SOO ATCALS Equipment Infrastructure Upgrade_V2.pdf

PDF 1 MB Posted

Attached to
Air Traffic Control and Landing System Equipment Upgrade
Solicitation number
FA820126R0007
Issued by

About this file

Statement of Objectives Summary

This Statement of Objectives (SOO) defines requirements for an Air Traffic Control and Landing System (ATCALS) Equipment Infrastructure Upgrade at Hill Air Force Base, Utah, with a period of performance of one year post-award. The contractor must engineer, furnish, install, and test (EFI&T) a comprehensive fiber optic telecommunications infrastructure including underground conduit systems, nine new Quazite hand-holes (HH-1 through HH-9), new network equipment cabinets, backboards, and fiber optic distribution panels (FODPs) at multiple locations. The project involves installing approximately 24-strand, 48-strand, and 72-strand single-mode fiber optic cables connecting Building 10 (B10) and Building 1 (B1) to remote air traffic control facilities including Glide Slope (10755), North FMQ-19 (10773), Mid FMQ-19 (10761), South FMQ-19 (10715), and Localizer (10599). All work must comply with current TIA telecommunications installation standards, RUS bulletins for cable and conduit installation, and BICSI outside plant design standards. The contractor shall provide all equipment, tools, materials, labor, and incidental services necessary for project completion.

The contractor must deliver extensive documentation including a Site Visit Request Letter within 5 calendar days of award, weekly status reports, installation schedules, as-built drawings with geospatial data, test plans, and acceptance test reports. All fiber optic cables must undergo comprehensive testing including OTDR and optical power meter tests per TIA 526-7-A standards at 1310 nm and 1550 nm wavelengths. Quality assurance support, monthly integrated process team meetings, and contractor personnel including a dedicated project manager and on-site point of contact are required throughout the project. The contractor must maintain a one-year warranty on all equipment and workmanship, comply with all federal/state/local environmental regulations and Hill AFB-specific safety requirements including confined space entry protocols, obtain required permits (AF Forms 103, 332, and 1024), and provide final acceptance documentation via AFTO 747 form. All deliverables are subject to government acceptance and approval, with professional standards and recommended software tools required. The contractor must be an experienced telecommunications contractor with a minimum of three years of experience in telecommunications systems installations.

View the file

Other files

File Type Posted
ATCALS_Solicitation QandA.pdf PDF
PFAS South Runway Location2_v2.pdf PDF
PFAS North Runway Location_v1.pdf PDF
ATCALS_Solicitation QandA.docx DOCX document
ATCALS_Solicitation QandA.docx DOCX document
ATCALS Deliverables table.pdf PDF
Solicitation - FA820126R0007.pdf PDF
ATCALS Instructions and Evaluation Factors.pdf PDF
ATCALS CDRLs.pdf PDF
WD_ATCALS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF OBJECTIVES (SOO)

For

Air Traffic Control and Landing System (ATCALS) Equipment

Infrastructure Upgrade at

Hill AFB UT

22 Aug 2025

Prepared By

38 ES/ENIU

4064 Hilltop Road

Tinker AFB OK 73145-2713

Page | 2

1.0 Contents

1. SCOPE

2.0 REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 Safety Requirements

2.1.3 Security Requirements

2.1.4 Environmental Compliance

2.1.6 Integrated Process Team (IPT)

2.1.7 Quality Assurance

2.1.8 Contractor Personnel

2.1.9 Warranty

2.1.10 Manuals and Practices

2.2 SPECIFIC REQUIREMENTS

2.2.1 Network Cabinet. N/A

2.2.2 Outside Plant Requirements

2.2.2.1 Existing Maintenance Holes

2.2.2.2 Measurements

2.2.2.3 Underground Utilities Markings

2.2.2.4 Splice Connectors

2.2.2.5 Labeling

2.2.2.6 FOC Terminations

2.2.2.8 Cable Racks and Cable Rack Supports

2.2.2.9 Grounding

2.2.2.10 Underground Conduit System

2.2.3 Requirement Installation

2.2.3.1 Infrastructure Installation

2.2.3.1.4.1 From B10 to B1

2.2.3.1.4.2 From B10 to MH-20016-02

2.2.3.1.4.3 From MH-20016-02 to HH-1

2.2.3.1.4.4 From MH-20016-02 to MH-20017-06

2.2.3.1.4.5 SPLICING at MH-20016-02

In MH-20016-02, the Contractor shall splice the following SM FOCs into new 72-strand SM

FOC. 16

2.2.3.1.4.6 From HH-1 to 10775 (Glide Slope)

Page | 3

2.2.3.1.4.7 From HH-1 to 10773 (Nort FMQ-19)

2.2.3.1.4.8 SPLICING at HH-1

In HH-1, the Contractor shall splice the following SM FOCs into new 24-strand SM FOC. 16

2.2.3.1.4.9 From MH-20017-06 to 10761 (Mid FMQ-19)

2.2.3.1.4.10 From MH-20017-06 to HH-7

2.2.3.1.4.11 SPLICING at MH-20017-06

In MH-20017-06, the Contractor shall splice the following SM FOCs into new 48-strand SM-

FOC. 17

2.2.3.1.4.12 From HH-7 to 10715 (South FMQ-19)

2.2.3.1.4.13 From HH-7 to 10599 (Localizer)

2.2.3.1.4.14 SPLICING at HH-7

In HH-7, the Contractor shall splice the following SM FOCs into new 36-strand SM FOC. 17

