SFRL 10393282 RECAP AIRSTA E-CITY RUNWAY 1-19 RFP.pdf

PDF 14 MB Posted

Attached to
RECAPITALIZE RUNWAY 1-19 at U. S. COAST GUARD BASE ELIZABETH CITY, NC.
Solicitation number
70Z04725RPCNI0001
Issued by

About this file

This document is a Request for Proposal (RFP) for the recapitalization of Runway 1-19 at U.S. Coast Guard Base Elizabeth City, North Carolina. The project involves restoring the 4,518-foot by 150-foot runway and associated taxiways to operational condition, including the installation of LED edge lighting, guidance signs, and other components to meet FAA standards. The RFP also includes an option for constructing a north turnaround pad compatible with the largest operating aircraft, the HC-130. This design-build project is posted exclusively for contractors on the current DHS/USCG National Multiple Award Construction Contract III (NMACC III), Pool 1. The RFP outlines the required services, materials, and construction standards, and provides details on the agency (Department of Homeland Security U.S. Coast Guard), the solicitation number, and the type of opportunity (solicitation).

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP GUIDE SPECIFICATIONS

FOR

FDCC

RECAPITALIZE RUNWAY 1-19

USCG BASE ELIZABETH CITY

ELIZABETH CITY, NC

DATE: 02 JULY 2024

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

FACILITIES DESIGN & CONSTRUCTION CENTER

FDCC Norfolk

5505 ROBIN HOOD ROAD SUITE K

NORFOLK, VIRGINIA 23513-2413

UNITED STATES COAST GUARD

REQUEST FOR PROPOSAL

Recapitalize Runway 1-19 21-10393282

USCG Base Elizabeth City, NC

FROM: Facilities Design & Construction Center (Norfolk)

BENEFITING UNIT: USCG Base Elizabeth City, NC

POINTS OF CONTACT:

ORGANIZATION FUNCTION EMAIL PHONE

FDCC DESIGN PM,

Kevin Suriano Kevin.e.suriano@uscg.mil (571) 607-8341

SIGNATURES:

Design PM Date

Design Supervisor Date

Project Execution Supervisor Date

Project Execution Branch Chief Date

THIS PAGE IS INENTIONALLY BLANK

PROJECT RFP REQUIREMENTS

SECTION TITLE

T.O.C. TABLE OF CONTENTS

01110 DESIGN-BUILD GENERAL PARAGRAPHS

01200 DESIGN-BUILD PROGRESS PAYMENTS

01320 DESIGN-BUILD PROGRESS SCHEDULE

01330 DESIGN-BUILD SUBMITTAL PROCEDURES

01450 QUALITY CONTROL

01500 TEMPORARY COR FACILITIES AND EQUIPMENT

01505 PROJECT MANAGEMENT MEETINGS

01781 OPERATION AND MAINTENANCE DATA DOCUMENTATION

01800 DESIGN-BUILD CRITERIA

1.1 GENERAL PROJECT REQUIREMENTS AND DESCRIPTION

1.2 ROLES OF RFP SPECIFICATIONS & DRAWINGS

1.3 SUSTAINABLE DESIGN

1.4 CIVIL AND SITE WORK

1.5 GEOTECHNICAL

1.8 STRUCTURAL

1.9 DEMOLITION

1.13 ELECTRICAL

1.16 TELECOMMUNICATIONS

1.18 ENVIRONMENTAL DESIGN, PERMITS, CONTROLS, AND PROTECTION

01802 CONSTRUCTION DESIGN DOCUMENTS

01803 RECORD DOCUMENTS AND DRAWINGS

01900 LIST OF RFP DRAWINGS, EXHIBITS, AND ATTACHMENTS

APPENDIX A CRITERIA FOR COMPUTER GENERATED DRAWINGS

APPENDIX B CRITERIA FOR ELECTRONIC DELIVERABLES

APPENDIX C ADEPT FILE NAMING

APPENDIX D DESIGN NARRATIVE

APPENDIX E INDUSTRY STANDARDS FOR CONSTRUCTION DOCUMENTS

APPENDIX G O&M Part 1 – EXISTING SAM USCG MAINTAINED EQUIPMENT

APPENDIX G O&M Part 2 – EQUIPMENT ENROLLMENT FORM

APPENDIX G O&M Part 3 – JOB PLAN DETAILS

APPENDIX H CONSTRUCTION FORMS

ATTACHMENT A GEOTECHNCIAL

ATTACHMENT B ENVIRONMENTAL

ATTACHMENT C CONSTRUCTION RECORDS

ATTACHMENT D PHOTOS

ATTACHMENT E PROJECT MANAGEMENT DATA SHEETS (PMDS)

ATTACHMENT F AIRCRAFT DATA

ATTACHMENT G PAVEMENT RECORD DATA

ATTACHMENT H

RFP DRAWINGS

RAPIDGate

SECTION 01110 Page 1 of 10

SECTION 01110_DESIGN-BUILD GENERAL PARAGRAPHS

Part 1 GENERAL

1.1 OVERVIEW

Located in the heart of Northeastern North Carolina, United States Coast Guard (USCG) Base Elizabeth City is comprised of 822 acres of real estate, including runways, taxiways, airport traffic control tower, roadways, and more than 100 buildings.

Base Elizabeth City provides a wide variety of mission support services to units and personnel, including general administration and personnel management, medical/dental, supply, procurement and warehousing, industrial services, facilities maintenance, computer/electronics support as well as morale and recreational services. Base Elizabeth City coordinates and provides regional mission support activities within the Fifth Coast Guard District. The Base is a regional command that provides logistics, engineering, administrative, financial, purchasing, and health care services to Coast Guard units throughout North Carolina. The Base Commander synergizes field support delivery, establishes local command unity, and integrates the technical authority of logistics and service centers, product and service lines, and local, coordinated service delivery.

