This solicitation is for the construction of a new Military Working Dog Kennel at Joint Base Andrews in Camp Springs, Maryland. The project includes an Administrative Building, Dog Kennel, Quarantine Kennel, outdoor dog training and support areas, and demolition of existing kennel facilities totaling 2,703 square feet. The delivery method is design-bid-build. The Navy is the contracting agency. The solicitation is full and open competition with a best value tradeoff source selection. Proposals are due by January 19, 2022. The period of performance is 563 calendar days from award. Pricing is firm fixed price for the base work and options. There are no set-asides but small business participation is an evaluation factor.
View the file
Other files for this federal contract opportunity
Show all 38
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR5871178
P-3009, Military Working Dog Kennel, JBA
Competition Requirement: Full and Open Competition
Source Selection Process: Best Value Source Selection (BVSS) Trade-Off Process
Contract Type: Firm Fixed Price
All inquiries must be submitted no later than 10 calendar days prior to the proposal due date. Inquires shall be submitted in w riting via email to:
Daniel Russell at email daniel.russell.civ@us.navy.mil and Cynthia Crow der at email cynthia.y.crow der.civ@us.navy.mil
All amendments, draw ings, specif ications w ill be posted to SAM.GOV w ebsite https://sam.gov/w orksp
DAMILA ADAMS (202)685-0557
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
15-Dec-2021
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________563 calendar days after receiving aw ard, notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________3 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________05 Nov 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
NAVAL FACILITIES ENGINEERING SYS COMMAND
1314 HARWOOD STREET SE
WASHINGTON DC 20374
N40080
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: (202) 685-3192 TEL: FAX:
N4008021R1178 53
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
N4008021R1178
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each CLIN 0001 - Base Price
FFP
Base Price for CLIN 0001 shall be the entire work for Administrative Building in accordance with the specifications and drawings of the project but not including work specified in CLIN 0002 – CLIN 0009 Option Items.
FOB: Destination
PURCHASE REQUEST NUMBER: ACQR5871178
NET AMT
CLIN 0002 - Base Price
FFP
Base Price for CLIN 0002 shall be the entire work for Dog Kennels Building including Breezeway in accordance with the specifications and drawings of the project but not including work specified in CLIN 0001, and CLIN 0003 – CLIN 0009 Option Items.
CLIN 0003 Base Price
FFP
Base Price for CLIN 0003 shall be the entire work for Training Area, all civil work and demolition of the existing kennel facility in accordance with the specifications and drawings of the project but not including work specified in CLIN 0001, CLIN 0002, and CLIN 0004– CLIN 0009 Option Items.
CLIN 0004 Optional 1: Quarantine Bulding
FFP
Bid Option for CLIN 0004 shall be the entire work for Quarantine Building in accordance with the specifications and drawings of the project.
CLIN 0005 - Option 2: Outdoor Storage
FFP
Bid Option for CLIN 0005 shall be the entire work for Outdoor Storage in
CLIN 0006 - Option 3: Explosive Storage
FFP
Bid Option for CLIN 0006 shall be the entire work for Explosive Storage in
CLIN 0007 - Option 4: Security
FFP
Bid Option for CLIN 0007 shall be the entire work for Security in accordance with the specifications and drawings of the project.
CLIN 0008 - Option 5: FF&E Handling Admi
FFP
(1)Basis of the Bid for CLIN 0008 shall be establishment of a HAR for any possible future work associated with FF&E / Collateral Equipment.
(See Notes).
(2) HANDLING & ADMINISTRATIVE RATE (HAR)(NTE 5%) % X $0 =
(3) TOTAL FF&E AMOUNT : (1) + (2) = (3)=
CLIN 0009 Option 6 Audio Vis/Security
FFP
(1) Basis of the Bid for CLIN 0008 shall be establishment of a HAR for any possible future work associated with FF&E / Collateral Equipment.
