Sol_140P8626Q0009.pdf
PDF 770 KB Posted
- Attached to
- Replace Pump Station 840 Generator, GOGA Federal contract opportunity
- Solicitation number
- 140P8626Q0009
About this file
This is a Request for Quotation (RFQ) issued by the National Park Service (NPS) at Golden Gate National Recreation Area for replacement of pump station 840 generator and related equipment. The solicitation number is 140P8626Q0009, issued February 10, 2026, with quotations due by March 2, 2026, at 12:00 PM Pacific Standard Time. This is a Total Small Business Set-Aside restricted to concerns with annual gross receipts not exceeding $19,000,000 under NAICS code 238210 (Electrical Contractors). The contract will be a firm-fixed-price purchase order with a 365-day performance period commencing within 10 days of notice to proceed. An organized site visit is scheduled for February 18, 2026, at 10:00 AM PST, requiring RSVP by February 17, 2026.
The base requirement (Line Item 1) is to replace the 840 generator set on a lump-sum basis. Option Item 1 (Line Item 2) is to replace the automatic transfer switch, also on a lump-sum basis. Quotations must include pricing for both the base item and option item. Quoters must submit the completed SF-1442 form, Section B price schedule, acknowledgment of amendments, Technical Information and Past Performance form, technical approach narrative (limited to two pages), and proof of current California Contractor State License (A, B, or C-10 Electrical). Submission is by email only to Quinn Rankin at Quinn_Rankin@nps.gov with RFQ number in subject line. Davis-Bacon wage rates apply. Contractors must furnish performance and payment bonds within 10 days of award if the contract exceeds $35,000. Liability insurance of $500,000 per person, $1,000,000 per occurrence, and $500,000 property damage is required prior to work commencement. Questions must be received by February 24, 2026, by 10:00 AM PST, with responses posted by February 27, 2026. Award will be made to the responsible quoter whose quotation is most advantageous considering price, relevant experience, past performance, California contractor license status, and technical approach.
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P8626Q0009
NPS, PWR - GOGA MABO
Building 201, Fort Mason San Francisco CA 94123
Quinn_Rankin@nps.gov
0044035297
PPG
Quinn Rankin
02/10/2026
03/02/2026
10 365
The National Park Service (NPS) at Golden Gate National Recreation Area (GOGA) has a requirement to replace pump station 840 generator. The Contractor shall provide all supervision, labor, equipment, testing, and supplies necessary to complete the work as identified in the project specifications and associated documents provided as attachments to the solicitation.
The North American Industry Classification System (NAICS) Code for this requirement is 238210-Electrical
Contractors, with a corresponding size standard of $19,000,000 in annual gross receipts for the past three years.
This acquisition is a Total Small Business Set-Aside. Quotations are solicited only from small business concerns. Quotations received from concerns that are not small business concerns shall not be considered.
The Government anticipates award of a firm-fixed-price purchase order resulting from this solicitation.
Evaluation for award will be made in accordance with the simplified acquisition procedures outlined in
FAR Part 13.106. The Government anticipates issuing an order resulting from this request for quotation
Continued...
1 31
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS, PWR - GOGA MABO
Building 201, Fort Mason San Francisco CA 94123
PPG
Quinn Rankin
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
to the responsible quoter whose quotation will be most advantageous to the Government, price and other factors considered as listed in the
Request for Quotation (see Section M).
See Attachment 1 Scope of Work for a detailed description of the requirement.
Refer to provisions and clauses and other attachments for additional information about this requirement and instructions on how to submit a quotation.
Site Visit: See Section L for details regarding the organized site visit.
Submit questions only through email to the person identified in Section L.
Quotations must be received in their entirety via email as instructed in Section L no later than the date and time specified in Block 13 of the SF-1442. Quoters who do not submit clear identifiable documentation in accordance with the instructions may not be accepted or considered further for award.
A bid bond is not required. Contractors are reminded that any amount awarded over $35,000 requires submission of a payment bond. Any amount over $150,000.00 requires both payment and performance bonds. Bonds are due no later than 10 calendar days after award and are required for 100% of the awarded amount.