Base Elizabeth City supports aviation operations for the tenant commands Air Station Elizabeth City, Aviation Logistics Center (ALC) and the HC-27J Aviation Projects Acquisition Center (APAC). The Airfield is a joint use facility that serves both civilian and military aircraft operations. Approximately 55,000 total flight operations are conducted each year and are a mix of military and civilian operations. Military operations are approximately 55% of the total and rotary wing comprise 50% of the military total.

The fixed wing aircraft assigned to Air Station Elizabeth City are HC-130J model. Depot maintenance for all fixed wing aircraft (HC-27J, HC-144, and HC-130J/H) is performed by the ALC, which conducts flight operations required by respective maintenance cycles as well as developmental testing and evaluation for various system prototypes. C-27 and HC-144 fixed wing aircraft conduct flight operations in conjunction with their respective maintenance cycles at ALC.

The Elizabeth City-Pasquotank County Airport Authority (ECPCAA) operates under a joint-use agreement and real property license with the United States Coast Guard.

The Airfield Complex consists of the active primary Runway 10-28, the closed alternate cross-wind Runway 1-19, and various associated taxiways and aprons. Runway 1-19 is currently closed to all flight operations due to its severely degraded structural and functional condition.

Runway 1-19 was designated as a primarily civilian aviation runway under the terms of a joint use agreement and real property license (circa 1995) to allow the airport authority to operate within the USCG Base Elizabeth City’s boundaries. The USCG chose to limit investment in the maintenance of runway 1-19 as it was deemed to be of marginal benefit to military flight operations. Runway 1-19 has been closed to USCG aircraft since 2008 due to its poor condition and load carrying restriction, however, it remained open to civilian (light) aircraft

SECTION 01110 Page 2 of 10 flight operations until 2015, at which time it was closed to all air traffic. Additionally, Runway 1-19 access taxiways Kilo and portions of Golf were also closed for similar reasons.

Presently, USCG Flight operations are regularly delayed, aborted or cancelled due to out of limit crosswinds on Runway 10-28. As a mitigating measure, when unfavorable wind and/or weather conditions are anticipated, the ready Air Station C-130 aircraft redeploy to another location if possible. Relocation typically adds SAR response time and incurs other additional costs. When excessive crosswinds arise unexpectedly, flight operations even for SAR missions may be forced to be suspended.

Aircraft at ALC for maintenance are not typically able to redeploy, but maintenance testing may be impacted if out of limits crosswind conditions are experienced for a prolonged period.

Aircraft delayed in arriving or departing due to crosswinds impact ALC operations negatively and disrupt normally tight maintenance schedules.

1.2 SCOPE OF WORK

Provide all services and materials necessary to design-build demolition and construction for the project entitled ‘Recapitalize Runway 1-19’ at USCG Base Elizabeth City, NC. Do the work according to this specification and as shown on the Government-accepted, Contractor-originated drawings. Provide all services and materials necessary. The major items of work shall consist of the following:

1.2.1 Paving Scope

1.2.1.1 [BASE] Runway 1-19 (RW 1-19): Restore Runway 1-19 (RPUID 24082) to operational conditions as a crosswind, alternate runway for the design mix aircraft at its present dimension of 4,518-feet in length and 150-feet in width. New pavement surfaces shall be Portland Cement Concrete. Note, existing pavement layer thickness vary. Refer to Attachment G- Pavement Record Data.

1.2.1.2 [BASE] Taxiway Kilo (TW K): Full width asphalt pavement removal (i.e milling) and overlay of all bituminous pavement sections down to the underlying concrete pavement surface. Note, existing pavement layer thickness vary. Refer to Attachment G- Pavement Record Data.

1.2.1.3 [BASE] Taxiway Golf (TW G): Full width asphalt pavement removal (i.e milling) and overlay of all bituminous pavement sections down to the underlying concrete pavement surface. Note, existing pavement layer thickness vary. Refer to Attachment G- Pavement Record Data.

1.2.1.4 [OPTION #1] RW 1-19 Turnaround Pad: Construct a concrete Turn-around pad for H-C130 aircraft at the North end of RW 1-19. Construction shall be in accordance with the requirements of UFC 03-260-01 for Army and Air Force facilities based upon the HC-130 aircraft. Demolition shall include the removal of the existing PCC pavement section to natural subgrade. New construction shall include the demolition of existing pavements and tie-into exiting airfield taxiways and runways. New work shall include all required airfield lights, navigation aids, to include feeders and duct banks, and pavement striping/markings. The Contractor’s DOR is responsible for pavement thickness requirements.

1.2.2 Lighting Scope

Provide and install operational LED edge lighting, guidance signs, lighting system components supporting taxiways for Runway 1-19 and various taxiways, as shown in the

SECTION 01110 Page 3 of 10

RFP drawings. All lighting shall comply with FAA standards (FAA AC 150/5340-30). The major work items include, but are not limited to the following:

1.2.2.1 [BASE] Airfield Lighting Vault and Tower Airfield Lighting Control System (ALCS): Disconnect and dispose old lighting system and provide and install all work necessary to tie in the new airfield lights into the existing airfield lighting vault Air Traffic Control Tower (ATCT), as necessary to ensure operability.

1.2.2.2 [BASE] Edge Lights: Demolish and dispose of existing airfield edge lighting system and components, and installs new elevated LED edge light fixtures, to include light bases, duct banks, handholds, cabling, isolation transformers, and miscellaneous components to ensure compliance with FAA standards, as noted in the RFP Drawings.

