This is a Request for Quote (RFQ) for construction services issued by the National Park Service for heat pump replacement work at Brown v. Board of Education National Historic Park (BRVB) in Topeka, Kansas.
The solicitation seeks quotes for removal, disposal, and replacement of existing water-to-water heat pumps and geothermal circulation pumps, along with installation of a refrigeration detection and mitigation system via ventilation and shunt trip of mechanical room ignition sources. The project magnitude is estimated between $50,000 and $100,000, with a firm-fixed-price contract anticipated for award by July/August 2026 and performance beginning in August 2026. Quotes are due by August 4, 2026 at 12:00 PM ET and must be submitted via email in PDF format to craig_bryant@ios.doi.gov. An organized site visit is scheduled for July 8, 2026 at 10:00 AM CT at Monroe Elementary School. The contract includes a 10-day performance notice period and 120-calendar-day completion timeline. This is a 100% small business set-aside under NAICS code 238220 with a $19 million size standard. Offerors must be registered in SAM with active status and possess a Unique Entity Identifier. Construction Wage Rate Requirements for Shawnee County, Kansas apply. Performance and payment bonds are required within 10 days of award, with 100% payment bond required. Award will be made to the responsible offeror providing the best value based on price, technical capability, and prior experience, evaluated in groups of three starting with the lowest-priced quotes. The contracting officer is Craig Bryant at craig_bryant@ios.doi.gov, (330) 524-8442.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Specifications_-_Heat_Pump_Replace_0001.pdf | ||
| Site_Visit_Sign-in_Sheet_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Sol_140P6426Q0069_Amd_0001.pdf | ||
| Attachment_-_Drawings-Plans.pdf | ||
| Attachment_-_Submittal_List.pdf | ||
| Price_Schedule_-_Heat_Pump_Replace.pdf | ||
| Specifications_-_Heat_Pump_Replace.pdf | ||
| Attachment_-_Construction_Contract_Administration.pdf | ||
| Price_Schedule_-_Heat_Pump_Replace.xlsx | XLSX spreadsheet | |
| Technical_Questionnaire.pdf | ||
| Wage_Determination_-_Shawnee_Co.pdf | ||
| Attachment_-_Notice_to_Contractors.pdf | ||
| Technical_Questionnaire.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NO.
5. REQUISITION/PURCHASE REQUEST NO.
CODE
6. PROJECT NO.
8. ADDRESS OFFER TO
4. CONTRACT NO.
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
NEGOTIATED (RFP) REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF
SEALED BID (IFB) INVITATION FOR BID
9. FOR
INFORMATION CALL
PAGES
140P6426Q0069
NPS, MWR - Ohio MABO 1113 West Aurora Road Sagamore Hills OH 44067-1678
0044045011
PMO
Craig Bryant 4407173706
06/22/2026
08/04/2026
10 120 See Project Specifications
Scope of Work: Work will consist of providing all labor, materials, tools and other equipment necessary for removal, disposal, and replacement of existing water to water heat pumps and geothermal circulation pumps. Installation of refrigeration detection and mitigation system via ventilation and shunt trip of mechanical room ignition sources.
Magnitude of Construction: Between $50,000 and $100,000
This project is subject to the Construction Wage Rate Requirements Statute
Set Aside: Total Small Business Set Aside
Site Visit: An organized site visit has been scheduled for this project. See Provision 52.236-27 Site
Visit (Construction) for all site visit information
Type of Acquisition: A firm-fixed price contract will be awarded
Continued...
1 29
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Continued...
AMENDMENT
NUMBER
DATE.
NPS, MWR - Ohio MABO 1113 West Aurora Road Sagamore Hills OH 44067-1678
PMO
Craig Bryant
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P6426Q0069
Submission Requirements: See pages #11-13 of the solicitation
Delivery: 120 Days After Notice to Proceed
Delivery Location Code: 0011283108
NPS, MWR, Brown v. Board
1515 SE Monroe Street
Topeka KS 66612-1143 US
00010 Heat Pump Replacement IAW attached Project
Specifications and supporting documents
140P6426Q0069 Heat Pump Replacement - BRVB Page 4 of 29
I. DESCRIPTION
THIS IS A NOTICE OF INTENT FOR REQUEST FOR QUOTE. This is a combined synopsis/solicitation for commercial construction services prepared in accordance with FAR Part 12. This announcement constitutes the only solicitation. Offers are being requested and a separate written solicitation will not be issued.