(See Note)
(2) HANDLING & ADMINISTRATIVE RATE (HAR)(NTE 5%) % X $0 =
(3) TOTAL A/V AMOUNT: (1) + (2) = (3)
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
0002 N/A N/A N/A N/A
0003 N/A N/A N/A N/A
0004 N/A N/A N/A N/A
0005 N/A N/A N/A N/A
0006 N/A N/A N/A N/A
0007 N/A N/A N/A N/A
0008 N/A N/A N/A N/A
0009 N/A N/A N/A N/A
Section 00 21 13 - Instructions to Bidders
INSTRUCTION TO OFFERORS
INSTRUCTION TO OFFERORS
1. TITLE: P-3009 MILITARY WORKING DOG KENNEL, JOINT BASE ANDREWS, CAMP
SPRINGS, MD
2. PROJECT DESCRIPTION: Military working dog housing, administrative offices, conference rooms, transient rooms for handlers required to stay overnight, kitchen/break room, restrooms/showers with a locker area, utility space, fire detection and alarm system, communications networks (computer/phone VOIP), utilities (electrical, water, sanitary sewer),storm water management, security perimeter fence, lighting, parking (staff, visitors, three MWD trailers, five patrol cars, support vehicles),access roads, outdoor fenced areas (one large area for exercising MWDs and two small areas as holding spaces), overhang to protect MWD transport trailers and patrol cars, landscaping, and other required site improvements and incidental related work. In addition, this project includes the demolition works of the existing Military Working Dog Kennel facilities including existing administrative building, kennel structures and other related facilities as shown on the drawings.
3. POINT OF CONTACT: The primary point of contact for this procurement is Damila Adams at Damila.a.adams.civ@us.navy.mil. The secondary point of contact is Cynthia Crowder at Cynthia.y.crowder.civ@us.navy.mil
4. DISCLOSURE OF MAGNITUDE: In accordance with DFARS 236.204(ii), the construction magnitude of this project is between $10,000,000 and $25,000,000.
5. TYPE OF CONTRACT: Firm-Fixed Price
6. ACQUISITION STRATEGY: This procurement is Unrestricted, Full and Open
7. NORTH AMERICA INDUSTRY CLASSIFICATION SYSTEM (NAICS) CODE: 236220 –
Commercial and Institutional Building Construction with a size standard of $39.5M.
8. SOURCE SELECTION PROCESS: Best Value Trade Off
9. CONTRACT COMPLETION DATE: Work under this contract shall commence 15 days after award and shall be completed within 563 calendar days after contract award (this includes time for bond approval).
10. PROPOSAL ACCEPTANCE PERIOD: The Offeror’s price is valid for 90 days from the receipt of proposals.
11. PRE-PROPOSAL CONFERENCE/SITE VISIT
Will be issued via amendment.
12. REQUEST FOR INFORMATION (RFI): Offerors are required to review the entire solicitation package before submitting questions. All inquiries must be submitted NLT January 10th 2022 by 2:00 PM EST. All inquiries must be submitted in writing and emailed to Damila Adams Damila.a.Adams@us.navy.mil and Cynthia Crowder at cynthia.y.crowder.civ@us.navy.mil with inquiries attached as a WORD document. No tables please.
13. DELIVERY OF PROPOSAL: Proposal shall be electronically no later than 2:00 PM EST on
19 January 2022. Proposals shall be submitted utilizing the Solicitation Module in the Procurement Integrated Enterprise Environment (PIEE). Department of Defense (DoD) training for industry partners is available at https//dodprocurementtoolbox.com/site-pages/solicitation-module. Additional Web Based Training is available at https://pieetraining.eb.mil/wbt/xhtml/wbt/sol/index.xhtml.
Please allow SUFFICENT TIME for your proposal to be received within the Government’s electronic system prior to the proposed cutoff date/time. All proposals must be received prior to the due date and time. Any proposals submitted after the time set for receipt will be documented with the date and hour of receipt and may be held unopened until after award. The file shall be documented in accordance with FAR 15.208.
Facsimile copies and hard copies will NOT be accepted. NO HAND DELIVERY IS
ALLOWED.
