This document is a Section B pricing schedule from a solicitation for the Federal Aviation Administration's (FAA) requirement for the procurement of pre-cast concrete shelters. The solicitation number is 6973GH-24-R-00036 and it is for an Indefinite Delivery, Indefinite Quantity (IDIQ) contract.

The pricing schedule lists Contract Line Item Numbers (CLINs) for the manufacture and delivery of 12'x20' and 12'x36' pre-cast concrete shelters over a 3-year base period. The quantities range from 1 to 6 shelters per CLIN, with unit prices per shelter and per mile for delivery. The total estimated value is not provided. Proposals are due by 5:00 PM CST on September 2, 2024, and must be submitted electronically to the contract specialist. The FAA will award a firm-fixed-price construction contract under their Acquisition Management System in place of the Federal Acquisition Regulation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6973GH-24-R-00036

Section B (continued)

CLIN Description Quantity Unit Price

00001 BASE Manufacture 12x20 Pre-cast concrete shelters 1 EA $___________

$ Per Mile $___________

3 EA $___________

00002 BASE Delivery of 12x20 Pre-Fabricated Concrete Shelters 1

00003 BASE Manufacture 12x36 Pre-cast concrete shelters

00004 BASE Delivery of 12x36 Pre-Fabricated Concrete Shelters

00005 Year 1 Manufacture 12x20 Pre-cast concrete shelters

$ Per Mile $___________

2 EA $___________

$ Per Mile $___________ 00006 Year 1 Delivery of 12x20 Pre-Fabricated Concrete Shelters 2

00007 Year 1 Manufacture 12x36 Pre-cast concrete shelters 6 EA $___________

6 $ Per Mile $___________ 00008 Year 1 Delivery of 12x36 Pre-Fabricated Concrete Shelters

00009 Year 2 Manufacture 12x20 Pre-cast concrete shelters 3 EA $___________

$ Per Mile $___________ 00010 Year 2 Delivery of 12x20 Pre-Fabricated Concrete Shelters 3

00011 Year 2 Manufacture 12x36 Pre-cast concrete shelters 6 EA $___________

6 $ Per Mile $___________ 00012 Year 2 Delivery of 12x36 Pre-Fabricated Concrete Shelters

00013 Year 3 Manufacture 12x20 Pre-cast concrete shelters 3 EA $___________

$ Per Mile $___________ 00014 Year 3 Delivery of 12x20 Pre-Fabricated Concrete Shelters 3

00015 Year 3 Manufacture 12x36 Pre-cast concrete shelters 6 EA $___________

00016 Year 3 Delivery of 12x36 Pre-Fabricated Concrete Shelters 6 $ Per Mile $___________

TOTAL COST: MANUFACTURE & INSTALLATION 12X20 & 12X36 SHELTERS $___________

TOTAL COST: DELIVERY 12X20 & 12X36 SHELTERS $___________/Mile