55th Civil Engineer Squadron
Statement of Objective
Date: 10 Aug 2020 Project #: SGBP 21-2062 Project Title: Paint West & South Exterior Walls, B301D
Objectives:
Repaint exterior walls and peripheral items on South and West sides of Building 301D at Offutt AFB.
Coordination Scope Items:
• Perform a direct applied Eifs to South wall in need of repair. Preparation of existing surface to any application of materials. Skimming of the existing surface with Sto (or approved equal) base coat, with 4.5oz Sto (or approved equal) Mesh embedded. Sto (or approved equal) Essence Medium Sand Finish in a color to match the existing facade. Caulking on 90 iron plates (potential source of water infiltration). Control joints or V cut joints installed into new plaster requiring joint sealants.
• Prepare remaining surfaces for paint by pressure washing to remove flaking or chipping paint, dirt, grease, bird excrement, or any other foreign material that may prevent full paint adhesion per paint manufacturer specifications.
• Paint walls, personnel doors and frames, overhead doors and frames, gutters, downspouts, trim and miscellaneous items. Match existing paint scheme when applying new paint.
• Protect existing exterior signs and lettering during painting operations.
• Pedestrian control is the responsibility of the contractor. Traffic detours must be marked clearly and concisely and meet MUTCD standards. Minimum 2-week notice shall be provided to the government of any building entrance or traffic detours or closures.
• Contractor shall ensure overspray is minimal and does not track onto Private Owned Vehicles and other government property.
• The Contractor shall furnish all required services, labor, tools, material, and equipment necessary to complete the installation and integration of the prime mission equipment in accordance with the approved site design and installation plan. In addition, the Contractor shall be responsible for the following actions:
a. Obtaining all necessary security and safety clearances for facilities and personnel. This includes obtaining flight line and escort badges necessary for unaccompanied work within a secure area.
b. Obtaining environmental and life safety approvals.
c. Acquiring all necessary federal, state, local and base environmental and civil engineering permits and approval.
d. Cleaning-up and restoring the site to its original or better condition within 10 work days after project completion. This includes removal of any portable offices that may have been used to support implementation of the site design at the base.
e. Repairing damage to Government property resulting from contractor activities, assuring the property is returned to its original or better condition.
f. Removing all debris at the end of each shift or more frequently if required to keep the work area safe and useable.
g. Disposing of excess equipment and materials in accordance with General
Requirements. Provide waste diversion data as required.
h. Provide 3064 / 3065 , 1354 and submittals as dictated by the Government.
i. Refer to Specification sections 00 10 00, 01 33 00, 01 57 19 and 09 90 00 for additional information that may pertain to this project.
Project #: SGBP 21-2061 Project Title: Paint Interior Hallways & Stairways, B323
Provide a proposal to provide all labor, equipment, and materials as required to patch and paint all Hallways and Stairwells in B323.
Objectives:
• This project bid will include manpower to remove/re-install wall hangings, light and electrical outlet covers.
• Patch/skim coat walls to have a smooth surface before painting. Painting will consist of at least 2 coats on walls and door frames.
• Paint specs are SW 7079 Ponder (grey). Door frames will match existing color.
• As Built Drawings will be made available as required.
General Requirements:
• Item 1: All work will meet the International Building Code, Uniform Plumbing Code, National Electrical Code, NFPA 72 and any other applicable code requirement.
• Item 2: Maintain work site in a clean and orderly manner so that the safest possible site is provided for workers and AF members.
• Item 3: Infrastructure: The Contractor shall furnish all necessary infrastructure and incidentals to the installation of the prime mission equipment. The Contractor shall ensure that the infrastructure conforms to Offutt Design Compatibility Guidelines (DCG) for base architectural and civil engineering standards, all applicable base construction standards and complies with applicable federal, state and local codes and regulations.
• Item 4: Equipment Installation and Integration: The Contractor shall furnish all required services, labor, tools, material, and equipment necessary to complete the installation and integration of the prime mission equipment in accordance with the approved site design and installation plan. No alterations, additions, or deletions shall be made unless by prior approval of the Contracting Officer (CO).
• In addition, the Contractor shall be responsible for the following actions:
o Please refer to 00 10 00, 01 33 00, 01 57 19 and 01 33 01 of the Specs for additional information that may pertain to this project.
| Coordination Scope Items: |
| Project #: SGBP 21-2061 |
| Project Title: Paint Interior Hallways & Stairways, B323 |
| Provide a proposal to provide all labor, equipment, and materials as required to patch and |
| paint all Hallways and Stairwells in B323. |
| Objectives: |
| This project bid will include manpower to remove/re-install wall hangings, light |
| and electrical outlet covers. |
| Patch/skim coat walls to have a smooth surface before painting. Painting will |
| consist of at least 2 coats on walls and door frames. |
| Paint specs are SW 7079 Ponder (grey). Door frames will match existing color. |
| As Built Drawings will be made available as required. |
| General Requirements: |
| Item 1: All work will meet the International Building Code, Uniform Plumbing |
| Code, National Electrical Code, NFPA 72 and any other applicable code |
| requirement. |
| Item 2: Maintain work site in a clean and orderly manner so that the safest |
| possible site is provided for workers and AF members. |
| Item 3: Infrastructure: The Contractor shall furnish all necessary infrastructure and |
| incidentals to the installation of the prime mission equipment. The Contractor shall |
| ensure that the infrastructure conforms to Offutt Design Compatibility Guidelines |
| (DCG) for base architectural and civil engineering standards, all applicable base |
| construction standards and complies with applicable federal, state and local codes |
| and regulations. |
| Item 4: Equipment Installation and Integration: The Contractor shall furnish all |
| required services, labor, tools, material, and equipment necessary to complete the |
| installation and integration of the prime mission equipment in accordance with the |
| approved site design and installation plan. No alterations, additions, or deletions |
| shall be made unless by prior approval of the Contracting Officer (CO). |
| In addition, the Contractor shall be responsible for the following actions: |
| o Please refer to 00 10 00, 01 33 00, 01 57 19 and 01 33 01 of the Specs for |
| additional information that may pertain to this project. |