14. PROPOSAL ORGANIZATION AND FORMAT: The proposal submitted in response to this solicitation shall be clear, concise, and shall contain sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposals should not simply rephrase or restate the Government’s requirements, but rather should demonstrate convincing rationale to address how the offeror intends to meet these requirements. The offer shall be compliant with the requirements as stated in the RFP. Nonconformance with the solicitation requirements, specified organization and content may result in elimination or misevaluation of the proposal. All claimed technical capabilities to meet the requirements shall be realistic and are subject to verification by the Government. Offerors should assume that the Government has no prior knowledge of the offeror’s business and that the Government will base its evaluation on the information contained in the offeror’s proposals.
Cross-Referencing: To the greatest extent possible, each volume shall be written on a stand-alone basis so that its contents may be evaluated with a minimum of cross referencing to other volumes of the proposal. Information required for proposal evaluation which is not found in its designated volume will be assumed to have been omitted from the proposal. Cross-referencing within a proposal volume is permitted where its use would conserve space without impairing clarity.
Volume I: Technical Proposal: Volume I shall contain the Offerors entire technical proposal in a single pdf., sectioned appropriately by major evaluation factor with the following characteristics: (1) Text pages 8 ½ x 11 format, minimum 10 point font. (2) Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address. (3) Technical Factors 1-4 Volume II: Price Proposal: Volume II shall contain the Offerors price proposal in a single pdf.
With the following information in the pricing volume, the Offeror shall provide the following information:
1. Include a cover page with Solicitation Number, Solicitation Title, Prime Contractor Name, Address, Phone Number, Fax Number, DUNS, Cage Code, Point of Contact, phone number, and email address.
2. Text pages 8 ½ x 11 format, minimum 10 point font.
3. Completed SF 1442 signed with all amendments acknowledged.
4. Completed Price Schedule.
5. Online Representation and Certifications and proof of registration in System for Award Management (SAM)
6. Confirmation of filing of VETS-4212 and/or VETS report for the cycle.
7. Bid Guarantee in accordance with FAR Clause 52.228-1 Bid Guarantee.
8. Responsibility Determination Information (see below).
9. Small Business Subcontracting Plan. (see below).
The offeror is required to submit a complete Price Schedule that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00010 – Solicitation Contract Form in SF 1442. All required proposal documents shall be submitted in accordance with FAR 15.208.
(i) Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide its DUNS Number, CAGE code, and Federal Tax ID number with its proposal.
(ii) Bid bond (SF-24). Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.
(iii). SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00600 of the Solicitation is not provided in SAM, include the representation or certification in your price proposal.
(iv). FAPIIS Certification. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) Certification as required by FAR 52.209-7, Information Regarding Responsibility Matters. VETS-4212 registration. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm, if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS- 4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.
(v). VETS-4212 registration. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.gov/vets/vets4212.htm, if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.
ADDITIONAL INFORMATION TO BE SUBMITTED WITH PRICE PROPOSAL
PACKAGE: RESPONSIBILITY DETERMINATION INFORMATION - In order to be eligible for award, the offeror must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards. The offeror shall provide the following information in the price proposal package:
- One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror’s firm has a line of credit – provide information on how many figures offeror can borrow against the line of credit (i.e. medium 6 figures – exact line of credit is not required).
- The offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.
- Description of offeror’s facilities and equipment.
- Other offeror’s work presently under contract.
Although required to be submitted with offeror’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. Proposal packages from unsuccessful offerors will not be returned to the offeror, but shall be destroyed by the Contracting Officer. No certificate of destruction will be issued.
SMALL BUSINESS SUBCONTRACTING PLAN INFORMATION:
In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the attached Small Business Subcontracting Plan template.
Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB, but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.
NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars.
Small Business: 37.44% HUBZone: 8.75%
SDVOSB: 4.22%
SDB: 23.57%
WOSB: 6%
The SBSP shall be consistent with the commitments offered in the Small Business Utilization and Participation Factor. In accordance with DFARS 215.304©(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.
Please note that SMSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontractor plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.