1.2.2.3 [BASE] Guidance Signs: Airfield guidance signs and runway distance signs are not FAA compliant (i.e., incorrectly labeled, missing, outdated, or lack required position spacing, offset and height). Removing existing guidance signs, installing new LED guidance signs, mandatory hold signs, and distance remaining signs on new foundations per FAA requirements.

1.2.2.4 [BASE] Threshold Lights: Demolish and dispose of the existing runway threshold lighting system and components, and install new LED Runway End Identifier (REIL) light, to include light bases, duct banks, handholds, cabling, isolation transformers, and miscellaneous components to ensure compliance with FAA standards, as noted in the RFP Drawings.

1.2.2.5 [BASE] RW 1-19 Visual Approach Slope Indicator (VASI): Demolish and dispose of the existing Visual Approach Slope Indicator (VASI) system and install a new Precision Approach Path Indicators (PAPI) lighting system.

1.3 ITEMS FURNISHED TO CONTRACTOR BY FDCC

1.3.1 One electronic set of the final approved Contract documents at the time of award.

1.3.2 One electronic copy of any changed document due to a Contract modification

1.3.3 One electronic copy of all FD&CC forms referred to herein. Reproduce as necessary.

1.3.4 Publications incorporated into the technical provisions by reference will not be provided by the Government. Provide those references at the project site when necessary for clarification, or if required for reference to assist with quality control.

1.4 CONTRACTOR RESPONSIBILITY

This contract contains both prescriptive and performance-based criteria. The design and subsequent construction shall incorporate all ancillary components as necessary to provide a complete and functional facility for the intended purpose. Where direction is given, it is directed to the Contractor. In each case the meaning is as though written “the Contractor shall….”

1.4.1 The term "COR" is an abbreviation for "Contracting Officer's Representative."

The Term “GCI” is an abbreviation for “Government Contracted Inspector.”

1.5 WORK HOURS

SECTION 01110 Page 4 of 10

1.5.1 All work, except work that requires a runway closure, is authorized at the site from 0700 hours to 1700 hours, Monday through Friday, subject to local jurisdiction approval. No work is allowed on weekends or Federal holidays unless authorized by the

KO.

1.5.2 Hours for night are 2200 to 0700 hours, Monday through Friday.

1.5.3 The USCG expects to utilize the runway 10-28 for Search and Recovery (SAR) launch and recovery missions 24-hours a day and seven days a week, including holidays.

See Section 01111, Paragraph 2.2 for additional scheduling requirements for work within Runway Safety Areas.

1.5.4 The Contracting Officer may grant approval to work extended hours provided the request is made 5 calendar days in advance and the work will not impact USCG Airfield Operations. Extended work hours are from 1700-2200, hours Monday-Friday and 0700- 1700 hours Saturday, Sunday and Federal Holidays.

1.6 SECURITY AND CONTRACTOR USE OF PREMISES

1.6.1 All lay down or staging areas for materials, equipment and Contractor vehicle parking shall be located within the indicated Contractor staging area and site, as shown on RFP Drawings.

1.6.2 Site access for material deliveries for project scope within the airfield interior shall be limited to the one of two Airfield Entry Gates identified within the RFP drawings. All other material deliveries shall utilizes the main gate.

1.6.3 Shipments of equipment, materials, and supplies shall be addressed to the contractor - not the Government. The contractor shall be on hand to accept shipments;

the Government will not accept shipments.

1.6.4 The Contractor's equipment shall be conspicuously marked for identification.

1.6.5 The project site is an active Coast Guard installation and will remain so throughout the construction period. The Contractor shall perform and conduct their work to minimize interference with Coast Guard operations. Contractor personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the Contracting Officer's Representative (COR).

1.6.6 The Contractor shall become familiar with and obey station fire, traffic, and security regulations. Contractor personnel are not allowed in facilities not directly related to the work required under this contract. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the Contracting Officer's Technical Representative.

1.6.7 US Coast Guard Base Elizabeth City has implemented the RAPIDGate Program for their security protocol. The contractor shall register with RAPIDGate and obtain security passes in accordance with the instructions below prior to commencing any on site work. See Attachment ‘H’ for RAPIDGate Details.

1.6.8 The Contractor shall submit a list of all personnel who will be working on site for security reasons. The list shall include the following minimum items: Name of employee, current address, and social security number, date of birth, citizenship and gender. The list shall be submitted to the USCG Base Elizabeth City’s Facilities Engineering office, a minimum of two weeks prior to starting work. The Contractor may submit a revised list at any time during the project. Only personnel on the approved listing will be allowed on the site.

SECTION 01110 Page 5 of 10

1.6.9 The Contractor shall submit the required information on the Base Elizabeth City Visitor Request form to the GCI at least 5 days prior to arrival. Visitors possessing Rapid Gate credentials need not submit a visitor access request.

For vehicle access, the following is required:

(a) Vehicles shall have current proof of insurance and registration

(b) Drivers shall have valid driver’s license

(c) All passengers and personnel shall have a valid driver’s license or other State-issued identification that includes photograph, name and address

1.6.10 All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual's driver's license, or a company issued ID. The identification shall be laminated, and show a facial picture of the individual. Individuals without proper ID will be escorted off the Coast Guard premises.

1.6.11 DRIVING RESTRICTIONS

1.6.11.1 Contractor shall obey all station fire, traffic, and security regulations.

Traffic shall come to a stop at 0800 and at Sunset when colors is sounded and the flag is raised and lowered.

1.6.11.2 Drivers shall follow all posted speed limits and base regulations.

Failure to comply with base regulation may result in revocation of personnel access.

1.6.11.3 All contractor vehicles and traffic (unless otherwise authorized), shall remain within the designated work limits or within 10-feet of haul/access routes.