2.2.4 Project Residue

2.2.5 Site Restoration

2.2.6 Service Outages

2.2.7 National Pollution Discharge Elimination System (NPDES)

2.2.8 Identification/Marking

2.2.9 Installation Schedules

2.2.10 Weekly Status Reports

2.2.11 Drawings

2.2.12 Test and Acceptance/Installation Test Plan

2.2.12.2 Acceptance/Installation Test Report

2.2.13 Final Acceptance IAW AFTO “747 Cyberspace Infrastructure System

Acceptance”

2.2.14 Deliverable Summary

3.0 GENERAL INFORMATION

3.1 Period of Performance

3.2 Place of Performance

3.3 Hours of Operation

3.4 Holidays/Down Days

3.5 Base Support

4.0 Project Drawing

Page | 4

1. SCOPE.

This Statement Of Objectives (SOO) defines the requirement for the Contractor to engineer, furnish, install and test (EFI&T) the Air Traffic Control and Landing System (ATCALS)

Equipment Infrastructure Upgrade at Hill AFB UT.

The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. The Contractor shall comply with the current TIA telecommunication installation and testing commercial standard and base installation standards. All equipment, supplies, and materials provided shall be new and not refurbished.

This is only a proposed solution. The Contractor may make any recommendations pertaining to the accomplishment of this requirement in their proposal.

2.0 REQUIREMENTS.

2.1 GENERAL REQUIREMENTS.

2.1.1 Safety Requirements.

The contractor shall remain in compliance with all Federal, State, county, and base security and safety laws, regulations, policies, and requirements.

2.1.2 Site Coordination.

The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation. (CDRL 0001)

2.1.2.1 Confined Space.

The Contractors and Sub-contractors entering spaces on Hill AFB UT are responsible for the safety of their personnel and for their own permit space program as outlined in DAFMAN 91-

203. All confined space operations must be coordinated with the Base Safety Office prior to starting work. The primary Contractor is responsible for all Sub-contractor confined space operations.

2.1.2.2 Accident/Incident Reporting and Investigation.

The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel. Notification shall be provided to Base 75

ABW/SCXP Project Manager and the Base Safety Office unless otherwise stated in the SOO.

The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to investigate the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.

2.1.2.3 Work Area(s).

At day’s end, the Contractor shall remove all debris and surplus materials from the workplace.

Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the workday. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard. The contractor shall co-ordinate with Base 75 ABW/SCXP to ensure that any locking manhole covers are put back in place at the end of each workday.

Page | 5

2.1.2.4 Traffic Control.

In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall notify Base 75 ABW/SCXP PM NLT 10 calendar days in advance to inform base Security Forces and Emergency Services personnel of the planned disruptions.

2.1.2.5 Airfield Driving.

Any person operating a motor vehicle inside the airfield fence on Hill AFB UT shall coordinate with airfield management to obtain the required training/certifications IAW local procedures.

2.1.3 Security Requirements.

The Contractor shall process and provide a Site Visit Request Letter to Base 75 ABW/SCXP within 5 calendar days after contract award. (CDRL 0002) This letter shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel who shall be performing work under this SOO. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the

Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations.

2.1.3.1 Security Clearances.

Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work may take place in secure areas where Contractor employees must be always escorted. The Contractor must coordinate access to secure areas at least five (5) calendar days ahead of time. It is the Government’s responsibility to provide escorts.

2.1.3.2 Operational Security (OPSEC).

Network infrastructure drawings (MHDS, MH/HH locations, fiber paths, etc.) are on Base 75

ABW/SCXP Critical Information List and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “Controlled Unclassified Information (CUI),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. IAW AFI 10-701, OPSEC Considerations, the contractor shall follow the OPSEC guidance/plan (AFI10-701) to ensure the protection of CUI data either furnished by the government or produced by the contractor.

2.1.4 Environmental Compliance.

The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations, and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The Contractors are responsible to know and follow all applicable Federal, State, Local and Air Force regulations for environmental protection, including waste disposal, sewer discharge, air emissions, and storm water requirements. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Hill AFB UT. The Prime

Contractor shall ensure that their subcontractors (if any) comply with these specifications.

2.1.5 Permits.

The Contractor shall be responsible to coordinate, complete and process all permits required to complete the installation prior to any trenching, horizontal directional boring or modifications to a

Page | 6 facility, maintenance hole (MH) or hand-hole (HH). For example:

• Digging permit, AF Form 103 shall be submitted through BCE 14 calendar days in advance of digging activities. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 remains current.

• Confine space entry permit, AF Form 1024 shall be coordinated through base safety office. The Contractor shall be prepared to provide proof of their Confined Space

Training Program along with the AF Form 1024 to base safety.

• Base Civil Engineering Work Clearance Request, AF Form 332 shall be submitted through BCE 14 calendar days in advance of planned work.

• The Contractor shall trench, excavate, and mark and barricade open trenches IAW

OSHA Standards.

All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them and ensure that the AF Form 103 remains current. The contractor shall take precautions to protect existing infrastructure. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage.