15. BASIS OF AWARD:
a. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.
b. As stated in the solicitation, the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting
Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
c. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
d. As stated in the solicitation, all technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price.
e. Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board’s assessment of the identified weakness(s) and the associated risk to successful contract performance resulting from the weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
16. EVALUATION FACTORS FOR AWARD:
a. The solicitation requires the evaluation of Price and the following non-price factors:
Factor 1 - Experience Factor 2 - Past Performance Factor 3 - Safety Factor 4 - Small Business Utilization
The distinction between experience and past performance is that experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance relates to both the relevance of recent efforts and how well a contractor has performed on the contract.
2. The relative order of importance of the non-cost/price evaluation factors is the technical factors 1, 3, and 4 are of equal importance to each other and, when combined are equal in importance to the past performance evaluation/performance confidence assessment factor 2.
When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.
The importance of price will increase if the Offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered
3. Basis of Evaluation and Submittal Requirements for Each Factor.
Price:
(1) Solicitation Submittal Requirements: Provide pricing for each CLIN on the SF1442 or other pricing sheet(s) provided.
(2) Basis of Evaluation: The Government will evaluate price based on the total price.
Total price consists of the base bid and all option items. The Government intends to evaluate all options and has included the provision of FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
(b) Non-cost/price Factors:
Factor 1 – Experience:
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information:
(1) Construction Experience:
Submit a minimum of two (2) and a maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience on relevant projects that are similar in size, scope, and complexity to the RFP.
For purposes of this evaluation, a relevant project is further defined as:
1. Size: Approximately 10,000 SF or larger and final construction cost of $12,000,000 or more.
2. Scope: New construction of a military working dog facility or comparable facilities, e.g. police working dog kennels, dog training center or dog support facilities.
3. Complexity: New construction of facilities that meet the Size and Scope criteria, above, inclusive of one or more of the following:
a. Experience with obtaining permits from local regulatory agencies for storm water management and erosion and sediment control.
b. Experience with new construction projects with comparable size, scope and complexity which required contingency planning due to unscheduled limited site access and/or work stoppage due to airfield operations.
c. Demolition of existing facilities with hazardous material abatement from and area larger than 2,000 SF.
Projects submitted for the Offeror shall be completed within the past five (5) years prior to the date of issuance of this RFP.
A project is defined as a construction project performed under a single task order or contract.
For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project.
The attached Construction Project Data Sheet (Attachment A) is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) 8 1/2” x 11” double-sided page or two (2) 8 1/2” x 11” single-sided pages.
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods). In addition, the description should also address any sustainable features for the project, including specific descriptions of those features. Provide applicable documentation on projects that were validated and/or certified through U.S. Green Building Council (USGBC) or the equivalent organization or process.
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. Offerors who fail to submit experience for all Joint Venture members may be rated lower. Offerors are still limited to a total of five (5) projects combined.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.
(b) Basis of Evaluation:
The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant aggregate experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. A minimum of two (2) and maximum of five (5) projects for construction must be submitted. Any projects submitted in excess of the five (5) for Construction Experience will not be considered.
Offerors who submit relevant projects that demonstrate experience self-performing relevant features of work may receive a higher rating than those who do not demonstrate self-performance.
Proposals may be strengthened if submitted construction projects possess:
a. Demonstrate experience with the new construction on military installations.
b. Experience with obtaining permits from Maryland Department of Environment for storm water management and erosion sediment control may be considered more favorably than those that do not demonstrate said experience.
c. Relevant projects that demonstrate experience with military working dog facilities may be considered more favorably than those that do not.
d. Relevant projects that demonstrate experience on military installations may be considered more favorably than those that do not.
e. Relevant projects that demonstrate experience with sustainable features may be considered more favorably than those that do not.
Factor 2 – Past Performance:
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1, Experience. If a completed CPARS evaluation is not available for a project that was submitted under Factor 1, Experience, the offeror shall submit Past Performance Questionnaires (Attachment B) for that project. The Offeror shall provide completed Past Performance Questionnaires (PPQ) in the proposal. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s).
The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s points of contact, Contract Specialist Damila Adams at damila.a.adams.civ@us.navy.mil and Cynthia Crowder at Cynthia.y.crowder.civ@us.navy.mil.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Experience. Offerors may also address any adverse past performance issues. Explanations shall not exceed two (2) double-sided 8 1/2” x 11” pages (or four (4) 8 1/2” x 11” single-sided pages) in total.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
Performance award or additional information submitted will not be considered.