All contractor access vehicles shall be radio equipped for Air Traffic Control Tower (ATCT) communication or be escorted by a vehicle equipped with radio communication. Under no circumstances shall the Contractor be allowed on any areas outside of its defined work areas authorized in advance by the Contracting Officer's Representative (COR).

1.6.11.4 All drivers accessing or crossing a portion of the active aircraft movement area (aprons, taxiways, runway 10-28) must receive Airfield Driver Training from USCG Airfield Manager prior to accessing these areas.

1.7 DEFINITIONS

The following terms are defined as follows:

(a) Day(s): calendar day(s), unless otherwise noted

(b) FDCC: Facilities Design & Construction Center

(c) FE: Facility Engineer

(d) KO: Contracting Officer

(e) PM: FDCC Project Manager

(f) COR: FDCC Contracting Officer's Representative

(g) EIC: FDCC Engineer-in-Charge

(h) OR: FDCC Onsite Representative (Inspector)

(i) A/E: Architect-Engineering Firm

(j) GCI: Government Contracted Inspector

SECTION 01110 Page 6 of 10

(k) QAM: Contractor's Quality Assurance Manager

(l) DOR: Contractor's Design Engineer of Record

(m) KR: Contractor

(n) DCR: Design Clarification Request to the Government clarifying contract/RFP requirements

(o) RFI: Request for Information sent internally between Construction Contractor and the Contractors DOR clarifying design

1.8 REFERENCES AND ORDER OF PRECEDENCE

Where specifications or standards documents are referenced in these Contract documents, they apply as if they were incorporated into the contract, except if specifically noted otherwise. If there are differences between referenced documents and any contract documents the following precedence applies.

(a) Contract

(b) RFP Specification

(c) RFP Drawings

(d) References

(e) Applicable code or standard governing the work in question

1.9 OTHER STATION WORK

The Coast Guard and other contractors may be performing work at and adjacent to the project site during the time of this Contract. Cooperate and coordinate deliveries, access, and work with the Coast Guard and other contractors in accordance with Contract Clause

FAR 52.236-8.

1.10 NEW UTILITY SERVICES

Make all arrangements with the local utility providers and pay all fees, charges, and costs of any nature associated with establishing and installing new, temporary (during construction), and subsequent permanent utility services required to ensure permanent and uninterrupted utility service at project completion. The contract documents may provide a conceptual plan for utility layouts. These plans shall be confirmed by the contractor during the bidding stage with the local utility provider to determine the exact materials, equipment placement, and other features that may be required by the specific utility provider. The term utility service includes, but is not limited to meters, mains, service lines, high voltage feeders, transformers, force mains, lift stations, tanks, etc. The contractor is responsible for coordinating the work with the utility provider to insure the utility connection to the site is completed and that there is no delay in the prosecution of the work or completion of the project. Utility services include electricity, water, sewer, and telephone. All utilities within the base are owned by the Government. The local electrical provider is as follows:

Company/Govt Office Service Telephone Number Dominion Power Electricity 757-857-2050 City of Elizabeth City Water 252-337-6628 City of Elizabeth City Sewer 252-335-2196

SECTION 01110 Page 7 of 10

Piedmont Natural Gas Natural Gas 252-264-3759 Century Link – CG C4IT Telephone 757-638-2496

1.11 PERMITS

Contractor’s responsibility for permits is discussed in Section I contract clause 52.236-7 “Permits and Responsibilities” and in Section 01800 paragraph 1.18 “Design Related Permits”. Section 01802 paragraph 1.7 “State and Local Government Consultation, Review and Inspection” provides additional guidance on coordination with state and local officials. In addition the contractor shall pay for and obtain all temporary permits for construction of this contract work. The Contractor shall comply with all terms and conditions of permits, whether the Contractor or the Government obtains the permit.

1.12 DRAWINGS FURNISHED

One electronic copy of the plans and specifications will be furnished to the Contractor without charge.

1.13 WORK SEQUENCE

Specific parts of the work shall be completed according to a fixed timetable and sequence.

Those requirements are described in detail in RFP 01111 and on the RFP Drawings.

1.14 GOVERNMENT-FURNISHED ITEMS

None

1.15 RELOCATED EQUIPMENT AND ITEMS

None

1.16 UTILITY OUTAGES

1.16.1 Non-Airfield Utility Interruptions: Limit all utility interruptions to four hours or less, sequence your work to complete and restore the service. Provide temporary services of equal capacity and service, if the interruption will exceed 4 hours in a single work week.

Prior to interrupting or shutting down any utility, make a request for the interruption to the COR in writing at least 5 days before the anticipated interruption. Identify the utility, reason for interruption, start time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the COR.

1.16.2 Airfield Lighting System(s) Interruptions: Prior to interrupting or shutting down any utility that impacts the airfield lighting system, make a request for the interruption to the COR in writing at least 5 days before the anticipated interruption. Identify the utility, reason for interruption, start time of interruption, sequence of work to complete and to restore the service. Do not interrupt utilities until authorized by the COR. All airfield lighting utility interruptions, regardless of duration, shall be coordinated with the COR.

Provide temporary services of equal capacity and service to ensure continuity of airfield lighting systems.

1.17 UNDERGROUND UTILITIES

SECTION 01110 Page 8 of 10

The underground utility locations shown on the drawings are not exact. Use a private utility locator service, at contractor expense, to locate underground utilities. Notify the COR and the cognizant utility companies at least 48 hours before excavating. Mark the excavation route and intersecting utilities. Where excavation will cross an existing utility line, use hand tools to excavate for a distance of 5 feet on each side of the intersection location shown on the drawings. Once exposed, protect underground utilities from damage.

(a) Make utility cut-over and interruptions after the normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in contract clause H.3 "Work outside Regular Work Hours.