Solicitation number 140P6426Q0069 is issued as a request for quote (RFQ) for Heat Pump Replacement at Brown v. Board of Education National Historic Park (BRVB).
This acquisition is set-aside for small business concerns. This solicitation incorporates provisions and clauses by reference. The full text of provisions and clauses may be accessed electronically at www.acquisition.gov.
This requirement is a 100% total small business set-aside. The associated NAICS code is 238220. The small business size standard is $19M. Provisions and clauses are incorporated in this solicitation document.
Anticipated Award Date: summer 2026 – performance to begin Aug 2026
To be considered for award your company must obtain a Unique Entity Identifier (UEI). Your company must also be registered in the System for Award Management (SAM) and be considered a small business for the size standard associated with the NAICS code found in block 10 on page one (1) of this solicitation, and this registration must be “active” in SAM at the time of quote/proposal close date/time - as well as, at the time of award and throughout the entire award/contract performance.
Website: https://www.sam.gov
If you have any registration questions or if you need assistance with registration or updating SAM, please contact the National APEX Accelerator nearest you.
Website: Home - National Apex Accelerator Alliance // APEX Accelerators
GENERAL INFORMATION:
This solicitation is a Request for Quote (RFQ) Solicitation issued on Standard Form (SF) 1442. Award of this contract will be made according to FAR Part 12 Acquisition of Commercial Products and Commercial Services. All references to “proposal” in this solicitation shall be understood to mean “quotation.”
Quotations shall be evaluated in an impartial manner and consideration given to those with the highest perceived value to the government.
Work will consist of providing all labor, materials, tools and other equipment necessary for removal, disposal, and replacement of existing water to water heat pumps and geothermal circulation pumps.
Installation of refrigeration detection and mitigation system via ventilation and shunt trip of mechanical room ignition sources. We anticipate that work will begin in the summer of 2026.
PROJECT MAGNITUDE: Between $50,000 and $100,000
TYPE OF CONTRACT: This will be a firm-fixed price contract expected to be awarded to a prime contractor by July/Aug 2026 with performance to begin in August 2026.
http://www.acquisition.gov/ https://www.sam.gov/ https://www.napex.us/ https://www.apexaccelerators.us/#/
140P6426Q0069 Heat Pump Replacement - BRVB Page 5 of 29
Construction Wage Rate Requirements for Shawnee County, KS will apply.
EVALUATION FACTORS: will be addressed in the official solicitation
SITE VISIT: Please see solicitation for details
The contracting office will not provide hardcopies or email copies of the solicitation.
Construction Contract Administration
Federal Acquisition Regulation (FAR) 36.211(b) and RFO FAR 36.101-4 requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: FAR Overhaul - Part 36 | Acquisition.GOV
COMPLIANCE WITH RECENT EXECUTIVE ORDERS 14148/14208
System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals— Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Agencies will not consider or use these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
The following Federal Acquisition Regulation (FAR) provisions and clauses shall be applicable to this solicitation and award: For full text version of these provisions and clauses, please go to the following internet address: www.acquisition.gov
II. SUBMISSION REQUIREMENTS
Closing Response Date/Time:
Quotes are due by 4 Aug 2026 @ 12PM ET
Contact Point or Contracting Officer:
Craig Bryant - email - craig_bryant@ios.doi.gov
Questions regarding this solicitation:
Will only be accepted until 14 July 2026 @
12PM ET
Submission Requirements / How to Submit an Offer:
Offers to be submitted via email
Please see pages #11-13 of this solicitation for submission requirement details.
https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-36 https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-36 http://www.acquisition.gov/ mailto:craig_bryant@ios.doi.gov
140P6426Q0069 Heat Pump Replacement - BRVB Page 6 of 29
III. LIST OF LINE-ITEMS
ITEM NUMBER ITEM QUANTITY UNIT OF MEASURE
0010 Heat Pump Replacement IAW attached Project Specifications and supporting documents
LS
IV. DESCRIPTION OF REQUIREMENT(S)
Independently, and not as an agent of the Government, the contractor/vendor shall furnish all labor, materials, and equipment necessary to provide heat pump replacement construction services at BRVB.