2.1.6 Integrated Process Team (IPT).

The Contractor shall chair a monthly/or as needed an IPT meeting that includes Contractor representatives, the Government Contracting Officer (CO), the CSI-B, the System Engineer(s), the Government Project Manager, and other base personnel as required. The Contractor shall provide an agenda NLT 1 working day prior to the scheduled meetings. The Contractor shall provide worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other necessary information to ensure success and timely completion of contract requirements. The

Contractor shall record meeting minutes and distribute to the attendees NLT 1 working day after each meeting. (CDRL 0003)

2.1.7 Quality Assurance.

The Contractor shall provide Quality Assurance Support for the entire life of the project. The

Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and/or discrepancies throughout the life of the project. A weekly report (soft copy) shall be delivered/submitted to COR by COB

Monday, indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them. (CDRL 0004)

2.1.8 Contractor Personnel.

2.1.8.1 Project Management.

The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation. (CDRL 0005)

2.1.8.2 Site Point of Contact (POC).

The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site

POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours for the duration of the project, up to and until final acceptance by the

Page | 7

Government PM and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the Government, including quality, safety, and discrepancy matters. (CDRL 0005)

2.1.8.3 Personnel Requirements.

The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English and shall be on site to coordinate permits, clearances, and receive shipments/material related to the task order.

2.1.8.4 Minimum Contractor Qualifications.

All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.

2.1.8.5 System for Award Management (SAM).

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Installation via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address https://www.sam.gov .

Reporting inputs shall be for the labor executed during the period of performance during each

Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. (CDRL 0006) Contractors may direct questions to the SAM help desk.

2.1.9 Warranty.

The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. The warranty shall be, at a minimum, IAW the standard or equivalent. This warranty shall include a one year workmanship warranty. The warranty period shall start from the date of system and/or project acceptance. The Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.

2.1.10 Manuals and Practices.

The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practices/users guide for each system installed as provided by the original manufacturer with all new equipment. (CDRL 0007)

2.2 SPECIFIC REQUIREMENTS.

As indicated in this SOO and attached Project Drawing, the Contractor shall EFI&T the

ATCALS Equipment Upgrade from B10 to the following locations along with associated fiber distribution panels (FODPs) plus all associated splicing and termination.

• B1 (24-strand SM FOC)

• 10755 (Glide Slope) (12-strand SM FOC)

• 10773 (North FMQ-19) (12-strand SM FOC)

• 10761 (Mid FMQ-19) (12-strand SM FOC)

• 10715 (South FMQ-19) (12-strand SM FOC)

• 10599 (Localizer) (12-strand SM FOC) https://www.sam.gov/

Page | 8

2.2.1 Network Cabinet. N/A

2.2.2 Outside Plant Requirements.

2.2.2.1 Existing Maintenance Holes.

The Contractor shall be responsible for pumping out maintenance holes/handholes. Water from maintenance holes/handholes shall be drained onto grass, when possible, to act as a natural filter; then it may be pumped out onto the surrounding ground, as long as there is no impact on roads, driveways, or vehicle traffic. Mud and debris shall be disposed of IAW base requirements. If Contractor comes across a manhole with contaminated water, the Contractor shall coordinate with the environmental office in Base CE.

2.2.2.2 Measurements.

Any distances provided in this SOO are approximated and should NOT be used for ordering materials or determining duct lengths.

2.2.2.3 Underground Utilities Markings.

The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or horizontal directional boring and shall take precautions to protect existing infrastructure. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings and for ensuring AF Form 103 (Dig Permit) remains current.

2.2.2.4 Splice Connectors.

All splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for

Splicing.

2.2.2.5 Labeling.

The Contractor shall label all equipment and cables they install, and cables identified for re-use in accordance with TIA-606-C and as directed by Base 75 ABW/SCXP.

2.2.2.5.1 New Ducts.

New ducts shall be permanently labeled on the wall of each building/Maintenance hole

(MH)/Handhole (HH) indicating the connecting building/Maintenance hole/Handhole at the other end of the duct (for example, “To MH-306H”). The same information shall appear on the

Contractor’s completed as-built-drawings.

2.2.2.5.2 Fiber Optic Distribution Panel (FODP) Marking.

Each FODP shall be stenciled/marked with black ink or paint or adhesive backed decals in letters and numbers. The cover of all new fiber optic distributions (FODPs) shall be labeled to conform to the system used by local maintenance personnel to identify FODPs that terminate fiber. If the manufacturer has not identified the sequence in which ports on FODPs (pigtail modules) are counted, the Contractor shall provide designation labels/strips to identify the sequence in which they are counted. Each splice tray shall be marked to identify the fiber count contained in the splice tray. The marking shall identify the FODP by number (building number), cable number, and count.

Example (FODP): FODP 10 - 1, 1-24 SM

Page | 9

2.2.2.5.3 FOC Tags.

All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand-holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a maintenance-hole, put a tag on the cable, approximately 2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. Tagging and labeling of new cables shall be IAW the following:

Example (FOC Tag): 24L8.3F

FO 10 - 1, 1-24

First line: “24” stands for Fiber Count. “L” stands for Loose Tube Buffer or (“T”) for Tight Tube

Buffer. “8.3” stands for Single Mode. “F” stands for Filled Core (otherwise leave blank).

Second line and following: “FO” stands for Fiber Optic cable. “10 - 1” stands for from building number 10 to 1 “1-24” stands for Cable/Strand Count.

2.2.2.6 FOC Terminations.

Fiber optic cable termination shall be LC connectors, with no splicing (home run installation), and no jumpers.

