This document outlines requirements for a Job Order Contract (JOC) to provide facilities maintenance and repair services to the Federal Bureau of Investigation's National Capital Region. The contract has a minimum value of $50,000 and a maximum of $24.5 million over five years. It is a competitive small business set-aside limited to firms holding an active Top Secret facilities clearance located within 50 miles of the JEH Building in Washington, D.C. Proposals are due by March 5, 2024 with evaluations beginning as submissions are received. The JOC will require weekly contractor meetings for the first month and ongoing periodic performance evaluations to assess quality, timeliness and customer satisfaction. A final performance review will be conducted at the end of the first year and any option periods exercised.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION E – INSPECTION AND ACCEPTANCE
E.1 INSPECTION AND ACCEPTANCE
(a) Inspection of reports shall be conducted at destination by the Contracting
Officers Representative (COR) or their authorized designee. Inspection shall consist of an examination of the report for (1) compliance with the specifications or Statement of Work, (2) thoroughness with respect to content, and (3) quality with respect to generally acceptable professional standards.
(b) The COR shall provide the contractor his written comments and recommendations on the content and quality of each progress report within thirty (30) calendar days after receipt deliverable item. A copy of the COR’s comments shall be concurrently furnished to the Contracting Officer designated in the clause entitled “Contract Administration” in Section G.
(c) The COR shall provide the Contractor written comments and recommendations on the content of the preliminary draft copy of the Final
Report within thirty (30) calendar days after the receipt of that deliverable item. A copy of the COR’s comments shall be concurrently furnished to the
Contracting Officer designated in the clause entitled “Contract
Administrator” in Section G. The COR’s comments and recommendations shall be addressed in the final report.
(d) The COR shall review the Final Report and shall, within thirty (30) calendar days, notify the contractor, in writing, with a concurrent copy to the
Contracting Officer designated in Section G, of the acceptability of the Final
Report. Should the Final Report be determined unacceptable, the COR shall notify the Contracting Officer within ten (10) calendar days after receipt thereof. In such event the COR’s inspection report shall address (1) the deficiencies noted and (2) recommendations for corrective action. Within ten
(10) calendar days after receipt of the COR’s inspection report, the
Contracting Officer shall notify the contractor. Failure to so inspect and provide the required notification within the time frame set forth above shall not be construed as acceptance.
E.2 PERFORMANCE EVALUATION MEETINGS
Evaluation meetings may be held for both the overall contract and individual task orders.
SECTION E – INSPECTION AND ACCEPTANCE
The Contractor shall also meet with the Government's representatives weekly during the first month of the contract. Thereafter, meetings will be as often as necessary at the discretion of the Contracting Officer or their designated representative. A mutual effort will be made to resolve all problems identified. The written minutes of these meetings, prepared by the Contractor, shall be signed by the Contractor's representative and the Government's representative. Should the
Government not concur with the minutes, the Contractor shall make changes proposed by the Government. If the Contractor disagrees with the changes made by the Government, the Contractor shall state, in writing, to the Contracting Officer or their designated representative any areas of disagreement within five (5) calendar days.
In addition, the Government will periodically assess, in writing, the Contractor's overall performance to date on this contract. The Government may evaluate the
Contractor more frequently if it becomes necessary. The Contractor will have thirty (30) calendar days to submit written comments on each evaluation performed.
E.3 Notice of Completion of Task Orders
Final acceptance of the work performed on the individual Task Orders shall follow the procedures identified in Quality Control.
The FBI will complete a Contractor Performance Evaluation for each year of the
JOC. The purpose of the performance evaluations is to help the Contractor and the
Government access customer satisfaction of the work completed. A copy will be provided to the contractor. There will also be a Contractor Performance Evaluation completed at the end of the first year of the Contract and at the end of any option.
This evaluation will encompass all work performed during the year.