Please see attached Project Specifications and other supporting documentation for details outlining additional pertinent information of this requirement.
V. DELIVERY INFORMATION/TERMS / PERIOD OF
PERFORMANCE
Please see attached Project Specifications and other supporting documentation for details outlining period of performance, to include place of performance.
VI. LIST OF PROVISIONS (BY REFERENCE)
52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): www.acquisition.gov
(End of provision)
140P6426Q0069 Heat Pump Replacement - BRVB Page 7 of 29
52.252-5 Authorized Deviations in Provisions (Nov 2020)
As prescribed in 52.107(e), insert the following provision in solicitations that include any FAR or supplemental provision with an authorized deviation. Whenever any FAR or supplemental provision is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the provision when it is used without deviation, include regulation name for any supplemental provision, except that the contracting officer shall insert "(DEVIATION)" after the date of the provision.
Authorized Deviations in Provisions (Nov 2020)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any ______________ [insert regulation name](48 CFR Chapter______) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation (Jan 2017) 52.204-7 System for Award Management - Registration (Nov 2024) (DEVIATION Mar 2026) 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations – Representation (Nov 2015) (DEVIATION May 2026) 52.212-1 Instructions to Offerors - Commercial Products and Commercial Services (Sep 2023) (DEVIATION Mar 2026) 52.214-34 Submission of Offers in the English Language (Apr 1991) 52.214-35 Submission of Offers in U.S. Currency (Apr 1991) 52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan-Certification (Aug 2009)
DEVIATION DATE
52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications (Jun 2020) DEVIATION DATE 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (Dec 2025) (DEVIATION Mar 2026)
VII. LIST OF CLAUSES (BY REFERENCE)
52.252-2 Clauses Incorporated by Reference (Feb 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): www.acquisition.gov
(End of clause) https://www.acquisition.gov/far/part-52#FAR_52_107
140P6426Q0069 Heat Pump Replacement - BRVB Page 8 of 29
52.252-6 Authorized Deviations in Clauses (Nov 2020)
As prescribed in 52.107(f), insert the following clause in solicitations and contracts that include any FAR or supplemental clause with an authorized deviation. Whenever any FAR or supplemental clause is used with an authorized deviation, the contracting officer shall identify it by the same number, title, and date assigned to the clause when it is used without deviation, include regulation name for any supplemental clause, except that the contracting officer shall insert "(DEVIATION)" after the date of the clause.
Authorized Deviations in Clauses (Nov 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any _____ [insert regulation name] (48 CFR _____) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-13 System for Award Management Maintenance (Oct 2018) (DEVIATION Mar 2026) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) (DEVIATION May 2026) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) (DEVIATION May 2026) 52.212-4 Terms and Conditions—Commercial Products and Commercial Services (Nov 2023) (DEVIATION Mar 2026) 52.219-6 Notice of Total Small Business Set-Aside (Mar 2020) (DEVIATION Jan 2026) 52.219-8 Utilization of Small Business Concerns (Jan 2025) (DEVIATION Jan 2026) 52.219-28 Post-Award Small Business Program Rerepresentation (Jan 2025) (DEVIATION Jan 2026) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) (DEVIATION May 2026) 52.222-3 Convict Labor (Jun 2003) (DEVIATION May 2026) 52.222-4 Contract Work Hours and Safety Standards- Overtime Compensation (Mar 2018) (DEVIATION May 2026) 52.222-6 Construction Wage Rate Requirements (Aug 2018) (DEVIATION May 2026) 52.222-7 Withholding of Funds (May 2014) (DEVIATION May 2026) 52.222-8 Payrolls and Basic Records (Jul 2021) (DEVIATION May 2026) 52.222-9 Apprentices and Trainees (Jul 2005) (DEVIATION May 2026) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) (DEVIATION May 2026) 52.222-11 Subcontracts (Labor Standards) (May 2014) (DEVIATION May 2026) 52.222-12 Contract Termination-Debarment (May 2014) (DEVIATION May 2026) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) (DEVIATION May 2026) 52.222-15 Certification of Eligibility (May 2014) 52.222-19 Child Labor-Cooperation with Authorities and Remedies (Mar 2026) (DEVIATION May 2026) 52.222-35 Equal Opportunity for Veterans (Jun 2020) (DEVIATION May 2026) 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) (DEVIATION May 2026) 52.222-37 Employment Reports on Veterans (Jun 2020) (DEVIATION May 2026) https://www.acquisition.gov/far/part-52#FAR_52_107