(b) Basis of Evaluation:
This evaluation will consider how well the Offeror’s team performed on relevant projects submitted under Factor 1 – Experience and may also consider past performance on other projects currently documented in known sources.”
The Government will consider the recency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s team’s past performance will be used as a means of evaluating the Offeror’s team’s probability to successfully meet the requirements of the RFP.
Offerors lacking relevant past performance history will receive a NEUTRAL Confidence rating.
Past performance ratings of “Substantial Confidence” or “Satisfactory Confidence” hold more value than a “Neutral Confidence” rating and will be considered more favorably in the evaluation of past performance.
Factor 3 – Safety
The Offeror shall submit the following information: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate for the specified five (5) calendar years; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative as described further below. For a partnership or joint venture, the Offeror shall submit separate DART and TCR for the specified five (5) CY for each contractor who is part of the partnership or joint venture; however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.
The attached Safety Data Sheet (Attachment E) SHALL be used to submit the Offeror’s safety information below.
NOTE: DART and TCR shall not be submitted for subcontractors.
1. DART Rate: Submit five (5) previous complete calendar years’ CY2020, CY2019, CY2018, CY2017, and CY2016 worth of data (not an overall average). If the Offeror has no DART rate or a “0” DART rate, for any year, affirmatively state so and explain why.
a. Dart cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.
b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.
| 𝑫𝑨𝑹𝑻 | 𝑹𝑨𝑻𝑬 | ||||
| Number | of | DART | Incidents | x | 200,000 |
Total Number of Enployee Labor Hours Worked
2. TCR Rate: Submit five (5) previous complete calendar years’ CY2020, CY2019, CY2018, CY2017, and CY2016 worth of data (not an overall average). If the Offeror has no TCR rate or a “0” TCR rate, for any year, affirmatively state so and explain why.
a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.
b.Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.
| 𝑻𝑪𝑹 | 𝑹𝑨𝑻𝑬 | ||||
| Number | of | TCR | Incidents | x | 200,000 |
Total Number of Enployee Labor Hours Worked
3. Technical Approach for Safety: Submit a narrative that addresses the following:
a. Describe the Offeror’s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describe the evaluation process used to select potential subcontractors.
c. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout the performance of the contract (to include the Offeror’s own in-house workforce).
d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided 8 ½ X 11 pages or one (1) double-sided size 8 ½ X 11 page.
4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
(b) Basis of Evaluation:
The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
1. DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Any negative trends require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data or “0” responses without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the DART rate to the level of risk:
Risk DART Rate
Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0
2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Any negative trends require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data or “0” responses without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the TCR rate to the level of risk:
Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49 Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0
3. Technical Approach to Safety Narrative. To determine the degree to which the Offeror:
a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.
c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.
d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided, size 8 ½ x 11 pages or one (1) double-sided size 8 ½ X 11 page. Information on pages beyond this will not be considered.
4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
Factor 4 – Small Business Utilization
It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Historically Underutilized Business
Zone Small Business (HUBZone SB), Woman-Owned Small Business (WOSB), Small Disadvantaged Business (SDB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.
This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation and commitment for this requirement. The Offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and its planned level of commitment to small business if awarded a contract under this solicitation.
1. All Offerors (both Other than Small Businesses (OTSB) AND SBs shall use Attachment F (Historical Small Business Utilization) to demonstrate their historical utilization of SBs. Attachment F shall be provided for each project submitted under Factor 1, Experience. Failure to submit Attachment F for each project submitted under Factor 1, Experience, or the failure to fully complete Attachment F will result in a deficiency.
2. All Offerors (both OTSBs and SBs) shall use Attachment G (Small Business
Participation Commitment Document (SBPCD)) to submit the following required information for evaluation of this factor:
• To demonstrate commitment to use small business concerns in the performance of this contract, identify all planned subcontractors by name that will be used to support each specific small business category (i.e., SB, HUBZone SB, WOSB, SDB, VOSB, and SDVOSB). Identify the type and complexity of product/service to be subcontracted, the estimated subcontract value, and the type of commitment (i.e., teaming agreement, letter of commitment, etc.) with each subcontractor.