(b) Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

(c) Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, and fire alarm shall be considered utility cut-overs. All outages shall be restored prior to the start of normal working hours on the next work day as defined in contract clause H.3 "Work Outside Regular Work Hours." This time limit includes time for deactivation and reactivation.

(d) Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for the normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.

1.18 WEATHER

1.18.1 Delays caused by unusually severe weather (FAR Clause 52.249-10). Unusually severe weather will be considered unforeseeable and unusually severe if it is more severe than the statistical 3-year average for the appropriate weather parameters established by the National Weather Service. See Section 01320 for “Anticipated Weather Delays” for additional requirements.

1.18.2 Should warnings of severe weather be issued, the Contractor shall take every practical precaution to minimize danger to persons, the work, and to adjacent property.

Precautions shall include, but not limited to, closing all openings, removing all loose material, tools and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.19 STORM PROTECTION

Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practicable precaution to minimize danger to person, the work, and to adjacent property.

Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

1.20 MANUFACTURER'S INSTRUCTIONS

Particular items and products specified in the sections are to be provided and/or installed according to the manufacturer's printed instructions. For bidding and contract performance purposes, the contractor is deemed to be aware of the requirements of these instructions.

SECTION 01110 Page 9 of 10

1.21 RECEIPT OF MATERIALS

Shipments of equipment, materials, and supplies shall be addressed to the contractor - not the Government. The contractor must be on hand to accept shipments; the Government will not accept shipments.

1.22 DELIVERY, STORAGE, AND HANDLING OF MATERIALS

Deliver, store, and handle products and materials according to the manufacturer's printed instructions and as follows:

1.22.1 Deliver products and materials in manufacturer's original unopened packages or containers bearing manufacturer's labels.

1.22.2 Store products subject to damage from the elements in weather tight enclosures;

maintain temperature and humidity within the ranges stated in the manufacturer's printed instructions.

1.22.3 Store fabricated products off the ground on platforms, blocking, or skids. Cover or protect products that may discolor or deteriorate due to exposure to the elements.

Provide ventilation to avoid condensation.

1.22.4 Store loose granulated material on solid surfaces such as paving, plywood, or sheet material to prevent mixing with foreign matter. Provide drainage to prevent sheet material from mixing with foreign matter and prevent flow or ponding of rainwater.

Prevent mixing of materials.

1.23 MINOR DEMOLITION, CUTTING, AND PATCHING:

1.23.1 Provide Contracting Officer 24-hour notice before commencing demolition.

1.23.2 Cut surfaces such as masonry, plaster, tile, and metal in straight lines at natural points of division.

1.23.3 Materials for patching, filling-in, repairing, and extending work shall be new, and shall be similar in appearance and equal in quality to the materials used in the adjoining construction or the removed materials when they were new.

1.23.4 Protect existing construction, surfaces, and equipment from damage. Damaged existing construction, surfaces, or equipment shall be restored or replaced to match existing conditions or new adjoining work.

1.23.5 Dust: Erect and maintain temporary dust tight partitions or barriers to prevent the spread of dust, fumes, and noise to other parts of the building. Seal off return air grilles in the areas enclosed by dust barriers. Vent areas enclosed by dust barriers to the outside and provide filters on these vents. Before removing the dust barrier, completely clean the area enclosed by the barrier and both sides of the barrier itself. Cover existing equipment to protect it from dust.

1.23.6 Disassemble, disconnect, cut, remove, and alter existing construction and equipment without damaging other construction or equipment that is to remain or be reused. Cut and remove to the limits shown on the drawings, or, if not shown, to the minimum extent necessary for the proper installation of new work. Piping shall be removed and capped so as to be concealed in the finished work.

1.23.7 Cut, move, and remove existing construction as necessary to do the work;

replace and restore when work is completed.

SECTION 01110 Page 10 of 10

1.23.8 Completely remove applied finish flooring such as ceramic floor and base, and resilient tile flooring and base, including mastic, to structural floor.

1.23.9 Patching: Patch to provide a neatly finished installation and to restore surfaces and items to the condition they were in before the work started. Where removals leave holes and damaged surfaces that will be exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces and to provide surfaces that are suitable for the provision of the new work. Install materials according to standard trade practice. Provide a smooth, even line of transition where patched work adjoins existing construction or new work. Patches or repairs shall match existing conditions or new adjoining work and shall provide a uniform finish and texture over the entire surface. When existing finish cannot be matched, refinish the entire surface to the nearest intersection.

1.23.10 Transitions: Make smooth and even transitions where new work abuts or aligns with existing construction. Where finished surfaces are cut such that a smooth transition with new work is not possible, terminate the existing surface along a straight line at a natural point of division and submit written recommendations to the COR on how to proceed.

1.23.11 Adjustments: Where removal of partitions results in adjacent spaces becoming one, rework floors, walls, and ceilings to a smooth plane without breaks, steps, and bulkheads.

1.24 CONTRACTING OFFICER'S AUTHORITY

In no event shall any understanding or agreement between the contractor and any Government employee other than the Contracting Officer on any contract, modification, change order, letter or verbal direction to the Contractor be effective or binding upon the Government. All such actions must be formalized by a proper contractual document executed by an appointed Contracting Officer. The contractor is hereby put on notice that in the event a Government employee, other than the Contracting Officer, directs a change in the work to be performed, or increases the scope of the work to be performed, it is the contractor's responsibility to make inquiry to the Contracting Officer before making the deviation.

Payments will not be made without being authorized by an appointed Contracting Officer with the legal authority to bind the Government.

Part 2 PRODUCTS

NOT USED.

Part 3 EXECUTION

NOT USED.