140P6426Q0069 Heat Pump Replacement - BRVB Page 9 of 29
52.222-40 Notification of Employee Rights Under the National Labor Relations Act (Dec 2010) (DEVIATION May 2026) 52.222-50 Combating Trafficking in Persons (Oct 2025) (DEVIATION May 2026) 52.222-55 Minimum Wages Under Executive Order 14026 (Jan 2022) (DEVIATION May 2026) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) (DEVIATION May 2026) 52.222-90 Addressing DEI Discrimination by Federal Contractors (Mar 2026) (DEVIATION May 2026) 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (May 2024) (DEVIATION May 2026) 52.223-23 Sustainable Products (May 2024) (DEVIATION May 2026) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance -- Work on a Government Installation (Jan 1997) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021) (DEVIATION May 2023) 52.228-15 Performance and Payment Bonds- Construction (Jun 2020) (DEVIATION May 2023) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) (DEVIATION Oct 2025) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-29 Terms for Financing of Purchases of Commercial Products and Commercial Services (Nov 2021) 52.232-30 Installment Payments for Commercial Products and Commercial Services (Nov 2021) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) DEVIATION DATE 52.233-3 Protest after Award (Aug 1996) DEVIATION DATE 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) DEVIATION DATE 52.236-2 Differing Site Conditions (Apr 1984) (DEVIATION Jan 2026) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) (DEVIATION Jan 2026) 52.236-5 Material and Workmanship (Apr 1984) (DEVIATION Jan 2026) 52.236-6 Superintendence by the Contractor (Apr 1984) (DEVIATION Jan 2026) 52.236-7 Permits and Responsibilities (Nov 1991) (DEVIATION Jan 2026) 52.236-8 Other Contracts (Apr 1984) (DEVIATION Jan 2026) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) (DEVIATION Jan 2026) 52.236-10 Operations and Storage Areas (Apr 1984) (DEVIATION Jan 2026) 52.236-11 Use and Possession Prior to Completion (Apr 1984) (DEVIATION Jan 2026) 52.236-12 Cleaning Up (Apr 1984) (DEVIATION Jan 2026) 52.236-13 Accident Prevention (Nov 1991) (DEVIATION Jan 2026) 52.236-14 Availability and Use of Utility Services (Apr 1984) (DEVIATION Jan 2026) 52.236-15 Schedules for Construction Contracts (Apr 1984) (DEVIATION Jan 2026) 52.236-17 Layout of Work (Apr 1984) (DEVIATION Jan 2026) 52.236-21 Specifications and Drawings for Construction (Feb 1997) (DEVIATION Jan 2026) 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (Apr 1984) 52.240-91 Security Prohibitions and Exclusions (Dec 2025) (DEVIATION Mar 2026)
140P6426Q0069 Heat Pump Replacement - BRVB Page 10 of 29
52.240-93 Basic Safeguarding of Covered Contractor Information Systems (Dec 2025) (DEVIATION Mar 2026) 52.246-21 Warranty of Construction (Mar 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-4 Termination for Convenience of the Government (Services) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)
VIII. PROVISIONS AND CLAUSES INCORPORATED BY FULL TEXT
52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (Feb 2016) (DEVIATION May 2026)
(a) As required by sections 744 and 745 of Division E of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L 113-235), and similar provisions, if contained in subsequent appropriations acts, the Government will not enter into a contract with any corporation that--
(1) Has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability, where the awarding agency is aware of the unpaid tax liability, unless an agency has considered suspension or debarment of the corporation and made a determination that suspension or debarment is not necessary to protect the interests of the Government; or
(2) Was convicted of a felony criminal violation under any Federal law within the preceding 24 months, where the awarding agency is aware of the conviction, unless an agency has considered suspension or debarment of the corporation and made a determination that this action is not necessary to protect the interests of the Government.