Liability Insurance is also required prior to commencement of work. See Section I for details regarding Liability Insurance.
System updates may lag policy updates. The
System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-33
Public Disclosure of Greenhouse Gas Emissions and Reduction Goals-Representation, and paragraph (t) of 52.212-3, Offeror
Representations and Certifications-Commercial
Products and Commercial Services. Agencies will
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
not consider or use these representations.
Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
The government reserves the right to cancel this solicitation. All costs associated with the preparation of quotes are at the contractor's own expense.
Delivery: 365 Days After Notice to Proceed
Delivery Location Code: 0011283305
NPS, GOLDEN GATE NRA
Bldg. 201, Fort Mason
San Francisco CA 94123-1307 US
00010 Replace 840 Genset (Generator Set)
Product/Service Code: H943
Product/Service Description: OTHER
QC/TEST/INSPECT- PUMPS AND COMPRESSORS
00020 Option Item 1: Replace Automatic Transfer
Switch
(Option Line Item)
Anticipated Exercise Date 1
Product/Service Code: H943
Product/Service Description: OTHER
QC/TEST/INSPECT- PUMPS AND COMPRESSORS
Request for
Quotation
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Part I – THE SCHEDULE
SECTION A – SOLICITATION/CONTRACT FORM
Solicitation, Offer, and Award (SF 1442) - pages 1- 4 of this package.
SECTION B – SUPPLIES OR SERVICES AND PRICES
B.1 – Bid Schedule
Contract Price Schedule National Park Service (NPS) - Golden Gate National Recreation Area
PARK - PMIS: GOGA-350388
Developed Area: Marin Headlands
Project Title:
Replace Generator and Automatic Transfer Switch (ATS) at Lift Station 840
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts governs.
Round totals and extended prices to whole dollars.
Contract Line- Item
Number
(CLIN)
Contract Line-Item (CLIN) Title Quantity Unit of
Measure Total Price
1 BASE ITEM: Replace Generator 1 LS
TOTAL BASE PRICE (Contract Line-Item Number 1)
2 OPTION ITEM 1: Replace ATS 1 LS
TOTAL BASE PLUS OPTION (Contract Line-Item Numbers 1 2
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1 – Project Specifications
See the attached project specifications and associated documents, listed in Section J of this procurement, for project requirements.
(End of Clause)
SECTION D – PACKAGING AND MARKING
There are no clauses in this section.
SECTION E – INSPECTION AND ACCEPTANCE
E.1 – 52.246-12 – Inspection of Construction (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may --
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the
Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
SECTION F – DELIVERIES OR PERFORMANCE
F.1 –52.211-10 – Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 365 days following receipt of the notice to proceed.
The time stated for completion shall include final cleanup of the premises.
F.3 – 52.242-14 Suspension of Work (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1)by an act of the Contracting Officer in the administration of this contract, or
(2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed-
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting
Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
F.4 – Deliverable (Post-Award): Contractor’s Daily Logs
Contractor shall prepare a daily log for each day’s work is performed under this contract. Copies of daily logs shall be submitted to the Contracting Officer, and may be compiled and submitted weekly, with payroll. Time necessary for completion of daily log is approximately 15 to 30 minutes. The contractor may choose to use its own format if the following elements are included on the log:
(a) Project Name
(b) Contract number
(c) Date
(d) Prime Contractor and/or Subcontractor
(e) Work performed, including number of employees by job categories (indicate if "prime" or "sub")
(f) Heavy equipment on job, hours worked (indicate if "prime" or "sub")
(g) Materials delivered
(h) Official visitors to site
(i) Inspections performed
(j) Verbal instruction received from government on construction deficiencies
(k) Certification (prime contractor's signature/COR's signature)
SECTION G – CONTRACT ADMINISTRATION DATA
G.1 – Contract Administration
The Contracting Officer's Representative (COR) for this contract will be:
Named at time of award
The Contracting Officer (CO) with overall responsibility for this contract will be:
Quinn Rankin
Quinn_Rankin@nps.gov
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
G.2 –1452.201-70 – Authorities and Delegations (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the
Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The
Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the
COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.3 – 1452.204-70 – Release of Claims – Department of the Interior (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form
(DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 10 of
G.4 – Construction Contract Administration
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies to provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at:
https://www.doi.gov/pam/acquisition/policy/constructioncontract.
