Sol_140P2125R0025.pdf
PDF 904 KB Posted
- Attached to
- HAFC NISI EXHIBIT FABRICATION Federal contract opportunity
- Solicitation number
- 140P2125R0025
About this file
This is a solicitation (140P2125R0025) from the National Park Service (NPS) seeking exhibit fabrication and installation services for the Ninety Six National Historic Site visitor center in South Carolina. The work is being procured as a firm-fixed-price task order under an existing Indefinite Delivery Indefinite Quantity (IDIQ) contract for Exhibit Fabrication Services.
The scope includes fabrication, delivery, and installation of new first-floor exhibits, including object cases, graphic panels, models, illustrations, audio-visual elements, and audio description capabilities. Key personnel required include a Model Maker, Mount Maker, and Illustrator. Proposals are due by March 10, 2025 at 10:00 AM EDT and must be submitted electronically to dee_dee_bender@nps.gov in two volumes (Technical Capability and Price). Primary exhibit installation must be completed by November 30, 2025, with all punch list items and audio description work completed by December 31, 2025. The technical evaluation factors, in descending order of importance, are Samples of Work, Proposed Key Personnel, and Past Performance. These non-price factors when combined are significantly more important than price in the best value trade-off evaluation.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2125R0025_Amd_0002.pdf | ||
| Sol_140P2125R0025_Amd_0001.pdf | ||
| Attachment_C_NISI_Content_Specialties_012024-final.pdf | ||
| Attachment_D_NISI_Database_Reports_012024-final.pdf | ||
| Attachment_E_NISI_AO_and_Case_Schedule_012024-final.pdf | ||
| Attachment_A_NISI__Production__Exhibit_Drawings_012024-final.pdf | ||
| Attachment_F_NISI-_Cost_Estimate_Form.xlsx | XLSX spreadsheet | |
| Attachment_B_NISI_Graphic_Layouts_012024-final.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
February 6, 2025
Subject: Solicitation Number 140P2125R0025
Exhibit Fabrication for Ninety Six National Historic Site
In accordance with the terms and conditions of your Indefinite Delivery Indefinite Quantity (IDIQ) contract with the National Park Service for Exhibit Fabrication Services, enclosed is a competitive requirement for Ninety Six National Historic Site (NISI). You are invited to prepare and submit, in writing, a proposal for performance of the work in accordance with the rates and provisions set for in the IDIQ contract. Work shall be performed in accordance with the enclosed Scope of Work consisting of 32 pages. The government anticipates award of a firm-fixed-price task order resulting from this solicitation.
All questions shall be submitted in writing via email to Dee Dee Bender at dee_dee_bender@nps.gov no later than 10:00 am EDT on February 20, 2025. Any questions received after this time may not be answered before proposals are due. All questions submitted shall reference specific parts of the solicitation including page numbers. An amendment will be issued to answer all questions received in response to this solicitation.
The proposal shall be separated into two separate Volumes and contain the information outlined in the solicitation under Item 9, Instructions to Offerors.
Proposals shall be received no later than 10:00 am, EDT on March 10, 2025. Proposals received after this date/time and at the location specified in this announcement, will be considered late and handled as a late proposal. The proposal shall be submitted electronically via email to dee_dee_bender@nps.gov with the subject line clearly identifying “Solicitation Number 140P2125R0025 – Exhibit Fabrication for Ninety Six National Historic Site”. Offers by telephone, transmitted via facsimile (fax), or submitted through SAM.gov will not be accepted.
Offerors who contact anyone regarding this project, other than personnel within the Office of Acquisition Management, Harpers Ferry Center, including but not limited to, the park or other HFC Personnel, may be automatically excluded from competition.
Shelia D. Bender Contracting Officer mailto:dee_dee_bender@nps.gov
SEE ADDENDUMIS CHECKED
CODE 18a. PAYMENT WILL BE MADE BY
CODE
FACILITYCODE
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
OFFEROR
PHF
Harpers Ferry WV 25425 IDC Building 67 Mather Place DOI, NPS, HFC - Acquisition Managem
0011283480 CODE 16. ADMINISTERED BYCODE
X
X
X
337212
SIZE STANDARD:
% FOR:SET ASIDE:UNRESTRICTED ORPWA
REQUEST FOR
PROPOSAL
(RFP)
INVITATION
FOR BID (IFB)
10. THIS ACQUISITION ISCODE
REQUEST FOR
QUOTE (RFQ)
14. METHOD OF SOLICITATION
13b. RATING
NORTH AMERICAN INDUSTRY
CLASSIFICATION STANDARD
(NAICS):
SMALL BUSINESS
03/10/2025 1000 ED
02/06/2025
3045356227Shelia Bender (No collect calls)
INFORMATION CALL:
FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME
4. ORDER NUMBER3. AWARD/ 6. SOLICITATION
140P2125R0025
5. SOLICITATION NUMBER
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF
1 32 0044006984OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
TELEPHONE NO.
17a. CONTRACTOR/
Harpers Ferry WV 25425 IDC Building, 67 Mather Place NPS, Harpers Ferry Center
15. DELIVER TO
Denver CO 80225 P.O.Box 25287 MS WCP
9. ISSUED BY
7.