(b) The Offeror represents that—
(1) It is [ ] is not [ ] a corporation that has any unpaid Federal tax liability that has been assessed, for which all judicial and administrative remedies have been exhausted or have lapsed, and that is not being paid in a timely manner pursuant to an agreement with the authority responsible for collecting the tax liability; and
(2) It is [ ] is not [ ] a corporation that was convicted of a felony criminal violation under a Federal law within the preceding 24 months.
140P6426Q0069 Heat Pump Replacement - BRVB Page 11 of 29
ADDENDUM TO 52.212-1 INSTRUCTIONS TO OFFERORS - COMMERCIAL PRODUCTS AND
COMMERCIAL SERVICES (Sep 2023) (DEVIATION Mar 2026)
GENERAL INFORMATION
The National Park Service (NPS) is seeking quotations for construction services as attached in the accompanying Statement of Work/Project Specifications. The NPS intends to conduct this acquisition by use of simplified acquisition procedures in accordance with FAR Part 12.
To assure timely and equitable evaluation of quotes, offerors must follow the instructions contained herein. Offerors are required to meet all requirements, including terms and conditions, representations and certifications, and technical requirements. The offeror shall submit in the quote all requested information specified in this section of the Request for Quote (RFQ) at or before the exact time specified. There will be no public opening of the quotes received as a result of this RFQ. Failure to adhere to quotation requirements, at the time of submission, may result in the quotation being unacceptable to the Government and eliminated or ineligible from consideration for award.
North American Industry Classification System (NAICS) code and small business size standard. The NAICS code for this acquisition is 238220 with a size standard of $19 Million.
To be considered for award your company must obtain a Unique Entity Identifier (UEI). Your company must be registered in the System for Award Management (SAM) and be considered a small business for the size standard associated with the NAICS code stated above/utilized throughout this solicitation - this registration must have an “active” status in SAM, NO EXCEPTIONS, at the time of RFQ/RFP submission close date – as well as, at the time of award and throughout the entire award/contract performance.
The direct SAM website for registration is: SAM.gov | Home. If you have any registration questions or need assistance, please call the SAM helpdesk. You may also receive assistance by contacting the Procurement Technical Assistance Center nearest you at their website: Home - National Apex Accelerator Alliance // APEX Accelerators
Submit, at a minimum, an offer that conforms to the solicitation documents. By submission of an offer, the offeror unconditionally assents to the terms and conditions in this solicitation and in any solicitation attachments. Quotes offering alternative stipulations to the requirements of this solicitation will NOT be considered or accepted.
This RFQ does not commit the Government to any costs incurred in the preparation and submission of a quote or for any other costs incurred by any firm submitting a quote in response to this solicitation. Note specifically that the Offeror will not be participating in a sealed bid procurement process under this acquisition method. Issuance of this RFQ does not constitute an award commitment on the part of the Government.
All firms, prime contractors or subconsultants, involved in developing the design or specifications for this construction solicitation are not eligible and prohibited from receiving any part of this construction award. Quotes from or containing firms under these circumstances will not be considered for award.
If a respondent believes that requirements in these instructions contain an error, omission, or are otherwise flawed, the respondent shall immediately notify the Contracting Officer in writing (email is the preferred method) with supporting rationale prior to the closing of this RFQ.
Quotation must be valid for a minimum of 90 days.
Award is subject to and based on the availability of funds. This project is currently funded based upon an independent cost estimate.
Respondents shall not contact any government personnel related to this requirement other than the Contracting Officer and Contracting Specialist.
https://sam.gov/content/home https://www.napex.us/ https://www.apexaccelerators.us/#/
140P6426Q0069 Heat Pump Replacement - BRVB Page 12 of 29
All questions should be emailed directly to the Contracting Specialist. Only written RFI’s will be considered and responded to by the Government. NPS responses to RFIs will be posted as an amendment to the solicitation.
A) OFFER DUE DATE
1. To be considered for award, all quotes for this solicitation must be received no later than the date and time noted in the solicitation unless changed by amendment. Offerors are responsible for submitting quotes so as to reach the Government office designated in the solicitation by the time specified in the solicitation.