G.5 – Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (APR
2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's
Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the
Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4
Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
The Contractor shall submit a draft Invoice Package, including copies of the following documents, to the
National Park Service’s (NPS) Contracting Officer’s Representative (COR), with a copy to the
Contracting Officer, a minimum of 5 working days prior to submitting the formal Invoice through IPP.
Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the
NPS Contracting Officer (CO) and the Contractor. If the COR recommends acceptance, the Contractor shall submit a copy of the final version of the COR’s checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the COR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments as required by contract clause 52.232-5)
3. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records.
4. Completed copy of the Payroll Report PII Certification sheet
5. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
6. A copy of the current construction schedule (refer to project specification section 013216)
7. A copy of the current Schedule of Values (refer to project specification section 013216)
The Contractor must use the IPP website for submitting requests for payment. The Contractor
Government Business Point of Contact (as listed SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
https://www.doi.gov/pam/acquisition/policy/constructioncontract https://www.ipp.gov/
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its quotation.
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1 – Wage Rates
Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section J). The project is in Marin County, California.
H.2 – Workers Compensation
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of Section 3700 of the Labor Code of the State of
California. Evidence of coverage is required before commencement of project work.
H.3 – Site-Specific Safety Plan
A site-specific safety plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site-specific plan. The site-specific safety and health plan shall establish in detail the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site-specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site-specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
As work proceeds, the site-specific safety plan shall be adapted to new situations and new conditions.
Changes and modifications to the accepted site-specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions to safeguard on-site personnel, visitors, the public, and the environment.
Prior to submittal to the COR, the site-specific safety plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The contractor shall submit to the CO and COR the contractor's site-specific safety and health plan for review and acceptance by the NPS
Safety Representative.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and
Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 12 of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
H.4 – Archeological Findings
(a) Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall suspend operations at the site of discovery;
notify Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, he will be compensated by an equitable adjustment under the General Provisions of the Contract.
H.5 – Conduct of Operations
At all times the Contractor shall conduct his organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with approval of the Contracting Officer.
Part II – Contract Clauses
SECTION I – CONTRACT CLAUSES
I.1 – 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): Part 52 - Solicitation
Provisions and Contract Clauses | Acquisition.GOV
52.203-17 Contractor Employee Whistleblower Rights (NOV 2023)
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
(JAN 2017)
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020)
52.204-13 System for Award Management Maintenance (OCT 2018)
52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)
52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) https://www.acquisition.gov/far/part-52
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 13 of
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance
Services or Equipment (NOV 2021)
52.204-27 Prohibition on a ByteDance Covered Application (JUN 2023)
52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JAN 2025)
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)
52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Products and
Commercial Services) (OCT 2025) (DEVIATION FEB 2025)
52.215-8 Order of Precedence – Uniform Contract Format (OCT 1997)
52.219-6 Notice of Total Small Business Set-Aside (NOV 2020)