END OF SECTION

SECTION 01111 Page 1 of 6

SECTION 01111 - D/B GENERAL PARAGRAPHS

1.1 PROJECT SEQUENCE

Part 2 PRODUCT

2.1 CONSTRUCTION PHASING & CONSTRAINTS

Specific parts of the work must be completed according to a fixed timetable and sequence.

Those requirements are described in detail in the following paragraphs and on the Plans.

2.1.1 Locate the trailers where indicated on the plan sheets of the RFP.

2.1.2 Fence the entire work area on base to the access gate with a minimum 6’.0 high fence with a full covering of filter fabric.

2.1.3 All Contractor parking and lay down will be within their work area. Allow two parking space for the COR/CI.

2.1.4 Airfield Paving

The Contractor shall prepare and submit to the KO, a project phasing plan for airfield paving work. Prior to re-opening pavement to aircraft and vehicular traffic, permanent markings shall be applied.

2.2 CONSTRUCTION ACTIVITY CONSTRAINTS

2.2.1 Interference with Airfield Operations

2.2.1.1 The Contractor shall be prohibited from crossing the active Runway 10-28, unless specifically authorized. To ensure continuity of USCG’s airfield operations, the Contractor’s work inside of the airfield perimeter has been subdivided into two zones; Zone I (North) and Zone II (South). A south gate location and a north gate location have been established for this project. The Contractor shall use the north gate for all North Zone work, which includes all work north of RW 10-28. The Contractor shall use the south gate for all South Zone work, which includes all work south of the RW 10-28. See RFP Drawings for additional work notes.

2.2.1.2 Zone I (North)

2.2.1.2.1 The Contractor shall complete all work within Zone I (North) within 210 calendar days. This includes all BASE and OPTION work.

2.2.1.2.2 The Contractor is responsible for access control of the North Gate.

2.2.1.3 Zone II (South)

2.2.1.3.1 The Contractor shall complete all work within Zone II (South) within 180 calendar days.

2.2.1.3.2 The Zone II Access Gate will require USCG contracted security guards for operation. The Contractor is not responsible for contracting security guards, however, shall coordinate with the USCG as follows:

2.2.1.3.2.1 Provide a schedule, including hours of operation, for the use of the Zone II Access Gate with the 95% Design Submittal.

SECTION 01111 Page 2 of 6

2.2.1.3.2.2 Provide a minimum of 72-hour notice for any changes to the previously submitted schedule.

2.2.1.3.2.3 Provide a temporary Guard House as required in Section 01500, Paragraph 1.5.

2.2.2 The Contractor shall be responsible for airfield mowing requirements within the Construction zones. Airfield mowing is a potential hazard to airfield operations. Airfield mowing shall adhere to these safety requirements and precautions while working within proximity of runways, taxiways, parking aprons, and runway end zones. The grass height shall be maintained no lower than 7-inches and no taller than 14-inches.

2.2.3 Scheduling: Schedule work to accommodate aircraft operations. The Coast FGuard will make every effort to schedule aircraft operations so as to permit the maximum amount of time for contractor activities. However, in the event of an emergency, intense operational demand, adverse wind conditions, and other such unforeseen difficulties, the contractor shall discontinue operations at the specified locations in the aircraft operation area for the safety of the contractor and military personnel and the protection of Government property. Submit a schedule in accordance with Section 01320 describing work to be accomplished, work locations relative to distances from buildings, runways, etc., and dates and times work is scheduled. Keep the Contracting Officer and the Contracting Officer’s Representative apprised of any changes to this schedule.

2.2.4 The USCG expects to utilize RW 10-28 for Search and Recovery (SAR) launch and recovery missions during all nightly closures, to include when the Contractor’s work within Runway Safety Areas to the active RW 10-28 (i.e. runway edge light only work, demolition, or paving). Work within Runway Safety Areas shall be coordinated with COR at least 07 days prior to necessary closures to Runway 10-28. All closures shall be performed at night with an operational plan to pull back construction activities for launch and recovery of SAR aircraft. For bidding purposes, the Contractor shall assume one nightly SAR mission interruption. For SAR missions, the Contractor shall be required to move back from the edge of the runway within 15-minutes prior notice for up to 30-mintues when notified from the Air Traffic Control Tower.

2.2.5 Hazards to Airfield and Heliport Operations: In accordance with the Contractor’s approved Safety Plan Compliance Document (SPCD) as required in Section 01330, Para

1.1.1 and including the Partial Construction Safety and Phasing Plan (see below), the Contractor shall adhere to these safety requirements and precautions while working within proximity of runways, taxiways, parking aprons, runway end zones.

Partial Construction Safety and Phasing Plan (CSPP) Airfield Feature Min setback distance Reference Remarks

Taxiways 50 ft from taxiway edge COMDTINST M3710.1G, Chap 4

25 ft wingtip clearance required for all acft, C-130 is controlling acft

Aprons 50 ft from apron edge COMDTINST M3710.1G, Chap 4

25 ft wingtip clearance required for all acft, C-130 is controlling acft

Runway 175 ft from runway edge during active work

FAA AC 150/5300-

13, Table 3-1

Runway Safety Area (RSA) extends out to

SECTION 01111 Page 3 of 6

325 ft from runway edge for unattended equipment during non-work hours

FAA AC 150/5370-

2, Chap 2 & FAA

AC 150/5300-13,

Table 3-1

175 ft from runway edge

“Equipment shall be removed from the Runway Object Free Area (ROFA) when not in use” ROFA extends out 400 ft from centerline (325 ft from runway edge)

2.2.5.1 Airfield Operations: The contractor shall coordinate work that impacts airfield operations with the USCG Airfield Manager and have the flexibility to adjust the schedule as required to accommodate USCG operations. The contractor shall provide sufficient crews and equipment necessary to accomplish work in the time period specified.