• To demonstrate maximum practicable participation of small businesses, identify
(in terms of dollar value and percentage of the total contract value) the Offeror’s proposed small business participation. The minimum required small business participation (i.e. work to be performed by small business as the prime contractor and/or work to be performed by small business subcontractors) is 20%. All Offerors who are not able to meet the minimum total small business participation rate of 20% (of the total contract value) shall provide a detailed explanation why the minimum total small business participation rate cannot be achieved.
Large business Offerors may achieve the minimum total small business participation rate through subcontracting to small businesses.
Small business Offerors may achieve the minimum total small business participation rate through their own performance/participation as a prime and also through a joint venture, teaming arrangement, and/or subcontracting with other small business concerns.
Offerors are encouraged to exceed this percentage and seek meaningful levels of participation in each of the small business categories (i.e., SB, HUBZone SB, WOSB, SDB, VOSB, and SDVOSB) consistent with efficient contract performance. Offerors are required to provide a detailed explanation for the methods used to develop the small business participation rates.
If the Offeror does not intend to subcontract, provide a detailed explanation why subcontracting would not result in efficient contract performance.
(b) Basis of Evaluation:
The extent to which the Offeror has demonstrated a history of consistently supporting Government policies concerning the utilization of small business concerns (including all of the various socioeconomic categories of small business, HUBZone SB, WOSB, SDB, VOSB, SDVOSB) and success in achieving goals established by subcontracting plans on prior contracts.
The extent to which the Offeror has demonstrated an achievable commitment to use small businesses (including HUBZone SB, WOSB, SDB, VOSB, SDVOSB) in the performance of this contract in the SBPCD. The SBPCD will be evaluated to determine the extent to which small business concerns are specifically identified by name and socioeconomic category in the document and the quantitative degree to which small business concerns (including HUBZone, WOSB, SDB, VOSB, and SDVOSB) will participate relative to the total contract value. The complexity and variety of the work small business concerns will perform and the degree of commitment to use named sources through formal teaming agreements, letters of intent/commitment will be evaluated to assess achievability of the commitment. This minimum small business participation rate, through work performed by the small business prime and/or subcontracting with small businesses, shall exceed 20% of the total contract value, unless the Offeror provides a reasonable and well-documented explanation for why 20% small business participation rate cannot be achieved.
Section 00 70 00 - Conditions of the Contract
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 0002 N/A N/A N/A Government 0003 N/A N/A N/A Government 0004 N/A N/A N/A Government 0005 N/A N/A N/A Government 0006 N/A N/A N/A Government 0007 N/A N/A N/A Government 0008 N/A N/A N/A Government 0009 N/A N/A N/A Government
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
JUN 2020
52.203-13 Contractor Code of Business Ethics and Conduct JUN 2020 52.203-14 Display of Hotline Poster(s) JUN 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
JUN 2020
52.204-2 Security Requirements MAR 2021 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.207-3 Right of First Refusal of Employment MAY 2006 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
JUN 2020
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research JUN 2020 52.211-10 Commencement, Prosecution, and Completion of Work APR 1984 52.211-13 Time Extensions SEP 2000 52.211-15 Defense Priority And Allocation Requirements APR 2008 52.215-2 Audit and Records--Negotiation JUN 2020 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.216-7 Alt I Allowable Cost and Payment (Aug 2018) - Alternate I FEB 1997 52.219-4 Notice of Price Evaluation Preference for HUBZone Small
Business Concerns
SEP 2021
52.219-14 Limitations On Subcontracting SEP 2021 52.219-16 Liquidated Damages-Subcontracting Plan SEP 2021 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards - Overtime
Compensation
MAY 2018
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-34 Project Labor Agreement MAY 2010 52.222-35 Equal Opportunity for Veterans JUN 2020 52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons OCT 2020 52.222-54 Employment Eligibility Verification OCT 2015 52.
This is the start of the file's text. The full file is on GovTribe.