52.219-28 Post-Award Small Business Program Representation (JAN 2025)
52.222-3 Convict Labor (JUN 2003)
52.222-6 Construction Wage Rate Requirements (AUG 2018) (DEVIATION FEB 2025)
52.222-7 Withholding of Funds (MAY 2014)
52.222-8 Payrolls and Basic Records (JUL 2021)
52.222-9 Apprentices and Trainees (JUL 2005) (DEVIATION FEB 2025)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (MAY 2014) (DEVIATION FEB 2025)
52.222-12 Contract Termination-Debarment (MAY 2014) (DEVIATION FEB 2025)
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulation
(MAY 2014)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (MAY 2014)
52.222-36 Equal Opportunity For Workers with Disabilities (JUN 2020)
52.222-50 Combating Trafficking in Persons (OCT 2025)
52.222-55 Minimum Wages Under Executive Order 14026 DEVIATION (OCT 2023)
52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2022)
52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (MAY
2024) (DEVIATION FEB 2025)
52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024)
52.223-23 Sustainable Products and Services (MAY 2024) (DEVIATION FEB 2025)
52.225-9 Buy American – Construction Materials (OCT 2022)
52.225-11 Buy American – Construction Materials Under Trade Agreements (NOV 2023)
52.225-13 Restriction on Certain Foreign Purchases (FEB 2021)
52.226-7 Drug-Free Workplace (MAY 2024)
52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (MAY 2024)
52.227-1 Authorization and Consent (JUN 2020)
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020)
52.227-4 Patent Indemnity – Construction Contracts (DEC 2007)
52.228-2 Additional Bond Security (OCT 1997)
52.228-11 Individual Assurety- Pledge of Assets (FEB 2021) (DEVIATION MAY 2023)
52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022)
52.228-13 Alternative Payment Protections (JULY 2000)
52.228-14 Irrevocable Letter of Credit (NOV 2014)
52.228-15 Performance and Payment Bonds – Construction (JUN 2020)
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 14 of
52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014)
52.232-27 Prompt Payment for Construction Contracts (JAN 2017)
52.232-33 Payment by Electronic Funds Transfer-System for Award Management (OCT 2018)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023)
52.233-1 Disputes-(MAY 2014)-Alternate I (DEC 1991)
52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)
52.236-2 Differing Site Conditions (APR 1984)
52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)
52.236-5 Material and Workmanship (APR 1984)
52.236-6 Superintendence by the Contractor (APR 1984)
52.236-7 Permits and Responsibilities (NOV 1991)
52.236-8 Other Contracts (APR 1984)
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
(APR 1984)
52.236-10 Operations and Storage Areas (APR 1984)
52.236-11 Use and Possession Prior to Completion (APR 1984)
52.236-12 Cleaning Up (APR 1984)
52.236-13 Accident Prevention (NOV 1991)
52.236-17 Layout of Work (APR 1984)
52.236-21 Specifications and Drawings for Construction (FEB 1997)
52.236-26 Preconstruction Conference (FEB 1995)
52.242-17 Government Delay of Work (APR 1984)
52.243-5 Changes and Changed Conditions (APR 1984)
52.244-6 Subcontracts for Commercial Items and Commercial Services (OCT 2025)
52.246-12 Inspection of Construction (AUG 1996)
52.246-21 Warranty of Construction (MAR 1994)
52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form)
(APR 1984)
52.249-10 Default (Fixed-Price Construction) (APR 1984)
52.253-1 Computer Generated Forms (JAN 1991)
I.2 –52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—
PROHIBITION (DEC 2023)
(a) Definitions. As used in this clause—
Covered article, as defined in 41 U.S.C. 4713(k), means—
(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;
(2) Telecommunications equipment or telecommunications service, as those terms are defined in section
3 of the Communications Act of 1934 ( 47 U.S.C. 153);
(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or
(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.
https://www.govinfo.gov/link/uscode/41/4713 https://www.govinfo.gov/link/uscode/40/11101 https://www.govinfo.gov/link/uscode/47/153 https://www.ecfr.gov/current/title-32/part-2002
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 15 of
FASCSA order means any of the following orders issued under the Federal Acquisition Supply Chain
Security Act (FASCSA) requiring the removal of covered articles from executive agency information systems or the exclusion of one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201–1.303(d) and (e):
(1) The Secretary of Homeland Security may issue FASCSA orders applicable to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.
(2) The Secretary of Defense may issue FASCSA orders applicable to the Department of Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of
FASCSA order may be referred to as a DoD FASCSA order.
