About this file
This document is a Scope of Services for Engineering Project 1182-2023 involving the City of Fort Myers, focusing on a comprehensive environmental/infrastructure project. The project requires the contractor to provide all labor and materials for construction and associated grant documentation, with specific tasks including non-vegetative and vegetative debris removal, underwater debris removal, sediment removal and transport, Ballard bank repair, weekly inspection reports, and record drawings. The bid tasks are structured with various measurement units such as cubic yards, linear feet, mileage, and a lump sum, with each task having a "Not To Exceed" (NTE) cost designation.
The project mandates extensive documentation for potential reimbursement, including detailed invoices, material records, daily employee time tracking, equipment operation logs, and weekly construction progress reports. All work must comply with federal requirements, specifically OSHA regulations and the Contract Work Hours and Safety Standards Act. While specific unit costs are not filled in, the document provides a structured framework for bidders to propose pricing for each task. The documentation requirements are rigorous, emphasizing transparency, precise record-keeping, and adherence to safety and labor standards, suggesting this is likely an environmentally focused infrastructure improvement or restoration project.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Services Engineering Project 1182-2023
Provide all labor and materials for the construction and required grant documentation based on the plans, specifications, and other contract documents.
The following documentation is required to support the City of Fort Myers request for reimbursement of:
a. Invoices covering actual costs of materials used in constructing the eligible EWP project measures.
b. Records documenting the type, quality, and quantities of materials actually used in constructing the eligible EWP project measures.
c. Daily time records for each employee showing name, classification, wage rate, hours, and dates actually employed for constructing the eligible EWP project measures.
d. Equipment operating records showing the type and size of equipment, hourly rate, actual hours of operation and dates used to install the eligible EWP project measures. Equipment idle time is not eligible in-kind construction services, even if on the job site, and should not be included in the equipment operating records.
e. Weekly construction progress reports that include on-site inspections of work accomplished for the period, work planned, problems encountered.
d. Provide PE-certified as-built drawings and quantities for the project.
Construction shall adhere to the following federal requirement: Ensure that all contractors and sub-contractors are performing their work in accordance with OSHA regulations and the Contract Work Hours and Safety Standards Act (40 USC 3701-3708) as supplemented by Department of Labor regulations (29 CFR Part 5).
BID TASKS.
TASK UNITS UNIT COST TOTAL COST (NTE)
1. Non-Vegetative Debris Removal Cubic Yards (NTE)
2. Vegetative Debris Removal Cubic Yards (NTE)
3. Underwater Debris Removal Linear Feet (NTE)
4. Sediment Removal Cubic Yards (NTE)
5. Sediment Transport Mileage (NTE)
6. Ballard Bank Repair Linear Feet (NTE)
7. Inspection Reports Weekly (NTE)
8. Record Drawings Lump Sum