Solar Charging Workstations Installation RFP26HHL012_Amendedv2.docx

DOCX document 26 KB Posted

Attached to
Solar Charging Stations Installation
Solicitation number
P27000009
Issued by
Hawaii County, Hawaii

About this file

This is a Request for Proposals (RFP) issued by the State of Hawaii Department of Hawaiian Home Lands (DHHL) for the installation of seven solar charging workstations at library locations across Hawaii and the DHHL Molokai District Office. The solicitation (RFP-26-HHL-012) seeks qualified contractors to install equipment at two Molokai locations (Molokai Public Library and DHHL Molokai District Office), one Hawaii Island location (Naalehu Public Library), three Oahu locations (Waimanalo, Kapolei, and Nanakuli Public Libraries), and one Kauai location (Hanapepe Public Library). DHHL will provide all equipment and arrange shipment to island docks; contractors are responsible for transporting equipment from docks to installation sites, site preparation, installation, anchoring, and final testing. Four of the seven locations require new concrete pads with ADA-compliant accessibility features. A pre-offer conference is scheduled for July 15, 2026 at 10:00 AM HST. Questions are due August 18, 2026 at 5:00 PM HST with answers posted August 20, 2026 at 5:00 PM HST. Proposals are due September 4, 2026 at 5:00 PM HST and must be submitted electronically via HIePRO. Installation must be completed within 30 calendar days of Notice to Proceed for each location. The contract will be awarded to a single contractor for all locations on a firm fixed-price basis per island, with progress payments upon completion of each location and final payment upon acceptance. A one-year workmanship warranty on installation is required.

The not-to-exceed total project cost is $435,400, with pricing required for each island and location, broken down by equipment transport, site preparation, concrete work (where applicable), installation, and testing. The project is federally funded through the NTIA Tribal Broadband Connectivity Program (Award ID: NT23TBC0290054) and requires compliance with all applicable federal requirements including Davis-Bacon prevailing wage standards, Equal Employment Opportunity regulations under Executive Order 11246, Clean Air Act and Federal Water Pollution Control Act compliance, and debarment and suspension verification through SAM.gov. Contractors must submit signed federal compliance certifications, current Hawaii Compliance Express (HCE) Certificates, appropriate contractor licenses (CT or C-8), certificates of insurance (general liability and workers compensation), and completed Surety Proposal Bond forms. All installations must comply with current ADA guidelines, Hawaii Accessibility Code, and the 2021 International Building Code as adopted by Hawaii, with mandatory 5-foot minimum clearance for general accessibility around stations. Proposals will be evaluated on technical qualifications (40%), compliance documentation (20%), and cost (40%).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATE OF HAWAI'I

DEPARTMENT OF HAWAIIAN HOME LANDS

REQUEST FOR PROPOSALS

Solicitation No.: RFP-26-HHL-012 Title: Installation of Solar Charging Stations Installation Federal Grant Project: NTIA Tribal Broadband Connectivity Program Award ID: NT23TBC0290054

1. INTRODUCTION

The Department of Hawaiian Home Lands (DHHL) is seeking proposals from qualified contractors to install seven (7) solar charging workstations at library locations across Hawaii and the DHHL Molokai District Office. Equipment will be provided by DHHL and shipped to island docks. Contractors are responsible for transporting equipment from docks to installation sites (in coordination with DHHL), site preparation, installation, anchoring, and final testing.

Offerors may submit a single proposal for all locations. Pricing shall be provided for each island and location.

2. SCOPE OF WORK

2.1 Installation Locations

DHHL requires installation of solar charging stations at the following locations:

Island
Location
Concrete Pad Required
Molokai
Molokai Public Library, 15 Ala Malama Street, Kaunakakai, HI 96748
Yes
Molokai
DHHL Moloka'i District Office, 600 Mauna Loa Highway, Kaunakakai, HI 96748
Yes
Hawaii Island
Naalehu Public Library, 95-5669 Mamalahoa Highway, Naalehu, HI 96772
Yes
Oahu
Waimanalo Public Library, 41-1320 Kalanianaole Highway, Waimanalo, HI 96795
No
Oahu
Kapolei Public Library, 1020 Manawai Street, Kapolei, HI 96707
Yes
Oahu
Nānākuli Public Library, 89-070 Farrington Highway, Waianae, HI 96792
No
Kauai
Hanapepe Public Library, 4490 Kona Road, Hanapepe, HI 96716
Yes

2.2 Work Requirements

The contractor shall perform the following work at each location:

1. Equipment Transport

1. Coordinate with DHHL on equipment arrival at island docks

1. Transport DHHL-provided equipment from dock to installation site

1. Provide secure storage if needed between pickup and installation

1. Site Preparation

1. Survey and verify exact placement location with DHHL and facility representatives

1. Verify ADA compliance of proposed installation site and access pathways

1. Obtain necessary permits from facility owners and local authorities

1. Complete Surety Proposal Bond forms (Exhibit D) (*amended)

1. Concrete Work (where required)

1. Excavate and prepare site per plans (Exhibit A)

1. Install rebar and formwork as specified

1. Pour and finish concrete pad to specified dimensions and tolerances

1. Allow adequate curing time before installation

1. Installation

1. Uncrate and inspect DHHL-provided equipment

1. Install and level station per manufacturer specifications

1. Anchor station using self-ballast system or as specified

1. Ensure ADA compliance of final installation including clear space and approach paths

1. Testing and Acceptance

1. Verify solar panel operation and charging functionality

1. Test all charging outlets (AC, USB-A, USB-C)

1. Document installation with photographs

1. Provide training to facility staff on basic operation

1. Cleanup and Documentation

1. Remove all debris, packaging, and construction materials

1. Restore site to clean condition

1. Submit installation completion report with photos and test results

2.3 ADA Compliance

All installations shall comply with current ADA guidelines and Hawaii Accessibility Code. Contractors shall ensure proper clearances, approach paths, and accessible seating arrangements per Exhibit A plans.

2.4 Schedule

Installation shall be completed within 30 calendar days of receiving Notice to Proceed for each location. DHHL will coordinate equipment delivery and issue separate Notices to Proceed for each island group.

3. FEDERAL FUNDING COMPLIANCE

This project is funded by federal funds (NTIA TBCP Grant NT23TBC0290054) and contractors must comply with all applicable federal requirements including:

Equal Employment Opportunity:

1. Executive Order 11246 - Non-discrimination and affirmative action requirements Davis-Bacon Prevailing Wage Requirements:

1. Construction work exceeding $2,000 must comply with Davis-Bacon prevailing wage rates

1. Contractors must submit certified payroll reports Environmental and Procurement Compliance:

1. Clean Air Act and Federal Water Pollution Control Act compliance

1. Debarment and Suspension verification (SAM.gov exclusions)

1. Anti-Lobbying requirements (Byrd Amendment) Required Certifications:

All bidders must provide signed federal compliance certifications including:

1. Equal Employment Opportunity certification

1. Davis-Bacon compliance acknowledgment

1. Debarment/suspension certification

1. Anti-lobbying certification

4. PROPOSAL SUBMISSION REQUIREMENTS

4.1 Proposal Format

Proposals shall be submitted electronically via HIePRO and include:

Technical Proposal:

1. Company qualifications and relevant project experience

1. Proposed work plan and schedule for each island

1. Personnel qualifications and subcontractor list (if applicable)

1. ADA compliance approach Cost Proposal:

1. Pricing for each island:

1. Molokai (2 locations, both with concrete pads)

1. Hawaii Island (1 location with concrete pad)

1. Oahu (3 locations, 1 with concrete pad)

1. Kauai (1 location with concrete pad)

1. Breakdown showing equipment transport, site preparation, concrete work (if applicable), installation, and testing

1. Overall cost is not to exceed FOUR HUNDRED THIRTY-FIVE THOUSAND FOUR HUNDRED DOLLARS ($435,400.00) Compliance Documentation:

1. Federal compliance certifications (complete package)

1. Current Hawaii Compliance Express (HCE) Certificate

1. Contractor license (CT or C-8 as applicable)

1. Certificate of insurance (general liability, workers compensation)

1. Surety proposal bond forms (complete package) (*amended)

4.2 Offeror Options

Offerors must submit proposals for:

1. All locations statewide

DHHL will award contract to a single contractor to provide services for all the different islands and locations.

5. EVALUATION CRITERIA

Proposals will be evaluated using the following criteria:

1. Technical Qualifications (40%) - Experience, work plan, and personnel qualifications

1. Compliance (20%) - Complete package of compliance certifications/ documentation

1. Cost (40%) - Total project cost per island

6. CONTRACT TERMS

1. Contract Type: Firm Fixed Price per island

1. Payment Terms: Progress payments upon completion of each location with final payment upon acceptance

1. Performance Period: 30 calendar days per location from Notice to Proceed

1. Warranty: 1-year workmanship warranty on installation

7. PROPOSAL SCHEDULE

1. Pre-Offer Conference: July 15, 2026 at 10:00 AM HST

1. Questions Due: August 18, 2026 at 5:00 PM HST (*amended)

1. Answers Posted: August 20, 2026 at 5:00 PM HST (*amended)

1. Proposals Due: September 4, 2026 at 5:00 PM HST (*amended)

8. POINT OF CONTACT

Name: Aislen Bacalso, Broadband Coordination Assistant Phone: (808) 570-4883 Email: aislen.v.bacalso@hawaii.gov Method of Submission: HIePRO only Questions and Clarifications: All questions must be submitted electronically through HIePRO. DHHL may refuse to answer questions received outside of HIePRO or after the deadline.

ATTACHMENTS

1. Exhibit A – Installation Plans and Specifications

1. Exhibit B – Solar Charging Station Equipment Specifications

1. Exhibit C – Federal Compliance Certification Package

1. Exhibit D – Surety Proposal Bond Forms (*amended)

File details come from the government source that posted it. Updated .