO PRE-RENOVATION SURVEY REPORTS AND

SPECIFICATIONS.

ALL CONTRACTORS SHALL BE AWARE THAT ASBESTOS HAS BEEN DETECTED IN THE FOLLOWING MATERIALS. ANY DISTURBANCE TO ASBESTOS-CONTAINING MATERIALS SHALL BE PERFORMED BY A LICENSED ASBESTOS ABATEMENT CONTRACTOR EMPLOYING CERTIFIED EMPLOYEES.

· TAN FLANGE SEALANT ON SHEET METAL DUCTS THROUGHOUT THE FACILITY. OBSERVED ON BOTH BARE METAL DUCTS AND BENEATH FIBERGLASS

BATT INSULATION.

· WHITE END SEALANT ON FIBERGLASS PIPE INSULATION ON THE SECOND, THIRD, FOURTH AND TWELFTH FLOORS (DOES NOT INCLUDE INSULATION ON

PIPING TO THE EIGHTH FLOOR MEDIVATORS IN ROOM 814A).

· INTERMITTENT SEGMENTS OF CORRUGATED-STYLE AIRCELL PIPE INSULATION ON DOMESTIC WATER PIPES ABOVE THE SECOND FLOOR CEILINGS.

THE ACM AIRCELL PIPE INSULATION IS NOT READILY ACCESSIBLE AND IS NOT ANTICIPATED TO BE DISTURBED BY THIS PROJECT.

· 12” X 12” BEIGE FLOOR TILES IN THE FOURTH FLOOR MACHINE ROOM 437C.

· WHITE END SEALANT AND PAPER AND FOIL JACKET ON FIBERGLASS INSULATION ON PIPING IN THE FOURTH FLOOR MACHINE ROOM 437C.

· CLOTH JACKET AND TAPE ON YELLOW FIBROUS INSULATION ON THE EXTERIOR FACING WALL IN THE FOURTH FLOOR MACHINE ROOM 43C.

· MUD INSULATION ON ROOF DRAINS IN THE TWELFTH FLOOR MACHINE ROOM.

IF ASBESTOS-CONTAINING MATERIALS ARE ACCIDENTALLY DISTURBED, IF UNIDENTIFIED SUSPECT ASBESTOS-CONTAINING MATERIALS ARE DISCOVERED WITHIN PROJECT LIMITS OR UNKNOWN HAZARDOUS MATERIALS, ARE FOUND, CEASE WORK WITHIN THE AFFECTED ARE, CORDON OFF THE AFFECTED AREA OR ROOM AT THE LIMITS OF DISTURBANCE OR THE UNKNOWN MATERIALS, AND CONTACT THE OWNER'S REPRESENTATIVE.

AA-2

ASBESTOS ABATEMENT 3RD FLOOR PLAN

1-HA-103

AA-7

HVAC DUCT

WITH ACM

FLANGE

SEALANT

ABOVE

STERILIZERS

HVAC DUCT WITH

ACM FLANGE

SEALANT ABOVE

HARD CEILING

SPS CLEAN SIDE

AA-7

APPROXIMATE LOCATIONS

OF HARD WALL BARRIERS

TO BE CONSTRUCTED BY

THE GENERAL

CONTRACTOR. REFER TO

G1-004.

PROPOSED

ACCESS

DOOR #1

REFER TO DRAWING AD-104 FOR ACCESS

AFTER CEILING DEMOLITION.

NO DEMOLITION OF THE SECOND FLOOR

CEILING ANTICIPATED FOR PLUMBING WORK.

PROPOSED 3 CHAMBER

DECON & WASTE OUT

ENCLOSURE.

