Sol_140A1624R0010.pdf
PDF 289 KB Posted
- Attached to
- Many Farms High School Construction Build. Federal contract opportunity
- Solicitation number
- 140A1624R0010
About this file
This document is a solicitation for construction services to build the Many Farms High School located in Many Farms, Arizona. The project includes construction of approximately 97,000 GSF of new buildings, renovation of 47,000 GSF of existing buildings, 30,571 GSF of new quarters, outdoor athletic facilities, and utility infrastructure.
The solicitation is for a firm-fixed-price construction contract with an estimated price range over $10,000,000. Key requirements include a project labor agreement, tribal taxes and employment rights compliance, and background investigations for on-site personnel. Proposals are due by 2:00 PM ET on July 12, 2024, and the period of performance is 1,156 calendar days after notice to proceed. The solicitation is being issued by the Bureau of Indian Affairs Central Office.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
BIA CENTRAL 00016
12201 Sunrise Valley Drive
Contracting Office Mail Stop-244
A16
Reston VA 20192 laurie.sherrod@bia.gov emmanuel.riddle@bia.gov
Emmanuel Riddle 0000000000
1x 04/15/2024
140A1624R0010
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Statement of Work dated 4/1/2024, 100% Construction Documents dated 2/2/2024, Project Manual dated 3/6/2024, 2007 BIA School Facilities Design Handbook dated
3/30/2007, Many Farms High School Final Space Allocate Agreement dated 4/29/2021, Indian Affairs (IA) Educational Space Criteria Handbook dated 11/1/2005, IA Division of Safety and Risk Management (DSRM) Safety, Health and Accessibility Design
Guidelines for Architects, Engineers and Design Firms dated 5/2021, IA DSRM Safety and Health Adopted Codes, Policy and Mandatory Standards dated 3/2019, IA DSRM Final
Inspection and Certificate of Occupancy Guidelines dated 5/2020, Guiding Principles for Sustainable Federal Buildings dated 12/2020, Department of Labor Wage
Determination AZ20240022 dated 1/12/2024, and all terms and conditions.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 1156 calendar days and complete it within ________________ ________________ calendar days after receiving
07/12/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
BIA CENTRAL 00016
12201 Sunrise Valley Drive
Contracting Office Mail Stop-244
A16
Reston VA 20192
Laurie Sherrod
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 24
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140A1624R0010
This information is provided for the following project: Many Farms High School Construction
Services.
The purpose of this project is for construction, with cultural considerations outlined in the construction documents, of approximately 97,000
GSF of new buildings, renovation of approximately
47,000 GSF of existing buildings, new construction of 30,571 GSF of 30 new quarters, outdoor athletic facilities, and replacement of campus utility infrastructure. Many Farms High
School is a school operated by the BIE, serving
Native American high school students from the
Many Farms, AZ area, which is approximately 23 miles north of Chinle, AZ.
1. Funding: An award will be made under this solicitation, as funds are presently available.
The Government reserves the right to cancel this solicitation / Task Order Request for Proposal
(TORFP) before the closing date.
2. Contract Clauses: All contract clauses contained in the base Construction Multiple Award
Contracts (C-MAC) IDIQ contract are hereby incorporated into this solicitation. The clauses contained in this TORFP will supplement the clauses in the base C-MAC IDIQ contract.
3. Proposal Acceptance Period/Date: The proposal acceptance period shall extend ninety (90) days past the TORFP closing date.
4. TORFP Deadline: Proposals are due by 2:00 P.M.
Eastern Time (ET) on the date specified in the transmittal of this TORFP.
5. Questions and Answers: Any questions relating to this solicitation shall be submitted to the following individuals: Contract Specialist (CS) and Contracting Officer (CO) no later than 5:00 pm ET on May 20, 2024, unless otherwise specified. Each question shall also reference the volume #, page #, and discipline it refers to.
6. On-site Access: Site Visit will be held on May
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 24
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140A1624R0010
13, 2024, at 1:00 pm MT at Many Farms High
School. Attendance by all firms interested in proposing on this project is highly encouraged.
Please note the Navajo Nation DOES observe daylight saving time even though Arizona does not. RSVPs for attendance at the site visit shall be emailed to the CS and CO by 3:00 pm ET on Friday, May 10, 2024. The email shall include a list of names and company affiliation of who will be in attendance.
7. Period of Performance: One thousand one hundred and fifty-six days (1,156) Calendar Days after receipt of Notice to Proceed (NTP).
8. In accordance with FAR Part 36.204(h)
Disclosure of the Magnitude of Construction
Projects estimated price range is more than
$10,000,000.
9.Special attention is called to FAR Clause
52.236-7, Permits and Responsibilities and FAR
Clause 52.229-3, Federal, State, and Local Taxes.
Offerors are responsible for contacting the tax authorities and tribe or tribal organization involved with regard to any requirements regarding state taxes, tribal taxes, royalties and/or other applicable tribal laws or ordinances. Any costs associated with this section shall be included in the contractor's firm fixed price proposal. Contractor is responsible for contacting the appropriate TERO office for coordination and approvals. Please refer to Section H and the applicable clauses for additional information about these requirements.
10.Points of Contact:
Contract Specialist: Emmanuel Riddle, emmanuel.riddle@bia.gov
Contracting Officer: Laurie Sherrod, laurie.sherrod@bia.gov
Period of Performance: 09/02/2024 to 11/01/2027
00010 Many Farms High School
Anticipated Award Type: Firm-fixed-price
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
5 24
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140A1624R0010
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00020 Many Farms Day School Dormitory
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00030 Maintenance Building and Bus Shelter
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00040 Residential Quarters
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00050 Civil Improvements
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00060 Athletic Fields
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
00070 FF&E
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
6 24
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140A1624R0010
Anticipated Award Type: Firm-fixed-price
Product/Service Code: Y1CA
Product/Service Description: CONSTRUCTION OF
SCHOOLS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
140A1624R0010 Many Farms High School Construction Services
SECTION B – PRICE SCHEDULE
Propose your best prices for each of the work items in accordance with the Statement of Work (SOW) and attachments. Price Proposals must be submitted following the price schedule/format herein.
Incomplete price proposals will not be considered for award.
CLIN DESCRIPTION UNIT UNIT PRICE TOTAL PRICE
0010 Many Farms High School 1 Job $ $
0020 Many Farms High School – Dormitory 1 Job $ $
Many Farms High School – Maintenance Building and Bus Shelter 1 Job $ $
Many Farms High School - Residential Quarters 1 Job $ $
Many Farms High School – Civil Improvements 1 Job $ $
Many Farms High School – Athletic Fields 1 Job $ $
0070 FF&E 1 Job $ $
Subtotal $ Taxes (including TERO if applicable) $
TOTAL $
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1. Disclosure of the magnitude of construction projects. In accordance with FAR 36.204, the estimated price range of this project is:
More than $10,000,000.
* Please refer to Section J of this solicitation for additional scoping documents.
SECTION D – PACKAGING AND MARKING
* Please refer to the C-MAC IDIQ contract for requirements related to this section.
SECTION E – INSPECTION AND ACCEPTANCE
* Please refer to the C-MAC IDIQ contract for requirements related to this section.
SECTION F – DELIVERIES OR PERFORMANCE
F.1. FAR 52.211-10 Commencement, Prosecution, and Completion of Work (April 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1156 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
* Please refer to the C-MAC IDIQ contract for all additional requirements related to this section.
SECTION G – CONTRACT ADMINISTATION DATA
* Please refer to the C-MAC IDIQ contract for requirements related to this section.
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1. TRIBAL TAXES, REQUIREMENTS AND/OR RESTRICTIONS
(a) Special attention is called to FAR Clause 52.236-7, Permits and Responsibilities and FAR Clause 52.229-3, Federal, State, and Local Taxes. Offerors are responsible for contacting the tax authorities and tribe or tribal organization involved with regard to any requirements regarding state taxes, tribal taxes, royalties and/or other applicable tribal laws or ordinances. Any costs associated with this section shall be included in the contractor’s proposal.
(b) Contractor is responsible for contacting the appropriate Tribal Employment Rights Office (TERO) for coordination and approvals.
H.2. BACKGROUND INVESTIGATION
Background investigations are required for on-site workers for this project. See the SOW cited in Section J and C-MAC IDIQ contract section H.1. for specific details.
H.3. PROJECT LABOR AGREEMENTS
This task order requires a project labor agreement. FAR 52.222-33 Alt II (Jan 2024) has been added to this task order. The project labor agreement will be required after award and shall be submitted in accordance with FAR 52.222-33 Alt II (Jan 2024) and FAR 52.222-34 Alt II (Jan 2024).
Please note, currently the C-MAC IDIQ contract contains FAR 52.222-34 Alt I (May 2010), however all C-MAC IDIQ contracts will be modified to update this FAR clause to FAR 52.222- 34 Alt II (Jan 2024) before the task order is awarded.
* Please refer to the C-MAC IDIQ contract for all additional requirements related to this section.
SECTION I – CONTRACT CLAUSES
I.1. FAR 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL
CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)
Consistent with this clause, on completion of this contract please submit the estimated percent-age of total recovered material content for EPA-designed items to the appointed Contracting Officer’s Representative (COR).
I.2. FAR 52.236-4 PHYSICAL DATA (APRIL 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of, or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by the methods outlined in the Program of Requirements document titled “20% Conceptual Design Final Document” dated May 26, 2022, and Planning Document dated July 2018, including topographical survey, Geotechnical Investigation Report, Floodplain Analysis Report and Phase 1 Environmental Site Assessment.
(b) Weather conditions
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON (5) DAY WORK WEEK *
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
(7) (6) (4) (1) (1) (1) (3) (4) (2) (1) (1) (5)
The above schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
(End of clause)
I.3. DIAR 1452.228-70 LIABILITY INSURANCE – DEPARTMENT OF THE INTERIOR
(JULY 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
$_100,000.00__each person, Workers Compensation and Employers’ Liability Insurance
$_500,000.00__each occurrence, General Liability Insurance, Bodily Injury Liability Insurance
$_500,000.00__property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
* Please refer to the C-MAC IDIQ contract for all additional requirements related to this section.
SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
ATTACHMENT TITLE OF DOCUMENT OR FORM PAGES
1 Statement of Work (SOW) 9
2 Construction Documents (CD) 1,071
3 Project Manual 1,774
4 2007 BIA Facilities Design Handbook 574
5 MFHS Final Space Allocation Agreement 10
6 2020 Education Space Criteria Handbook 60
7 Division of Safety and Risk Management, Safety: Health and Accessibility Design Guidelines for Architects, Engineers and Design Firms May 2020
8 Indian Affairs Safety and Health Adopted Codes, Policy and Mandatory Standards March 2019
9 Division of Safety and Risk Management Final Inspection and Certificate of Occupancy Guidelines May 2020
10 Council on Environmental Quality Guiding Principles for Sustainable Federal Buildings and Associated Instructions December 2020
11 Equipment template guidance 5
12 Equipment template v2 1
13 MFHS Construction Phasing Plan Example 8
14 Navajo Tribal Utility Authority (NTUA) Many Farms’ School Infrastructure Upgrade Cost Estimate Letter
15 IA Form 3000v2 Material Approval Submittal 2
16 IA Form C113 Progress Schedule 2
17 IA Form C713 Progress Report 1
18 SF 1413 Statement and Acknowledgement Form (Subcontracting)
19 SF 24 Bid Bond Form 2
20 SF 25 Performance Bond Form 2
21 SF 25A Payment Bond Form 2
22 DOL Wage Determination AZ20240022 dated 1/12/2024 6
If conflicts or contradictions occur between attachments, the order of precedence for all documents, in descending order of precedence is: this solicitation; the Project Manual, 100% Construction Documents, Statement of Work; DSRM Safety, Health and Accessibility Design Guidelines for Architects, Engineers, and Design Firms May 2020; IA Safety & Health Adopted Codes, Policy & Mandatory Standards March 2019; DSRM Final Inspection and Certificate of Occupancy Guidelines;
the Facilities Design Handbook 2007; 2020 Educational Space Determination; Many Farms High School Space Allocation Agreement, and Guiding Principles for Sustainability.
SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER
STATEMENTS OF OFFERORS OR RESPONDENTS
All representations, certifications, and other statements made at the C-MAC IDIQ level.
* Please refer to the C-MAC IDIQ contract for all additional requirements related to this section.
SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS
FAR 52.222-33 Notice of Requirement for Project Labor Agreement, Alt II (Jan 2024)
(a) Definitions. As used in this provision, the following terms are defined in clause 52.222-34, Project Labor Agreement, of this solicitation “construction,” “labor organization,” “large-scale construction project,” and “project labor agreement.”
(b) Offerors shall—
(1) Negotiate or become a party to a project labor agreement with one or more labor organizations for the term of the resulting construction contract; and
(2) Require its subcontractors to become a party to the resulting project labor agreement.
(c) The project labor agreement reached pursuant to this provision shall-
(1) Bind the Offeror and subcontractors engaged in construction on the construction project to comply with the project labor agreement;
(2) Allow the Offeror and all subcontractors to compete for contracts and subcontracts without regard to whether they are otherwise parties to collective bargaining agreements;
(3) Contain guarantees against strikes, lockouts, and similar job disruptions;
(4) Set forth effective, prompt, and mutually binding procedures for resolving labor disputes arising during the term of the project labor agreement;
(5) Provide other mechanisms for labor-management cooperation on matters of mutual interest and concern, including productivity, quality of work, safety, and health; and
(6) Fully conform to all statutes, regulations, Executive orders, and agency requirements.
(d) Any project labor agreement reached pursuant to this provision does not change the terms of the resulting contract or provide for any price adjustment by the Government.
(e) The Offeror shall submit to the Contracting Officer a copy of the project labor agreement with its offer.
(End of Provision)
Alternate II (JAN 2024). As prescribed in 22.505 (a)(3), substitute the following paragraph (b) in lieu of paragraphs (b) through (e) of the basic provision:
(b) If awarded the contract, the Offeror shall—
(1) Negotiate or become a party to a project labor agreement with one or more labor organizations for the term of the resulting construction contract; and
(2) Require its subcontractors to become a party to the resulting project labor agreement.
L.1. General: To assure timely and equitable evaluation of the proposal, the offeror shall follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors.
Failure to meet all requirements may result in an offer being ineligible for award. The response must consist of two (2) separate volumes:
L.1.1. Volume 1, Technical Proposal
L.1.2. Volume 2, Price Proposal https://www.acquisition.gov/far/52.222-34#FAR_52_222_34 https://www.acquisition.gov/far/22.505#FAR_22_505
L.2. Price Evaluation: The Contracting Officer has determined there is a high probability of adequate price competition for this acquisition. Upon examination of the initial offers, the Contracting Officer will review this determination and if, in the Contracting Officer’s opinion, adequate price competition exists no additional cost information will be requested.
L.3. Submittal of Proposals and Inquiries: Offerors must submit one proposal via e-mail (may be broken into multiple e-mails if the proposal’s total file size exceeds 10MB) separated in two (2) separate volumes: Volume 1, Technical Proposal, and Volume 2, Price Proposal.
L.4. SPECIAL NOTICE TO OFFERORS.
L.4.1. The exclusive responsibility for Source Selection will reside with the Government. Proprietary information submitted in response to this solicitation shall be clearly marked as such and will be protected from unauthorized disclosure as required by Subsection 27 of the Office of Procurement Policy Act as amended (41 U.S.C. 423) (hereinafter referred to as "the Act") and as implemented in the FAR. Any unmarked proprietary information will be considered releasable under the restrictions of the Freedom of Information Act.
L.4.2. For submission requirements designated as “shall” or “must,” failure to provide the requested information will be considered a deficiency. For submission requirements designated as “should,” failure to provide the requested information may result in a lower rating for the specified factor.
L.5. FORMAL COMMUNICATIONS
The following Points of Contact (POC) are provided for this acquisition. Address any questions or concerns you may have to both POCs via e-mail listed below no later than the date specified in Form SF-1442. Answers will be provided only in response to written requests for clarification. Written questions shall be emailed to the addresses indicated below.
Emmanuel Riddle Laurie Sherrod Contractor Contract Specialist Contracting Officer emmanuel.riddle@bia.gov laurie.sherrod@bia.gov
The Government will not accept a facsimile proposal.
L.6. GENERAL SUBMISSION REQUIREMENTS
L.6.1. Submissions exceeding a file size of 10MB shall be broken into multiple e-mails or coordinated with the POCs to assure successful file sharing. No hard copies of proposals will be accepted (hand delivered or traditional mail). The Government reserves the right to request hard copies in binder format in the event of a formal protest.
L.6.2. Proposals shall not contain classified data. The use of hyperlinks in proposals are prohibited. The Government will not be responsible for proposals delivered to any location or to anyone other than the Contracting Office.
L.6.3. Offerors are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete proposal. Failure to furnish a complete proposal at the time of proposal submission may result in an unacceptable proposal that the Government eliminates from consideration for award.
L.6.5. Offerors are cautioned that “parroting” of the requirements of the SOW or Plans and Specifications with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of their proposal.
L.6.6. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
L.6.7. Disposition of Unsuccessful Proposals: in compliance with FAR Subpart 4.8, the Government will retain one copy of all unsuccessful proposals.
L.7. FORMATTING REQUIREMENTS
L.7.1. Proposal submission shall be in PDF format compatible with the latest version of Adobe Acrobat, except for price breakdown information, which shall be submitted in a spreadsheet format compatible with the latest version of Microsoft Excel.
L.7.2. Please use titles of volumes in the following format:
L.7.2.1. Solicitation Number _Company Name_ Volume 1 Technical Proposal
L.7.2.2. Solicitation Number _Company Name_ Volume 2 Price Proposal
L.7.3. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or Times New Roman fonts are required. Tables and illustrations may use a reduced font size no less than 8-point and may be landscape oriented. Files shall use the following page setup parameters: Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge – Header, Footer 0.5” Page Size, Width – 8.5” Page Size, Height – 11.”.
L.7.4. The submission shall be clearly indexed and logically assembled. Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be numbered consecutively and identified by the complete company name, date, and solicitation number in the header and/or footer. A Table of Contents shall be included.
L.8. PAGE LIMITS
Volume Evaluation
Factor Title Page Limit
1 Experience 10 2 Capacity 5 3 Key Personnel 201
4 Technical Approach Narrative 10 2 5 Price no limit
L.8.1. All pages with written content, except cover letters, Table of Contents pages, tables, illustrations, glossary, section dividers, sketches or drawings, teaming agreements and appendices will be counted in the page calculation. Pages that exceed the page limitations will be removed, not read, and not evaluated.
L.9. VOLUME I – TECHNICAL PROPOSAL
L.9.1. Factor 1: Experience
L.9.1.1 The Offeror shall submit a minimum of three (3) and a maximum of five
(5) projects that best demonstrate its team’s experience on recent and relevant projects that are similar in scope, complexity, size, and price to the work required under this solicitation.
If more than five (5) projects are submitted, only the first five (5) projects will be evaluated.
L.9.1.2 At least one (1) project shall be provided for the prime Offeror (the entity signing the SF1442). If the Offeror is a Joint Venture (JV), recent and relevant project experience shall be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have experience, such projects shall be submitted for each Joint Venture partner.
L.9.1.3 The Offeror may utilize experience of a subcontractor or affiliate to demonstrate experience under this evaluation factor. To be considered relevant, projects submitted to demonstrate a subcontractor’s or affiliate's experience must correlate to the work to be performed by the subcontractor or affiliate under the proposed task order.
L.9.1.4 Projects provided must be completed within the past ten (10) years, as of the issue date of this solicitation, to be considered recent. A project is defined as work performed under a single task order or contract. For multiple award and Indefinite Delivery Vehicle (IDV) (e.g., Indefinite Delivery/Indefinite Quantity
(IDIQ) type contracts, the contract as a whole should not be submitted as a project;
rather, Offerors should submit the work performed under a task order as a project.
L.9.2 Factor 2: Capacity: Describe how the offeror and its team have the capacity to undertake the work described by this solicitation given all work currently being performed by the offeror and all work scheduled to be performed during the period of performance described in the solicitation. Proposals should include a list of all on-going and scheduled work for the offeror and proposed team members. Specifically identify any work on this list that is being performed for Indian Affairs.
L.9.3. Factor 3: Key Personnel: Identify and provide résumés for Key Personnel who will perform the work of this project and their assigned roles. Key Personnel will include: the Project Manager, Site Superintendent, Quality Control Manager, and Site Safety and Health Officer (SSHO). All roles shall be filled by separate individuals; dual hatting is not acceptable.
Résumés shall be provided for all Key Personnel, including name, employee’s position description, education, and qualifying academic, design, construction, Professional Registration, and experience. The proposal shall clearly indicate the entity employing the Key Personnel.
Minimum standards for each Key Personnel position are addressed in Section M - Evaluation Factors for Award. The Key Personnel proposed for this factor will be binding to the Offeror selected for award. Any changes to Key Personnel after task order award must be approved in writing by the Contracting Officer.
L.9.4 Factor 4: Technical Approach Narrative
L.9.4.1. The Offeror shall submit a narrative discussion in response to the project described in the project documents.
L.9.4.2. The narrative shall describe the Offeror's approach to the work. It shall:
L.9.4.2.1. Describe an overall approach to the work that demonstrates the offeror’s understanding of the work, including creativity and thoroughness shown in understanding the objectives of the SOW, specific tasks, risks and risk mitigation measures, and planned execution of the project.
L.9.4.2.2. Provide an organizational diagram showing clear, logical lines of authority from the Project Manager to Subcontracting Management, including Superintendence, Safety, and Quality Control.
L.9.4.2.3. Describe teaming arrangements, including overall structure and management of the project team; identify roles, responsibilities, and contractual relationships between the various firms. The team proposed for this factor will be binding to the Offeror selected for task order award.
Any changes to this team after award must be approved in writing by the Contracting Officer.
L.9.4.2.4. Describe how the Offeror will ensure quality consistently across the team.
L.9.4.3. Offerors must assume the Government has no prior knowledge of their capabilities, work processes, facilities, and experience. The Government will base its evaluation on the information presented in the Offeror’s proposal. Elaborate brochures or documentation binding, detailed artwork, or other embellishments are unnecessary and are not desired.
L.10. VOLUME II – PRICE PROPOSAL
L.10.1. Factor 5: Price
L.10.1.1. The Offeror shall provide a table of contents and shall number all pages consecutively. Volume II shall be submitted in a separate file from Volume I. The price proposal shall be broken down into sections as defined below.
L.10.1.2. Section 1: The name(s) and title(s) of the person(s) authorized to negotiate and sign a contract. Also, provide a Certificate of Corporate Authority or other applicable documentation of authorized signature(s) for each authorized individual.
L.10.1.3. Section 2: The Offer (the SF1442) duly executed with an original signature by an official authorized to bind the company.
L.10.1.4. Section 3: Acknowledgement of all amendments to the solicitation in accordance with the instructions on the Standard Form 30 (Amendment form).
L.10.1.5. Section 4: The completed Section K of the solicitation (i.e., Representations, Certifications, and Other Statements of Offerors). All cost and pricing data supplied by Offerors will represent data other than certified cost or pricing data as defined by FAR 2.101. Representations, Certifications, and Other Statements may also be accomplished via sam.gov, but must be complete and up to date prior to the proposal deadline.
L.10.1.6. Section 5: Each Offeror is required to complete the Price Schedule in this solicitation.
L.10.1.7. Section 6: Fully executed Bid Guarantee, Standard Form (SF) 24, Bid Bond.
SECTION M – EVALUATION FACTORS FOR AWARD
M.1. GENERAL INFORMATION
M.1.1. The policies in FAR subpart 15.3 do not apply to this ordering process. This order will utilize the fair opportunity process outlined in FAR 16.505(b)(1). This order will be placed on a competitive basis. The factors below will be used in evaluating proposals, and award will be made on a best value basis.
M.1.2. The Government intends to award without requesting proposal revisions. If proposal revisions are required, the Government may request revisions from any number of offerors, including only one, some, or all offerors.
M.2. BASIS FOR AWARD
M.2.1. The award will be made based on the best overall (i.e., best value) proposal that is determined to be the most beneficial to the Government with tradeoffs made between the non-price and price factors. The Government may select other than the lowest price or other than the most highly rated Offer. To receive consideration for award, a rating of relevant must be achieved for Factor 1 and a rating of no less than “Acceptable” must be achieved for Factors 2, 3 & 4 (the other non-price factors).
M.2.2. During the evaluation of each proposal, the Government will assign a rating for Factors 1 through 4. The following factors are listed in descending order of importance and will be used to evaluate each proposal:
M.2.2.1. Factor 1: Experience
M.2.2.2. Factor 2: Capacity
M.2.2.3. Factor 3: Key Personnel
M.2.2.4. Factor 4: Technical Approach Narrative
M.2.2.5. Factor 5: Price
M.2.3. For the best value determination, Factors 1-4 are listed in descending order of importance. All evaluation factors other than price, when combined, are approximately equal to price.
M.3. Factor 1: Experience
M.3.1. There are two (2) aspects to the experience evaluation: recency and relevancy. In accordance with the instructions in Section L, Factor 1, Offerors shall submit a minimum of three (3) and a maximum of five (5) projects that best demonstrate its team’s experience on recent and relevant projects that are similar in scope, complexity, size, and price to the work required under this solicitation. If more than five (5) projects are submitted, only the first five (5) projects will be evaluated.
M.3.1.1 Recency. An evaluation of each proposed project will be made to determine if it is recent. Recency is defined as completion within the ten (10) years preceding the date of issuance of this solicitation. Proposed projects that fail this condition will not be evaluated. More recent projects will have a greater impact on the Relevancy Rating (see Table 1 below) than less recent effort.
M.3.1.2 Relevancy. The Government will conduct an in-depth evaluation of all information submitted to determine how closely the work performed under those contracts relates to the services described in the SOW. Specifically, relevant is defined as contracts of similar size, scope, and magnitude, involving the type of services described in the solicitation.
Offerors are required to explain what aspects of each contract are deemed relevant to complexity and magnitude as related to the requirements of this solicitation.
Failure to provide required relevancy description may impact the relevancy rating.
In determining relevancy for individual projects, consideration will be given to the effort, or portion of the effort, being proposed by the Offeror, teaming partner, or subcontractor whose contract is being reviewed and evaluated. In other words, the work performed by the entity under the submitted project will be compared to the work proposed to be performed by that same entity under the project described in this solicitation.
The Government will use the relevancy definitions in Table 1 below when assessing recent, relevant contracts.
Table 1. Relevancy Rating Rating Definition
Very Relevant Submitted projects involved essentially the same scope and magnitude of effort and complexities this solicitation. Projects completed more recently may be considered more relevant.
Relevant Submitted projects completed within the last 10 years involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Submitted projects completed within the last 10 years involved some elements of the scope or a lesser magnitude of effort or complexity than this solicitation requires.
Not Relevant Submitted projects completed within the last 10 years involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
M.4. Factor 2: Capacity
M.4.1. This factor will evaluate each offeror’s team’s existing project commitments to determine if the offeror and its team have the resources (capacity) to perform the required work in the required timeframe. At a minimum, the proposal must show that the offeror has the resources or access to the resources to perform the work in the time required. This factor is not intended to provide for allocation or “equitable distribution” of orders under the C-MAC or to place an order ceiling on individual C-MAC holders, a prohibited practice that is counter to the principle of fair opportunity.
M.4.2. A proposal may be more highly rated for this factor if it demonstrates that the offeror’s resources exceed its commitments.
M.4.3. This factor will be rated using the definitions in Table 2.
Table 2. Capacity Rating Definition
Good
The proposal convincingly shows that the offeror has the resources or access to the resources to perform the work in the time required. No Deficiencies are found.
Acceptable The proposal adequately shows that the offeror has the resources or access to the resources to perform the work in the time required. No Deficiencies are found.
Unacceptable
The proposal does not meet all requirements, has an identified Deficiency, or has a combination of Weaknesses and/or Significant Weaknesses that present an unacceptable level of risk that the offeror cannot perform the work in the time required.
risk.
M.5. Factor 3: Key Personnel
M.5.1. This factor will evaluate the extent to which the key personnel meet the desired experience and education listed below. Proposals may be more highly rated if they offer key personnel who exceed the minimum requirements or offer additional professional qualifications.
M.5.2 Proposals may be more highly rated if they offer key personnel whose resumes demonstrate experience with projects similar in scope, complexity, size, and cost or price to the Many Farms High School Construction Services project.
M.5.3. This factor will be rated using the definitions in Table 4 and the desired qualifications in Table 3.
Table 3. Key Personnel Desired Qualification Requirements Position Desired Qualification Requirements
Project Manager
- 10 years design-build construction management experience, BS degree in construction management or engineering related field, and at least one of the following certifications or registrations:
- Active Certified Construction Manager (CCM) certified by the Construction Manager Certification Institute.
OR
- Active Project Management Professional (PMP) certification issued by the Project Management Institute
OR
- Active Certified Professional Constructor (CPC) certified by the American Institute of Constructors & Constructor Certification Commission
OR
- Active Designated Design-Build Professional certification administered by the DBIA
OR
If no certification, then Project Manager shall have 20 years of design-build construction management experience instead of 10.
Site Superintendent
- 10 years of experience as Construction Site Superintendent
- Completion of the 30-hour OSHA Construction safety class or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the OSHA 30-hour course
Quality Control Manager - 8 years of experience as a Quality Control Manager
Site Safety and Health Officer (SSHO)
- 8 years of construction industry safety experience or five years if she or he possesses a Certified Safety Professional (CSP) or safety and health degree.
- Completion of the 30-hour OSHA Construction safety class or as an equivalent, 30 hours of formal construction safety and health training covering the subjects of the OSHA 30-hour course
M.6. Factor 4: Technical Approach Narrative
M.6.1. This factor will evaluate the Offeror’s narrative describing its approach for accomplishing the work described in the Many Farms High School Construction Services SOW and project documents. To be considered acceptable, the Offeror must demonstrate an understanding of the specific requirements described in the solicitation and demonstrate the ability of their approach to accomplish those requirements.
M.6.2. The factor will be evaluated on the extent to which the narrative:
M.6.2.1. Is logical and free of contradictory or conflicting information.
M.6.2.2. Describes an approach to resourcing, organizing, and communicating on the proposed project that is consistent with requirements in the project description.
M.6.2.3. Provides a level of detail and specificity to this project that demonstrates that the Offeror understands the requirements.
M.6.3. This factor may be more highly rated if the narrative describes an approach to resourcing, organizing, executing, and communicating on the proposed project that reduces the risk of unsuccessful contract performance.
M.6.4. This factor will be rated using Table 4.
Table 4. Technical Approach Rating Definition
Good
Proposal meets all requirements and presents benefits identified by a combination of Significant Strengths and/or Strengths. If Weaknesses and/or Significant Weaknesses are present, the associated risks are outweighed by the evaluated benefits. No Deficiencies are found.
Acceptable Proposal meets all requirements with essentially offsetting benefits and risks presented by Significant Strengths, Strengths, Weaknesses and/or Significant Weaknesses, if any are present. No Deficiencies are found.
Unacceptable
Proposal may have Significant Strengths or Strengths. However, the benefits presented are irrelevant because the proposal does not meet all requirements or has a combination of Weaknesses, Significant Weaknesses or Deficiencies that present an unacceptable level of risk.
risk.
M.7 Factor 5: Price
M.7.1. The contract awarded from this solicitation will be Firm-Fixed-Price construction.
Price reasonableness analysis will be performed by the Government to determine that the proposal prices offered are complete, fair, and reasonable. Normally, competition establishes price reasonableness. Comparison of the proposed prices is expected to satisfy the requirement to perform a price analysis, however, the Government may, if necessary, analyze the Offeror’s price breakdown in Section B to establish reasonableness of an otherwise successful offeror’s price. The Government reserves the right to conduct price realism analysis.
M.7.2. For purposes of award, the total evaluated price will include all prices for the contract in its entirety as identified in Section B-PRICE SCHEDULE. Offerors must submit pricing for all line items. The total evaluated price for purposes of the Best Value Trade Off and award will be determined by the total sum of the line items in the PRICE SCHEDULE, and as shown in SF-1442 Block 17. The additional information in the Price Breakdown will only be requested from the successful offeror and is not to be included in the proposal.
M.8. FINAL SELECTION
M.8.1. The Contracting Officer will award to the Offeror whose proposal conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, all factors considered.
END OF TASK ORDER REQUEST FOR PROPOSAL