IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

9. FOR INFORMATION

CALL:

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See ).

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

12b. CALENDAR DAYS

YES NO

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AMOUNTS

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

FA460020B0001

Section A - Solicitation/Contract Form

Section B - Supplies or Services and Prices/Cost

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

Patch & Paint Interior Hallways and Stairwells B323 IAW the Statement of Objectives (SOO) Product Service Code: Z2AA Firm Fixed Price

1.0 Lot

Labor Rates

Category: Building Construction Including Work on Industrial Sites Rate Title: Painter Rate: 14.26 Sub Category:

Section C - Description/Specifications/Statement of Work

Requirements Patch and Paint all Interior Hallways and Stairwells B323 in accordance with the Statement of Objectives

(SOO)

Section D - Packaging and Marking

Not Applicable

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.246-12 Inspection of Construction. 1996-08

0001 Inspection and Acceptance Location Both Destination Instructions: Inspection and Acceptance location is Building 323, Offutt AFB.

DoDAAC: F3H3G2 Cage:

DunsNumber:

Duns4Number:

CountryCode: USA

55 CES CEC

AF BPN NO MILSBILLS PROCESSES

106 PEACEKEEPER DR STE 2N3

OFFUTT AFB, NE 68113 4019

United States

OfficeCode:

Eddie Haer Telephone: 4022944195 Email: eddie.haer@us.af.mil

Section F - Deliveries or Performance

Delivery Schedule Ship To Address

Delivery Schedule From date of lead time event to delivery 90 Calendar Days Date of Notice to Proceed Receipt

Place of Performance DoDAAC: FA4600 Cage:

DunsNumber:

Duns4Number:

CountryCode: USA

FA4600 55 CONS PKP

BLDG 323C CP 402 232 6459

106 PEACEKEEPER DR STE 2N3

OFFUTT AFB, NE 68113

United States

OfficeCode:

Eddie Haer Telephone: 4022944195 Email: eddie.haer@us.af.mil

Period of Performance From

31 JUL 2020

To

31 OCT 2020

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.247-34 F.o.b. Destination. 1991-11

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date 252.201-7000 Contracting Officer's Representative 1991-12 252.204-7006 Billing Instructions. 2005-10 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. 2018-12 252.236-7000 Modification Proposals--Price Breakdown 1991-12

DFARS Clauses Incorporated by Full Text

252.232-7006 Wide Area WorkFlow Payment Instructions. 2018-12

As prescribed in 232.7004(b), use the following clause:

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) As used in this clause- Definitions.

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as Electronic invoicing.

authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) To access WAWF, the Contractor shall- WAWF access.

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice WAWF training.

Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer WAWF methods of document submission.

Protocol.

(f) The Contractor shall use the following information when submitting payment requests and receiving reports WAWF payment instructions.

in WAWF for this contract or task or delivery order:

(1) The Contractor shall submit payment requests using the following document type(s): Document type.

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

Invoice 2in1

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(f) [Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in Document routing.

WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC F87700

Issue By DoDAAC FA4600

Admin DoDAAC FA4600

Inspect By DoDAAC F3H3G2

Ship To Code ____

Ship From Code ____

Mark For Code ____

Service Approver (DoDAAC) F3H3G2

Service Acceptor (DoDAAC) F3H3G2

Accept at Other DoDAAC ____

LPO DoDAAC ____

DCAA Auditor DoDAAC ____

Other DoDAAC(s) ____

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in Payment request.

accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

Not Applicable

Section I - Contract Clauses

FAR Clauses Incorporated by Reference

Number Title Effective Date

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation.

2017-01

52.204-13 System for Award Management Maintenance. 2018-10 52.204-18 Commercial and Government Entity Code Maintenance. 2016-07 52.211-13 Time Extensions. 2000-09 52.214-29 Order of Precedence-Sealed Bidding. 1986-01 52.219-6 Deviation 2020-O0008 Notice of Total Small Business Set-Aside (DEVIATION 2020-O0008) 2020-03 52.222-3 Convict Labor. 2003-06 52.222-6 Construction Wage Rate Requirements. 2018-08 52.222-7 Withholding of Funds. 2014-05 52.222-8 Payrolls and Basic Records. 2018-08 52.222-9 Apprentices and Trainees. 2005-07 52.222-10 Compliance with Copeland Act Requirements. 1988-02 52.222-11 Subcontracts (Labor Standards). 2014-05 52.222-12 Contract Termination-Debarment. 2014-05 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. 2014-05 52.222-14 Disputes Concerning Labor Standards. 1988-02 52.222-15 Certification of Eligibility. 2014-05 52.223-5 Pollution Prevention and Right-to-Know Information. 2011-05 52.223-19 Compliance with Environmental Management Systems. 2011-05 52.232-8 Discounts for Prompt Payment. 2002-02 52.232-11 Extras. 1984-04 52.232-27 Prompt Payment for Construction Contracts. 2017-01 52.232-39 Unenforceability of Unauthorized Obligations. 2013-06 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. 2013-12 52.236-5 Material and Workmanship. 1984-04 52.236-7 Permits and Responsibilities. 1991-11 52.242-14 Suspension of Work. 1984-04 52.243-5 Changes and Changed Conditions. 1984-04 52.246-21 Warranty of Construction. 1994-03 52.249-4 Termination for Convenience of the Government (Services) (Short Form). 1984-04