2.2.5.2 Daytime Markings: During daylight hours, mark stationary and mobile equipment with international orange and white checkered flags; mark the material and work site with yellow flags.

2.2.5.3 Nighttime Markings: During nighttime, which begins two hours before sundown and ends two hours after sunrise, mark stationary and mobile equipment, material and the work site with red obstruction lights. Should the USCG Airfield Manager determine that red obstruction lights could confuse pilots; the red lenses shall be replaced with lenses of the color designated in the Contractor’s approved SPCD (see Section 01330, Para 1.1.1). Mobile equipment should be equipped with amber colored flashing beacon or strobe per FAA AC150/5210-5.

2.2.5.4 Excavation: Excavate only trenches for which back-fill material is on site and ready for placement. Immediately, back-fill and compact open trenches as specified.

Prior to any excavation provide an underground utility locate from a company licensed and commercially practicing these services.

2.2.5.5 Operational Safety and Security during Construction: Adhere to the procedures and requirements outlined in FAA Advisory Circular No. 150/5370- 2G, Operational Safety on Airports During Construction. Submit a Construction Safety Phasing Plan (CSPP) outlining the planning effort to assure airfield safety throughout the duration of the project. Factors as outlined in AC 150/5370-2G include identification of affected areas, description of current operations, allowances for temporary changes to operations adhere with the required measures to revised operations. The plan shall be submitted to the Contracting Officer and will be reviewed by USCG Airfield Manager (AFM) personnel for approval. The plan will only be accepted after it is approved by the AFM. The plan shall comply with the requirements of AC 150/5370-2G for construction operations, material stockpiling, equipment operation and related construction activities.

2.2.5.5.1 General. Contractors working at the USCG Station Elizabeth City shall adhere to the standards and requirements contained herein. The AFM’s safety and security objective is to achieve incident‐free and secure construction project.

SECTION 01111 Page 4 of 6

2.2.5.5.2 Airfield Security. Maintenance of the secured area is subject to US Coast Guard security requirements, and shall meet those standards for access control, movement of ground vehicles, and identification of construction contractor and tenant personnel. The Contractor and its personnel shall be aware of the increased security, and familiar with the security policies of the US Coast Guard as directed by the COR, AFM, and Coast Guard Police Department.

2.2.5.5.3 Emergency Notification. In the event of any situation or condition that may adversely affect the operational safety of the Airfield, the Contractor shall immediately notify the AFM. If the condition has an immediate impact on aircraft operations or an emergency situation exists, immediately notify the Air Traffic Control Tower followed by the AFM.

2.2.5.5.4 Airfield Coordination. The Contractor shall coordinate with the AFM through the COR early to schedule runway or taxiway shutdowns and facility shutdowns and restarts so the AFM can coordinate with FAA Air Traffic Control Tower (ATCT). Contractor to ensure that any relocation or adjustments to NAVAIDs, or changes to grades in critical areas, requiring an FAA flight inspection before restarting the facility be processed accordingly.

Flight inspections shall be coordinated and scheduled well in advance of the intended facility restart.

2.2.5.5.5 FAA Form 7460-1 Notice of Proposed Construction. 14 CFR Part

77.9 states that any person or organization who intends to sponsor construction or alterations shall notify the FAA if proposed construction or alteration is within 20,000 feet of a public use or military airport that exceeds a 100:1 surface from any point on the runway. Any changes to the pavement on an airfield, i.e., construction/modification/resurfacing of runways, taxiways, aprons, etc. require an FAA aeronautical hazard determination. Contractor responsible for all notification requirements with the FAA.

Note: The construction area is along a major Coast Guard airport and runway. Use of tall equipment, such as cranes, will require FAA clearance and AFM clearance before crane operations may occur. Clearance notifications to both the FAA and the AFM shall be a responsibility of the Contractor and shall ensure all permit requirements are submitted and approved. The AFM coordinates all crane/equip requests with base flying units and publishes a NOTAM.

2.2.5.5.6 NAVAIDS Shutdown. For emergency (short notice) notification impact on NAVAIDs, contact the AFM (OPS-1) at 252-334-5388. If construction operations require a shutdown of a NAVAID for more than 24 hours or more than 4 hours daily on consecutive days, Contractor shall provide a 50 day minimum notice to the Airport prior to facility shutdown.

The AFM shall notify the appropriate FAA ATO Service Area Planning and Requirements (P&R) Group a minimum of 45 days prior to implementing an event that causes impacts to NAVAIDs. The AFM will coordinate work for a NAVAID shutdown with the FAA, including any necessary reimbursable agreements and flight checks. The Contractor is responsible for all NAVAID notifications and shall provide procedures in the project that will address utility outages and cable cuts that could impact NAVAIDs.

2.2.5.5.7 Hazardous Material. Contractors operating construction vehicles and equipment on the Airfield shall be prepared to expeditiously contain and clean up spills resulting from fuel, hydraulic fluid, or other chemical fluid

SECTION 01111 Page 5 of 6 leaks. Transport and handling of other hazardous materials on the Airfield also requires special procedures. The contractor is required to develop and implement spill prevention and response procedures for vehicle operations.

This includes maintenance of appropriate MSDS data and appropriate prevention/response equipment onsite. The contractor shall notify the AFM, COR, and Contracting Officer, in writing, immediately when a spill occurs.

2.2.5.5.8 Vehicle Operations. Vehicle and pedestrian access routes for Airfield construction projects shall be controlled to prevent inadvertent or unauthorized entry of persons, vehicles, or animals onto the Airport Operations Area (AOA). The AFM will coordinate requirements for vehicle operations with airport tenants, the Air Traffic Manager and contractors.

2.2.5.5.8.1 All personnel operating a motor vehicle on Airport property shall have a valid state driver’s license. North Carolina State Motor Vehicle Laws will be observed when operating a vehicle on the Airport.