2.2.2.7 FOC Maintenance Loop.

The Contractor shall install a minimum of a 50 foot fiber optic cable maintenance loop at the first MH from the building, at each splice point MH location and at every third manhole. The maintenance loop shall be properly labeled and securely supported by two cable hooks. Cable hooks are to be positioned so the highest one supports the underside of the top of the coil and the bottom hook supports the underside of the bottom of the coil. The maintenance loop shall have a cable tag. The same information shall appear on the Contractor’s completed as-built-drawings.

2.2.2.8 Cable Racks and Cable Rack Supports.

Cable racks shall be installed in maintenance holes and hand holes as required - this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case.

Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips.

All cables shall be supported using racking clips, cable racks, and cable hooks.

2.2.2.9 Grounding.

Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.

necessary to properly bond/ground the cable in HHs shall be provided by the Contractor.

Reference ANSI/TIA 607

2.2.2.10 Underground Conduit System.

The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Provide a minimum of 12" cover of clean fill above the conduit. Backfill material shall be clean and free from all organic material, clay, marl or unstable materials, debris, lumps, or broken paving. No rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation, if it meets the above requirements. Directional drilling shall be used for major road

Page | 10 crossings. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts shall be appropriately protected when placed under paved surfaces.

2.2.2.10.1 Composition.

The ducts shall be corrosion resistant and 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW

NEMA TC-2. For unique situations the ducts shall be EPC-80-PVC (Schedule 80) IAW NEMA

TC-2, high density polyethylene (HDPE) SIDR 11.5, Galvanized Iron Pipe (GIP) or “thickwall” stainless steel. Schedule 80 PVC shall be limited to risers. High density polyethylene (HDPE)

SIDR 11.5 shall be used when directional boring is used. GIP or stainless steel shall be used under taxiways and runways. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.

2.2.2.10.2 Installation.

Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS

Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. Ducts installed beneath roads and parking areas shall be protected. It is understood that in some locations, especially at paved surface crossings, the Contractor may bore and substitute 4-inch

I.D. HDPE conduit (Roll pipe, suitable for the application) for 4-inch PVC conduit. Also, if

HDPE is used, it shall be SIDR 11.5 so that the inside diameter of the HDPE shall match the inside diameter of the PVC. HDPE shall not be placed directly into a MH. The Contractor shall transition to PVC from HDPE prior to terminating conduit into these structures. In maintenance holes (MH) with knockouts, conduits shall start at the bottom knockout, allowing for upward future expansion.

All ducts did not install a crossroads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts and drain slope of ducts shall be accomplished IAW BICSI

Outside Plant Design Reference Manual (OSPDRM) and RUS Bulletin 1751F-643. Do not allow the ducts to twist or tangle between Maintenance holes.

2.2.2.10.3 Paved Surface Crossings.

The Contractor shall cut and restore, and/or horizontal directional drilling (HDD) to cross paved surfaces. Paved surfaces may be asphalt, concrete, brick, or some type of paving stone. Paved surfaces include roads, driveways, sidewalks and parking lots. Paved surface crossings shall be

IAW guidelines set forth by the base civil engineer (BCE). At a minimum, grade of PVC conduit at open trench paved surface crossings, or crossings which are planned for paving in the future, shall be Schedule 40 and shall be concrete encased. If horizontal directional drilling

(HDD) is used, then it shall be following commonly accepted telecommunications industry standards and practices relative to the installation, stabilization, and protection of conduits through a bore under a paved surface. The decision whether to trench (cut and patch) across or

Page | 11 horizontal directionally drill under paved surfaces is at the discretion of the BCE and shall be made on a case-by-case basis.

2.2.2.10.4 Bends and Sealing.

All bends between MHs/HHs shall be a minimum of ten times (10X) the diameter of the duct size (i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of

90 degrees where practical. Coordinate with Base 75 ABW/SCXP if runs have bends that total more than 90 degrees is required. Ducts shall have bell ends and enter a MH/HH perpendicular to the surface of the wall through which it is entering. All ducts/innerducts entering MH/HH shall be sealed. Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment.

In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.

2.2.2.10.5 Utility Separation.

When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.

2.2.2.10.6 Spacers and Tracer Wire.

Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals. At least one duct or roll pipe shall have tracer wire or be otherwise locative from the surface. All new tracer wire installed for this project needs to have a wire nut and label installed at all wire ends, and those wire ends secured but not connected to grounds.

The tracer wire shall be exposed; free from the conduit and capped (insulated). The tracer shall be secured and routed to the maintenance hole or hand-hole neck to a point where maintenance personnel may access the wire without having to enter the maintenance hole/hand-hole and tagged with a label so indicating it as a “Duct Tracer Wire to xxx – Do Not Remove (where xxx is the other end of the wire).” Tracer wires shall not be connected to any grounding system.

Tracer wire shall be pulled back from building entrances until it is underground to prevent lightning damage.

2.2.2.10.7 Warning Tape.

Cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route.

The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.

2.2.2.10.8 Entrance Conduits into Existing Maintenance Holes.

When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if knockout doesn’t exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts shall be a minimum of 18 inches from either the floor or ceiling of the maintenance hole if practical. Ducts shall have bell ends and enter the maintenance hole perpendicular to the surface of the wall through which it is entering and shall be installed flush with the interior wall of the maintenance hole. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.

