This document is a Scope of Work (SOW) for a Halon Fire Suppression System Replacement project at the San Francisco Maritime National Historical Park. The project involves replacing obsolete fire suppression control panels in Landmark Building E, located at Fort Mason Center, with new Fenwal 2200 and Kidde KDR-100 systems. The work includes system documentation, removing old panels, installing new panels, rewiring pull stations, installing ten new smoke detectors and bases, installing four batteries, conducting system checks and pre-tests, changing out tank initiators, and verifying tank pressure.
The project requires careful handling due to the historic nature of the building, with specific instructions to protect historical fabric and minimize disruption to park staff. All work must be performed by a qualified Fenwal 2200 and Kidde KDR-100 service company, adhering to the National Fire Alarm and Signaling Code (NFPA 72). The contractor is responsible for removing debris, cleaning surfaces, and scheduling a final inspection with the park's Contracting Officer's Representative to ensure the project is thoroughly clean and ready for use.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8625Q0045_Amd_0004.pdf | ||
| Section_J_-_Att_No__009_2025-02-25_SAN-FRANCISCO-MARITIME-38-BLDG-E_SuppressionScan_0004.pdf | ||
| Section_J_-_Att_No__008_2025-02-25_SAN-FRANCISCO-MARITIME-38--1ST-F_SuppressionScan_0004.pdf | ||
| Section_J_-_Att_007_Photos_0003.pdf | ||
| Section_J_-_Att_No__006_2025-05-05_Halon_Pre-Bid_Site_Visit_Sign-In_Sht_0003.pdf | ||
| Sol_140P8625Q0045_Amd_0003.pdf | ||
| Sol_140P8625Q0045_Amd_0002.pdf | ||
| Sol_140P8625Q0045_Amd_0001.pdf | ||
| Section_J_-_Att_No__005_Updated_Quote_Sheet_0001.xlsx | XLSX spreadsheet | |
| Sol_140P8625Q0045.pdf | ||
| Section_J_-_Att_No__002_Photos.pdf | ||
| Section_J_-_Att_No__003_SCA_WD2015-5637_San_Francisco_County.pdf | ||
| Section_J_-_Att_No__004_Technical_Information.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
SAN FRANCISCO MARITIME NATIONAL HISTORICAL PARK
PMIS # 325009
Halon Fire Suppression System Replacement
April 17, 2025
PART 1: GENERAL
1.1 BACKGROUND
This project is required to repair and replace the existing Fenwal 2200 fire suppression control panel for the Fine Arts Room on the first floor and Kidde KDR-100 fire suppression control panel for the Rare
Vault Panel on the third floor in Landmark Building E, Fort Mason Center, San Francisco, The existing main control boards are obsolete and unavailable. Work includes purchase, delivery and installation of a
"like for like" replacement with the factory recommended equivalent Fenwal 2200 and Kidde KDR-100.
The work includes parts, installation and testing.
1.2 GENERAL CONDITIONS AND INFORMATION
A. Landmark Building E is owned by the Department of Interior, National Park Service, herein after called NPS, and is maintained by the San Francisco Maritime National Historical Park, (SAFR).
Landmark Building E is an historic structure, located within the Fort Mason Landmark District and care must be taken to protect historic fabric that is outside the scope of this contract. Damage to historic fabric will be reviewed by the park Historical Architect to consult on method of repair and will be repaired or replaced in-kind at Contractors expense.
B. Any particulars described for the work involved is given for guidance to the Contractor, however, the Contractor is to take his own measurements, dimensions and counts, and is responsible for the same.
C. All work described in this specification is for the preparation and repair work to the designated panels on the first floor Fine Arts Room and third floor Rare Vault panels at Building E. All repairs shall be accomplished in accordance with the provisions of the NPS Contract and Scope of Work. Additional work that will result in additional cost shall be carried out only when authorized in writing by the Contracting Officer.
D. The Contractor shall be responsible for removing and disposing of any debris from the work areas of Park that is generated by the Contractor during the workday.
E. All disturbed surfaces shall be cleaned and restored to the original appearance by the Contractor.
F. The Contractor shall immediately notify the Contracting Officer of any ambiguities, inconsistencies and errors discovered in this specification or between contracting documents and existing conditions.
G. Vendor is required to adhere to the National Fire Alarm and Signaling Code (NFPA 72) as accepted by the NPS AHJ, Authority Having Jurisdiction.
H. The workspace contains historical archives, and any work should provide barriers and controls for dust and debris.
I. All debris shall be minimized and contained as work progresses, access and egress for park staff shall be maintained.
J. All work for this contract shall be performed through a qualified Fenwal 2200 and Kidde KDR-
100 service company.
PART 2: SCOPE OF WORK/ SERVICES
Field verify all new and existing dimensions affecting the work of this contract before ordering materials, notify NPS COR of any discrepancies in writing.
Fine Arts Room Panel (First Floor) and Rare Vault Panel (Third Floor)
1. System documentation/work drawings
2. Remove old panels
3. Install new panels
4. Rewire pull stations
5. Install ten new smoke detectors and bases
6. Install four batteries
7. System check out
8. System pre-test
9. Change out tank initiators
10. Check tank pressure and add nitrogen if needed.
PART 3: INSPECTION / ACCEPTANCE
CLOSE OUT
1. Remove all tools, equipment, surplus, materials, and rubbish from the worksite.
2. Remove grease, dirt stains, foreign materials, and labels from finished surfaces.
3. Schedule the final inspection with park Contracting Officer’s Representative. At time of final inspection, project shall be thoroughly clean and ready for use.
END OF SCOPE OF WORK