THIS WILL BE A LARGE ASBESTOS ABATEMENT PROJECT

PROPOSED

ACCESS

DOOR #1

TYP.AA-7

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

STAMP

Dwg. of on e ei gh th in ch o ne fo ot

B

A

C

D

E

F th re e in ch es o ne fo ot 6"

6" on e an d on e ha lf in ch es o ne fo ot on e in ch o ne fo ot

6" 6" th re e qu ar te rs in ch o ne fo ot on e ha lf in ch o ne fo ot th re e ei gh th s in ch o ne fo ot on e qu ar te r i nc h on e fo ot

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

528-17-S38

3610 LAWSON ROAD « JAMESTOWN, NY 14701

(716) 484 - 1366 (716) 484 - 1519 FAX

P TRIOT

DESIGN & CONSULTING

STILL SERVING

STERILE PROCESSING SERVICE

EQUIPMENT REPLACEMENT

VA WESTERN NY HEALTHCARE SYSTEM

BUFFALO VA MEDICAL CENTER

3495 BAILEY AVENUE

BUFFALO, NY 14215

AREA OF WORK

95 Perry Street, Suite 300 Buffalo, NY 14203

ISSUED FOR CONSTRUCTION

1/8" = 1'-0"1 PARTIAL 4TH FLOOR PLAN

GENERAL NOTES

A. PERFORM ALL WORK IN ACCORDANCE WITH ALL APPLICABLE LOCAL, STATE, AND FEDERAL RULES, REGULATIONS, GUIDELINES, AND THE CONTRACT

DOCUMENTS.

B. IF ANY PREVIOUSLY-UNIDENTIFIED OR OTHERWISE UNANTICIPATED SUSPECT MATERIAL IS IDENTIFIED DURING CONSTRUCTION, STOP WORK AND NOTIFY THE OWNER OR THEIR REPRESENTATIVE FOR FURTHER DIRECTION. UNDER NO CIRCUMSTANCES SHALL THE CONTRACTOR COLLECT AND/OR ANALYZE BULK SAMPLES OF SUSPECT MATERIALS WITHOUT THE APPROVAL OF THE OWNER OR THEIR REPRESENTATIVE.

C. THE DISTURBANCE OF ANY ASBESTOS-CONTAINING MATERIAL (ACM), OR SUSPECT ACM, SHALL BE PERFORMED BY A LICENSED ASBESTOS

ABATEMENT CONTRACTOR.

D. ALL MATERIAL MEASUREMENTS AND/OR QUANTITIES AND LOCATIONS ARE APPROXIMATE AND FOR GENERAL ORIENTATION ONLY.

E. THE LOCATION OF SITE STORAGE OF MATERIAL, EQUIPMENT, WASTE TRAILER/DUMPSTER(S), AS WELL AS CONTRACTOR PARKING, ETC. SHALL BE

COORDINATED WITH AND APPROVED BY THE OWNER/OWNER'S REPRESENTATIVE.

F. CONTRACTOR IS RESPONSIBLE FOR ALL TOOLS, EQUIPMENT, AND SUPPLIES. CONTRACTOR IS ALSO RESPONSIBLE FOR PROVIDING LADDERS, SCAFFOLDING, LIFTS, PLANKING, ETC. AS REQUIRED TO PERFORM WORK. THE OWNER OR THEIR REPRESENTATIVE WILL NOT BE RESPONSIBLE FOR

LOST, DAMAGED, OR STOLEN ITEMS.

G. THE CONTRACTOR IS RESPONSIBLE FOR KEEPING THE WORK AREA IN A CLEAN AND SAFE CONDITION, PROVIDING TEMPORARY PROTECTION, PROTECTING BUILDING MATERIALS SCHEDULED TO REMAIN, AND TO PREVENT UNAUTHORIZED ACCESS DURING THE DURATION OF THE PROJECT.

REPAIR OF DAMAGE CAUSED AS A RESULT OF INADEQUATE TEMPORARY PROTECTION OR CONTRACTOR ACTIVITIES WILL BE THE RESPONSIBILITY OF

THE CONTRACTOR.

H. ALL REMOVED ASBESTOS-CONTAINING MATERIALS AND ASBESTOS-CONTAMINATED WASTE SHALL BE PROPERLY PACKAGED PRIOR TO BEING REMOVED FROM THE WORK AREA(S). WARNING LABELS SHALL BE APPLIED TO ASBESTOS WASTE CONTAINERS AS APPROPRIATE. ALL ASBESTOS-CONTAINING MATERIALS/ASBESTOS-CONTAMINATED WASTE REMOVED FROM THE WORK AREA(S) SHALL BE ACCOMPANIED BY A WASTE SHIPMENT RECORD. COMPLETED WASTE SHIPMENT RECORDS MUST BE PROVIDED TO THE OWNER AS PART OF THE CLOSEOUT DOCUMENTATION.