(3) The Director of National Intelligence (DNI) may issue FASCSA orders applicable to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph
(2) of this definition. This type of FASCSA order may be referred to as a DNI FASCSA order.
Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—
(1) The Office of the Director of National Intelligence;
(2) The Central Intelligence Agency;
(3) The National Security Agency;
(4) The Defense Intelligence Agency;
(5) The National Geospatial-Intelligence Agency;
(6) The National Reconnaissance Office;
(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of
Energy;
(9) The Bureau of Intelligence and Research of the Department of State;
(10) The Office of Intelligence and Analysis of the Department of the Treasury;
(11) The Office of Intelligence and Analysis of the Department of Homeland Security; or
(12) Such other elements of any department or agency as may be designated by the President, or designated jointly by the Director of National Intelligence and the head of the department or agency concerned, as an element of the intelligence community.
National security system, as defined in 44 U.S.C. 3552, means any information system (including any telecommunications system) used or operated by an agency or by a contractor of an agency, or other organization on behalf of an agency—
(1) The function, operation, or use of which involves intelligence activities; involves cryptologic activities related to national security; involves command and control of military forces; involves equipment that is an integral part of a weapon or weapons system; or is critical to the direct fulfillment of military or intelligence missions, but does not include a system that is to be used for routine administrative and business applications (including payroll, finance, logistics, and personnel management applications); or https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(d) https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(e) https://www.govinfo.gov/link/uscode/50/3003 https://www.govinfo.gov/link/uscode/44/3552
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 16 of
(2) Is protected at all times by procedures established for information that have been specifically authorized under criteria established by an Executive order or an Act of Congress to be kept classified in the interest of national defense or foreign policy.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of any covered articles, or any products or services produced or provided by a source.
This applies when the covered article or the source is subject to an applicable FASCSA order. A reasonable inquiry excludes the need to include an internal or third-party audit.
Sensitive compartmented information means classified information concerning or derived from intelligence sources, methods, or analytical processes, which is required to be handled within formal access control systems established by the Director of National Intelligence.
Sensitive compartmented information system means a national security system authorized to process or store sensitive compartmented information.
Source means a non-Federal supplier, or potential supplier, of products or services, at any tier.
(b) Prohibition.
(1) Unless an applicable waiver has been issued by the issuing official, Contractors shall not provide or use as part of the performance of the contract any covered article, or any products or services produced or provided by a source, if the covered article or the source is prohibited by an applicable FASCSA orders as follows:
(i) For solicitations and contracts awarded by a Department of Defense contracting office, DoD
FASCSA orders apply.
(ii) For all other solicitations and contracts DHS FASCSA orders apply.
(2) The Contractor shall search for the phrase “FASCSA order” in the System for Award Management
(SAM) at https://www.sam.gov to locate applicable FASCSA orders identified in paragraph (b)(1).
(3) The Government may identify in the solicitation additional FASCSA orders that are not in SAM, which are effective and apply to the solicitation and resultant contract.
(4) A FASCSA order issued after the date of solicitation applies to this contract only if added by an amendment to the solicitation or modification to the contract (see FAR 4.2304(c)). However, see paragraph (c) of this clause.
(5)
(i) If the contractor wishes to ask for a waiver of the requirements of a new FASCSA order being applied through modification, then the Contractor shall disclose the following:
(A) Name of the product or service provided to the Government;
(B) Name of the covered article or source subject to a FASCSA order;
(C) If applicable, name of the vendor, including the Commercial and Government Entity code and unique entity identifier (if known), that supplied or supplies the covered article or the product or service to the Offeror;
(D) Brand;
(E) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);
(F) Item description;
(G) Reason why the applicable covered article or the product or service is being provided or used;
(ii) Executive agency review of disclosures. The contracting officer will review disclosures provided in paragraph (b)(5)(i) to determine if any waiver is warranted. A contracting officer may choose not to pursue a waiver for covered articles or sources otherwise covered by a FASCSA order and to instead pursue other appropriate action.
https://www.sam.gov/ https://www.acquisition.gov/far/subpart-4.23#FAR_4_2304
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 17 of
(c) Notice and reporting requirement.