Page | 12

2.2.2.10.9 Conduit Protection.

The Contactor shall install the appropriate physical protection required for buried PVC conduits or HDPE Roll pipe, consistent with commonly accepted telecommunications industry practices relative to the task and to the environment in which they are installed and the loads (H-5, H-10, H-20, railroads, flight line, etc.) to which they are expected to be exposed. Type of protection may be dependent upon the specific application and shall be IAW applicable federal, state or local (Hill AFB Civil Engineering construction requirements) procedures. However, at a minimum, nonmetallic conduits shall be encased in concrete of minimum 3000 lb. /in2 compressive strength where vehicular traffic is above the pathway. The encasement shall be concrete of a wet type mix and shall be placed in such a manner as to ensure the concrete completely surrounds all conduits and no air voids are trapped in the mix a bend or sweep is placed in PVC nonmetallic duct bank between maintenance holes; the duct bank must be encased in concrete with a minimum compressive strength of 3000 pounds per square inch (psi).

2.2.2.10.10 Pull Tape.

All newly installed ducts left vacant shall be provided with a pull tape with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the maintenance holes/hand-holes and be secured to a cable rack or pulling iron, etc.

2.2.2.11 Excavation/Building Penetrations.

All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.

2.2.3 Requirement Installation.

This section describes the underground maintenance hole/conduit system, flexible geotextile multiple cell fabric inner-duct and fiber optic cable installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in according with TIA-758-B. Each cable installation shall be coordinated with Base 75

ABW/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.

See Project Drawing below for reference and estimated distances of existing and proposed infrastructure and cables routes. This is only a proposed solution.

The Contractor shall install underground outside plant infrastructure as described below.

2.2.3.1 Infrastructure Installation.

The contractor shall install the following new infrastructure. All new locations and distances are approximate. (Reference Project Drawing)

2.2.3.1.1 New Quazite Boxes.

The Contractor shall install nine (9) 30"x48"x36" Quazite Boxes (to be designated as HH-1, HH-

2, HH-3, HH-4, HH-5, HH-6, HH-7, HH-8 & HH-9). The approximate locations are shown on the Project Drawing. Coordinate with Base 75 ABW/SCXP for final Quazite Boxes details for installations.

Page | 13

2.2.3.1.2 New NEMA 4x Enclosure & Unistrut.

The Contractor shall install Unistrut framing and mount a NEMA 4x Enclosure (12”H x 12”W x

6”D) at 10773 (North FMQ-19), 10761 (Mid FMQ-19) & 10715 (South FMQ-19). The NEMA

4x Enclosure shall meet the rating (stainless steel, weather roof, corrosion, etc.). The final location and detail of the Unistrut & NEMA 4x Enclosure shall be provided by 75 ABW/SCXP.

2.2.3.1.3 New Backboard (BB).

The Contractor shall install one each BB at the following locations. The location of the backboard shall be provided by 75 ABW/SCXP.

• B1, Comm Room 201

• 10744 (Glide Slope) shelter

• 10773 (Localizer) shelter.

Newly installed backboards shall be AF-standard 0.75”-thick plywood, with two coats of white, fire-resistant paint.

2.2.3.1.4 New Fiber Optic Distribution Panel (FODP).

The Contractor shall install the FODPs at the locations below. Base 75 ABW/SCXP shall provide the final location of FODPs.

• B10: One 96-port FODP in existing rack

• B1: One 24-port FODP on the new wall mounted BB

• 10755 (Glide Slope): One 12-port FODP on the new wall mounted BB

• 10773 (North FMQ-19): One 12-port FODP in a new NEMA Box

• 10761 (Mid FMQ-19) : One 12-port FODP in a new NEMA Box

• 10715 (South FMQ-19): One 12-port FODP in a new NEMA Box

• 10599 (Localizer): One 12-port FODP on the new wall mounted BB

2.2.3.1.5 Duct bank Infrastructure.

2.2.3.1.5.1 The Contractor shall install approximately 2 feet of 1x4” conduit from MH-

20015-21 to MH-20015-34.

2.2.3.1.5.2 The Contractor shall install 1.25” HDPE Conduit Armor Guard as shown Table below

From To

Distance

(Feet)

Quantity Notes

MH-19016-02 HH-3 1,250 1 Trenching

HH-3 HH-2 1,250 1 Trenching

HH-2 HH-1 1,100 1 Trenching

HH-1 10775 (Glide

Slope) 25

1 Trenching/road cut then transition

2” conduit to existing J-Box at outside Glide Slope Shelter

HH-1 10773 (North

FMQ-19) 35

1 Trenching/road cut then transition

2” conduit to new NEMA Box

Page | 14

MH-20017-06 HH-4 1,250 1 Trenching

HH-4 10761 (Mid

FMQ-19) 825

1 Trenching then transition 2” conduit to new NEMA Box

MH-20017-06 HH-5 1,250 1 Trenching

HH-5 HH-6 1,250 1 Trenching

HH-6 HH-7 1,200 1 Trenching

HH-7 10715 (South

FMQ-19) 10

1 Trenching then transition 2” conduit to new NEMA Box

HH-7 HH-8 1,350 1 Trenching

HH-8 HH-9 1,300 1 Trenching

HH-9 10599

(Localizer) 10

1 Trenching then transition 2” conduit to existing J-Box at outside

Localizer Shelter

2.2.3.1.5.3 Geotextile Innerduct.

Install 1-3”x3 Geotextile Innerducts as shown in the table below. Each three cells shall have a separate thread color, and one of the three cells shall be detectable.