Offerors should consider and account for potential delays in transmissions between when an electronic submission is submitted and when an electronic submission is received. Late quotes will not be accepted.
B) QUESTIONS
Contractor questions regarding this solicitation will be accepted in writing by email to: craig_bryant@ios.doi.gov .
All questions shall be received no later than 14 July 2026 @ 12PM ET to be considered.
(Please reference provision 52.237-1 – Site Visit (Apr 1984) for site visit date).
C) TO SUBMIT AN OFFER / SUBMISSION REQUIREMENTS
1. Delivery of Offers:
Quotes shall be submitted via email. Quotes submitted via any means other than email shall not be accepted.
2. Quotes shall be sent to the following:
i. Contract Specialist: craig_bryant@ios.doi.gov
3. Title subject line for all quote submissions shall contain the solicitation number, project name and number of total emails (this is if the size limit of the attachment is too large to send in one email – please see size limits below), per the following example:
i. Subject: 140P6426Q0069 – Heat Pump Replacement – email 1 of 2
4. Submit quote documents in one quote package, PDF format, containing contents required as listed below in the CHECKLIST FOR QUOTE SUBMITTAL section.
i. Document titled as “QUOTE PACKAGE” in PDF format
5. Size Limits:
i. The total size limit of each email containing all attachments cannot/shall not exceed 25MB; so please ensure that the total size limit of individual attachments in the email conform with the size limitation for the total email attachment limit
ii. Page Format Restrictions and Limitations: Quotes will be 8 ½ " x 11" paper except for foldouts used for charts, tables, or diagrams, which may not exceed 11" x 17".
140P6426Q0069 Heat Pump Replacement - BRVB Page 13 of 29
CHECKLIST FOR QUOTE SUBMITTAL:
Document to Complete in Quote Package
Check Box
Checklist for Quote Submittal – the checklist is this page of the solicitation completed as the first page in the package
Signed acknowledgement of SF1442
Signed amendments (if applicable): Offeror shall acknowledge all solicitation amendments by signing the amendment and provide it with quote package OR acknowledge in Block 19 of SF 1442
Price/Bid Schedule: provide pricing on the attached Price/Bid Schedule. Total price shall be cited and if listed on the Solicitation Form, it must be the same amount listed. All pricing to be rounded to the nearest dollar. Alternate pricing and alternate quotes will not be accepted.
Provide Technical Capability:
Complete the attached Technical Questionnaire that describes how the company will successfully meet the needs of the project specifications/statement of work.
NOTE: Vendors are encouraged to provide detailed specific information. Failure to provide sufficient information so that the evaluation team cannot discern if the offeror has a thorough understanding of the work in question may lead to this item being deemed unacceptable. Information provided should be relevant to the project specifications and supporting documents.
Provide Prior Experience:
Complete a compiled list with prior experience references - preferably a minimum of 3 and/or a maximum of 5, which are most recent projects within the past five (5) years that provide information on the performance quality of work on relevant similar projects in size and scope as outlined in the project specifications:
• Brief description of project
• Point of contact information
NOTE: Contact information SHALL be provided, to include a brief description of the project, as well as point of contact information so that the Government may contact and confirm the information provided.
Additionally, the Government may consider any and all other sources of information, including, but not limited to, contacting the contractor or contracting officer of the projects provided or some other means.
If quoting an “or equal” item, must submit a detailed product specifications document/literature and ensure it is provided to confirm the item(s) are comparable
Contractor Core Data:
Offerors Company Name:_________________________________________________________
Cage Code / Offerors Unique Entity Identifier (UEI):___________________________________
Offerors POC:__________________________________________________________________
Offerors POC Email/Phone:_______________________________________________________
140P6426Q0069 Heat Pump Replacement - BRVB Page 14 of 29
52.212-2 Evaluation — Commercial Products and Commercial Services (Nov 2021) (DEVIATION Mar 2026)
(a) Evaluation factors: The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors will be used to evaluate offers:
(i) price;
(ii) technical capability of the item offered to meet the Government requirement;
(iii) prior experience
SEE AWARD SELECTION PROCESS section below
(b) Options (if applicable). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. The evaluation of options does not obligate the Government to exercise the option(s).