DFARS Clauses Incorporated by Reference

Number Title Effective Date 252.203-7000 Requirements Relating to Compensation of Former DoD Officials 2011-09 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. 2013-09 252.204-7003 Control of Government Personnel Work Product. 1992-04 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls. 2016-10 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. 2019-12 252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support. 2016-05 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. 2014-09 252.223-7008 Prohibition of Hexavalent Chromium. 2013-06 252.225-7048 Export-Controlled Items. 2013-06 252.232-7010 Levies on Contract Payments. 2006-12 252.232-7011 Payments in Support of Emergencies and Contingency Operations. 2013-05 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. 2013-06 252.243-7001 Pricing of Contract Modifications. 1991-12 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. 2010-10

FAR Clauses Incorporated by Full Text

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. 2016-02

As prescribed in 9.104-7 (d), insert the following provision:

REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A FELONY CONVICTION UNDER ANY

FEDERAL LAW (FEB 2016)

As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235), (a) and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a contract with any corporation that-

Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or (1) have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless an agency has considered suspension or debarment of the corporation and made a determination that suspension or debarment is not necessary to protect the interests of the Government; or

Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is (2) aware of the conviction, unless an agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.

The Offeror represents that-(b)

It is(1) is not a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability; and

It is(2) is not a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.

(End of provision)

52.211-10 Commencement, Prosecution, and Completion of Work. 1984-04

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within [10 days calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than .* The time stated for 31 Oct 2020 completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 Liquidated Damages-Construction. 2000-09

As prescribed in 11.503(b), insert the following clause in solicitations and contracts:

LIQUIDATED DAMAGES-CONSTRUCTION (SEPT 2000)

If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the (a) Government in the amount of for each calendar day of delay until the work is completed or accepted. [ ]$313.67 Contracting Officer insert amount

If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. (b) These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.225-9 Buy American-Construction Materials. 2014-05

As prescribed in 25.1102(a), insert the following clause:

BUY AMERICAN-CONSTRUCTION MATERIALS (MAY 2014)

. As used in this clause-(a) Definitions

-Commercially available off-the-shelf (COTS) item

Means any item of supply (including construction material) that is-(1)

A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);(i)

Sold in substantial quantities in the commercial marketplace; and(ii)

Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in (iii) the commercial marketplace; and

Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.(2)

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

-Cost of components means

For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the (1) construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation (2) costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

means-Domestic construction material

An unmanufactured construction material mined or produced in the United States;(1)

A construction material manufactured in the United States, if-(2)

The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its (i) components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

The construction material is a COTS item.(ii)

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

Domestic preference. (b) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction (1) material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item.

(See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs

(b)(2) and (b)(3) of this clause.

This requirement does not apply to information technology that is a commercial item or to the construction materials or components (2) listed by the Government as follows:

[ ]none Contracting Officer to list applicable excepted materials or indicate "none"

The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government (3) determines that-

The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to (i) the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

The application of the restriction of the Buy American statute to a particular construction material would be impracticable or (ii) inconsistent with the public interest; or

The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available (iii) commercial quantities of a satisfactory quality.

Request for determination of inapplicability of the Buy American statute. (c) (1) Any Contractor request to use foreign construction material (i) in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

A description of the foreign and domestic construction materials;(A)

Unit of measure;(B)

Quantity;(C)

Price;(D)

Time of delivery or availability;(E)

Location of the construction project;(F)

Name and address of the proposed supplier; and(G)

A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this (H) clause.

A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the (ii) format in paragraph (d) of this clause.

The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a (iii) duty-free certificate may be issued).

Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably (iv) foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer (2) and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is (3) noncompliant with the Buy American statute.

. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the (d) Data following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction Material Description

Unit of Measure

Quantity Price

(Dollars)

:Item1

Foreign construction material

Domestic construction material

Item2: ____ ____ ____

Foreign construction material

Domestic construction material

[ ]List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.

[ ]Include other applicable supporting information.

[ ]* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).

(End of clause)

52.228-13 Alternative Payment Protections. 2000-07

As prescribed in 28.102-3(b), insert the following clause:

ALTERNATIVE PAYMENT PROTECTIONS (JULY 2000)

The Contractor shall submit one of the following payment protections:(a)

A payment bond. An irrevocable letter of credit (ILC) Certificates of Deposit

The amount of the payment protection shall be 100 percent of the contract price.(b)

The submission of the payment protection is required within days of contract award.(c) 30

The payment protection shall provide protection for the full contract performance period plus a one-year period.(d)

Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to (e) access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow (f) agreement.

(End of clause)

52.232-5 Payments under Fixed-Price Construction Contracts. 2014-05

As prescribed in 32.111(a)(5), insert the following clause:

PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)

. The Government shall pay the Contractor the contract price as provided in this contract.(a) Payment of price

. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as (b) Progress payments determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

The Contractor's request for progress payments shall include the following substantiation:(1)

An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment (i) requested.

A listing of the amount included for work performed by each subcontractor under the contract.(ii)

A listing of the total amount of each subcontract under the contract.(iii)

A listing of the amounts previously paid to each such subcontractor under the contract.(iv)

Additional supporting data in a form and detail required by the Contracting Officer.(v)

In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be (2) taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-

Consideration is specifically authorized by this contract; and(i)

The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to (ii) perform this contract.

. Along with each request for progress payments, the Contractor shall furnish the following certification, or (c) Contractor certification payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that-

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

____ ( )Name

____ ( )Title

____ ( )Date

. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of (d) Refund of unearned amounts such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

Notify the Contracting Officer of such performance deficiency; and(1)

Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this (2) clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-

The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or(i)

The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the (ii) unearned amount.

. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be (e) Retainage made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

. All material and work covered by progress payments made shall, at the time of payment, become (f) Title, liability, and reservation of rights the sole property of the Government, but this shall not be construed as-

Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration (1) of any damaged work; or

Waiving the right of the Government to require the fulfillment of all of the terms of the contract.(2)

. In making these progress payments, the Government shall, upon request, reimburse the Contractor for (g) Reimbursement for bond premiums the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

. The Government shall pay the amount due the Contractor under this contract after-(h) Final payment

Completion and acceptance of all work;(1)

Presentation of a properly executed voucher; and(2)

Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that (3) the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.C.6305).

. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on (i) Limitation because of undefinitized work work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this (j) Interest computation on unearned amounts clause shall be-

Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior (1) to the date the Contractor receives the unearned amount; and

Deducted from the next available payment to the Contractor.(2)

(End of clause)

52.252-2 Clauses Incorporated by Reference. 1998-02

As prescribed in 52.107(b), insert the following clause:

CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov [ ]____ ____ Insert one or more Internet addresses

(End of clause)

52.252-6 Authorized Deviations in Clauses. 1984-04

As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation. Whenever any FAR or supplemental clause is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without deviation, include regulation name for any supplemental clause, except that the contracting officer shall insert "(DEVIATION)" after the date of the clause.

AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)

The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is (a) indicated by the addition of "(DEVIATION)" after the date of the clause.

The use in this solicitation or contract of any (48 CFR ) clause with an authorized deviation is (b) [ ]____ insert regulation name ____ indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of clause)

DFARS Clauses Incorporated by Full Text

252.236-7001 Contract Drawings and Specifications. 2000-08

As prescribed in 236.570(a), use the following clause:

CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall-

(1) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verify the figures before laying out the work;

(3) Promptly notify the Contracting Officer of any discrepancies;

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

(1) Large-scale drawings shall govern small-scale drawings; and

(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.

(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:

Title File Drawing No.

Combined Specifications ____ ____

(End of clause)

AFFARS Clauses Incorporated by Full Text

5352.201-9101 ACC Ombudsman 10/1/2019

(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.

(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).

(c) If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, Lt Col Aaron Judge, USAF Deputy Director of Contracting, OL-ACC Air Force Installation Contracting Agency Joint Base Langley-Eustis VA COMM: (757) 764-5372 DSN: 574-5372 aaron.judge@us.af.mil. Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/SMC ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571) 256-2431.

(d) The ombudsman has no authority to render a decision that binds the agency.

(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the contracting officer.

(End of clause)

5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS) 10/1/2019

(a) Contractors shall not:

(1) Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or

(2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.

[Note: This prohibition does not apply to manufacturing.]

(b) For the purposes of Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32- 7086) are Class I ODSs:

(1) Halons: 1011, 1202, 1211, 1301, and 2402;

(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and

(3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.

[NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Air Force definition of a Class I ODS.]

(End of clause)

5352.242-9000 Contractor Access to Air Force Installations 10/1/2019

(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.

(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver s license, current vehicle registration, valid vehicle insurance certificate, and <<1>> to obtain a vehicle pass.

(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.

(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with <<2>> citing the appropriate paragraphs as applicable.

(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.

(f) Failure to comply with these requirements may result in withholding of final payment.

Section J - List of Attachments

Attachment 1 - Site Visit and Bid Submission Attachment 2 - Wage Determination Attachment 3 - Combined Specifications (Section 1A, 1B, 1C) Attachment 4 - AF 66 Schedule of Material Submittals Attachment 5 - Statement of Objective (SOO) Attachment 6 - 55 SFS Contractor/Vendor NCIC Screening Template

Section K - Representations, Certification, and other Statements of Offerors

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.204-7 System for Award Management. 2018-10 52.214-18 Preparation of Bids-Construction. 1984-04

DFARS Clauses Incorporated by Reference

Number Title Effective Date

252.203-7005 Representation Relating to Compensation of Former DoD Officials. As prescribed in 203.171-4(b), insert the following provision:

2011-11

FAR Clauses Incorporated by Full Text

52.204-8 Annual Representations and Certifications. 2020-03

As prescribed in 4.1202(a), insert the following provision:

ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR?2020)

(a) The North American Industry Classification System (NAICS) code for this acquisition is .(1) [insert NAICS code]238320

The small business size standard is .(2) [insert size standard]$15M

The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, (3) but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.(1)

If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active (2) registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The Offeror shall indicate which option applies by checking one of the following boxes:

(i)

Paragraph (d) applies.

(ii)

Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c) The following representations or certifications in SAM are applicable to this solicitation as indicated:(1)

52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or (i) fixed-price contract with economic price adjustment is contemplated, unless-

The acquisition is to be made under the simplified acquisition procedures in part 13;(A)

The solicitation is a request for technical proposals under two-step sealed bidding procedures; or(B)

The solicitation is for utility services for which rates are set by law or regulation.(C)

52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to (ii) solicitations expected to exceed $150,000.

52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-(iii) Representation. This provision applies to all solicitations.

52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for (iv) Award Management.

52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that-(v)

Are not set aside for small business concerns;(A)

Exceed the simplified acquisition threshold; and(B)

Are for contracts that will be performed in the United States or its outlying areas.(C)

52.204-26, Covered Telecommunications Equipment or Services-Representation. This provision applies to all solicitations.(vi)

52.209-2, Prohibition on Contracting with Inverted Domestic Corporations-Representation.(vii)

52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is (viii) expected to exceed the simplified acquisition threshold.

52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law. (ix) This provision applies to all solicitations.

52.214-14, Place of Performance-Sealed Bidding. This provision applies to invitations for bids except those in which the place of (x) performance is specified by the Government.

52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the (xi) Government.

52.219-1, Small Business Program Representations (Basic, Alternates I, and II). This provision applies to solicitations when the (xii) contract will be performed in the United States or its outlying areas.

The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.(A)

The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast Guard.(B)

The provision with its Alternate II applies to solicitations that will result in a multiple-award contract with more than one NAICS (C) code assigned.

52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be (xiii) performed in the United States or its outlying areas.

52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-(xiv) 26, Equal Opportunity.

52.222-25, Affirmative Action Compliance. This provision applies to solicitations, other than those for construction, when the (xv) solicitation includes the clause at 52.222-26, Equal Opportunity.

52.222-38, Compliance with Veterans' Employment Reporting Requirements. This provision applies to solicitations when it is (xvi) anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of (xvii) USDA-designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA-(xviii) designated items.

52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-Representation. This provision applies to (xix) solicitations that include the clause at 52.204-7.)

52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.(xx)

52.225-4, Buy American-Free Trade Agreements-Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision (xxi) applies to solicitations containing the clause at 52.225-3.

If the acquisition value is less than $25,000, the basic provision applies.(A)

If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.(B)

If the acquisition value is $50,000 or more but is less than $83,099, the provision with its Alternate II applies.(C)

If the acquisition value is $83,099 or more but is less than $100,000, the provision with its Alternate III applies.(D)

52.225-6, Trade Agreements Certificate.