ALL ORIGINAL WASTE SHIPMENT RECORDS MUST BE PROVIDED TO THE OWNER WITHIN 35 DAYS OF THE WASTE LEAVING THE SITE.

I. COORDINATE ALL WORK ACTIVITIES WITH THE OWNER/OWNER'S REPRESENTATIVE TO ENSURE ONSITE ACTIVITIES ARE ACCEPTABLE TO THE OWNER, AND THAT REMOVALS ARE SUFFICIENT TO ACCOMMODATE THE PROJECT ACTIVITIES.

J. REFER TO SPECIFICATION SECTIONS 028213.21 AND 028333.13 AND THE CONTRACT DOCUMENTS FOR ADDITIONAL INFORMATION AND COORDINATION.

K. ABATEMENT WORK SHALL BE PHASED. FOR PROJECT PHASING REFER TO DRAWINGS GI-004 AND GI-005.

L. REFER TO DRAWING AD-104 FOR ACCESS AFTER CEILING DEMOLITION.

ASBESTOS ABATEMENT NOTES

AA-1 NOT USED.

AA-2 CONTRACTOR SHALL PROPERLY MAKE ALL PENETRATIONS INTO EXISTING SHEET METAL DUCTS IN THE VERTICAL CHASE TO ACCOMMODATE NEW DUCT TIE-IN AND ACCESS DOOR INSULATION AND NEW ENERGY RECOVERY COIL INSTALLATION. THE EXISTING DUCTS HAVE ASBESTOS-CONTAINING FLANGE SEALANT INTERMITTENTLY ON SEAMS AND EDGES. WRAP REMOVED SECTIONS OF DUCT IN TWO LAYERS OF 6-MIL FIRE RETARDANT POLY SHEETING PRIOR TO REMOVAL FROM THE REGULATED ABATEMENT WORK AREA. PREPARE DUCT SURFACES FOR INSTALLATION OF ACCESS DOORS OR CONNECTIONS WITH NEW DUCTS. CONTRACTOR IS RESPONSIBLE FOR ALL DEMOLITION REQUIRED TO

ACCESS AND REMOVE SEALANT.

AA-3 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF THE ASBESTOS-CONTAINING 12” X 12” FLOOR TILE. THE FLOOR TILE MASTIC IS NON-ASBESTOS. CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL OF ANY ITEMS, CABINETS OR EQUIPMENT THAT ARE ON TOP OF THE FLOOR TILE. THE MASTIC SHALL BE REMOVED AFTER CLEARANCE SAMPLES ARE OBTAINED. IF SOLVENT IS USED NEUTRALIZE PER MANUFACTURER'S INSTRUCTIONS TO ALLOW FOR INSTALLATION OF REPLACEMENT FLOORING BY OTHER TRADES.

AA-4 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF THE ASBESTOS-CONTAINING CLOTH JACKET AND TAPE ON YELLOW FIBROUS INSULATION AT THE WALL IN THE MECHANICAL ROOM LOUVER. REMOVE ALL INSULATION FROM THE WALL AND METAL LOUVER FRAME. THE

JACKET, TAPE AND ASSOCIATED DEBRIS ARE TO BE DISPOSED OF AS ASBESTOS-WASTE.

AA-5 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF ALL ASBESTOS-CONTAINING PIPE INSULATION AND NON-ACM MUD FITTING INSULATION INCLUDING END SEALANT ON PIPING AT THE CEILING OF MECHANICAL ROOM. REFER TO PLUMBING DEMOLITION DRAWINGS FOR APPROXIMATE

LOCATIONS OF PIPING REMOVAL.

AA-6 NOT USED.

AA-7 NOT USED.

LEAD AWARENESS NOTES

1. CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLYING WITH OSHA 29 CFR 1926.62: LEAD EXPOSURE IN CONSTRUCTION; INTERIM FINAL RULE FOR ALL ACTIVITIES DURING WHICH AN EMPLOYEE MAY BE OCCUPATIONALLY EXPOSED TO LEAD.