ATCALS Deliverables table.pdf

PDF 34 KB Posted

Attached to
Air Traffic Control and Landing System Equipment Upgrade
Solicitation number
FA820126R0007
Issued by

About this file

Summary of Statement of Objectives Deliverables and Schedule

This document is a Statement of Objectives (SOO) deliverables table that outlines 14 Contract Data Requirements Lists (CDRLs) with corresponding SOO paragraph references, specific deliverable descriptions, and submission thresholds. The deliverables span safety requirements, security requirements, integrated process team coordination, quality assurance reporting, contractor personnel designation, SAM.gov reporting, manuals and practices documentation, installation schedules, weekly status reporting, updated as-built drawings, geospatial deliverables, test and acceptance/installation planning, testing procedures, and final acceptance walk-throughs.

Key submission deadlines include: site visit request within 5 calendar days after award; SAM.gov reporting proof no later than November 1st; installation schedules no later than 10 business days after contract award; weekly status reports due close of business each Thursday; geospatial deliverables no later than 30 days after project completion; and the test and acceptance/installation plan with a draft cut-over plan due 10 calendar days after award and final plan due 30 calendar days before the actual cut-over date. Final acceptance requires a walk-through with Government point of contact(s) and routing of the AFTO 747 form. The deliverables indicate this is a construction or infrastructure installation project involving fiber optic components, testing, and government facility acceptance procedures.

View the file

Other files

File Type Posted
ATCALS_Solicitation QandA.pdf PDF
PFAS South Runway Location2_v2.pdf PDF
PFAS North Runway Location_v1.pdf PDF
ATCALS_Solicitation QandA.docx DOCX document
ATCALS_Solicitation QandA.docx DOCX document
SOO ATCALS Equipment Infrastructure Upgrade_V2.pdf PDF
Solicitation - FA820126R0007.pdf PDF
ATCALS Instructions and Evaluation Factors.pdf PDF
ATCALS CDRLs.pdf PDF
WD_ATCALS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOO Paragraph Deliverable THreshold IAW CDRL 0001 Safety Requirements

2.1.2, 2.1.2.1, IAW CDRL 0002 Security Requirements

2.1.3 Site Visit

Request

5 calendar days after award

IAW CDRL 0003 Integrated Process Team

2.1.6 As detailed in

para. 2.1.6

As detailed in para.

2.1.6

IAW CDRL 0004 Quality Assurance report and support

2.1.7 As detailed in

para. 2.1.7

As detailed in para.

2.1.7

IAW CDRL 0005

Contractor Personnel

2.1.8.1 Project Manager,

2.1.1.2 Site POC

IAW CDRL 0006 SAM.gov reporting

2.1.8.5 Proof of

SAM.GOV

reproting

NLT 1 November

IAW CDRL 0007 Manuals and Practices

2.1.10 As detailed in

para. 2.1.10

Upon project completion

IAW CDRL 0008

Installation Schedules

2.2.9 Complete

milestone schedule

NLT 10 business days after contract award, as significant schedule changes occur

IAW CDRL 0009 Weekly Status Report

2.2.10 Status report NLT COB each

Thursday

IAW CDRL 0010 Updated As-Built Drawings

2.2.11.1, 2.2.11.2 As-Built Drawings, Butterfly Drawings

0011 Geospatial Deliverables

2.2.11.3 As detailed in

para. 2.2.11.3

NLT 30 days after project completion

IAW CDRL 0012 Test and Acceptance/Installation Plan

2.2.12 As detailed in

para. 2.2.12

Draft Cut-over plan NLT 10 calendar days after award, Final plan 30 calendar days before actual cut-over date

IAW CDRL 0013 Testing 2.2.12.1, 2.2.12.1.1 (Fiber Optic), 2.2.12.1.2 (Optical Attenuation),

2.2.12.1.3 (Distance), 2.2.12.2.2 (Acceptance/Installation Test Report)

As detailed in section 2.2.12.1

IAW CDRL 0014 Final Acceptance

2.2.13 Walk-through

with Government POC(s), routing of AFTO 747