From To

Distance

(Feet)

Quantity Notes

MH-20015-16 B10, First Floor 50 1 Override in existing conduit

MH-20015-16 MH-20015-19 125 1 Override in existing conduit

MH-20015-21 MH-20015-34 2 1 In new conduit

MH-20015-32 MH-20015-31 2 1 Override in existing conduit

MH-20015-31 B1, J-Box 20 1 Override in existing conduit

MH-20016-02 MH-20016-01 655 1 In existing conduit

MH-20016-01 MH-19015-08 540 1 In existing conduit

MH-19015-08 MH-19015-02 555 1 In existing conduit

MH-19015-02 MH-19016-01 460 1 Override in existing conduit

MH-19016-01 MH-19016-02 195 1 Override in existing conduit

2.2.3.1.4 Fiber Optic Cable Installation.

The Contractor shall install single mode (SM), loose buffer tube, water blocked, outside plant

(OSP) fiber optic cable (FOC) suitable for underground applications. The intent is to install the cable in one continuous length, to the extent that it is practical. The cable shall meet RUS 7 CFR

1755.900 criteria; shall comply with industry standards with regard to manufacturers’ cable marking, jacket, rip cords, water blocking, fiber color coding, jacketing materials, etc. In addition, the FOC shall comply with industry standards with regard to mode field diameter, core cladding concentricity, attenuation, and dispersion characteristics at 1310 nm and 1550nm.

Page | 15

All fiber optic cables shall be installed in new or existing geotextile innerduct/innerduct.

2.2.3.1.4.1 From B10 to B1.

The Contractor shall install approximately 950 feet (Included Maintenance Loop) of 24-strand

SM FOC from B10, Second Floor, Comm Room to B1, Comm Room 201. Terminate 24-strand

SM FOC in a new 96-port FODP in B10, and in a new 24-port FODP in B1.

FROM TO

Distance

(Feet) Notes

B10, 2nd Floor B10, 1st Floor 20 In new corrugated innerduct

B10, 1st Floor MH-20015-16 50 In new Geotextile Innerduct

MH-20015-16 MH-20015-19 125 In new Geotextile Innerduct

MH-20015-19 MH-20015-20 165 In existing Geotextile Innerduct

MH-20015-20 MH-20015-21 50 In existing Geotextile Innerduct

MH-20015-21 MH-20015-34 2 In new Geotextile Innerduct

MH-20015-34 MH-20015-32 265 In existing Geotextile Innerduct

MH-20015-32 MH-20015-31 2 In new Geotextile Innerduct

MH-20015-31 B1, J-Box 20 In new Geotextile Innerduct

B1, J-Box B1, Comm Rm 201 25 In new corrugated innerduct

2.2.3.1.4.2 From B10 to MH-20016-02.

The Contractor shall install approximately 900 feet (Included Maintenance Loop) of 72-strand

SM FOC from B10, Second Floor, Comm Room to MH-20016-02. Terminate 72-strand SM

FOC in a new 96-port FODP in B10.

FROM TO

Distance

(Feet) Notes

B-10, 2nd Floor B-10, 1st Floor 20 In new corrugated innerduct

B-10, 1st Floor MH-2015-16 50 In new Geotextile Innerduct

MH-20015-16 MH-20015-19 125 In new Geotextile Innerduct

MH-20015-19 MH-20015-17 155 In existing Geotextile Innerduct

MH-20015-17 MH-20016-02 370 In existing Geotextile Innerduct

2.2.3.1.4.3 From MH-20016-02 to HH-1

The Contractor shall install approximately 6,300 feet (Included Maintenance Loop) of 24-strand

SM FOC from MH-20016-02 to HH-1.

FROM TO

Distance

(Feet) Notes

MH-20016-02 MH-20016-01 655 In new Geotextile Innerduct

MH-20016-01 MH-19015-08 540 In new Geotextile Innerduct

Page | 16

MH-19015-08 MH-19015-02 555 In new Geotextile Innerduct

MH-19015-02 MH-19016-01 460 In new Geotextile Innerduct

MH-19016-01 MH-19016-02 195 In new Geotextile Innerduct

MH-19016-02 New HH-3 1,250 In new Armor Guard conduit

New HH-3 New HH-2 1,250 In new Armor Guard conduit

New HH-2 New HH-1 1,150 In new Armor Guard conduit

2.2.3.1.4.4 From MH-20016-02 to MH-20017-06

The Contractor shall install approximately 3,200 feet (Included Maintenance Loop) of 48-strand

SM FOC from MH-20016-02 to MH-20017-06.

FROM TO

Distance

(Feet) Notes

MH-20016-02 MH-20016-03 585 In existing innerduct

MH-20016-03 MH-20016-06 245 In existing innerduct

MH-20016-06 MH-21016-01 675 In existing innerduct

MH-21016-01 MH-20016-07 400 In existing innerduct

MH-20016-07 MH-20016-04 290 In existing innerduct

MH-20016-04 MH-20016-05 140 In existing innerduct

MH-20016-05 MH-20017-06 620 In existing innerduct

2.2.3.1.4.5 SPLICING at MH-20016-02.

In MH-20016-02, the Contractor shall splice the following SM FOCs into new 72-strand SM

FOC.