(c) Notice of award. A written notice of award or acceptance of an offer furnished to the successful Offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
140P6426Q0069 Heat Pump Replacement - BRVB Page 15 of 29
AWARD SELECTION PROCESS
BASIS FOR AWARD
Award will be made in accordance with Simplified Acquisition evaluation procedures as set forth by FAR Part 12 – will be applied in the comparative evaluation of quotations to the offeror that provides the best value and most advantageous to the government based on price, technical, and prior experience. Technical Capability, prior experience and price will be evaluated by comparing quotes using an efficient and minimally burdensome process. This solicitation is not stating nor required to state the relative importance assigned to each evaluation factor and/or sub factor (FAR 12.203(c)(2)). The government reserves the right to consider any offer submitted in response to the solicitation, regardless of date/time prior to making a final award decision.
1. Price: a detailed breakdown of offeror’s price may be requested by the CO during evaluation
2. Technical Capability: Technical is the factual documentation of the firm’s ability to meet the specifications.
a. Offeror should submit any relevant evidence sufficient of technical capability which validates the offeror possesses, or has the ability to obtain, the technical knowledge, capability, business and managerial acumen, and experience to successfully perform a contract of the size and scope as described in this solicitation.
b. Failure to provide sufficient information so that the evaluation team cannot discern if the offeror has a thorough understanding of the work in question may lead to this item being deemed insufficient.
c. Further documentation may include, but is not limited to, additional references, identification of previous government contracts performed, licenses and or certifications, company capability statement/bio, photographs of relevant completed projects and awards, certificates of achievement, and letters of recognition pertinent to the disciplines/trades required of the work described in this solicitation.
3. Prior Experience: is the factual documentation or narrative of a firm’s experience, qualifications, and capability, along with providing examples of their firm’s most recent and relevant projects within the past five (5) years of similar size and scope.
a. Failure to provide sufficient information may lead to this item being deemed insufficient.
The government will evaluate quotes in groups of three (3), starting with the lowest priced quotes, proceeding upward, incrementally in price, until an awardee is selected. At that point, the evaluation process stops, and award will be made to the selected Offeror.
Price Reasonableness. A contract may not be awarded if the offeror’s price results in a cost to the government which is determined by the government not to be fair and reasonable. In determining the reasonableness and fairness of the offeror’s price, the contracting officer shall use competition and comparison of offers submitted or review prices found reasonable on previous purchases, the contracting officer’s personal knowledge of the products being purchased, and services being performed, comparison to an independent Government estimate, or any other reasonable basis. If multiple contract line items are included in the price schedule, prices will also be evaluated to determine whether any line items are unbalanced. Offerors are cautioned to distribute costs appropriately. The contracting officer will determine whether the final price is fair and reasonable and constitutes a fair market price.
The Government intends to evaluate quotations and award a contract without exchanges with offerors. Therefore, the offeror’s initial quotation should contain the offeror’s best terms from a cost or price and technical standpoint. The Government reserves the right to conduct exchanges if the Contracting Officer later determines them to be necessary. The Contracting Officer will also review the contractor’s past performance prior to making a final award decision.
The Government reserves the right to select a quote that provides benefit to the Government that exceeds the minimum but is not required to do so.
A written notice of award or acceptance of an offer mailed or otherwise furnished to the successful offeror within the time for acceptance specified constitutes an offer by the government. The contractor and Contracting Officer will both sign the final award to bind both parties. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether there are exchanges or negotiations after its receipt, unless a written notice of withdrawal is received before award.
140P6426Q0069 Heat Pump Replacement - BRVB Page 16 of 29
52.225-9 -- Buy American–Construction Materials (Oct 2022) DEVIATION DATE
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.
Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section40102(4)&num=0&edition=prelim
140P6426Q0069 Heat Pump Replacement - BRVB Page 17 of 29
(ii) A construction material manufactured in the United States, if–
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows: NONE http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title41-chapter83&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section1907&num=0&edition=prelim
140P6426Q0069 Heat Pump Replacement - BRVB Page 18 of 29
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to…