2. CONTRACT NO.
EFFECTIVE DATE
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
ISSUE DATE
DELIVERY FOR FREE ON BOARD
(FOB) DESTINATION UNLESS
BLOCK IS MARKED
11.
SEE SCHEDULE
12. DISCOUNT TERMS THIS CONTRACT IS A RATED
ORDER UNDER THE DEFENSE
PRIORITIES AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
13a.
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
8(A)
NPS, WASO - WCP Contracting
WOMEN-OWNED SMALL
BUSINESS (WOSB)
ECONOMICALLY DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
Exhibit Fabrication Services Ninety Six National Historic Site Firm Fixed Price
The contractor shall provide all services including labor, materials, facilities, and travel necessary to detail, fabricate, transport to the site, and install all exhibit elements in accordance with the specifications as detailed in this task order and its attachments.
Delivery: 12/31/2025
(Use Reverse and/or Attach Additional Sheets as Necessary)
HEREIN, IS ACCEPTED AS TO ITEMS:
X
XX
DATED
Shelia Bender
. YOUR OFFER ON SOLICITATION (BLOCK 5),
INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
ARE
ARE
31c. DATE SIGNED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
26. TOTAL AWARD AMOUNT (For Government Use Only)
OFFER
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
ARE NOT ATTACHED.
ARE NOT ATTACHED.
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
30b. NAME AND TITLE OF SIGNER (Type or print)
30a. SIGNATURE OF OFFEROR/CONTRACTOR
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
25. ACCOUNTING AND APPROPRIATION DATA
29. AWARD OF CONTRACT: REFERENCE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER
37. CHECK NUMBER
FINALPARTIAL
36. PAYMENT
FINALPARTIAL
35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER33. SHIP NUMBER
COMPLETE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)
42b. RECEIVED AT (Location)
42a. RECEIVED BY (Print)
41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
STANDARD FORM 1449 (REV. 11/2021) BACK
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
00010 NISI VC Exhibit
Product/Service Code: M1PB
Product/Service Description: OPERATION OF EXHIBIT
DESIGN (NON-BUILDING)
Period of Performance: 03/01/2025 to 12/31/2025
00020 NISI VC Exhibit Travel
Product/Service Code: M1PB
Product/Service Description: OPERATION OF EXHIBIT
DESIGN (NON-BUILDING)
Period of Performance: 03/01/2025 to 12/31/2025
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32 2 of
Contract Number 140P2122D____ Solicitation Number 140P2125R0025
EXHIBIT FABRICATION AND INSTALLATION SERVICES
NINETY SIX NATIONAL HISTORIC SITE - VISITOR CENTER
1. PROJECT BACKGROUND
Ninety Six National Historic Site (NISI) is an area of unique historical and archeological significance.
The unusual name was given by Charleston traders in the early 1700's because they thought it was the estimated remaining number of miles from here to the Cherokee village of Keowee in the upper South Carolina foothills. NISI proved to be a strategic location in the Revolutionary War. The first land battle south of New England was fought here in 1775. Later in the war, Ninety Six figured prominently in the Southern Campaign of the American Revolution. In 1780, the British fortified the strategically important frontier town. The earthen Star Fort remains as one of the best preserved examples of an original 18th century fortification.
The existing exhibits are outdated, damaged and need replacing, this task order shall be the full replacement of the first-floor exhibits at Ninety Six National Historic Site.
2. GENERAL REQUIREMENTS
The project shall be the fabrication and installation of new exhibits for the visitor center at Ninety Six National Historic Site (NISI) in Ninety Six, SC. The project includes coordination with the Contracting Officer (CO), Contracting Officer’s Representative (COR), and park staff.
The contractor shall provide all services including labor, materials, facilities, and travel necessary to detail, fabricate, transport to the site, and install all exhibit elements in accordance with the specifications as detailed in this task order and its attachments. The park is responsible for the removal of existing exhibits.
All work under this task order shall be performed in accordance with the terms herein, including all attachments. The government shall furnish, as appropriate, required data, materials, and access to project information necessary to perform the production of work as required.
2.1. Point of Contact
The contractor’s Project Manager (PM) shall be the primary point of contact between the contractor and COR. The contractor’s PM shall have full authority to act for the contractor on all matters relating to this task order, and shall perform the following work:
1. Be available to take or respond to telephone calls or electronic mail messages during normal hours of operation (8:30 am–5:00 pm local time).
2. Establish office procedures to ensure that messages are relayed to the Project Manager when out of the office or because of time zone differences.
3. Respond to emergency messages from the COR on the same day they are received. All non-urgent messages from the COR shall be responded to in no more than two (2) business days.
2.2. Quality Control
The contractor shall provide quality control to ensure that all elements of project work meet the requirements of the task order and base IDIQ contract specifications and that all modifications are implemented. The Project Manager shall provide routine inspections of in-house and subcontracted work to ensure it meets task order and base IDIQ contract specifications and shall oversee the quality of work produced and implemented at all phases of the project. The contractor shall oversee all work during installation to ensure that it adheres to task order and base IDIQ contract specifications and schedule for completion. Any work found not acceptable or compliant with the specifications shall be corrected prior to inspection or review by the COR.
2.3. Government Furnished Property
The contractor shall receive, inspect, and inventory all government-furnished materials and ensure that this material is forwarded to the appropriate unit or person within the contractor’s organization for use in the project. The Project Manager shall notify the COR via email within seven (7) days after receipt if government-furnished materials are not satisfactory for their intended purpose. The Project Manager shall notify the COR via email as soon as possible, but no later than three (3) business days, if government-furnished materials are lost or damaged while in the contractor’s possession. The contractor shall be responsible for the security and protection of government-furnished property or materials in connection with this task order. Following acceptance of all work by the government, the contractor shall return to the COR all government-furnished property.
2.3.1. Post Award Meeting
The following listed government-furnished property shall be provided at the post award meeting:
1. Production ready graphic files
2. Accessioned objects, see Attachment E_NISI_AO and Case_Schedule_012024-final
2.3.2. Exhibit Fabrication
The following listed government-furnished property shall be provided during exhibit fabrication for installation:
1. Accessioned objects, see Attachment E_NISI_AO and Case_Schedule_012024-final
2.4. Schedule
The contractor shall schedule, coordinate, oversee, and manage work produced and installed under this task order. Track work progress to ensure that the project is completed according to the schedule.
Coordinate and confirm the dates for all submittals and meetings with the COR.
2.4.1. Status Reports
Provide a monthly status report to the COR that includes the status of the project, issues that affect the schedule and budget, and an updated schedule based on the information at hand.
2.4.2. Project Schedule
The contractor shall produce a detailed, complete project schedule listing all required submittals and their review times. The project schedule shall include shop inspections, site visits, installation activities, and closeout submittals.
The contractor shall submit a preliminary project schedule to the COR for review and approval seven (7) working days prior to the post award meeting. The contractor shall update the approved schedule and resubmit to the COR three (3) working days prior to every project status meeting for the life of the project.
2.4.3. Installation Schedule
The contractor shall coordinate and confirm dates with the COR for shipment, delivery, and installation at the exhibit site.
2.5. Meetings, Travel, and Presentations
Meet with the CO, COR, and park staff as specified below. The contractor shall document all issues discussed and decisions made relative to the project. The contractor shall prepare and distribute to the COR a trip report or meeting minutes of all telephone conversations, site visits, in-person meetings, or other discussions related to the project.
Meeting Purpose Location or Type
Required Contractor Attendees
Duration/Days on site
Project coordination, and comment discussion and reconciliation
Conference Call or Virtual Meeting
Project Manager Weekly, 1-hour meetings (or as needed)
Post-award meeting and site visit
At Park Project Manager One, 8-hour day
Optional Building Prep site visit
At Park Project Manager One, 8-hour day
Preliminary Shop Inspection
At contractor facility
Project Manager One, 8-hour day
Final Shop Inspection
At contractor facility
Project Manager Up to two, 8-hour days if needed
Installation At Park Project Manager, Installation Crew
(TBD)
To be proposed by contractor
Audio Description Installation &
Testing
At Park Project Manager, Audio Describer
One, 8-hour day
2.6. Submittals
At any point in the exhibit fabrication process the COR may require informal submittals of the contractor’s work-in-progress to document the current status and level of production of the project.
The contractor shall coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with task order requirements. Forward all submittals to the COR for review and approval. Receive all reviewed submittals and take appropriate action according to the approval or rejection by the COR, as follows:
2.6.1. Approvals and Rejections
1. Approved Submittals – The contractor shall ensure that all changes, revisions, or additions required by review comments are addressed and incorporated into future submittals.
2. Rejected Submittals - When submittals are rejected, the COR will notify the contractor, in writing, identifying the reasons for rejection. The contractor shall ensure that the submittal is completed and/or revised as required and resubmitted within the time scheduled by the COR. Reasons for rejection include:
• Incomplete Submittals – Approval of the submittal is delayed because required elements are missing. The contractor shall submit all missing elements.
• Unacceptable Submittals – The submittal is rejected due to poor quality of work or work that does not otherwise meet the established project goals. The contractor shall submit new material.
2.6.2. Submittal Format
1. One (1) electronic PDF copy of each document submittal is required.
2. Two (2) copies of graphic prints and material samples are required.
3. One (1) physical sample of models, mock-ups, and prototypes is required.
4. Submittals shall be sent via overnight delivery service unless otherwise specified in the scope of work below.
2.6.3. Transmittal Sheet
The contractor shall include a transmittal in the form of a printed letter, PDF document, e-mail, or fax cover sheet along with all samples, proofs, prints, reports, digital files, digital images, and multimedia files, sent from the contractor to the COR. This includes all copies sent to the park or other copied recipients.
The transmittal shall include the following information:
• "From" (contractor's name and contact information);
• "To" (COR's name);
• Date submittal was shipped;
• Project name and park name;
• Itemized list of contents; and
• List of copied recipients who received the same submittals.
2.7. Accessibility
Exhibits fabricated for the National Park Service shall follow the latest published version of base contract Attachment 4, Programmatic Accessibility Guidelines for National Park Service Interpretive Media. These Guidelines are a combination of best practices, NPS and Department of the Interior directives, and federal laws. Federal laws include the Architectural Barriers Act, Sections 504 and 508 of the Rehabilitation Act as amended, and the 21st Century Communications and Video Accessibility Act.
2.7.1. Audiovisual Accessibility for Exhibits
Every audio, silent video, and audiovisual program in every exhibit is required to provide descriptive audio, hearing assistance, captions, and/or navigation buttons, as follows:
2.7.1.1 Audio-only Programs
Audio-only programs require hearing assist for the hard of hearing and captions for the deaf. The hearing assist requirement may be met using either sound wands with volume control and reset, or a FM transmitter and handheld receiver. Captions for the deaf are displayed on a monitor synched with the audio.
2.7.1.2. Silent Video Programs
Silent videos require descriptive audio for people who are blind or have low vision, and notification, via on-screen caption or label adjacent to the monitor, for the deaf or hard of hearing that the video is silent. Delivery of descriptive audio is provided in the exhibit through a headset jack, a sound wand, or via Wi-Fi streaming in conjunction with the Exhibit Audio Description Tour app. When descriptive audio is delivered via headset jack, a label with the raised AD symbol and headset icon is required.
2.7.1.3. Audiovisual Programs
Audiovisual programs in exhibits require descriptive audio for people who are blind or have low vision, hearing assist for the hard of hearing, and captions for the deaf. Any of the delivery methods for audio-only programs and silent video programs may be used to meet these requirements.
2.7.1.4. Navigation Buttons & Computer Interactives
In addition to the requirements outlined in para 2.7.1.3, Audiovisual Programs, touch screen user interfaces require external control navigation buttons for people with limited mobility.
3. FABRICATION AND INSTALLATION SERVICES
3.1. General
The contractor shall provide all technical, professional, non-personal services, including all labor, materials, equipment, supplies, facilities, travel, management, and supervision necessary to provide NISI with exhibit fabrication and installation services for the park visitor center. Work includes;
production of exhibits (including Pre-Fabrication submittals, and Fabrication); Shop Inspections (Preliminary and Final); Building Preparation; Installation (including Primary Installation, Punch List, and Audio Description); and Closeout. Work includes travel to the park to meet with the park staff, inspect sites, assess or recommend rehabilitation plans and/or scope of work, prepare cost estimates, provide or confirm measurements, and fabricate and install exhibits.
The contractor shall propose separate costs for the following optional elements noted in Attachment A NISI Production Exhibit Drawings_012024_final, Attachment B_NISI Graphic Layouts_012024_final, and in Attachment C_NISI Content Specialties_012024_final:
1. Scenic element to support tactile battleground table:
a. CE 06-01-010, Battleground mine tunnel
2. Graphic Layouts:
a. GL 02-01-010
b. GL 03-01-010
c. GL 03-02-010
d. GL 04-01-010
e. GL 05-01-010
f. GL 07-01-010
3.2. Specifications
The contractor shall perform all services required hereunder in accordance with this Statement of Work (SOW) and all attachments.
3.3. Design Control
In fabricating exhibitions hereunder, the contractor shall take into account as essential design and production considerations the following: life safety, barrier-free design, accessibility/universal design, sustainability, energy conservation, artifact conservation including daylight modulation from skylights and windows, if applicable, control of sound-spill from AV programs, security provisions, integration and compliance with existing architecture where relevant, lamping, functionality, maintenance, conservation, and durability restrictions.
3.4. Codes and Standards
All exhibits shall be produced and installed in accordance with applicable codes, standards, parameters or regulations noted in this or other sections of this task order, and in the location in which the exhibit shall be installed. In case of conflict between codes, standards, or regulations, the most stringent requirement shall apply.
3.4.1. Reference to standard specifications of any technical society, organization, or association, or to codes, manuals, or regulations of Federal or local authorities shall mean the latest standard, code manual, regulation, specification, or tentative specification adopted and published at least thirty (30) days prior to submittal of proposals, unless specifically stated otherwise.
3.4.2. Any code, standard, regulation, or specification listed below, in the attachments or otherwise referenced herein, that references the “authority having jurisdiction”, “local authority”, or “governmental authority” shall be interpreted to refer to the Contracting Officer as being this authority for purposes of interpreting/clarifying codes, standards, regulations, and specifications.
3.5. Post-award Conference Call
Upon award, the contractor shall participate in a project kick-off conference call to review contracting requirements and procedures with the project CO and COR.
3.6. Production Support
Production support from the Planning and Design contractor is not part of this contract. The COR and NISI park staff shall provide continuity and resolve questions regarding any design decisions or discrepancies remaining from the Planning and Design Documents.
3.7. Production
Work in this phase shall include production of all exhibit elements in accordance with the design intent as described in Attachment A_NISI Production Exhibit Drawings_012024-final. Work in this phase is organized into two (2) sub-phases: Pre-Fabrication Submittals and Fabrication. Pre- Fabrication includes the development of project documents that must be approved before production can occur.
Fabrication includes all tasks required to complete the production of exhibit elements.
3.7.1. Pre-Fabrication Submittals
During this phase, the contractor shall:
1. Attend a post-award meeting as follows:
a. Submit a meeting agenda to the COR for review and approval not later than seven (7) days prior to the post award meeting.
b. Travel to NISI in Ninety Six, SC to attend a post award meeting with the COR and park personnel. The meeting shall be one (1) eight-hour working day. The date of the meeting shall be determined within three (3) weeks of the Contract award.
c. Orient to the site and review existing site conditions and construction documents.
d. Conduct general project review, including the exhibit design drawings and work requirements.
e. Receive, review, inspect, document, and secure all government-furnished material, including drawings, planning documents, reference and source materials, and other project-related material.
f. Inspect, measure, and document accessioned and non-accessioned objects to be used in the exhibits, verifying final dimensions in accordance with Attachment D_NISI Database Reports_012024-final.
2. Prepare and submit an Exhibit Production Plan, as follows:
a. Establish key project milestones and timeframes for review for 25%, 40%, 80%, and 95% completion.
b. At each milestone, the contractor shall provide a revised exhibit production plan that reflects the current status of production.
c. The Exhibit Production Plan shall include the AV Production Plan.
3. Provide Fabrication Shop Drawings.
a. Modifications. The general design requirements shown in Attachment A_NISI
Production Exhibit Drawings_012024-final are intended to establish basic dimensions of units or modules, profiles, and sight lines of members. Within these limitations, the contractor shall be responsible for any modifications or additions as required to meet accessibility, durability, and safety standards as outlined in base contract Attachment 1, Exhibit Planning, Design, and Fabrication Specifications. The contractor shall submit proposed modifications to the COR for review and approval prior to implementing changes. The contractor shall maintain the visual design concept and operational features as shown, including members’ sizes, profiles, and alignment of components.
b. Electrical. The contractor shall provide equipment specifications, and a lighting and wiring diagram for all exhibit lighting as designed and specified in Attachment A_NISI Production Exhibit Drawings_012024-final. Building wiring and power shall be completed by the park. The contractor shall be responsible for acquiring and installing new track and fixtures, and for connecting fixtures to park-provided power throughout the exhibits. The contractor shall ensure that all physical loads are supported by adequate equipment and/or mounting devices as dictated by the state of South Carolina.
c. Object Cases. The requirements in base contract Attachment 1, Exhibit Planning, Design, and Fabrication Specifications—Section 18, Object Preservation and Protection shall take precedence over design and production notes shown in Attachment A_NISI Production Exhibit Drawings_012024-final. The contractor shall propose, for review and approval by the COR, any modifications to case design, dimensions, materials, finishes, mechanisms, object layouts, and case furniture that are required to meet NPS specifications.
d. Object Mounts. The contractor shall include drawings of proposed object mounts and exhibit case layouts, submitted in the form of shop drawings.
4. Provide Electronic Equipment submittals including plan drawings, wiring diagrams, and catalog cuts.
5. Provide two (2) physical copies of Material Sample Boards.
3.7.2. Fabrication
Each fabrication task may require a sub-series of steps to complete, and the contractor is not required to complete tasks in the order outlined below. All tasks shall be completed in accordance with base contract Attachment 1, Exhibit Planning, Design, and Fabrication Specifications—Section 27, Quality and Safety Standards for Fabrication.
Fabrication tasks include the following:
3.7.2.1. Content Specialties
Content Specialties under this task order include illustrations and artwork, new photography, natural history models, architectural and other cultural history models, life-sized figures, dioramas, reproduction historic objects, historic objects (accessioned or non-accessioned), maps and topographic models, and electronic programs.
1. Illustrations and Artwork. Custom illustration or artwork is required for several graphic panels, as shown in Attachment C_NISI Content Specialties_012024-final and Attachment B_NISI Graphic Layouts_012024-final. The production process for custom illustrations shall be as follows:
a. Refer to the Attachment C_NISI Content Specialties_012024-final for design intent, purpose, style, and other production details.
b. Submit the proposed illustration style, in accordance with Attachment
C_NISI Content Specialties_012024-final for review and approval.
c. Submit rough sketches of the illustrations, in the approved style.
d. Submit more refined sketches of each illustration, including color, that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
e. Submit 90% complete illustrations that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
f. Submit the final illustrations that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
Incorporate the illustrations into the appropriate graphic layout files.
Metadata shall be included in the final digital file and shall include information fields supplied by the COR, and found in base contract Attachment 9, Art Documentation Form.
2. Natural History Models. Custom natural history models are required under this task order and shall be produced with a high degree of realism and durability. Specific details and a full list of models can be found in Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final. The production process for natural history models shall be as follows:
a. Refer to Attachment C_NISI Content Specialties_012024-final, and
Attachment D_NISI Database Reports_012024-final for design intent, purpose, style, and other production details.
b. Submit a rough pencil sketch of the model in the approved style, in accordance with the Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final for review and approval.
c. Submit a more refined sketch that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
d. Submit a revision that shall incorporate any additional corrections, changes, modifications, or deficiencies identified by the COR.
e. Submit one (1) positive or other 3D draft of the model. Model samples shall be adequately sized to provide review of materials, colors, and finishes; and shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR during iterative review of the sketches.
f. Submit the final model that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
3. Architectural and Other Cultural History Models. Custom architectural and cultural history models are required under this task order and shall be produced with a high degree of realism and durability. Specific details and a full list of models can be found in Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final. The production process for architectural and cultural history models shall be as follows:
a. Refer to Attachment C_NISI Content Specialties_012024-final, and
Attachment D_NISI Database Reports_012024-final for design intent, purpose, style, and other production details.
b. Submit a rough pencil sketch of the model in the approved style, in accordance with the Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final for review and approval.
c. Submit a more refined sketch that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
d. Submit a revision that shall incorporate any additional corrections, changes, modifications, or deficiencies identified by the COR.
e. Submit one (1) positive or other 3D draft of the model. Model samples shall be adequately sized to provide review of materials, colors, and finishes; and shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR during iterative review of the sketches.
f. Submit the final model that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
4. Reproduction Historic Objects. Reproduction historic objects are required under this task order. Specific details and a full list of display objects are provided in Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final. The production process for reproduction historic objects shall be as follows:
a. Refer to Attachment C_NISI Content Specialties_012024-final and
Attachment D_NISI Database Reports_012024-final for design intent, purpose, style, and other production details.
b. Submit a rough pencil sketch of the object in the approved style, in accordance with the Attachment C_NISI Content Specialties_012024-final, and in Attachment D_NISI Database Reports_012024-final, for review and approval.
c. Submit a more refined sketch that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR.
d. Submit one (1) 3D sample of the object that shall incorporate all corrections, changes, modifications, or deficiencies identified by the COR, and shall clearly show the final materials, finishes, textures, and styles in progress.
e. Submit the final reproduction historic object that shall incorporate all corrections, changes, modifications, or deficiencies identified by the
COR.
5. Historic Objects (Accessioned or Non-accessioned). Historic objects are required under this task order. Specific details and a full list of display objects are provided in Attachment E_NISI_AO and Case_Schedule_012024-final, and in Attachment D_NISI Database Reports_012024-final. The production process for historic objects shall be as follows:
a. Refer to Attachment E_NISI_AO and Case_Schedule_012024-final and
Attachment D_NISI Database Reports_012024-final for design intent, purpose, style, and other production details.
b. Submit a report that details the conservation and mounting needs for the object, for review and approval.
6. Maps and Topographic Models. A custom topographic relief model is required under this task order. The production process for maps and topographic relief models shall be as follows:
a. Refer to Attachment C_NISI Content Specialties_012024-final for design intent, purpose, style, and other production details
b. Submit one (1) full-sized paper proof of the tactile topographic map.
The proof shall include geologic and topographical features, where appropriate, and any specified labels.
c. Submit three (3) foam mock-ups of a minimum 12”x12” section of the map, including a difference vertical exaggeration on each sample.
d. Submit one (1) 12”x12” painted sample of the map that depicts an actual 12”x12” segment of the map
e. Submit a minimum of five (5) photographs of work-in-progress as the topographic map or model is in production, prior to clear-coat or final finish application
f. Submit the final tactile map that shall incorporate all corrections, changes, and modifications identified by the COR in the previous map samples.
7. Electronic Programs. As part of the Exhibit Production Plan, the contractor shall submit an AV Production Plan that describes the production process required to produce each Electronic Program for review and approval by the COR. Specific details and a full list of Electronic Programs can be found in Attachment D_NISI Database Reports_012024-final.
The contractor shall follow all processes for AV Production as outlined in base contract Attachment 5, National Park Service Standard Specifications for Planning, Design, Production, and Installation of Electronic Programs, and as follows:
a. Pre-Production
i. Review themes, goals, objectives, program content, and accessibility requirements for each program.
ii. Review park resources and materials for possible inclusion in program. Identify additional sources for research and materials for each program.
iii. Submit a Treatment, draft script, and/or an inventory of park-furnished footage and/or an inventory of proposed still images for video programs; submit a list of proposed audio recordings for audio-only programs; and submit a Conceptual Design for animation programs. All Treatments, draft scripts, inventories, and Conceptual Design shall be in accordance with program description in Attachment D_NISI Database Reports_012024-final
iv. All deliverables for Electronic Programs shall be submitted electronically for review and approval. Multiple submissions may be required until approved by the COR.
b. Production
i. Provide a shooting script and filming schedule for video programs to the COR for review and approval, for all original footage that needs to be acquired by the contractor.
ii. Acquire principal photography for video program and submit all footage and footage logs to the COR for review and approval.
iii. Submit an edited assembly (string-out) of park-furnished footage for video programs to the COR for review and approval.
The result may necessitate the acquisition of additional footage from the park or other sources.
iv. Submit inventory of images for video programs that incorporate all required changes and substitutions from pre-production reviews to the COR for review and approval.
v. Submit proposed stock audio recordings for video and audio programs to the COR for review and approval. Each recording shall identify the sound in the file name structure.
vi. Submit a Work-In-Progress 1: storyboards, graphic layouts, modeling, and sample demonstrations illustrating movement;
and all approved elements incorporated into the sequence for animation programs to the COR for review and approval. These shall be approved by the COR prior to the final execution.
c. Post Production
i. Submit Rough Cut Edits and edit scripts for video and audio programs to the COR for review and approval. Multiple rough cuts and edit scripts may be required until approved by the COR.
Each rough cut shall be submitted with a revised script that corresponds to the most current edited version of the program.
ii. Submit three narrator samples to the COR for review and approval.
iii. Submit samples of music from a minimum of three (3) professional film composers or library music sources to the COR for review and approval.
iv. Submit samples of the proposed font and design style for all on-screen text, lower thirds, and Subtitles for the Deaf and Hard of Hearing (SDH) to the COR for review and approval.
v. Submit Fine Cut Edits and edit scripts for video and audio programs prior to the final online edits and sound mixes, to the COR for review and approval. Fine Cuts shall include a selection of approved composer’s music, sound effects, best resolution images or footage, highest quality audio, and all on-screen text and graphics (excluding credits). Multiple fine cuts and edit scripts may be required until approved by the COR. Each fine cut shall be submitted with a revised script that corresponds to the most current edited version of the program. The Fine Cuts shall be revised until ready for the online edit.
vi. Submit final assembly of images for digital slideshows to the COR for review and approval.
vii. Rights Package: The contractor shall submit a narrative description or spreadsheet that accounts for the copyright sources of all audiovisual elements proposed for use in each program—including public domain materials, purchased stock materials, and government-furnished materials—before the final programs are mastered. For those materials that are restricted, license agreements shall be submitted. Upon review and approval of the license agreements by the COR, any license that fails to meet the requirements shall be returned to the contractor for revisions. If the specified rights cannot be obtained, the contractor shall replace the element. The contractor shall submit scanned copies of all NPS Release Forms for talent, and scanned copies of all license agreements acquired by the contractor for copyrights and restricted materials being used in the production concurrent with the submission of Fine Cut Edits.
viii. Accessibility:
• Submit scripts for Audio Description (AD) and Subtitles for the Deaf and Hard of Hearing scripts to the COR for review and approval.
• Submit a transcript describing each sound clip used in audio programs, for use by visitors who are Deaf or Hard of Hearing, to the COR for review and approval.
• For programs without audio, there shall be an icon or text indicating the program has no audio, placed either on-screen or in proximity to the program monitor. Submit proposed icon or text to the COR for review and approval.
ix. Submit Final Animation Programs with all approved elements and animated movement to the COR for review and approval.
x. Online Edit, Sound Design and Mix, and Color Correction: The contractor shall submit the final edited versions with final sound design, mix, and color correction, as required by program type, to the COR for review and approval.
xi. Final Deliverables: Upon completion of the project, all elements shall be submitted to the COR along with a completed form of base contract Attachment 8, AV Completion Report.
3.7.2.2. Mock-ups and Prototypes
Mock-ups refer to working models that are fabricated simply, quickly, and at minimal cost in order to test a concept. They are full-scale representations of portions of an exhibit for the purpose of review, testing, and evaluation. Mock-ups are for review only, and shall not be incorporated into the final exhibit.
Prototypes are more refined than mock-ups, and closer to the final product in material, fabrication, and operation. Prototypes are portions of an exhibit such as an artifact case or an interactive mechanism that has a particular need to be reviewed and tested prior to fabrication of more elements of the same design.
The contractor shall provide the following:
1. Prototypes:
a. CE-06-01-010
b. CE-06-01-200
c. CE-01-02-300 Prior to the Preliminary Shop Inspection, the contractor shall provide the COR a report, with photo documentation, of the performance of the prototypes. All prototypes shall be available at the Preliminary Shop Inspection for review and testing.
All prototypes shall be corrected in accordance with the review and approval by the COR before being incorporated into the final exhibit.
3.7.2.3. Exhibit Structures and Cabinetry
The contractor shall provide adequate personnel and facilities to fabricate all structures and exhibit elements as required under this task order. The contractor’s Project Manager shall ensure the safety of staff and the quality of fabricated elements and shall facilitate reviews of work throughout fabrication.
All exhibit structures and cabinetry shall adhere to the highest safety, environmental, and quality standards set under the law, and in accordance with base contract Attachment 1, National Park Service Exhibit Planning, Design, and Fabrication Specifications.
All finishes, and particularly high-touch surfaces, shall be finishes than can be cleaned and sanitized with an alcohol-based cleaning solution. In additional, finishes shall be durable enough to withstand thousands of uses by visitors.
All exhibit structures and cabinetry shall be in accordance with Attachment A_NISI Production Exhibit Drawings_012024-final, and with base contract Attachment 2, Exhibit Conservation Guidelines.
3.7.2.4. Exhibit Graphics
The contractor shall provide fabrication of all two-dimensional exhibit graphics.
Graphic source material shall be government-furnished to the fabrication contractor in a digital format. The contractor shall be responsible for the following:
1. Review all government-furnished materials and notify the COR if the materials are inadequate for production.
2. Prepare digital files for specified output.
3. Scan high resolution images as needed to meet the print dimensions at
200ppi resolution.
http://www.conservation-wiki.com/wiki/Talk:Exhibition_Standards_%26_Guidelines
4. Link image and vector files to graphic layout files.
5. Adjust digital files for color corrections and bleed as needed.
6. Provide creative graphic design services to incorporate any government-provided illustrations, artwork, and new photography into graphic layout files for production.
7. Produce two (2) copies of full-sized unlaminated graphic proofs, samples, and layouts for review and approval by the COR prior to the Preliminary Shop Inspection; at the Preliminary Shop Inspection, provide full-sized unlaminated graphic proofs of all revisions requested during review.
8. Provide two (2) material production samples of each type of graphic substrate for review and approval by the COR.
9. Provide final, corrected graphic layouts.
3.7.2.5. Electronic Programs and Equipment
All Electronic Programs and associated Electronic Equipment shall be in compliance with the Information and Communication Standards of the Rehabilitation Act (see Section508.gov). Equipment and software components need to be carefully coordinated to ensure an effective presentation. Equipment compatibility relative to the designer’s vision is a critical element.
The contractor shall follow the pre-production, production, and post-production process for Electronic Programs described above in Section 3.7.2.1.7 of this task order, and in accordance with base contract Attachment 5, National Park Service Standard Specifications for Planning, Design, Production, and Installation of Electronic Programs.
The contractor shall be responsible for testing of all electronic equipment, and for the successful installation of all electronic programs that are part of the exhibits, including those that are government-provided.
3.7.2.6. Audio Description
Audio description shall include all exhibit elements. Exhibit elements include text, graphics, tactiles, interactives, scenic elements, electronic programs (audio and video), and navigational and operational instruction.
During Fabrication, the contractor shall provide the following:
1. Audio Description Production Plan, including Table of Contents with AD segment titles and submenus congruent with Scenes, Content Groups, and individual exhibit elements;
2. Audio Description diagram indicating power sources, styles, and locations of AD triggering hardware;
3. Audio Description draft script based on approved Table of Contents, triggers locations, exhibit drawings, exhibit elements, and production-ready graphics, which shall be available for testing during Installation.
http://section508.gov/
3.8. Shop Inspections
Work in this phase shall include the facilitation of visits by the COR to the contractor’s facility to view and inspect work on all exhibit elements. The contractor shall facilitate two (2) shop inspections by the COR.
3.8.1. Preliminary Shop Inspection
The contractor shall facilitate review of exhibits at the 40% completion milestone, and at a date to be determined in consultation with the COR. The Preliminary Shop Inspection shall be one
(1) eight-hour day.
The contractor shall provide the following at the Preliminary Shop Inspection:
1. Primary exhibit structures without final finishes, including:
• Battleground Table
• Wall Case Typical
• Rail Case Typical
• EX-08-01-001
2. Full-sized, unlaminated graphic proofs of any graphic layouts requiring revision during the previous graphic sample review.
3. In-progress versions of modeled elements.
4. 3” x 3” sample of CE-02-01-501, CE-02-01-502, CE-02-01-503
5. Prototypes of
• CE-06-01-010
• CE-06-01-200
• CE-01-02-300
3.8.2. Final Shop Inspection
All remaining exhibit structures, graphics, and content specialties shall be complete and fully operational for the final inspection, prior to Installation, and at a date to be determined in consultation with the COR. The Final Shop Inspection shall be one (1) eight-hour day.
The contractor shall provide the following:
1. To the greatest extent possible, all exhibit units shall be configured in a dimensioned area similar to that into which they shall be installed.
2. All operations of each Custom Element, Electronic Program, and Electronic Equipment shall be demonstrated to be fully functional in accordance with the design intent and applicable fabrication techniques.
3. All exhibit units with built-in lighting, electrical, mechanical, and electronic equipment shall be connected to power sources and demonstrated to be fully functional.
4. Document all shop inspection review comments and provide a shop inspection punch list to the COR. All punch list items identified at the Final Shop Inspection shall be corrected by the contractor prior to shipping exhibits to the installation site.
5. While at the Final Shop Inspection, conduct the Pre-Installation meeting.
3.9. Building Prep
A separate building prep site visit is optional but not required under this contract. The contractor shall verify site conditions during a site visit to be scheduled in consultation with the COR and based on the building construction schedule. The site visit shall be one (1) eight-hour day.
The contractor shall perform the following work:
1. Travel to NISI, Ninety Six, SC.
2. Verify whether exhibits, as approved for production, require any adjustments ahead of
Installation.
3. Prepare and submit documentation of any changes or updates to the installation site that impact the as-designed exhibits.
3.10. Installation
Exhibit elements shall be delivered to the installation site in as complete a state as possible to minimize the amount of on-site work to be done. Work in this phase shall include installation of all exhibit elements on site, and installation of all audio description equipment. Work is organized into the following sub-phases: Primary Installation, Installation Punch List, and Audio Description Installation.
3.10.1. Primary Installation
The contractor shall perform the following work:
1. Crate and ship exhibit elements to the installation site
2. Travel to NISI, Ninety Six, SC with the installation crew.
3. Install exhibit elements in accordance with the design intent, the approved shop drawings, approved revisions and modifications made during Fabrication, and in consultation with the COR.
4. The contractor shall be responsible for exhibit lighting fixtures and accessories; for completing connections of exhibit lighting and exhibit electronic equipment to existing electrical junctions; for the installation of exhibit lighting on site; and for the final placement and aiming of both building and exhibit lighting fixtures after exhibit elements have been installed.
5. Clean worksite of all debris and dust.
6. Clean artifact cases, install artifacts, perform all conservation requirements, and seal and secure cases.
7. Test and verify audio description draft script against installed exhibits and install audio description trigger hardware.
8. Conduct a walk-through inspection of completed and installed exhibits…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .