SECTION E - INSPECTION AND ACCEPTANCE.pdf

PDF 99 KB Posted

Attached to
FBI National Capital Region (NCR) Job Order Contract (JOC)
Solicitation number
15F06724R0000013
Issued by

About this file

This document outlines requirements for a Job Order Contract (JOC) to provide facilities maintenance and repair services to the Federal Bureau of Investigation's National Capital Region. The contract has a minimum value of $50,000 and a maximum of $24.5 million over five years. It is a competitive small business set-aside limited to firms holding an active Top Secret facilities clearance located within 50 miles of the JEH Building in Washington, D.C. Proposals are due by March 5, 2024 with evaluations beginning as submissions are received. The JOC will require weekly contractor meetings for the first month and ongoing periodic performance evaluations to assess quality, timeliness and customer satisfaction. A final performance review will be conducted at the end of the first year and any option periods exercised.

View the file

Other files

File Type Posted
SECTION B - SUPPLIES OR SERVICE AND PRICECOST (Amendment P00001).pdf PDF
Attachment H - Questions (Answered 20MAR24).pdf PDF
SECTION L Instructions Conditions and Notices to Offerors (Amendment P00001).pdf PDF
SECTION C -PERFORMANCE WORK STATEMENT JEH JOC (Amendment P00001).pdf PDF
15F06724R0000013_P00001_NCR_JOC.pdf PDF
Attachment P Wage Determination DC20240002 (as of 23 Feb 24).pdf PDF
SECTION M - EVALUATION CRITERIA (Amendment P00001).pdf PDF
Attachment K - LAR_SF_85_Completion_Guide.pdf PDF
Attachment F - Surety Form.pdf PDF
SECTION C -PERFORMANCE WORK STATEMENT JEH JOC.pdf PDF
Attachment G - Financial Questionnaire.pdf PDF
Attachment H - Questions Template.xlsx XLSX spreadsheet
Attachment B Joint Venture Partner Form.pdf PDF
Attachment E - Acquisition Risk Questions.pdf PDF
15F06724R0000013_NCR_JOC.pdf PDF
SECTION L Instructions Conditions and Notices to Offerors.pdf PDF
Attachment C-Past Performance Questionaire.pdf PDF
SECTION F - DELIVERIES OR PERFORMANCE.pdf PDF
SECTION H - SPECIAL CONTRACT REQUIREMENTS.pdf PDF
SECTION B - SUPPLIES OR SERVICE AND PRICECOST.pdf PDF
SECTION M - EVALUATION CRITERIA.pdf PDF
Attachment L - RSA Badge Request Form.pdf PDF
Attachment J - FD-857a NDA.pdf PDF
Attachment D - Past Performance Information (PPI) Contract Reference Sheet.docx DOCX document
SECTION G - CONTRACT ADMINISTRATION DATA.pdf PDF
Attachment A - CTC - FBI DC.pdf PDF
Attachment N FD-816 Access of Non-FBI Personnel to FBI Facilities Background Data Information Form.pdf PDF
Attachment M - SF-85 FBI LAR Form.pdf PDF
Attachment I Ethics Fact Sheet.pdf PDF
Attachment O Coeffecient Explained.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION E – INSPECTION AND ACCEPTANCE

E.1 INSPECTION AND ACCEPTANCE

(a) Inspection of reports shall be conducted at destination by the Contracting

Officers Representative (COR) or their authorized designee. Inspection shall consist of an examination of the report for (1) compliance with the specifications or Statement of Work, (2) thoroughness with respect to content, and (3) quality with respect to generally acceptable professional standards.

(b) The COR shall provide the contractor his written comments and recommendations on the content and quality of each progress report within thirty (30) calendar days after receipt deliverable item. A copy of the COR’s comments shall be concurrently furnished to the Contracting Officer designated in the clause entitled “Contract Administration” in Section G.

(c) The COR shall provide the Contractor written comments and recommendations on the content of the preliminary draft copy of the Final

Report within thirty (30) calendar days after the receipt of that deliverable item. A copy of the COR’s comments shall be concurrently furnished to the

Contracting Officer designated in the clause entitled “Contract

Administrator” in Section G. The COR’s comments and recommendations shall be addressed in the final report.

(d) The COR shall review the Final Report and shall, within thirty (30) calendar days, notify the contractor, in writing, with a concurrent copy to the

Contracting Officer designated in Section G, of the acceptability of the Final

Report. Should the Final Report be determined unacceptable, the COR shall notify the Contracting Officer within ten (10) calendar days after receipt thereof. In such event the COR’s inspection report shall address (1) the deficiencies noted and (2) recommendations for corrective action. Within ten

(10) calendar days after receipt of the COR’s inspection report, the

Contracting Officer shall notify the contractor. Failure to so inspect and provide the required notification within the time frame set forth above shall not be construed as acceptance.

E.2 PERFORMANCE EVALUATION MEETINGS

Evaluation meetings may be held for both the overall contract and individual task orders.

SECTION E – INSPECTION AND ACCEPTANCE

The Contractor shall also meet with the Government's representatives weekly during the first month of the contract. Thereafter, meetings will be as often as necessary at the discretion of the Contracting Officer or their designated representative. A mutual effort will be made to resolve all problems identified. The written minutes of these meetings, prepared by the Contractor, shall be signed by the Contractor's representative and the Government's representative. Should the

Government not concur with the minutes, the Contractor shall make changes proposed by the Government. If the Contractor disagrees with the changes made by the Government, the Contractor shall state, in writing, to the Contracting Officer or their designated representative any areas of disagreement within five (5) calendar days.

In addition, the Government will periodically assess, in writing, the Contractor's overall performance to date on this contract. The Government may evaluate the

Contractor more frequently if it becomes necessary. The Contractor will have thirty (30) calendar days to submit written comments on each evaluation performed.

E.3 Notice of Completion of Task Orders

Final acceptance of the work performed on the individual Task Orders shall follow the procedures identified in Quality Control.

The FBI will complete a Contractor Performance Evaluation for each year of the

JOC. The purpose of the performance evaluations is to help the Contractor and the

Government access customer satisfaction of the work completed. A copy will be provided to the contractor. There will also be a Contractor Performance Evaluation completed at the end of the first year of the Contract and at the end of any option.

This evaluation will encompass all work performed during the year.