(1) During contract performance, the Contractor shall review SAM.gov at least once every three months, or as advised by the Contracting Officer, to check for covered articles subject to FASCSA order(s), or for products or services produced by a source subject to FASCSA order(s) not currently identified under paragraph (b) of this clause.
(2) If the Contractor identifies a new FASCSA order(s) that could impact their supply chain, then the
Contractor shall conduct a reasonable inquiry to identify whether a covered article or product or service produced or provided by a source subject to the FASCSA order(s) was provided to the Government or used during contract performance.
(3)
(i) The Contractor shall submit a report to the contracting office as identified in paragraph (c)(3)(ii) of this clause, if the Contractor identifies, including through any notification by a subcontractor at any tier, that a covered article or product or service produced or provided by a source was provided to the
Government or used during contract performance and is subject to a FASCSA order(s) identified in paragraph (b) of this clause, or a new FASCSA order identified in paragraph (c)(2) of this clause. For indefinite delivery contracts, the Contractor shall report to both the contracting office for the indefinite delivery contract and the contracting office for any affected order.
(ii) If a report is required to be submitted to a contracting office under (c)(3)(i) of this clause, the
Contractor shall submit the report as follows:
(A) If a Department of Defense contracting office, the Contractor shall report to the website at https://dibnet.dod.mil.
(B) For all other contracting offices, the Contractor shall report to the Contracting Officer.
(4) The Contractor shall report the following information for each covered article or each product or service produced or provided by a source, where the covered article or source is subject to a FASCSA order, pursuant to paragraph (c)(3)(i) of this clause:
(i) Within 3 business days from the date of such identification or notification:
(A) Contract number;
(B) Order number(s), if applicable;
(C) Name of the product or service provided to the Government or used during performance of the contract;
(D) Name of the covered article or source subject to a FASCSA order;
(E) If applicable, name of the vendor, including the Commercial and Government Entity code and unique entity identifier (if known), that supplied the covered article or the product or service to the
Contractor;
(F) Brand;
(G) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);
(H) Item description; and
(I) Any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the information in paragraph (c)(4)(i) of this clause:
(A) Any further available information about mitigation actions undertaken or recommended.
(B) In addition, the Contractor shall describe the efforts it undertook to prevent submission or use of the covered article or the product or service produced or provided by a source subject to an applicable
FASCSA order, and any additional efforts that will be incorporated to prevent future submission or use https://dibnet.dod.mil/
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 18 of of the covered article or the product or service produced or provided by a source that is subject to an applicable FASCSA order.
(d) Removal. For Federal Supply Schedules, Governmentwide acquisition contracts, multi-agency contracts or any other procurement instrument intended for use by multiple agencies, upon notification from the Contracting Officer, during the performance of the contract, the Contractor shall promptly make any necessary changes or modifications to remove any product or service produced or provided by a source that is subject to an applicable FASCSA order.
(e) Subcontracts.
(1) The Contractor shall insert the substance of this clause, including this paragraph (e) and excluding paragraph (c)(1) of this clause, in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products and commercial services.
(2) The Government may identify in the solicitation additional FASCSA orders that are not in SAM, which are effective and apply to the contract and any subcontracts and other contractual instruments under the contract. The Contractor or higher-tier subcontractor shall notify their subcontractors, and suppliers under other contractual instruments, that the FASCSA orders in the solicitation that are not in
SAM apply to the contract and all subcontracts.
I.4 – 52.252-6 Authorized Deviations in Clauses (NOV 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Not Applicable (48 CFR) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
L.5 - 1452.228-70 – Liability Insurance – Department of Interior (JUL 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$500,000.00 each person
$1,000,000.00 each occurrence
$500,000.00 property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy
2/10/2026
Document No.
140P8626Q0009
Document Title
Replace Pump Station 840 Generator, Golden
Gate National Recreation Area
Page 19 of number and a…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .