Attach_13_-_MFHS_Const_Phasing_Plan_Example__3_2024.pdf

PDF 3 MB Posted

Attached to
Many Farms High School Construction Build. Federal contract opportunity
Solicitation number
140A1624R0010
Issued by
Department of the Interior Bureau of Indian Affairs Central Office

About this file

This document is a construction phasing plan example for the Many Farms High School Remodeling/Additions project under BIA Contract No. 140A1620D0006 / 140A1622F0164. The plan outlines the required phased approach for construction, with the contractor responsible for creating the final plan to be approved by the Bureau of Indian Affairs prior to construction.

The key phases include: Phase 0 - 9 months of infrastructure and softball field work; Phase 1 - 24 months of high school additions and utility/infrastructure work; Phase 2 - 9 months of high school renovation; Phase 3 - 12 months of athletic facilities construction; Phase 4 - 12 months of dormitory construction; Phase 5 - 10 months of maintenance facility remodel and bus shelter construction; and Phase 6 - 12 months of staff quarters and utility infrastructure. The plan emphasizes the requirement to maintain operation of all facilities during construction.

The related federal contract opportunity is Solicitation Number 140A1624R0010 for the Many Farms High School Construction Build, issued by the Department of the Interior Bureau of Indian Affairs Central Office.

View the file

Other files for this federal contract opportunity

Other files attached to Many Farms High School Construction Build., newest first.
File Type Posted
Sol_140A1624R0010_Amd_0002.pdf PDF
Sol_140A1624R0010_Amd_0001.pdf PDF
Phase_I_ESA-Many_Farms_0001.pdf PDF
Many_Farms_High_School_Pre-renovation_Hazardous_Materials_Assessment_Report_-_Buildings_1369_and_1161_0001.pdf PDF
Attach_14_-_NTUA_MF_Infrastructure_Uprade_Cost_Est_Ltr_4_5_24.pdf PDF
Attach_15_-_IA_Form_3000v2_Mat_Aprvl_Submittal.pdf PDF
Attach_20_-_SF-25_Performance_Bond_Form.pdf PDF
Attach_5_-_MFHS_Final_Space_Allocation_Agreement.pdf PDF
Attach_12_-_Equip_Template_v2.xlsx XLSX spreadsheet
Attach_19_-_SF-24_Bid_Bond_Form.pdf PDF
Attach_21_-_SF-25A_Payment_Bond_Form.pdf PDF
Attach_3_-_Project_Manual_3_6_24.pdf PDF
Attach_1_-_SOW_-_Final_4_1_24.docx DOCX document
Attach_6_-_Education_Space_Criteria_HB_11_1_05.pdf PDF
Attach_9_-_DSRM_Final_Inspect___Cert_of_Occupancy_GL_5_2020.pdf PDF
Attach_16_-_IA_Form_C113_Prog_Sched.pdf PDF
Attach_17_-_IA_Form_C713_Prog_Rpt.pdf PDF
Attach_18_-_SF-1413_Statement-Acknowledgement_Form_(Subcontracting).pdf PDF
Attach_22_-_DOL_WD_AZ20240022_1_12_24.pdf PDF
Sol_140A1624R0010.pdf PDF
Attach_4_-_2007_BIA_School_Facilities_Design_HB_3_30_07.pdf PDF
Attach_7_-_DSRM_Safety__Health_and_Access_Guidelines_4_AEs_5_2020.pdf PDF
Attach_8_-_IA_Safety-Health_Adopted_Codes-Policy-Standards_3_2019.pdf PDF
Attach_10_-_Guiding_Prin_4_Sustainable_Fed_Bldgs_12_2020.pdf PDF
Attach_11_-_Equip_Template_Guidance.docx DOCX document
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Start Finish

1 Design Phase Thu 9/1/22 Sat 11/11/23

2 Design Contract Award Thu 9/1/22 Thu 9/1/22

3 Field Services Thu 9/1/22 Thu 10/20/22

4 Pre Design Fri 9/2/22 Tue 10/11/22

5 20% Schematic Design Wed 10/12/22Wed 11/30/22

6 40% Design Development Thu 12/15/22 Tue 3/14/23

7 70% Construction Documents Thu 3/30/23 Tue 6/27/23

8 99% Construction Documents Wed 7/19/23 Sat 9/16/23

9 100% Document Submission Sun 10/8/23 Fri 11/10/23

10 Bid Procurement Set Deliverables Sat 11/11/23 Sat 11/11/23

11 Bid / Award Sat 11/11/23 Fri 12/15/23

12 Construction Phase Sat 12/16/23 Sun 4/4/27

13 Mobilize Sat 12/16/23 Thu 1/4/24

14 Phase 0: Infrastructure for HS Additions; New Softball Field - 9 moFri 1/5/24 Fri 10/4/24

15 Phase 1: HS Additions / SW Renovation - 24 mo Fri 7/5/24 Sat 7/4/26

16 Balance of Infrastructure / Tie-ins (Continuum) Sat 10/5/24 Sun 4/4/27

17 Phase 3: Football / Track / Baseball - 12 mo Sat 11/2/24 Sat 11/1/25

18 Phase 4: Dorms - 12 mo Sun 8/3/25 Fri 7/24/26

19 Phase 2: Balance of HS Renovation - 9 mo Sun 7/5/26 Sun 4/4/27

20 Phase 5: Remodel Votech for Maintenance; Construct Bus Garage - 9 moSun 7/5/26 Sun 4/4/27

21 Phase 6: Staff Quarters Development - 12 mo Sun 4/5/26 Sun 4/4/27

22 Project Completion Sun 4/4/27 Sun 4/4/27

23 Target Completion: 3 year construction duration Mon 12/14/26Mon 12/14/26

9/1

11/11

4/4

12/14

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2023 2024 2025 2026 2027

Mon 11/21/22 EXAMPLE Many Farms High School Remodeling / Additions

BIA Contract No.: 140A1620D0006 / 140A1622F0164

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

Construction Phasing Plan Example

EXAMPLE

UTILITY / INFRASTRUCTURE WORK

LONG TERM

CONTRACTOR

STAGING AREA

CONTRACTOR STAGING AREAS

PHASE 0: - 9 Months

Relocate Softball Field to allow construction of new loop road

Significant Roadway Construction work required to allow installation of new water and sewer mains.

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLE

HIGH SCHOOL ADDITIONS

UTILITY INFRASTRUCTURE

PROPOSED

REPLACEMENT

SANITARY SEWER

STATION

PROPOSED WATER

SOFTENING BUILDING

AND ASSOCIATED

BY-PASS WATER MAIN

LONG TERM

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 1: - 24 Months

Additional Utility Infrastructure and Storm Drain Work

Construct New Additions to High School - Create Classroom Swing Space to Allow Future Remodeling of Existing Building

VACATE

SOUTHERN MOST

EXISTING

CLASSROOMS

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLEEXISTING HIGH SCHOOL

REMODELING

POSSIBLE PARTIAL

OCCUPANCY OF NEW

ADDITIONS WHILE

REMODELING WORK IS

UNDERWAY

LONG TERM

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 2: - 9 Months

Remodel Existing High School -

POSSIBLE OCCUPANCY OF NEW

ADDITIONS

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLEATHLETIC FACILITIES

LONG TERM

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 3: - 12 Months

Construct New Competition Baseball Field and Football Stadium

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLEDORMITORY

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 4: - 12 Months

Construct New Dormitory Facility

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLEMAINTENANCE / BUS SHELTER

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 5: - 10 Months

Remodel Maintenance Facility / Construct New Bus Shelter

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

EXAMPLESTAFF QUARTERS

CONTRACTOR

STAGING AREA

STAGING AREA

PHASE 6: - 12 Months

Construct New Staff Quarters / Utility Infrastructure

The information above is a representative example of the required phased approach for construction of the project, and the requirement to maintain operation of all facilities during the construction period. The contractor is responsible for the creation of the final construction phasing plan that will be approved by The Bureau of Indian Affairs before construction begins.

File details come from the government source that posted it. Updated .