2.2.5.5.8.2 Aircraft will continue to use existing runways, aprons, and taxiways during the time that work under a contract is being performed. The Contractor shall, at all times, conduct the work as to create no hindrance, hazard, or obstacle to aircraft using the Airport.

2.2.5.5.8.3 Construction Site Parking. The CSPP will show parking areas for contractor employees to prevent any unauthorized entry of persons or vehicles onto the AOA, and penetration of protected airspace by parked vehicles. These areas will allow reasonable contractor employee access to the job site. The project area(s) shall be bounded by approved barricades identifying contractor personnel and vehicle area operation limits.

2.2.5.6 Construction Equipment Parking. Contractor employees shall park and service construction vehicles in an area designated by the AFM outside the Runway Object Free Area (ROFA) and never in the safety area of an active runway or taxiway. Contractor parking and equipment staging areas will be identified as the Contractor Staging Area in the drawing set in the project’s CSPP. Inactive equipment shall not be parked on a closed taxiway or runway, unless a complex setup makes movement of specialized equipment infeasible.

Construction vehicles shall be parked outside the ROFA when not in use by construction personnel (for example, overnight, on weekends, or during other periods when construction is not active.

2.2.5.7 Marking and Lighting of Vehicles. The Contractor shall abide by the requirements established under AC 150/5210-5D, Painting, Marking, and Lighting of Vehicles Used on an Airport. All vehicles and equipment operating in the AOA and in the general vicinity of the safety area or in aircraft movement areas shall be marked with flashing yellow/amber beacons or orange and white flags during daylight hours. In addition the vehicles and equipment will have identifying symbols at a minimum of 2 inch block type characters of contrasting color that are easily legible. During hours of darkness or low visibility they shall be marked with at least flashing yellow/amber beacons. Beacons and flags shall be maintained to standards in good working and operational condition. Beacons shall be located on the uppermost part of the vehicle structure, visible from any direction, peak intensity within the range of 40 to 400 candelas, and flash 75 +/- 15 flashes per minute. Flags shall be 3’ by 3’ with alternating 1’ by 1’international orange and white squares, and shall be replaced by the contractor if they become faded, discolored, or ragged or as determined by the Airfield Manager and COR.

SECTION 01111 Page 6 of 6

2.2.5.8 Required escorts. At no time will vehicles or personnel enter portions of the Airfield outside the contract area unless permitted and accompanied by an Airfield approved escort. All construction related activity taking place within any active area of the Controlled Movement Area (CMA) requires the presence of a licensed Airfield Driver escort having radio communication with the Control Tower. Spotters and/or flaggers having radio or telephone contact with the Control Tower may be used with the approval of the AFM and the Control Tower.

2.2.5.9 Driver Training. To ensure compliance with ECG’s Airfield Driving rules and regulations, all personnel who drive a vehicle or operate equipment in the AOA shall take the “Airfield Driver Training Briefing from the Airfield Manager” before operating on the Airfield, unless properly escorted. The training includes proper vehicle operations on various areas under normal, lost communications, and emergency conditions. Training is provided on-site by the AFM, coordinated on-demand through the GCI or project meetings, and takes approximately 1 hour.

2.2.5.10 Wildlife management. The CSPP shall be in accordance with AC 150/5200-33B, Hazardous Wildlife Attractants on or Near Airports, and Certalert 98-05, Grasses Attractive to Hazardous Wildlife. Construction contractors shall carefully control and continuously remove organic food waste, or food waste containers, and loose food materials (i.e. food wrappers) that might attract wildlife. Contractor personnel shall be aware of and avoid construction activities that can create wildlife hazards on airports.

2.2.5.11 Foreign Object Debris (FOD) Management. Special care and measures shall be taken to prevent Foreign Object Debris / Damage (FOD) when working in an airport environment. The Contractor shall be held responsible for implementing an approved FOD Plan that will be incorporated into the CSPP.

The FOD Management Plan will have procedures for prevention, regular cleanup, and containment of construction material and debris.

2.2.5.12 Miscellaneous

2.2.5.12.1 Concrete mixer chutes. Shall be retracted to a single chute while traveling on the AOA.

2.2.5.12.2 Forklift forks. Shall be raised no less than 6 inches and no more than 12 inches, and covered or protected by an approved pallet, when proceeding from one point to another.

2.2.5.12.3 Radio Contact. Construction vehicles operating in the CMA shall have radio contact with the Control Tower or shall be escorted by a vehicle that has radio contact with the Tower.

2.2.5.12.4 Runway Crossing. No person will operate vehicle or construction equipment belonging to or under the supervision of a contractor on or across a runway or taxiway, unless they have completed the Airfield Driver Training Course/Licensing or are escorted by Airfield Operations or a licensed airfield driver. These restrictions also apply to any person crossing a runway on foot.

2.2.5.12.5 Open-flame welding or torch cutting. Is prohibited unless adequate fire and safety precautions are provided and have been approved by COR.

NOTE: Under no circumstances are flare pots allowed on the Airfield at any time.

SECTION 01200 Page 1 of 4

SECTION 01200_DESIGN-BUILD PROGRESS PAYMENTS

This section covers the submittal requirements for design-build progress payments.

1.1 RELATED CONTRACT CLAUSE

Section I contract clause 52.232-5 "Payments under Fixed-Price Construction Contracts."

1.2 SUBMITTALS

(a) SD-01 Preconstruction Submittals

• Schedule of Prices for permits, design, and construction activities.

1.3 DESIGN SUBMITTALS

See Section 01820 Construction Design Documents for additional submittal requirements.

(a) Permit (application and submission)

(b) Initial 35% Design Submittal

(c) 65% Design Submittal

(d) Final…