• 24-strand SM FOC (Reference Para 2.2.3.1.4.3)

• 48-strand SM FOC (Reference Para 2.2.3.1.4.4)

2.2.3.1.4.6 From HH-1 to 10775 (Glide Slope).

The Contractor shall install approximately 75 feet (Included Maintenance Loop) of 12-strand SM

FOC from HH-1 to 10755 (Glide Slope). Terminate 12-strand SM FOC in new 12-port FODP in

10755 (Glide Slope).

2.2.3.1.4.7 From HH-1 to 10773 (Nort FMQ-19).

The Contractor shall install approximately 85 feet (Included Maintenance Loop) of 12-strand SM

FOC from HH-1 to 10773 (North FMQ-19). Terminate 12-strand SM FOC in new 12-port FODP in 10773 (North FMQ-19), NEMA Box.

2.2.3.1.4.8 SPLICING at HH-1.

In HH-1, the Contractor shall splice the following SM FOCs into new 24-strand SM FOC.

• 12-strand SM FOC (Reference Para 2.2.3.1.4.6)

• 12-strand SM FOC (Reference Para 2.2.3.1.4.7)

Page | 17

2.2.3.1.4.9 From MH-20017-06 to 10761 (Mid FMQ-19).

The Contractor shall install approximately 2,200 feet (Included Maintenance Loop) of 12-strand

SM FOC from MH-20017-06 to 10761 (Mid FMQ-19). Terminate 12-strand SM FOC in new

12-port FODP in 10761 (Mid FMQ-19), NEMA Box.

FROM TO

Distance

(Feet) Notes

MH-20017-06 New HH-4 1,250 In new Armor Guard conduit

New HH-4 10761 (Mid FMQ-19) 825 In new Armor Guard conduit

2.2.3.1.4.10 From MH-20017-06 to HH-7.

The Contractor shall install approximately 3,900 feet (Included Maintenance Loop) of 36-strand

SM FOC from MH-20017-06 to HH-7.

FROM TO

Distance

(Feet) Notes

MH-20017-06 New HH-5 1,250 In new Armor Guard conduit

New HH-5 New HH-6 1,250 In new Armor Guard conduit

New HH-6 New HH-7 1,300 In new Armor Guard conduit

2.2.3.1.4.11 SPLICING at MH-20017-06.

In MH-20017-06, the Contractor shall splice the following SM FOCs into new 48-strand SM-

FOC.

• 12-strand SM FOC (Reference Para 2.2.3.1.4.9)

• 36-strand SM FOC (Reference Para 2.2.3.1.4.10)

2.2.3.1.4.12 From HH-7 to 10715 (South FMQ-19).

The Contractor shall install approximately 50 feet (Included Maintenance Loop) of 12-strand SM

FOC from HH-7 to 10715 (South FMQ-19), NEMA Box.

2.2.3.1.4.13 From HH-7 to 10599 (Localizer).

The Contractor shall install approximately 2,900 feet (Included Maintenance Loop) of 12-strand

SM FOC from HH-7 to 10599 (Localizer). Terminate 12-strand SM FOC in new 12-port FODP in 10599 (localizer).

FROM TO

Distance

(Feet) Notes

New HH-7 New HH-8 1,350 In new Armor Guard conduit

New HH-8 New HH-9 1,350 In new Armor Guard conduit

New HH-9 10599 (Localizer) 10 In new Armor Guard conduit

2.2.3.1.4.14 SPLICING at HH-7.

In HH-7, the Contractor shall splice the following SM FOCs into new 36-strand SM FOC.

• 12-strand SM FOC (Reference Para 2.2.3.1.4.12)

• 12-strand SM FOC (Reference Para 2.2.3.1.4.13)

Page | 18

2.2.4 Project Residue.

All residue from this project shall be disposed of off base and in accordance with Federal, State, local and base environmental laws and regulations. All residue produced by horizontal directional boring operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal and state environmental laws and regulations. Under no circumstances shall the contractor stage or store boring residue in slurry ponds or other containment areas on Hill AFB UT.

2.2.5 Site Restoration.

The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. The Contractor shall comply with all base ground’s restoration requirements.

Common use areas shall be restored with sod.

2.2.6 Service Outages.

The Contractor shall be responsible for preventing any unscheduled (i.e., cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).

2.2.7 National Pollution Discharge Elimination System (NPDES).

If required by Base Civil Engineer (BCE), the Contractor shall obtain approvals for NPDES at

State and/or Federal level [in some locations this may be called the Storm Water Pollution

Prevention Plan (SWPPP)]. The storm water/environmental plan is the sole responsibility of the

Contractor. Base Civil Engineering/CEV shall review and advise to ensure minimum standards and storm water controls/BMPs are in place to ensure compliance; this is a compulsory item in the SOO and contract. The Contractor shall implement storm water controls/BMPs to ensure sediment, as a result of storm water runoff, does not enter storm drainage channels and/or inlets.

The Contractor shall conduct an initial meeting within 10 days of the Contractor site survey with the base environmental office to identify NPDES preparations and/or the storm water/environmental plan.

The Contractor shall review the NPDES requirements applicable to the base; develop a plan to comply with the NPDES; obtain approval of the NPDES plan from all appropriate government agencies; and comply with any other applicable state requirements for construction

2.2.8 Identification/Marking.

The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign

(minimum 8.5" x 11") on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the Contractor and

Site POC's names and local telephone numbers.

2.2.9 Installation Schedules.

The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system. All submissions shall be delivered electronically

Page | 19 in MS Office-compatible format NLT 10 business days after contract award and as significant schedule changes occur to be determined by the IPT. (CDRL 0008)

2.2.10 Weekly Status Reports.

The Contractor shall prepare a Weekly Status Report and distribute to the Government

Contracting Officer (CO), the System Engineer(s), the Government Project Manager, and other base personnel as required. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements. (CDRL 0009)

2.2.11 Drawings.

2.2.11.1 As-Built Drawings.

Base 75 ABW/SCXP shall supply existing system drawings, and the Contractor shall provide updated drawings in Visio for building and rack elevation; Visio and .pdf for OSP. These drawings shall depict the entire pathway and details of the installation, including but not limited to labeling, cables, innerducts and maintenance holes/handholes, conduits, maintenance loops, distances, bores, trenches, building entrances. Detailed butterfly drawings are also required. If the existing cable diagram or butterfly drawings are not available, the contractor shall create the missing cable diagram/ butterfly drawings to include all the components used in this project.

The Contractor shall record/deliver geospatial data of new outside plant distribution system.

(CDRL 0010)

2.2.11.2 Butterfly Drawings.

The Contractor shall record and submit butterfly, cable path and building penetration drawing information for all new installations including butterfly drawings for all maintenance holes and pull boxes that contain new or reused FOC. Drawings shall record the path and arrangement of new and reused fiber optic cables, splices, and the arrangement duct banks, ducts, inner-duct and shall show maintenance hole orientation with respect to geodetic north. Drawings shall be submitted in an easily read electronic format such as pdf. Scanned data sheets or legible Drawings are acceptable. (CDRL 0010)

2.2.11.3 Geospatial Deliverables.

The Contractor shall collect and record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole/duct system components and new cable components

(including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS)

Visualization Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand-hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The government shall review the shape files and transcribe the information to the CVC system. Provide geospatial data via CD as

Environmental Systems Research Institute (ESRI) Shape files. Shape files shall be delivered within 30 days of project completion. (CDRL 0011)

2.2.12 Test and Acceptance/Installation Test Plan.

The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested. Draft Cut-over Test Plan shall be submitted NLT 10 calendar days after contract award. Government comments shall be provided after review of the draft. A final plan shall be submitted 30 calendar days before the actual cut-over date. The Contractor shall test the

Page | 20 system to demonstrate to the Government quality assurance representative that the system is fully operational and meets or exceeds the specified requirements and that the system is fully ready to be placed into service. These tests shall be accomplished prior to the system being placed into service. (CDRL 0012)

2.2.12.1 Testing.

The Contractor shall conduct on-site testing IAW OEM’s installation manuals, practices and the appropriate vendor’s test procedures. The Contractor shall furnish all test equipment and personnel required to conduct all required testing. During any testing phase, the Government reserves the right to perform any of the contractor performed inspections and tests to assure solutions conform to prescribed requirements. The Contractor shall provide on-site support during the acceptance testing. The Contractor shall participate with the Government in testing the complete communications system. When any system, subsystem, component or requirement test fails to meet the requirements of the test, Government acceptance and payment shall be withheld until such time as the cause of the failure is corrected to the Government’s satisfaction.

After appropriate corrective action has been taken, all tests including those previously completed, related to the failed test and the corrective action shall be repeated and successfully completed prior to Government acceptance. (CDRL 0013)

2.2.12.1.1 Fiber Optic Tests.

All strands of all fiber optic cables shall be tested in accordance with TIA 526-7-A, Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent.

As a minimum, the following tests shall be performed. Both Optical Time Domain

Reflectometer (OTDR) and Optical Power Meter tests shall be used for all end-to-end circuits.

Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in Maintenance Holes, only one way OTDR testing is required. (CDRL 0013)

2.2.12.1.2 Optical Attenuation.

End to end attenuation tests shall be conducted on all fiber optic cable strands. Tests shall be accomplished to ensure the installed cable is within the specified parameters. (CDRL 0013)

2.2.12.1.3 Distance.

Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.

2.2.12.2 Acceptance/Installation Test Report.

The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan NLT 10 business days after Government Witness Testing is complete. (CDRL 0013)

2.2.13 Final Acceptance IAW AFTO “747 Cyberspace Infrastructure System

Acceptance”.

The Contractor shall schedule a final project walk-through with the Base POC, including Quality

Assurance Officer and Subject Matter Expert. The walk-through should be scheduled 5 calendar days prior to acceptance. The contractor shall route the AFTO 747 after the base has signed the test report and the walk-through has been completed. (CDRL 0014)

Page | 21

2.2.14 Deliverable Summary.

All deliveries are subject to Government acceptance and approval. They shall meet professional standards, and the requirements set forth in this Task Order. All deliverables shall be produced using recommended software tools/versions as accepted by the Government.

Service Delivery Table

SOO Paragraph Deliverable Threshold

IAW CDRL 0001 Safety

Requirements

2.1.2, 2.1.2.1, IAW CDRL 0002 Security

Requirements

2.1.3 Site Visit

Request

5 calendar days after award

IAW CDRL 0003 Integrated

Process Team

2.1.6 As detailed in

para. 2.1.6

As detailed in para.

2.1.6

IAW CDRL 0004 Quality

Assurance report and support

2.1.7 As detailed in

para. 2.1.7

As detailed in para.

2.1.7

IAW CDRL 0005

Contractor Personnel

2.1.8.1 Project Manager,

2.1.1.2 Site POC

IAW CDRL 0006 SAM.gov reporting

2.1.8.5…